1 CITY OF SAN CLEMENTE

CONSTRUCTION CONTRACT

PLAYGROUND SURFACING REPLACEMENT AT SAN GORGONIO PARK

1. PARTIES AND DATE.

This Contract is made and entered into this ____ day of January, 2025 by and between the City of San Clemente, a public agency of the State of California (“City”) and Robertson Industries, Inc., an Arizona Corporation with its principal place of business at 2140 East Cedar Street, Tempe, AZ 85281 (“Contractor”). City and Contractor are sometimes individually referred to as “Party” and collectively as “Parties” in this Contract.

2. RECITALS.

2.1 City. City is a public agency organized under the laws of the State of California, with power to contract for services necessary to achieve its purpose.

2.2 Contractor. Contractor desires to perform and assume responsibility for the provision of certain construction services required by the City on the terms and conditions set forth in this Contract. Contractor represents that it is duly licensed and experienced in providing the removal and replacement of the playground substrate surfacing at San Gorgonio Park related construction services to public clients, that it and its employees or subcontractors have all necessary licenses and permits to perform the services in the State of California, and that it is familiar with the plans of City. The following license classifications are required for this Project:

California Contractors License

2.3 Project. City desires to engage Contractor to render such services for the PLAYGROUND SURFACING REPLACEMENT AT SAN GORGONIO PARK (“Project”) as set forth in this Contract.

2.4 Project Documents & Certifications. Contractor has obtained, and delivers concurrently herewith, a performance bond, a payment bond, and all insurance documentation, as required by the Contract.

3. TERMS

3.1 Incorporation of Documents. This Contract includes and hereby incorporates in full by reference the following documents, including all exhibits, drawings, specifications and documents therein, and attachments and addenda thereto:
• Services/Schedule (Exhibit “A”)
• Plans and Specifications (Exhibit “B”)
• Special Conditions (Exhibit “C”)
• Contractor’s Certificate Regarding Workers’ Compensation (Exhibit “D”) • Public Works Contractor Registration Certification (Exhibit “E”) • Payment and Performance Bonds (Exhibit “F”)
• Insurance Requirements (Exhibit “G”)
• Addenda
• Change Orders executed by the City
Attachment 2
55452.01510\32977834.2
2 • 2009 Edition of the Standard Specifications for Public Works Construction (The Greenbook), Excluding Sections 1-8
• Notice Inviting Bids, if any
• Instructions to Bidders, if any
• Contractor’s Bid

3.2 Contractor’s Basic Obligation; Scope of Work. Contractor promises and agrees, at its own cost and expense, to furnish to the City all labor, materials, tools, equipment, services, and incidental and customary work necessary to fully and adequately complete the Project, including all structures and facilities necessary for the Project or described in the Contract (hereinafter sometimes referred to as the “Work”), for a Total Contract Price as specified pursuant to this Contract. All Work shall be subject to, and performed in accordance with the above referenced documents, as well as the exhibits attached hereto and incorporated herein by reference. The plans and specifications for the Work are further described in Exhibit “B” attached hereto and incorporated herein by this reference. Special Conditions, if any, relating to the Work are described in Exhibit “C” attached hereto and incorporated herein by this reference.

3.2.1 Change in Scope of Work. Any change in the scope of the Work, method of performance, nature of materials or price thereof, or any other matter materially affecting the performance or nature of the Work shall not be paid for or accepted unless such change, addition or deletion is approved in writing by a valid change order executed by the City. Should Contractor request a change order due to unforeseen circumstances affecting the performance of the Work, such request shall be made within five (5) business days of the date such circumstances are discovered or shall waive its right to request a change order due to such circumstances. If the Parties cannot agree on any change in price required by such change in the Work, the City may direct the Contractor to proceed with the performance of the change on a time and materials basis.

3.2.2 Substitutions/“Or Equal”. Pursuant to Public Contract Code Section 3400(b), the City may make a finding that designates certain products, things, or services by specific brand or trade name. Unless specifically designated in this Contract, whenever any material, process, or article is indicated or specified by grade, patent, or proprietary name or by name of manufacturer, such Specifications shall be deemed to be used for the purpose of facilitating the description of the material, process or article desired and shall be deemed to be followed by the words “or equal.”
Contractor may, unless otherwise stated, offer for substitution any material, process or article which shall be substantially equal or better in every respect to that so indicated or specified in this Contract. However, the City may have adopted certain uniform standards for certain materials, processes and articles. Contractor shall submit requests, together with substantiating data, for substitution of any “or equal” material, process or article no later than thirtyfive (35) days after award of the Contract. To facilitate the construction schedule and sequencing, some requests may need to be submitted before thirty-five (35) days after award of Contract.

Provisions regarding submission of “or equal” requests shall not in any way authorize an extension of time for performance of this Contract. If a proposed “or equal” substitution request is rejected, Contractor shall be responsible for providing the specified material, process or article. The burden of proof as to the equality of any material, process or article shall rest with Contractor.

The City has the complete and sole discretion to determine if a material, process or article is an “or equal” material, process or article that may be substituted. Data required to substantiate requests for substitutions of an “or equal” material, process or article data shall include a signed affidavit from Contractor stating that, and describing how, the substituted “or equal” 55452.01510\32977834.2
3 material, process or article is equivalent to that specified in every way except as listed on the affidavit. Substantiating data shall include any and all illustrations, specifications, and other relevant data including catalog information which describes the requested substituted “or equal” material, process or article, and substantiates that it is an “or equal” to the material, process or article. The substantiating data must also include information regarding the durability and lifecycle cost of the requested substituted “or equal” material, process or article. Failure to submit all the required substantiating data, including the signed affidavit, to the City in a timely fashion will result in the rejection of the proposed substitution.

Contractor shall bear all of the City’s costs associated with the review of substitution requests. Contractor shall be responsible for all costs related to a substituted “or equal” material, process or article. Contractor is directed to the Special Conditions (if any) to review any findings made pursuant to Public Contract Code section 3400.

3.3 Period of Performance.

3.3.1 Contract Time. Contractor shall perform and complete all Work under this Contract within one year, beginning the effective date of the Notice to Proceed (“Contract Time”).

Contractor shall perform its Work in strict accordance with any completion schedule, construction schedule or project milestones developed by the City. Such schedules or milestones may be included as part of Exhibits “A” or “B” attached hereto, or may be provided separately in writing to Contractor. Contractor agrees that if such Work is not completed within the aforementioned Contract Time and/or pursuant to any such completion schedule, construction schedule or project milestones developed pursuant to provisions of the Contract, it is understood, acknowledged and agreed that the City will suffer damage.

