Annual Report
Mitigation Fee Act
Pursuant to Government Code 66006
City of San Clemente
Fiscal Year 2021-22
Government Code Section 66006 provides that a local agency that requires the payment of development fees shall prepare an annual and five-year report detailing the status of those fees. The annual report must be made available to the public within 180 days of the end of the fiscal year. The City Council must review the report at the next regularly scheduled public meeting of the Council that falls at least fifteen (15) days after the information is made available to the public. Government Code Section 66013 has similar requirements for capacity charges.

Pursuant to Government Code Section 66006(b)(1) or section 66013(d), as applicable, the following information must be made available to the public:

1. Provide a brief description of the type of fee in the account or fund. a. Regional Circulation Financing and Phasing Program (RCFPP): The fees are used to mitigate the traffic impacts caused by new development in the Benefit Zones. The fees will cause development in the Benefit Zones to pay their fair share of the construction costs of improvements within the Benefit Zones.
b. Public Safety Construction Fee: The fees are used to mitigate the impact of new development on public safety services.
c. Civic Center Construction Fund Fee: The fees are used to mitigate the impact of new development on the need for additional municipal office space. d. Storm Drain Fee – Other Area (City Infill Development Areas): The fees are used to mitigate new development’s impact on the City’s Storm Drainage Facilities in the City Infill Development Areas.
e. Storm Drain Fee – Segunda Deschecha: The fees are used to mitigate new development’s impact on the City’s Storm Drainage Facilities in the Segunda Deschecha area. f. Storm Drain Fee – Prima Deschecha Canada: The fees are used to mitigate new development’s impact on the City’s Storm Drainage Facilities in the Prima Deschecha Canada area.
g. Storm Drain Fee – Marblehead: The fees are used to mitigate new development’s impact on the City’s Storm Drainage Facilities in the Marblehead area. h. Water Acreage Fee: The fees are used to mitigate the impact of new development on the City’s water system facilities.
i. Sewer Connection Fee: The fees are used to mitigate the impact of new development on the City’s water reclamation plant.

2. List the amount of the fee
a. Regional Circulation Financing and Phasing Program (RCFPP): Attached as Exhibit #1 b. Public Safety Construction Fee: Attached as Exhibit #2 c. Civic Center Construction Fund Fee: Attached as Exhibit #3 d. Storm Drain Fee – Other Area (City Infill Development Areas): Attached as Exhibit #4 e. Storm Drain Fee- Segunda Deschecha: Attached as Exhibit #4 f. Storm Drain Fee - Prima Deschecha Canada: Attached as Exhibit #4 g. Storm Drain Fee – Marblehead: Attached as Exhibit #4 h. Water Acreage Fee: Attached as Exhibit #5
i. Sewer Connection Fee: Attached as Exhibit #6

3. List the beginning and ending balance of the account or fund. a. Regional Circulation Financing and Phasing Program (RCFPP):

Beginning balance as of 7/1/21: $ 919,680
Ending balance as of 6/30/22: $ 925,633
b. Public Safety Construction Fee:

Beginning balance as of 7/1/21: $ 2,747,428
Ending balance as of 6/30/22: $ 1,537,109
c. Civic Center Construction Fund Fee:

Beginning balance as of 7/1/21: $ 564,323
Ending balance as of 6/30/22: $ 643,514
d. Storm Drain Fee – Other Area (City Infill Development Areas):

Beginning balance as of 7/1/21: $ 647,693
Ending balance as of 6/30/22: $ 290,316
e. Storm Drain Fee – Segunda Deschecha:

Beginning balance as of 7/1/21: $ 2,877,334
Ending balance as of 6/30/22: $ 2,745,111
f. Storm Drain Fee – Prima Deschecha Canada:

Beginning balance as of 7/1/21: $ 0
Ending balance as of 6/30/22: $ 0
g. Storm Drain Fee – Marblehead:

Beginning balance as of 7/1/21: $ 82,394
Ending balance as of 6/30/22: $ 73,693
h. Water Acreage Fee:

Beginning balance as of 7/1/21: $ 3,299,883
Ending balance as of 6/30/22: $ 3,236,337
i. Sewer Connection Fee:

