Section 00500
Contract
THIS CONTRACT is made this _____ day of _________, 2023, in the County of Orange, State of California, by and between the City of San Clemente hereinafter called City, and Jennette Company, Inc., a California corporation, hereinafter called Contractor. City and the Contractor for the considerations stated herein agree as follows:
SCOPE OF WORK. The Contractor shall perform all Work within the time stipulated the contract and shall provide all labor, materials, equipment, tools, utility services, and transportation to complete all of the Work required in strict compliance with the Contract Documents as specified in Article 5 below for the following Project:
WRP SPLITTER BOX REHABILITATION, PROJECT NO. 14206
The Contractor and its surety shall be liable to City for any damages arising as a result of the Contractor’s failure to comply with this obligation.
TIME FOR COMPLETION. The Work shall be commenced on the date stated in City’s Notice to Proceed. The Contractor shall complete all Work required by the Contract Documents within 120 working days from the commencement date stated in the Notice to Proceed. By its signature hereunder, Contractor agrees the time for completion set forth above is adequate and reasonable to complete the Work.
CONTRACT PRICE. City shall pay to the Contractor as full compensation for the performance of the Contract, subject to any additions or deductions as provided in the Contract Documents, and including all applicable taxes and costs, the sum of Three Hundred Seventy-Nine Thousand and Five Hundred Dollars ($379,500). Payment shall be made as set forth in the General Conditions.
At any time during the term of the Contract, City may, pursuant to the terms and provisions of the Contract Documents, request that the Contractor perform additional work. Contractor shall not perform, nor be compensated for, additional work without written authorization from the City pursuant to the terms and provisions of the Contract Documents. This project includes a 19% contingency in the amount of Seventy Two Thousands and One Hundred Dollars ($72,100) for unforeseen conditions. In no event shall approved additional work exceed such project contingency, nor shall the total amount of compensation for work performed under this Contract, including approved additional work, exceed Four Hundred Fifty One Thousand Six Hundred Dollars ($451,600).
LIQUIDATED DAMAGES/EARLY COMPLETION INCENTIVE. In accordance with Government Code section 53069.85, it is agreed that the Contractor will pay City the sum of $750 for each and every calendar day of delay beyond the time prescribed in the Contract Documents for finishing the Work, as Liquidated Damages and not as a penalty or forfeiture. In the event that Liquidated Damages are not paid, the Contractor agrees City may deduct that amount from any money due or that may become due the Contractor under the Contract. This Article does not exclude recovery of other damages specified in the Contract Documents.
COMPONENT PARTS OF THE CONTRACT. The “Contract Documents” include the following:
Contract
Bid Form
Contractor’s Certificate Regarding Workers’ Compensation Bid Bond
Designation of Subcontractors
Information Required of Bidders
Non-Collusion Declaration form
Iran Contracting Act Certification
Public Works Contractor Registration Certification
Performance Bond
Payment Bond
General Conditions
Special Conditions
Technical Specifications
Addenda
Plans and Drawings
Approved and fully executed change orders
Any other documents contained in or incorporated into the Contract The Contactor shall complete the Work in strict accordance with all of the Contract Documents.
All of the Contract Documents are intended to be complementary. Work required by one of the Contract Documents and not by others shall be done as if required by all. This Contract shall supersede any prior agreement of the parties.
PROVISIONS REQUIRED BY LAW. Each and every provision of law required to be included in these Contract Documents shall be deemed to be included in these Contract Documents. The Contractor shall comply with all requirements of applicable federal, state and local laws, rules and regulations, including, but not limited to, the provisions of the California Labor Code and California Public Contract Code which are applicable to this Project.
INDEMNIFICATION. Contractor shall provide indemnification as set forth in the General Conditions.
PREVAILING WAGES. Contractor shall be required to pay the prevailing rate of wages in accordance with the Labor Code which such rates shall be made available at City of San Clemente Public Works Department or may be obtained online at http//www.dir.ca.gov/dlsr. and which must be posted at the job site.
IN WITNESS WHEREOF, the parties hereto have caused this Agreement to be duly executed on the respective dates set forth opposite of their signatures.
CITY OF SAN CLEMENTE
By:________________________________
Andy Hall, City Manager
ATTEST:
Dated: ____________________, 2023
______________________________
CITY CLERK of the City of
San Clemente, California
APPROVED AS TO FORM:
____________________________
Elizabeth A. Mitchell, City Attorney
APPROVED AS TO AVAILABILITY
OF FUNDING:
________________________________
Finance Authorization
JENNETTE COMPANY, INC.
(“CONTRACTOR”)
By:_____________________________
Brian Jennette, CEO, Secretary and CFO
Dated: __________________, 2023
END OF CONTRACT
55452.01510\32905704.2
97 APPENDIX 3
technical specifications