3.3.2 Force Majeure. Neither City nor Contractor shall be considered in default of this Contract for delays in performance caused by circumstances beyond the reasonable control of the non-performing party. For purposes of this Contract, such circumstances include but are not limited to, abnormal weather conditions; floods; earthquakes; fire; pandemics or epidemics; war; riots and other civil disturbances; strikes, lockouts, work slowdowns, and other labor disturbances; sabotage or judicial restraint. Should such circumstances occur, the non-performing party shall, within a reasonable time of being prevented from performing, give written notice to the other party describing the circumstances preventing continued performance and the efforts being made to resume performance of this Contract. Contractor’s exclusive remedy in the event of delay covered under this section shall be a non-compensable extension of the Contract Time.

3.3.3 Liquidated Damages. Pursuant to Government Code Section 53069.85, Contractor shall pay to the City as fixed and liquidated damages the sum of One Thousand Dollars ($1,000) per day for each and every calendar day of delay beyond the Contract Time or beyond any completion schedule, construction schedule or Project milestones established pursuant to the Contract.

3.4 Standard of Performance; Performance of Employees. Contractor shall perform all Work under this Contract in a skillful and workmanlike manner, and consistent with the standards generally recognized as being employed by professionals in the same discipline in the State of California. Contractor represents and maintains that it is skilled in the professional calling necessary to perform the Work. Contractor warrants that all employees and subcontractors shall have sufficient skill and experience to perform the Work assigned to them. Finally, Contractor represents that it, its employees and subcontractors have all licenses, permits, qualifications and approvals of whatever nature that are legally required to perform the Work, including any required business license, and that such licenses and approvals shall be maintained throughout the term 55452.01510\32977834.2
4 of this Contract. As provided for in the indemnification provisions of this Contract, Contractor shall perform, at its own cost and expense and without reimbursement from the City, any work necessary to correct errors or omissions which are caused by Contractor’s failure to comply with the standard of care provided for herein. Any employee who is determined by the City to be uncooperative, incompetent, a threat to the safety of persons or the Work, or any employee who fails or refuses to perform the Work in a manner acceptable to the City, shall be promptly removed from the Project by Contractor and shall not be re-employed on the Work.

3.5 Control and Payment of Subordinates; Contractual Relationship. City retains Contractor on an independent contractor basis and Contractor is not an employee of City. Any additional personnel performing the work governed by this Contract on behalf of Contractor shall at all times be under Contractor’s exclusive direction and control. Contractor shall pay all wages, salaries, and other amounts due such personnel in connection with their performance under this Contract and as required by law. Contractor shall be responsible for all reports and obligations respecting such additional personnel, including, but not limited to: social security taxes, income tax withholding, unemployment insurance, and workers’ compensation insurance.

3.6 City’s Basic Obligation. City agrees to engage and does hereby engage Contractor as an independent contractor to furnish all materials and to perform all Work according to the terms and conditions herein contained for the sum set forth above. Except as otherwise provided in the Contract, the City shall pay to Contractor, as full consideration for the satisfactory performance by Contractor of the services and obligations required by this Contract, the below-referenced compensation in accordance with compensation provisions set forth in the Contract.

3.7 Compensation and Payment.

3.7.1 Amount of Compensation. As consideration for performance of the Work required herein, which includes everything that is reasonably foreseeable related thereto, City agrees to pay Contractor the Total Contract Price of One Hundred Forty-Four Thousand and Five Hundred Sixty-Five Dollars ($144,565.00) (“Total Contract Price”) provided that such amount shall be subject to adjustment pursuant to the applicable terms of this Contract or written change orders approved and signed in advance by the City.

3.7.2 Payment of Compensation. If the Work is scheduled for completion in thirty (30) or less calendar days, City will arrange for payment of the Total Contract Price upon completion and approval by City of the Work. If the Work is scheduled for completion in more than thirty (30) calendar days, City will pay Contractor on a monthly basis as provided for herein. On or before the fifth (5th) day of each month, Contractor shall submit to the City an itemized application for payment in the format supplied by the City indicating the amount of Work completed since commencement of the Work or since the last progress payment. These applications shall be supported by evidence which is required by this Contract and such other documentation as the City may require. The Contractor shall certify that the Work for which payment is requested has been done and that the materials listed are stored where indicated. Contractor may be required to furnish a detailed schedule of values upon request of the City and in such detail and form as the City shall request, showing the quantities, unit prices, overhead, profit, and all other expenses involved in order to provide a basis for determining the amount of progress payments.

3.7.3 Prompt Payment. City shall review and pay all progress payment requests in accordance with the provisions set forth in Section 20104.50 of the California Public Contract Code. However, no progress payments will be made for Work not completed in accordance with this Contract. Contractor shall comply with all applicable laws, rules and regulations relating to the proper payment of its employees, subcontractors, suppliers or others. 55452.01510\32977834.2
5 3.7.4 Contract Retentions. From each approved progress estimate, five percent (5%) will be deducted and retained by the City, and the remainder will be paid to Contractor. All Contract retention shall be released and paid to Contractor and subcontractors pursuant to California Public Contract Code Section 7107.

3.7.5 Other Retentions. In addition to Contract retentions, the City may deduct from each progress payment an amount necessary to protect City from loss because of: (1) liquidated damages which have accrued as of the date of the application for payment; (2) any sums expended by the City in performing any of Contractor’s obligations under the Contract which Contractor has failed to perform or has performed inadequately; (3) defective Work not remedied; (4) stop notices as allowed by state law; (5) reasonable doubt that the Work can be completed for the unpaid balance of the Total Contract Price or within the scheduled completion date; (6) unsatisfactory prosecution of the Work by Contractor; (7) unauthorized deviations from the Contract; (8) failure of Contractor to maintain or submit on a timely basis proper and sufficient documentation as required by the Contract or by City during the prosecution of the Work; (9) erroneous or false estimates by Contractor of the value of the Work performed; (10) any sums representing expenses, losses, or damages as determined by the City, incurred by the City for which Contractor is liable under the Contract; and (11) any other sums which the City is entitled to recover from Contractor under the terms of the Contract or pursuant to state law, including Section 1727 of the California Labor Code. The failure by the City to deduct any of these sums from a progress payment shall not constitute a waiver of the City’s right to such sums.

3.7.6 Substitutions for Contract Retentions. In accordance with California Public Contract Code Section 22300, the City will permit the substitution of securities for any monies withheld by the City to ensure performance under the Contract. At the request and expense of Contractor, securities equivalent to the amount withheld shall be deposited with the City, or with a state or federally chartered bank in California as the escrow agent, and thereafter the City shall then pay such monies to Contractor as they come due. Upon satisfactory completion of the Contract, the securities shall be returned to Contractor. For purposes of this Section and Section 22300 of the Public Contract Code, the term “satisfactory completion of the contract” shall mean the time the City has issued written final acceptance of the Work and filed a Notice of Completion as required by law and provisions of this Contract. Contractor shall be the beneficial owner of any securities substituted for monies withheld and shall receive any interest thereon. The escrow agreement used for the purposes of this Section shall be in the form provided by the City.