Beginning balance as of 7/1/21: $ 7,376,929
Ending balance as of 6/30/22: $ 7,068,650

4. List the amount of the fees collected and the interest earned. a. Regional Circulation Financing and
Fees Collected Interest Earned
/Investment Income
Phasing Program (RCFPP): $ 91,896 $ (24,251)
b. Public Safety Construction Fee: $ 292,749 $ (69,003) c. Civic Center Construction Fund Fee: $ 96,360 $ (14,173) d. Storm Drain Fee – Other Area
(City Infill Development Areas): $ 231 $ (14,941)
e. Storm Drain Fee – Segunda Deschecha: $ 955 $ (66,375) f. Storm Drain Fee –
Prima Deschecha Canada: $ 0 $ 0
g. Storm Drain Fee – Marblehead: $ 0 $ (1,901)
h. Water Acreage Fee: $ 48,720 $ (90,879)
i. Sewer Connection Fee: $ 0 $ (175,746)

5. Provide an identification of each public improvement on which fees were expended and the amount of the expenditures on each improvement, including the total percentage of the cost of the public improvement that was funded with the fees.

Attached as Exhibit #7

6. Provide an identification of an approximate date by which the construction of the public improvements will commence if the local agency determines that sufficient funds have been collected to complete financing on an incomplete public improvement, and the public improvement remains incomplete. For capacity charges, this section also details any public improvements anticipated to be provided in the following year. a. Regional Circulation Financing and Phasing Program (RCFPP):

The City has determined that sufficient funds have been collected to complete the design for Ave Pico Bike and Pedestrian Path, Vera Cruz to Frontera, Phase I (project no. 17337). Design is underway and planned for completion in early 2023, with construction anticipated in Spring 2025.

The City has determined that sufficient funds have been collected to complete the design for Pico Widening, I-5 to Frontera, project (project no.18325). Design is underway and planned for completion in early 2022, with construction anticipated in Spring 2023. b. Public Safety Construction Fee:

The City has determined sufficient funds have been collected to complete the second phase of the Calle Negocio remodel project to incorporate a Police Sub-Station on the 2nd Floor. Construction began in Fiscal Year 2021 and was completed in Fall 2022 (project no. 10546).
c. Civic Center Construction Fund Fee:

The City has determined sufficient funds have been collected to complete the second phase of the Calle Negocio remodel project to incorporate a Police Sub-Station on the 2 nd Floor. Construction began in Fiscal Year 2021 and completion is anticipated in Fiscal Year 2023 (project no. 10546).
d. Storm Drain Fee – Other Area ( City Infill Development areas):

The City has determined that sufficient funds have been collected to complete the City Master Plan of Drainage – Other Areas project (Project no. 34001). The Master Plan development commenced in 2016, with a draft master plan completed by a consultant in FY2018-19. The plan is currently under review with the City Attorney, and it is anticipated that the City Council will adopt the plan in 2023.

The City has determined that sufficient funds have been collected to complete the MOOS05 Montalvo Canyon Outlet project (Project no. 16004). The MOOS05 Montalvo Canyon Outlet project commenced in 2016 and the City continued working with the California Coastal Commission until the project was finally permitted in 2022. Currently the final plans, based on Coastal Commission’s conditions, are being completed with construction anticipated in Fall 2023.

The City has determined that sufficient funds have been collected to complete the Storm Drain Improvements at PCH & Camino San Clemente project (project no. 10016).

The project was completed in early 2022.

The City has not determined that sufficient funds have been collected to complete any improvements ultimately recommended in the Master Plan project.

e. Storm Drain Fee – Segunda Deschecha:

The City has determined that sufficient funds have been collected to complete the City Master Plan of Drainage – Segunda Deschecha project (Project no. 34003). The Master Plan development commenced in 2016, with a draft master plan completed by a consultant in FY2018-19. The plan is currently under review with the City Attorney, and it is anticipated that the City Council will adopt the plan sometime in 2023.

