17.28.240 Public Utilities.
A. Purpose and Intent. The purpose of this section is to ensure that public utility facilities, such as substations or reservoirs, and antennas (other than satellite antennas and antennas on City property, which are regulated elsewhere) are located and built in a manner which is compatible with adjacent uses. An additional purpose of this section is to define the review process for public utilities initiated by the City and those initiated by outside agencies. Please refer to Section 17.28.070, Antennas on City Property, and Section 17.28.080, Satellite Antennas, for regulations for other types of antennas.
B. Review Requirements.
1. City Projects. For the required review process for City-initiated public utility projects, please refer to the City's Public Works Department policy on the review of capital improvement projects.
2. Projects Initiated by Outside Agencies/Applicants.
a. Major utilities shall require the approval of a Conditional Use Permit, in accordance with Section 17.16.060, Conditional Use Permits. Major utilities shall include, but shall not be limited to, reservoirs, utility substations, including electrical distribution and transmission substations, and above-ground pump stations, such as sewage and potable water system pump stations, antennas (other than satellite antennas, antennas on City property, and small cell facilities) and similar facilities. If the installation of the antenna is stealth, as determined by the City Planner, then the process is administrative and no Conditional Use Permit is required. The standards in Subsection (C)(1), Minimum Standards for Projects Initiated by Outside Agencies, Major Utilities, shall apply to major utilities initiated by outside agencies. The City Engineer shall be responsible for determining whether a utility is major. b. Minor utilities shall be permitted outright, subject to the concurrent review requirements found in Section 17.12.090, Consideration of Concurrent Applications. Minor utilities shall include, but shall not be limited to, below-ground pump stations, stand pipes, and transformers. The standards in Subsection (C)(2), Minimum Standards for Projects Initiated by Outside Agencies, Minor Utilities, shall apply to minor utilities initiated by outside agencies. The City Engineer shall be responsible for determining whether a utility is minor. c. Public utility distribution and transmission line towers and poles, and underground facilities for distribution of gas, water, telephone and electricity shall be allowed in all zones without obtaining a Conditional Use Permit. However, all routes and heights of proposed electric transmission systems of 69 KV and over, telephone main trunk cables, from one central office to another and water or gas transmission mains which are above ground, shall be located in conformance with the General Plan of the City. d. Small cell facilities shall require the approval of a Wireless Permit in accordance with Section 17.16.075.
3. Modifications to Existing Antenna Facilities. The City Planner shall review and decide on requests to modify existing wireless towers or base station structures that support antennas, transceivers, or other related equipment. This includes the addition and removal of wireless transmission equipment such as the co-location of new transmission equipment, the removal of transmission equipment, or the replacement of transmission equipment. Modifications shall not substantially change the physical dimensions of the wireless tower or base station, as defined by the Federal Communications Commission. The City Planner may approve projects that meet minimum standards in Section 17.28.070(D)(5).
C. Minimum Standards for Projects initiated by Outside Agencies.
1. Major Utilities.
a. Compatibility. All buildings, structures and landscaping shall be visually compatible with surrounding development. b. Development Standards. The standards for major utilities shall be determined through the Conditional Use Permit process. c. Location. Please refer to the permitted and conditional use tables in Chapters 17.32, Residential Zones and Standards through 17.48, Public Zones and Standards.
2. Minor Utilities.
a. Compatibility. All minor utilities shall be placed underground or shall be screened in accordance with Section 17.24.050, Building Equipment and Services and Their Screening. b. Development Standards. Minor utilities shall comply with the standards for ground-mounted equipment in Section 17.24.050, Building Equipment and Services and Their Screening. c. Location. Please refer to the permitted and conditional use tables in Chapters 17.32, Residential Zones and Standards through 17.48, Public Zones and Standards. d. Parking. The parking requirements for a public utility use such as an electric distribution and transmission substation, public utility service yard or similar use may be waived or modified, subject to the approval of a Conditional Use Permit in accordance with Section 17.16.060, Conditional Use Permits, upon a finding that the use requires no full-time or permanent employees.
3. Modifications of Existing Wireless Towers or Base Station Structures. Refer to Section 17.28.070(D)(5) for minimum standards that apply to modifications of existing wireless towers or base station structures.
4. Small Cell Facilities.
a. Design and Development Standards. The design and development standards, which contain aesthetic and location criteria for small cell facilities shall be adopted by Resolution of the City Council. (Ord. 1304 § 21, 2005; Ord. 1172 § 3 (part), 1996)
(Ord. No. 1594, § 3(Exh. A, § 30), 5-5-2015; Ord. No. 1690 , § 3(Exh. A), 2-18-2020) Created: 2023-09-21 11:12:45 [EST]