3.7.7 Title to Work. As security for partial, progress, or other payments, title to Work for which such payments are made shall pass to the City at the time of payment. To the extent that title has not previously been vested in the City by reason of payments, full title shall pass to the City at delivery of the Work at the destination and time specified in this Contract. Such transferred title shall in each case be good, free and clear from any and all security interests, liens, or other encumbrances. Contractor promises and agrees that it will not pledge, hypothecate, or otherwise encumber the items in any manner that would result in any lien, security interest, charge, or claim upon or against said items. Such transfer of title shall not imply acceptance by the City, nor relieve Contractor from the responsibility to strictly comply with the Contract, and shall not relieve Contractor of responsibility for any loss of or damage to items.

3.7.8 Labor and Material Releases. Contractor shall furnish City with labor and material releases from all subcontractors performing work on, or furnishing materials for, the Work governed by this Contract prior to final payment by City.

3.7.9 Prevailing Wages. Contractor is aware of the requirements of California Labor Code Section 1720 et seq., and 1770 et seq., as well as California Code of Regulations, 55452.01510\32977834.2
6 Title 8, Section 16000 et seq., (“Prevailing Wage Laws”), which require the payment of prevailing wage rates and the performance of other requirements on “public works” and “maintenance” projects. Since the Services are being performed as part of an applicable “public works” or “maintenance” project, as defined by the Prevailing Wage Laws, and since the total compensation is $1,000 or more, Contractor agrees to fully comply with such Prevailing Wage Laws. City shall provide Contractor with a copy of the prevailing rates of per diem wages in effect at the commencement of this Contract upon request. Contractor shall make copies of the prevailing rates of per diem wages for each craft, classification or type of worker needed to execute the Services available to interested parties upon request, and shall post copies at Contractor’s principal place of business and at the project site. Contractor shall defend, indemnify and hold the City, its officials, officers, employees and agents free and harmless from any claim or liability arising out of any failure or alleged failure to comply with the Prevailing Wage Laws. Contractor and any subcontractor shall forfeit a penalty of up to $200 per calendar day or portion thereof for each worker paid less than the prevailing wage rates.

3.7.10 Apprenticeable Crafts. When Contractor employs workmen in an apprenticeable craft or trade, Contractor shall comply with the provisions of Section 1777.5 of the California Labor Code with respect to the employment of properly registered apprentices upon public works. The primary responsibility for compliance with said section for all apprenticeable occupations shall be with Contractor. The Contractor or any subcontractor that is determined by the Labor Commissioner to have knowingly violated Section 1777.5 shall forfeit as a civil penalty an amount not exceeding $100 for each full calendar day of noncompliance, or such greater amount as provided by law.

3.7.11 Hours of Work. Contractor is advised that eight (8) hours labor constitutes a legal day’s work. Pursuant to Section 1813 of the California Labor Code, Contractor shall forfeit a penalty of $25.00 per worker for each day that each worker is permitted to work more than eight (8) hours in any one calendar day and forty (40) hours in any one calendar week, except when payment for overtime is made at not less than one and one-half (1-1/2) times the basic rate for that worker.

3.7.12 Payroll Records. Contractor and each subcontractor shall keep an accurate payroll record, showing the name, address, social security number, work classification, straight time and overtime hours worked each day and week, and the actual per diem wages paid to each journeyman, apprentice, worker, or other employee employed by him or her in connection with the public work. The payroll records shall be certified and shall be available for inspection at all reasonable hours at the principal office of Contractor in the manner provided in Labor Code section 1776. In the event of noncompliance with the requirements of this section, Contractor shall have 10 days in which to comply subsequent to receipt of written notice specifying in what respects such Contractor must comply with this section. Should noncompliance still be evident after such 10-day period, Contractor shall, as a penalty to City, forfeit not more than $100.00 for each calendar day or portion thereof, for each worker, until strict compliance is effectuated. The amount of the forfeiture is to be determined by the Labor Commissioner. A contractor who is found to have violated the provisions of law regarding wages on Public Works with the intent to defraud shall be ineligible to bid on Public Works contracts for a period of one to three years as determined by the Labor Commissioner. Upon the request of the Division of Apprenticeship Standards or the Division of Labor Standards Enforcement, such penalties shall be withheld from progress payments then due. The responsibility for compliance with this section is on Contractor. The requirement to submit certified payroll records directly to the Labor Commissioner under Labor Code section 1771.4 shall not apply to work performed on a public works project that is exempt pursuant to the small project exemption specified in Labor Code Section 1771.4. 55452.01510\32977834.2
7 3.7.13 Contractor and Subcontractor Registration. Pursuant to Labor Code sections 1725.5 and 1771.1, all contractors and subcontractors that wish to bid on, be listed in a bid proposal, or enter into a contract to perform public work must be registered with the Department of Industrial Relations. No bid will be accepted nor any contract entered into without proof of the contractor’s and subcontractors’ current registration with the Department of Industrial Relations to perform public work. Contractor is directed to review, fill out and execute the Public Works Contractor Registration Certification attached hereto as Exhibit “E” prior to contract execution.

Notwithstanding the foregoing, the contractor registration requirements mandated by Labor Code Sections 1725.5 and 1771.1 shall not apply to work performed on a public works project that is exempt pursuant to the small project exemption specified in Labor Code Sections 1725.5 and 1771.1.

3.7.14 Labor Compliance; Stop Orders. This Project is subject to compliance monitoring and enforcement by the Department of Industrial Relations. It shall be the Contractor’s sole responsibility to evaluate and pay the cost of complying with all labor compliance requirements under this Contract and applicable law. Any stop orders issued by the Department of Industrial Relations against Contractor or any subcontractor that affect Contractor’s performance of Work, including any delay, shall be Contractor’s sole responsibility. Any delay arising out of or resulting from such stop orders shall be considered Contractor caused delay subject to any applicable liquidated damages and shall not be compensable by the City. Contractor shall defend, indemnify and hold the City, its officials, officers, employees and agents free and harmless from any claim or liability arising out of stop orders issued by the Department of Industrial Relations against Contractor or any subcontractor.

3.8 Performance of Work; Jobsite Obligations.

3.8.1 Water Quality Management and Compliance.

3.8.1.1 Water Quality Management and Compliance. Contractor shall keep itself and all subcontractors, staff, and employees fully informed of and in compliance with all local, state and federal laws, rules and regulations that may impact, or be implicated by the performance of the Work including, without limitation, all applicable provisions of the Federal Water Pollution Control Act (33 U.S.C. §§ 1300); the California Porter-Cologne Water Quality Control Act (Cal Water Code §§ 13000-14950); local ordinances regulating discharges of storm water; and any and all regulations, policies, or permits issued pursuant to any such authority regulating the discharge of pollutants, as that term is used in the Porter-Cologne Water Quality Control Act, to any ground or surface water in the State.