The City has determined that sufficient funds have been collected to complete the Storm Drain Improvements at 1601 Calle Las Bolas project (project no. 10015). The project is under construction with completion anticipated in Spring 2023.

The City has not determined that sufficient funds have been collected to complete any improvements ultimately recommended in the Master Plan project. f. Storm Drain Fee – Prima Deschecha Canada:

The City has determined that sufficient funds have been collected to complete the City Master Plan of Drainage – Prima Deschecha project (Project no. 34002). The Master Plan development commenced in 2016, with a draft master plan completed by a consultant in FY2018-19. The plan is currently under review with the City Attorney, and it is anticipated that the City Council will adopt the plan sometime in 2022.

The City has not determined that sufficient funds have been collected to complete any improvements ultimately recommended in the Master Plan project. g. Storm Drain Fee – Marblehead:

The City has determined that sufficient funds have been collected to complete the City Master Plan of Drainage – Marblehead project (Project no. 34004). The Master Plan development commenced in 2016, with a draft master plan completed by a consultant in FY2018-19. The plan is currently under review with the City Attorney, and it is anticipated that the City Council will adopt the plan sometime in 2023.

The City has not determined that sufficient funds have been collected to complete any improvements ultimately recommended in the Master Plan project. h. Water Acreage Fee:

The City has determined that sufficient funds have been collected to complete the Reeves Pump Station project (Project no. 17405) in the Marblehead Coastal area. Final design of the Pump Station was completed in 2019, and construction is expected to begin in Fall 2023.

The City has not determined that sufficient funds have been collected to complete the Recycled Water Expansion – Phase II project (Project no. 17407). The project will analyze the potential to expand the existing recycled system. The project commenced in 2017 and design and partial construction are expected to be completed in calendar year 2023.

The City has determined that sufficient funds have been collected to complete the Dana Point Ocean Water Desalinization Study project (Project no. 38401). The study is complete, salvage of the pumping system and project closeout was completed in FY2022.

The City has not determined that sufficient funds have been collected to complete any desalinization project ultimately recommended in the Study project.

The City has not determined that sufficient funds have been collected to complete any improvements ultimately recommended in the Master Plan project. i. Sewer Connection Fee:

The City has determined that sufficient funds have been collected to complete the Sewer System SCADA Improvement project (Project no. 12605). Project design is complete, with construction delayed due to lack of funding based on the bids received.

Staff is evaluating other options to complete the project.

The City has determined that sufficient funds have been collected to complete the SMWD Trampas Recycled Water Reservoir project (Project no. 12207). Final Agreement for capacity purchase into the project is being finalized.

The City has determined that sufficient funds have been collected to complete the SMWD Pico Recycled Water Pump Station project (Project no. 12206). Final Agreement for capacity purchase into the project is being finalized.

7. Provide a description of each inter-fund transfer or loan made from the account or fund, including the public improvement on which the transferred or loaned fees will be expended and, in the case of an inter-fund loan, the date on which the loan will be repaid, and the rate of interest that the account or fund will receive on the loan.

A $25,890 transfer from the City’s Regional Circulation and Financing and Phasing Program was made to the Gas Tax Fund to fund a portion of the Camino Del Rio and La Pata Extensions (project no. 18316).

8. Provide the amount of any refunds made from surplus fees and the amount of any allocations made pursuant to subdivision (f) of Section 66001. (Subdivision (f) of Section 66001 requires reallocation of surplus fees where the administrative costs of refunding the fees exceed the amount to be refunded.)
a. Regional Circulation Financing and Phasing Program (RCFPP):

None
b. Public Safety Construction Fee:

None
c. Civic Center Construction Fee:

None
d. Storm Drain Fee – Other Area (City Infill Development Areas):

None
e. Storm Drain Fee – Segunda Deschecha:

None
f. Storm Drain Fee – Prima Deschecha Canada:

None
g. Storm Drain Fee – Marblehead:

None
h. Water Acreage Fee:

None
i. Sewer Connection Fee
None
FISCAL YEAR 2022

CITY OF SAN CLEMENTE
RCFPP Impact Fee
Effective July 1, 2021
Exhibit #1
RCFPP (Regional Circulation Financing Phasing Program)
Zone I & II - Marblehead Inland and Coastal
Single Family $7,970/DU
Multi-Family $4,649/DU
Non-Residential $4.50/SF
Zone III - Rancho San Clemente
Single Family $1,340/DU
Multi-Family $782/DU
Non-Residential $1.50/SF
Zone IV - Forster Ranch
Single Family $1,105/DU
Multi-Family $645/DU
Non-Residential TBD
Zone V - Talega Valley City
Single Family $740/DU
Multi-Family $432/DU
Non-Residential $1.00/SF
Zone VI - Talega Valley County
Single Family $545/DU
Multi-Family $318/DU
Non-Residential $1.00/SF
Zone VII, VIII, IX, X
Single Family $900/DU
Multi-Family $525/DU
Non-Residential $1.50/SF
Note:

1. DU stands for Dwelling Unit.

2. SF stands for Square Foot.

3. TBD stands for To Be Determined.

FISCAL YEAR 2022

CITY OF SAN CLEMENTE
Public Safety Construction Fee
Effective January 1, 2022
Exhibit #2
Public Safety Construction Fee
Each Residential Unit $1,776.10
Commercial Unit $442.61/1000 sq. ft.

Fee fluctuates annually (Jan 1st) based on the Consumer Price Index and is charged to every new residential and commercial unit.

Note:

DU stands for Dwelling Unit.

FISCAL YEAR 2022

CITY OF SAN CLEMENTE
Civic Center Construction Fund Fee
Effective January 1, 2022
Exhibit #3
Civic Center Construction Fund Fee
Residential Unit $611.40
Fee fluctuates annually (Jan 1st) based on the Consumer Price Index and is charged to every new residential unit.

Note:

DU stands for Dwelling Unit.

FISCAL YEAR 2022

CITY OF SAN CLEMENTE
Storm Drain Fees
Effective July 1, 2021
Exhibit #4
Storm Drainage Fee:

Other Areas $600/acre
Segunda Deshecha $3,409/acre
Prima Deshecha Canada $5,633/acre
Marblehead Coastal $1,650/acre
FISCAL YEAR 2022

CITY OF SAN CLEMENTE
Water Acreage Fee
Effective July 1, 2021
Exhibit #5
Water Acreage Fee
For developments having estimated water demand with the water usage limits set forth herein, the water acreage assessment charge (water connection fee) shall be:

Estimated Water Demand not to exceed*
Existing Developed Areas:

Residential 450 gal/DU/Day* $2,388/acre or
398/DU,
whichever is
greater
Commercial 2500 gal/acre/day* $2,388/acre
Industrial 3500 gal/acre/day* $2,388/acre
Undeveloped Areas:

Residential n/a; fee per DU $3,156/DU
Commercial 2500 gal/acre/day* $10,500/acre
Industrial 3500 gal/acre/day* $10,500/acre
*All requests for commercial or industrial water service, and for multiple residential water service in the "existing developed area" shall be reviewed by the City Engineer for determination of compliance of the proposed use with the above water demand.

For developments which exceed the water demand limits listed above, the water acreage fee shall be calculated as follows:

Existing Developed Areas:

Residential $0.884/gal/day
Commercial $0.955/gal/day
Industrial $0.682/gal/day
Undeveloped Areas:

Residential n/a; fee per DU $3,156/DU
Commercial $4.20/gal/day
Industrial $3.00/gal/day
Note:

1. DU stands for Dwelling Unit.

2. Gal stands for Gallon.

FISCAL YEAR 2022

CITY OF SAN CLEMENTE
Sewer Connection Fee
Effective July 1, 2021
Exhibit #6
Sewer Connection Fee: (Acct. 001-000-32372)
(**Sewer Connection Fees were previously automatically increased by 10% at the beginning of each year per San Clemente Municipal Code Sections 13.24.220 and 13.24.250, Ord. 874.

There has been a temporary moratorium approved by City Council on December 17, 2019 via resolution 19-055.