3.8.1.2 Compliance with the Statewide Construction General Permit.

Contractor shall comply with all conditions of the most recent iteration of the National Pollutant Discharge Elimination System General Permit for Storm Water Discharges Associated with Construction Activity, issued by the California State Water Resources Control Board (“Permit”). It shall be Contractor’s sole responsibility to file a Notice of Intent and procure coverage under the Permit for all construction activity which results in the disturbance of more than one acre of total land area or which is part of a larger common area of development or sale. Prior to initiating work, Contractor shall be solely responsible for preparing and implementing a Storm Water Pollution Prevention Plan (SWPPP) as required by the Permit. Contractor shall be responsible for procuring, implementing and complying with the provisions of the Permit and the SWPPP, including the standard provisions, and monitoring and reporting requirements as required by the Permit. The Permit requires the SWPPP to be a “living document” that changes as necessary to meet the conditions and requirements of the job site as it progresses through difference phases of 55452.01510\32977834.2
8 construction and is subject to different weather conditions. It shall be Contractor’s sole responsibility to update the SWPPP as necessary to address conditions at the project site.

3.8.1.3 Other Water Quality Rules Regulations and Policies.

Contractor shall comply with the lawful requirements of any applicable municipality, drainage City, or local agency regarding discharges of storm water to separate storm drain systems or other watercourses under their jurisdiction, including applicable requirements in municipal storm water management programs.

3.8.1.4 Cost of Compliance. Storm, surface, nuisance, or other waters may be encountered at various times during construction of The Work. Therefore, the Contractor, by submitting a Bid, hereby acknowledges that it has investigated the risk arising from such waters, has prepared its Bid accordingly, and assumes any and all risks and liabilities arising therefrom.

3.8.1.5 Liability for Non-Compliance. Failure to comply with the Permit is a violation of federal and state law. Pursuant to the indemnification provisions of this Contract, Contractor hereby agrees to defend, indemnify and hold harmless the City and its officials, officers, employees, volunteers and agents for any alleged violations. In addition, City may seek damages from Contractor for any delay in completing the Work in accordance with the Contract, if such delay is caused by or related to Contractor’s failure to comply with the Permit.

3.8.1.6 Reservation of Right to Defend. City reserves the right to defend any enforcement action brought against the City for Contractor’s failure to comply with the Permit or any other relevant water quality law, regulation, or policy. Pursuant to the indemnification provisions of this Contract, Contractor hereby agrees to be bound by, and to reimburse the City for the costs (including the City’s attorney’s fees) associated with, any settlement reached between the City and the relevant enforcement entity.

3.8.1.7 Training. In addition to the standard of performance requirements set forth in paragraph 3.4, Contractor warrants that all employees and subcontractors shall have sufficient skill and experience to perform the Work assigned to them without impacting water quality in violation of the laws, regulations and policies described in paragraph 3.8.1.

Contractor further warrants that it, its employees and subcontractors will receive adequate training, as determined by City, regarding the requirements of the laws, regulations and policies described in paragraph 3.8.1 as they may relate to the Work provided under this Agreement. Upon request, City will provide the Contractor with a list of training programs that meet the requirements of this paragraph.

3.8.2 Safety. Contractor shall execute and maintain its work so as to avoid injury or damage to any person or property. Contractor shall comply with the requirements of the specifications relating to safety measures applicable in particular operations or kinds of work. In carrying out its Work, Contractor shall at all times be in compliance with all applicable local, state and federal laws, rules and regulations, and shall exercise all necessary precautions for the safety of employees appropriate to the nature of the Work and the conditions under which the Work is to be performed. Safety precautions as applicable shall include, but shall not be limited to, adequate life protection and lifesaving equipment; adequate illumination for underground and night operations; instructions in accident prevention for all employees, such as machinery guards, safe walkways, scaffolds, ladders, bridges, gang planks, confined space procedures, trenching and shoring, fall protection and other safety devices, equipment and wearing apparel as are necessary or lawfully required to prevent accidents or injuries; and adequate facilities for the proper inspection and maintenance of all safety measures. Furthermore, Contractor shall prominently display the 55452.01510\32977834.2
9 names and telephone numbers of at least two medical doctors practicing in the vicinity of the Project, as well as the telephone number of the local ambulance service, adjacent to all telephones at the Project site.

3.8.3 Laws and Regulations. Contractor shall keep itself fully informed of and in compliance with all local, state and federal laws, rules and regulations in any manner affecting the performance of the Contract or the Work, including all Cal/OSHA requirements, and shall give all notices required by law. Contractor shall be liable for all violations of such laws and regulations in connection with Work. If Contractor observes that the drawings or specifications are at variance with any law, rule or regulation, it shall promptly notify the City in writing. Any necessary changes shall be made by written change order. If Contractor performs any work knowing it to be contrary to such laws, rules and regulations and without giving written notice to the City, Contractor shall be solely responsible for all costs arising therefrom. City is a public entity of the State of California subject to certain provisions of the Health & Safety Code, Government Code, Public Contract Code, and Labor Code of the State. It is stipulated and agreed that all provisions of the law applicable to the public contracts of a municipality are a part of this Contract to the same extent as though set forth herein and will be complied with. Contractor shall defend, indemnify and hold City, its officials, officers, employees and agents free and harmless, pursuant to the indemnification provisions of this Contract, from any claim or liability arising out of any failure or alleged failure to comply with such laws, rules or regulations.

3.8.4 Permits and Licenses. Contractor shall be responsible for securing City permits and licenses necessary to perform the Work described herein, including, but not limited to, any required business license. While Contractor will not be charged a fee for any City permits, Contractor shall pay the City’s business license fee, if any. Any ineligible contractor or subcontractor pursuant to Labor Code Sections 1777.1 and 1777.7 may not perform work on this Project.

3.8.5 Trenching Work. If the Total Contract Price exceeds $25,000 and if the Work governed by this Contract entails excavation of any trench or trenches five (5) feet or more in depth, Contractor shall comply with all applicable provisions of the California Labor Code, including Section 6705. To this end, Contractor shall submit for City’s review and approval a detailed plan showing the design of shoring, bracing, sloping, or other provisions to be made for worker protection from the hazard of caving ground during the excavation of such trench or trenches. If such plan varies from the shoring system standards, the plan shall be prepared by a registered civil or structural engineer.

3.8.6 Hazardous Materials and Differing Conditions. As required by California Public Contract Code Section 7104, if this Contract involves digging trenches or other excavations that extend deeper than four (4) feet below the surface, Contractor shall promptly, and prior to disturbance of any conditions, notify City of: (1) any material discovered in excavation that Contractor believes to be a hazardous waste that is required to be removed to a Class I, Class II or Class III disposal site; (2) subsurface or latent physical conditions at the site differing from those indicated by City; and (3) unknown physical conditions of an unusual nature at the site, significantly different from those ordinarily encountered in such contract work. Upon notification, City shall promptly investigate the conditions to determine whether a change order is appropriate. In the event of a dispute, Contractor shall not be excused from any scheduled completion date and shall proceed with all Work to be performed under the Contract, but shall retain all rights provided by the Contract or by law for making protests and resolving the dispute.

3.8.7 Underground Utility Facilities. To the extent required by Section 4215 of the California Government Code, City shall compensate Contractor for the costs of: (1) locating and 55452.01510\32977834.2
10 repairing damage to underground utility facilities not caused by the failure of Contractor to exercise reasonable care; (2) removing or relocating underground utility facilities not indicated in the construction drawings; and (3) equipment necessarily idled during such work. Contractor shall not be assessed liquidated damages for delay caused by failure of City to provide for removal or relocation of such utility facilities.

3.8.8 Air Quality. Contractor must fully comply with all applicable laws, rules and regulations in furnishing or using equipment and/or providing services, including, but not limited to, emissions limits and permitting requirements imposed by the California Air Resources Board (CARB). Although CARB limits and requirements are more broad, Contractor shall specifically be aware of their application to "portable equipment", which definition is considered by CARB to include any item of equipment with a fuel-powered engine. Contractor shall indemnify City against any fines or penalties imposed by CARB, or any other governmental or regulatory agency for violations of applicable laws, rules and/or regulations by Contractor, its subcontractors, or others for whom Contractor is responsible under its indemnity obligations provided for in this Agreement.

3.8.9 State Recycling Mandates. Contractor shall comply with State Recycling Mandates. Any recyclable materials/debris collected by the contractor that can be feasibly diverted via reuse or recycling must be hauled by the appropriate handler for reuse or recycling.

3.9 Completion of Work. When Contractor determines that it has completed the Work required herein, Contractor shall so notify City in writing and shall furnish all labor and material releases required by this Contract. City shall thereupon inspect the Work. If the Work is not acceptable to the City, the City shall indicate to Contractor in writing the specific portions or items of Work which are unsatisfactory or incomplete. Once Contractor determines that it has completed the incomplete or unsatisfactory Work, Contractor may request a reinspection by the City. Once the Work is acceptable to City, City shall pay to Contractor the Total Contract Price remaining to be paid, less any amount which City may be authorized or directed by law to retain. Payment of retention proceeds due to Contractor shall be made in accordance with Section 7107 of the California Public Contract Code.

3.10 Claims; Government Code Claim Compliance.

3.10.1 Intent. Effective January 1, 1991, Section 20104 et seq., of the California Public Contract Code prescribes a process utilizing informal conferences, non-binding judicial supervised mediation, and judicial arbitration to resolve disputes on construction claims of $375,000 or less. Effective January 1, 2017, Section 9204 of the Public Contract Code prescribes a process for negotiation and mediation to resolve disputes on construction claims. The intent of this Section is to implement Sections 20104 et seq. and Section 9204 of the California Public Contract Code. This Section shall be construed to be consistent with said statutes.

3.10.2 Claims. For purposes of this Section, “Claim” means a separate demand by the Contractor, after a change order duly requested in accordance with the terms of this Contract has been denied by the City, for (A) a time extension, (B) payment of money or damages arising from Work done by or on behalf of the Contractor pursuant to the Contract, or (C) an amount the payment of which is disputed by the City. A “Claim” does not include any demand for payment for which the Contractor has failed to provide notice, request a change order, or otherwise failed to follow any procedures contained in the Contract Documents. Claims governed by this Section may not be filed unless and until the Contractor completes all procedures for giving notice of delay or change and for the requesting of a time extension or change order, including but not necessarily limited to the change order procedures contained herein, and Contractor’s request for a change has been denied in whole or in part. Claims governed by this Section must be filed no later than 55452.01510\32977834.2
11 fourteen (14) days after a request for change has been denied in whole or in part or after any other event giving rise to the Claim. The Claim shall be submitted in writing to the City and shall include on its first page the following in 16 point capital font: “THIS IS A CLAIM.” Furthermore, the claim shall include the documents necessary to substantiate the claim. Nothing in this Section is intended to extend the time limit or supersede notice requirements otherwise provided by contract for the filing of claims, including all requirements pertaining to compensation or payment for extra Work, disputed Work, and/or changed conditions. Failure to follow such contractual requirements shall bar any claims or subsequent lawsuits for compensation or payment thereon.

3.10.3 Supporting Documentation. The Contractor shall submit all claims in the following format:

3.10.3.1 Summary of claim merit and price, reference Contract Document provisions pursuant to which the claim is made

3.10.3.2 List of documents relating to claim:
(A) Specifications
(B) Drawings
(C) Clarifications (Requests for Information)
(D) Schedules
(E) Other

3.10.3.3 Chronology of events and correspondence

3.10.3.4 Analysis of claim merit

3.10.3.5 Analysis of claim cost

3.10.3.6 Time impact analysis in CPM format

3.10.3.7 If Contractor’s claim is based in whole or in part on an allegation of errors or omissions in the Drawings or Specifications for the Project, Contractor shall provide a summary of the percentage of the claim subject to design errors or omissions and shall obtain a certificate of merit in support of the claim of design errors and omissions.

3.10.3.8 Cover letter and certification of validity of the claim, including any claims from subcontractors of any tier, in accordance with Government Code section 12650 et seq.

3.10.4 City’s Response. Upon receipt of a claim pursuant to this Section, City shall conduct a reasonable review of the claim and, within a period not to exceed 45 days, shall provide the Contractor a written statement identifying what portion of the claim is disputed and what portion is undisputed. Any payment due on an undisputed portion of the claim will be processed and made within 60 days after the public entity issues its written statement.

3.10.4.1 If City needs approval from its governing body to provide the Contractor a written statement identifying the disputed portion and the undisputed portion of the 55452.01510\32977834.2
12 claim, and the governing body does not meet within the 45 days or within the mutually agreed to extension of time following receipt of a claim sent by registered mail or certified mail, return receipt requested, City shall have up to three days following the next duly publicly noticed meeting of the governing body after the 45-day period, or extension, expires to provide the Contractor a written statement identifying the disputed portion and the undisputed portion.

3.10.4.2 Within 30 days of receipt of a claim, City may request in writing additional documentation supporting the claim or relating to defenses or claims City may have against the Contractor. If additional information is thereafter required, it shall be requested and provided pursuant to this subdivision, upon mutual agreement of City and the Contractor.

3.10.4.3 City’s written response to the claim, as further documented, shall be submitted to the Contractor within 30 days (if the claim is less than $50,000, within 15 days) after receipt of the further documentation, or within a period of time no greater than that taken by the Contractor in producing the additional information or requested documentation, whichever is greater.

3.10.5 Meet and Confer. If the Contractor disputes City’s written response, or City fails to respond within the time prescribed, the Contractor may so notify City, in writing, either within 15 days of receipt of City’s response or within 15 days of City’s failure to respond within the time prescribed, respectively, and demand an informal conference to meet and confer for settlement of the issues in dispute. Upon receipt of a demand, City shall schedule a meet and confer conference within 30 days for settlement of the dispute.