Residence or Dwelling Unit, Including Apts.:

Fee Area "A" (areas previously subdivided prior to Ordinance 663 dated 3/5/76) $0** Fee Area "B" (areas subdivided after Ordinance 663, dated 3/5/76, and not included in the original Sewer Assessment District No. 85-1*) $0**
Commercial & Industrial
Fee Areas "A" and "B" (All areas except those included in the original Sewer Assessment District No. 85-1) $0**
Hotel, Motel, Mobile Homes, Etc.

Fee Area "A" (areas previously subdivided prior to Ordinance 663 dated 3/5/76) First Unit: $0**
Each Subsequent Unit: $0**
Fee Area "B" (areas subdivided after Ordinance 663, dated 3/5/76 and not included in the original Sewer Assessment District No. 85-1*)
First Unit: $0**
Each Subsequent Unit: $0**
*Above fees applicable to properties not included in the original Assessment District No. 85-1 (Wastewater Treatment Facilities), which was subsequently refinanced. Properties included in said District have been assessed for sewer facilities and not subject to above fees.

VERIFICATION OF SEWER ASSESSMENT to be obtained from Engineering Division prior to issuance of building permits.

Note:

DU stands for Dwelling Unit.

Exhibit #7
FISCAL YEAR 2021-2022

CITY OF SAN CLEMENTE
Section 5
Public Improvement Expenditures
Project Name Project # Expenditure % Funded
with Fees
Regional Circulation Financing and Phasing Program (RCFPP) Ave Pico - Class I Bike/Ped Path Ph I 17337 $ 27,119.36 100% Camino Del Rio and La Pata Extensions 18316 $ 25,890.00 100% Ave Pico Widening - I-5 - Frontera 18325 $ 4,172.50 100% General Fund administrative reimbursement $ 4,510.00 ** 100% Pubic Safety Construction Fee
Negocio 2nd Floor Design 10546 $ 1,419,480.49 75%
General Fund administrative reimbursement $ 14,584.00 ** 100% Civic Center Construction Fund Fee
City Hall Relocation 18804 $ 29,815.44 50%
General Fund administrative reimbursement $ 2,996.00 ** 100% Storm Drain Fee – Other Area (City Infill Development Areas) SD Improvement at PCH & Camino 10016 $ 283,941.22 100%
MOOS05 Montalvo Canyon Outlet 16004 $ 47,615.76 100%
General Fund administrative reimbursement $ 11,110.00 ** 100% Storm Drain Fee – Segunda Deschecha
City Master Plan of Drainage - Segunda Deschecha 34003 $ 4,284.48 100% SD Improvements at 1601 Calle Las Bolas 10015 $ 48,833.00 100% Catch Basin and SD Improvements 12003 $ 5,055.08 100%
General Fund administrative reimbursement $ 8,630.00 ** 100% Storm Drain Fee – Marblehead
General Fund administrative reimbursement $ 6,800.00 ** 100% Storm Drain Fee – Prima Deschecha Canada
General Fund administrative reimbursement $ - ** 100%
Exhibit #7
FISCAL YEAR 2021-2022

CITY OF SAN CLEMENTE
Section 5
Public Improvement Expenditures
Project Name Project # Expenditure % Funded
with Fees
Water Acreage Fee
Reeves Pump Station 17405 $ - * 100%
Recycled Water Expansion Phase II 17407 $ 6,327.66 * 100% Dana Point Ocean Water Desalinization Project 38401 $ - * 100% General Fund administrative reimbursement $ 15,060.00 ** 100% Sewer Connection Fee
Tertiary Filter Backwash Improvements 16207 $ - * 100%
SMWD Pico Recycled Water Pump Station 12206 $ - * 100%
SMWD Trampas Recycled Water Reservoir 12207 $ - * 100%
Cyprus Shores PS Relocation 12210 $ 81,019.54 100%
Recycled Water Conversion Program 34201 $ 8,934.75 100% WRP Efficiency Study 39202 $ 16,269.69 100%
General Fund administrative reimbursement $ 26,310.00 ** 100% * Projects are budgeted, but no costs incurred in the current year. ** Administrative costs is a reimbursement for overhead related to General government costs incurred such as city clerk, finance, treasury, and other general costs.