3.10.6 Mediation. Within 10 business days following the conclusion of the meet and confer conference, if the claim or any portion of the claim remains in dispute, City shall provide the Contractor a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed. Any payment due on an undisputed portion of the claim shall be processed and made within 60 days after City issues its written statement. Any disputed portion of the claim, as identified by the Contractor in writing, shall be submitted to nonbinding mediation, with City and the Contractor sharing the associated costs equally. City and Contractor shall mutually agree to a mediator within 10 business days after the disputed portion of the claim has been identified in writing, unless the parties agree to select a mediator at a later time.

3.10.6.1 If the Parties cannot agree upon a mediator, each Party shall select a mediator and those mediators shall select a qualified neutral third party to mediate with regard to the disputed portion of the claim. Each Party shall bear the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator.

3.10.6.2 For purposes of this section, mediation includes any nonbinding process, including, but not limited to, neutral evaluation or a dispute review board, in which an independent third party or board assists the Parties in dispute resolution through negotiation or by issuance of an evaluation. Any mediation utilized shall conform to the timeframes in this section.

3.10.6.3 Unless otherwise agreed to by City and the Contractor in writing, the mediation conducted pursuant to this section shall excuse any further obligation under Section 20104.4 to mediate after litigation has been commenced.

3.10.6.4 The mediation shall be held no earlier than the date the Contractor completes the Work or the date that the Contractor last performs Work, whichever is 55452.01510\32977834.2
13 earlier. All unresolved claims shall be considered jointly in a single mediation, unless a new unrelated claim arises after mediation is completed.

3.10.7 Procedures After Mediation. If following the mediation, the claim or any portion remains in dispute, the Contractor must file a claim pursuant to Chapter 1 (commencing with Section 900) and Chapter 2 (commencing with Section 910) of Part 3 of Division 3.6 of Title 1 of the Government Code. For purposes of those provisions, the running of the period of time within which a claim must be filed shall be tolled from the time the Contractor submits his or her written claim pursuant to subdivision (a) until the time the claim is denied, including any period of time utilized by the meet and confer conference or mediation.

3.10.8 Civil Actions. The following procedures are established for all civil actions filed to resolve claims subject to this Section:

3.10.8.1 Within 60 days, but no earlier than 30 days, following the filing or responsive pleadings, the court shall submit the matter to non-binding mediation unless waived by mutual stipulation of both parties or unless mediation was held prior to commencement of the action in accordance with Public Contract Code section 9204 and the terms of these procedures.. The mediation process shall provide for the selection within 15 days by both parties of a disinterested third person as mediator, shall be commenced within 30 days of the submittal, and shall be concluded within 15 days from the commencement of the mediation unless a time requirement is extended upon a good cause showing to the court.

3.10.8.2 If the matter remains in dispute, the case shall be submitted to judicial arbitration pursuant to Chapter 2.5 (commencing with Section 1141.10) of Title 3 of Part 3 of the Code of Civil Procedure, notwithstanding Section 1114.11 of that code. The Civil Discovery Act of 1986 (Article 3 (commencing with Section 2016) of Chapter 3 of Title 3 of Part 4 of the Code of Civil Procedure) shall apply to any proceeding brought under this subdivision consistent with the rules pertaining to judicial arbitration.

3.10.8.3 In addition to Chapter 2.5 (commencing with Section 1141.10) of Title 3 of Part 3 of the Code of Civil Procedure, (A) arbitrators shall, when possible, be experienced in construction law, and (B) any party appealing an arbitration award who does not obtain a more favorable judgment shall, in addition to payment of costs and fees under that chapter, also pay the attorney’s fees on appeal of the other party.

3.10.9 Government Code Claims. In addition to any and all contract requirements pertaining to notices of and requests for compensation or payment for extra work, disputed work, claims and/or changed conditions, Contractor must comply with the claim procedures set forth in Government Code sections 900 et seq. prior to filing any lawsuit against the City. Such Government Code claims and any subsequent lawsuit based upon the Government Code claims shall be limited to those matters that remain unresolved after all procedures pertaining to extra work, disputed work, claims, and/or changed conditions have been followed by Contractor. If no such Government Code claim is submitted, or if any prerequisite contractual requirements are not otherwise satisfied as specified herein, Contractor shall be barred from bringing and maintaining a valid lawsuit against the City. A Government Code claim must be filed no earlier than the date the work is completed or the date the Contractor last performs work on the Project, whichever occurs first. A Government Code claim shall be inclusive of all unresolved claims unless a new unrelated claim arises after the Government Code claim is submitted.

3.10.10 Non-Waiver. City’s failure to respond to a claim from the Contractor within the time periods described in this Section or to otherwise meet the time requirements of this 55452.01510\32977834.2
14 Section shall result in the claim being deemed rejected in its entirety. City’s failure to respond shall not waive City’s rights to any subsequent procedures for the resolution of disputed claims.

3.11 Loss and Damage. Except as may otherwise be limited by law, Contractor shall be responsible for all loss and damage which may arise out of the nature of the Work agreed to herein, or from the action of the elements, or from any unforeseen difficulties which may arise or be encountered in the prosecution of the Work until the same is fully completed and accepted by City.

In the event of damage proximately caused by an Act of God, as defined by Section 7105 of the Public Contract Code, the City may terminate this Contract pursuant to Section 3.17.3; provided, however, that the City needs to provide Contractor with only one (1) day advanced written notice.

3.12 Indemnification.

3.12.1 Scope of Indemnity. To the fullest extent permitted by law, Contractor shall defend (with counsel reasonably approved by City), indemnify and hold the City, its officials, employees, agents free and harmless from any and all claims, demands, causes of action, suits, actions, proceedings, costs, expenses, liability, judgments, awards, decrees, settlements, loss, damage or injury of any kind, in law or equity, to property or persons, including wrongful death, (collectively, “Claims”) in any manner arising out of, pertaining to, or incident to any alleged acts, errors or omissions, or willful misconduct of Contractor, its officials, officers, employees, subcontractors, consultants or agents in connection with the performance of the Contractor’s services, the Project or this Agreement, including without limitation the payment of all consequential damages, expert witness fees and attorneys’ fees and other related costs and expenses. Notwithstanding the foregoing, to the extent required by Civil Code section 2782, Contractor’s indemnity obligation shall not apply to liability for damages for death or bodily injury to persons, injury to property, or any other loss, damage or expense arising from the sole or active negligence or willful misconduct of the City or the City’s agents, servants, or independent contractors who are directly responsible to the City, or for defects in design furnished by those persons.

3.12.2 Additional Indemnity Obligations. In addition, Contractor shall pay and satisfy any judgment, award or decree that may be rendered against City or its officials, employees, agents as part of any such claim, suit, action or other proceeding. Contractor shall also reimburse City for the cost of any settlement paid by City or its officials, employees, agents as part of any such claim, suit, action or other proceeding. Such reimbursement shall include payment for City's attorney's fees and costs, including expert witness fees. Contractor shall reimburse City and its officials, employees, agents, for any and all legal expenses and costs incurred by each of them in connection therewith or in enforcing the indemnity herein provided.

Contractor's obligation to indemnify shall not be restricted to insurance proceeds, if any, received by the City, its officials, employees, agents.

3.13 Insurance. Contractor agrees to procure and maintain, at Contractor’s expense all insurance specified in Exhibit “H” attached hereto and by this reference incorporated herein.

Contractor shall require all subcontractors to carry the same policies and limits of insurance that the Contractor is required to maintain, unless otherwise approved in writing by the City.

3.14 Bond Requirements.

3.14.1 Payment Bond. If required by law or otherwise specifically requested by City in Exhibit “C” attached hereto and incorporated herein by reference, Contractor shall execute and provide to City concurrently with this Contract a Payment Bond in an amount required by the 55452.01510\32977834.2
15 City and in a form provided or approved by the City. If such bond is required, no payment will be made to Contractor until the bond has been received and approved by the City.

3.14.2 Performance Bond. If specifically requested by City in Exhibit “C” attached hereto and incorporated herein by reference, Contractor shall execute and provide to City concurrently with this Contract a Performance Bond in an amount required by the City and in a form provided or approved by the City. If such bond is required, no payment will be made to Contractor until the bond has been received and approved by the City.

3.14.3 Bond Provisions. Should, in City’s sole opinion, any bond become insufficient or any surety be found to be unsatisfactory, Contractor shall renew or replace the effected bond within (ten) 10 days of receiving notice from City. In the event the surety or Contractor intends to reduce or cancel any required bond, at least thirty (30) days prior written notice shall be given to the City, and Contractor shall post acceptable replacement bonds at least ten (10) days prior to expiration of the original bonds. No further payments shall be deemed due or will be made under this Contract until any replacement bonds required by this Section are accepted by the City. To the extent, if any, that the Total Contract Price is increased in accordance with the Contract, Contractor shall, upon request of the City, cause the amount of the bond to be increased accordingly and shall promptly deliver satisfactory evidence of such increase to the City.

If Contractor fails to furnish any required bond, the City may terminate the Contract for cause.

3.14.4 Surety Qualifications. Only bonds executed by an admitted surety insurer, as defined in California Code of Civil Procedure Section 995.120, shall be accepted. If a Californiaadmitted surety insurer issuing bonds does not meet these requirements, the insurer will be considered qualified if it is in conformance with Section 995.660 of the California Code of Civil Procedure, and proof of such is provided to the City.

3.15 Warranty. Contractor warrants all Work under the Contract (which for purposes of this Section shall be deemed to include unauthorized work which has not been removed and any non-conforming materials incorporated into the Work) to be of good quality and free from any defective or faulty material and workmanship. Contractor agrees that for a period of one year (or the period of time specified elsewhere in the Contract or in any guarantee or warranty provided by any manufacturer or supplier of equipment or materials incorporated into the Work, whichever is later) after the date of final acceptance, Contractor shall within ten (10) days after being notified in writing by the City of any defect in the Work or non-conformance of the Work to the Contract, commence and prosecute with due diligence all Work necessary to fulfill the terms of the warranty at its sole cost and expense. Contractor shall act sooner as requested by the City in response to an emergency. In addition, Contractor shall, at its sole cost and expense, repair and replace any portions of the Work (or work of other contractors) damaged by its defective Work or which becomes damaged in the course of repairing or replacing defective Work. For any Work so corrected, Contractor’s obligation hereunder to correct defective Work shall be reinstated for an additional one year period, commencing with the date of acceptance of such corrected Work.

Contractor shall perform such tests as the City may require to verify that any corrective actions, including, without limitation, redesign, repairs, and replacements comply with the requirements of the Contract. All costs associated with such corrective actions and testing, including the removal, replacement, and reinstitution of equipment and materials necessary to gain access, shall be the sole responsibility of Contractor. All warranties and guarantees of subcontractors, suppliers and manufacturers with respect to any portion of the Work, whether express or implied, are deemed to be obtained by Contractor for the benefit of the City, regardless of whether or not such warranties and guarantees have been transferred or assigned to the City by separate agreement and Contractor agrees to enforce such warranties and guarantees, if necessary, on behalf of the City.

In the event that Contractor fails to perform its obligations under this Section, or under any other 55452.01510\32977834.2
16 warranty or guaranty under this Contract, to the reasonable satisfaction of the City, the City shall have the right to correct and replace any defective or non-conforming Work and any work damaged by such work or the replacement or correction thereof at Contractor’s sole expense. Contractor shall be obligated to fully reimburse the City for any expenses incurred hereunder upon demand.

3.15.1 Warranty Bonds. At the time of completion of the project and prior to acceptance, a warranty bond in the amount of 25% of the contract price shall be required for a period of one (1) year after City recordation of Notice of Completion.

3.16 Employee/Labor Certifications.

3.16.1 Contractor’s Labor Certification. By its signature hereunder, Contractor certifies that he is aware of the provisions of Section 3700 of the California Labor Code which require every employer to be insured against liability for Worker’s Compensation or to undertake self-insurance in accordance with the provisions of that Code, and agrees to comply with such provisions before commencing the performance of the Work. A certification form for this purpose, which is attached to this Contract as Exhibit “D” and incorporated herein by reference, shall be executed simultaneously with this Contract.

3.16.2 Equal Opportunity Employment. Contractor represents that it is an equal opportunity employer and that it shall not discriminate against any employee or applicant for employment because of race, religion, color, national origin, ancestry, sex, age or other interests protected by the State or Federal Constitutions. Such non-discrimination shall include, but not be limited to, all activities related to initial employment, upgrading, demotion, transfer, recruitment or recruitment advertising, layoff or termination.

3.16.3 Verification of Employment Eligibility. By executing this Contract, Contractor verifies that it fully complies with all requirements and restrictions of state and federal law respecting the employment of undocumented aliens, including, but not limited to, the Immigration Reform and Control Act of 1986, as may be amended from time to time, and shall require all subcontractors and sub-subcontractors to comply with the same.

3.17 General Provisions.

3.17.1 City’s Representative. The City hereby designates the General Manager, or his or her designee, to act as its representative for the performance of this Contract (“City’s Representative”). City’s Representative shall have the power to act on behalf of the City for all purposes under this Contract. Contractor shall not accept direction or orders from any person other than the City’s Representative or his or her designee.

3.17.2 Contractor’s Representative. Before starting the Work, Contractor shall submit in writing the name, qualifications and experience of its proposed representative who shall be subject to the review and approval of the City (“′Contractor’s Representative”). Following approval by the City, Contractor’s Representative shall have full authority to represent and act on behalf of Contractor for all purposes under this Contract. Contractor’s Representative shall supervise and direct the Work, using his best skill and attention, and shall be responsible for all construction means, methods, techniques, sequences and procedures and for the satisfactory coordination of all portions of the Work under this Contract. Contractor’s Representative shall devote full time to the Project and either he or his designee, who shall be acceptable to the City, shall be present at the Work site at all times that any Work is in progress and at any time that any employee or subcontractor of Contractor is present at the Work site. Arrangements for responsible supervision, acceptable to the City, shall be made for emergency Work which may be required. 55452.01510\32977834.2
17 Should Contractor desire to change its Contractor’s Representative, Contractor shall provide the information specified above and obtain the City’s written approval.

3.17.3 Termination. This Contract may be terminated by City at any time, either with our without cause, by giving Contractor three (3) days advance written notice. In the event of termination by City for any reason other than the fault of Contractor, City shall pay Contractor for all Work performed up to that time as provided herein. In the event of breach of the Contract by Contractor, City may terminate the Contract immediately without notice, may reduce payment to Contractor in the amount necessary to offset City’s resulting damages, and may pursue any other available recourse against Contractor. Contractor may not terminate this Contract except for cause. In the event this Contract is terminated in whole or in part as provided, City may procure, upon such terms and in such manner as it may determine appropriate, services similar to those terminated. Further, if this Contract is terminated as provided, City may require Contractor to provide all finished or unfinished documents, data, diagrams, drawings, materials or other matter prepared or built by Contractor in connection with its performance of this Contract.

3.17.4 Contract Interpretation. Should any question arise regarding the meaning or import of any of the provisions of this Contract or written or oral instructions from City, the matter shall be referred to City’s Representative, whose decision shall be binding upon Contractor.

3.17.5 Anti-Trust Claims. This provision shall be operative if this Contract is applicable to California Public Contract Code Section 7103.5. In entering into this Contract to supply goods, services or materials, Contractor hereby offers and agrees to assign to the City all rights, title, and interest in and to all causes of action it may have under Section 4 of the Clayton Act (15 U.S.C. Section 15) or under the Cartwright Act (Chapter 2, commencing with Section 16700, of Part 2 of Division 7 of the Business and Professions Code) arising from purchases of goods, services, or materials pursuant to the Contract. This assignment shall be made and become effective at the time the City tender final payment to Contractor, without further acknowledgment by the Parties.

3.17.6 Notices. All notices hereunder and communications regarding interpretation of the terms of the Contract or changes thereto shall be provided by the mailing thereof by registered or certified mail, return receipt requested, postage prepaid and addressed as follows:

CONTRACTOR:

Robertson Industries, Inc.
2140 East Cedar Street
Tempe, AZ 85281
Attn: Vince Brantley, Sales Representative
CITY:

City of San Clemente
100 N Calle Seville
San Clemente, CA 92672
Attn: Samantha Wylie, Beaches, Parks & Recreation Director City of San Clemente
910 Calle Negocio
San Clemente, CA 92673
Attn: Laura Campagnolo, City Clerk
55452.01510\32977834.2
18 Any notice so given shall be considered received by the other Party three (3) days after deposit in the U.S. Mail as stated above and addressed to the Party at the above address. Actual notice shall be deemed adequate notice on the date actual notice occurred, regardless of the method of service.

3.17.7 Time of Essence. Time is of the essence in the performance of this Contract.

3.17.8 Assignment Forbidden. Contractor shall not, either voluntarily or by action of law, assign or transfer this Contract or any obligation, right, title or interest assumed by Contractor herein without the prior written consent of City. If Contractor attempts an assignment or transfer of this Contract or any obligation, right, title or interest herein, City may, at its option, terminate and revoke the Contract and shall thereupon be relieved from any and all obligations to Contractor or its assignee or transferee.

3.17.9 No Third Party Beneficiaries. There are no intended third party beneficiaries of any right or obligation assumed by the Parties.

3.17.10 Laws, Venue, and Attorneys’ Fees. This Agreement shall be interpreted in accordance with the laws of the State of California. If any action is brought to interpret or enforce any term of this Agreement, the action shall be brought in a state or federal court situated in the County of Orange, State of California.

3.17.11 Counterparts/Electronic Signature. This Contract may be executed in counterparts, each of which shall constitute an original. This Contract may be executed electronically with the same force and effect as an original ink signature. Bonds, if required, must be signed with original ink signatures and accompanied by notary acknowledgments.

3.17.12 Successors. The Parties do for themselves, their heirs, executors, administrators, successors, and assigns agree to the full performance of all of the provisions contained in this Contract.

3.17.13 [Reserved]

3.17.14 Solicitation. Contractor maintains and warrants that it has not employed nor retained any company or person, other than a bona fide employee working solely for Contractor, to solicit or secure this Contract. Further, Contractor warrants that it has not paid nor has it agreed to pay any company or person, other than a bona fide employee working solely for Contractor, any fee, commission, percentage, brokerage fee, gift or other consideration contingent upon or resulting from the award or making of this Contract. For breach or violation of this warranty, City shall have the right to terminate this Contract without liability.

3.17.15 Conflict of Interest. Contractor maintains and warrants that it has not employed nor retained any company or person, other than a bona fide employee working solely for Contractor, to solicit or secure this Agreement. Further, Contractor warrants that it has not paid nor has it agreed to pay any company or person, other than a bona fide employee working solely for Contractor, any fee, commission, percentage, brokerage fee, gift or other consideration contingent upon or resulting from the award or making of this Agreement. For breach or violation of this warranty, City shall have the right to rescind this Agreement without liability. For the term of this Contract, no official, officer or employee of City, during the term of his or her service with City, shall have any direct interest in this Contract, or obtain any present or anticipated material benefit arising therefrom. In addition, Contractor agrees to file, or to cause its employees or 55452.01510\32977834.2
19 subcontractors to file, a Statement of Economic Interest with the City’s Filing Officer as required under state law in the performance of the Work.

3.17.16 Certification of License.

3.17.16.1 Contractor certifies that as of the date of execution of this Contract, Contractor has a current contractor’s license of the classification indicated below under Contractor’s signature.

3.17.16.2 Contractors are required by law to be licensed and regulated by the Contractors’ State License Board which has jurisdiction to investigate complaints against contractors if a complaint regarding a patent act or omission is filed within four (4) years of the date of the alleged violation. A complaint regarding a latent act or omission pertaining to structural defects must be filed within ten (10) years of the date of the alleged violation. Any questions concerning a contractor may be referred to the Registrar, Contractors’ State License Board, P.O.

Box 26000, Sacramento, California 95826.

3.17.17 Authority to Enter Contract. Each Party warrants that the individuals who have signed this Contract have the legal power, right and authority to make this Contract and bind each respective Party.

3.17.18 Entire Contract; Modification. This Contract contains the entire agreement of the Parties with respect to the subject matter hereof, and supersedes all prior negotiations, understandings or agreements. This Contract may only be modified by a writing signed by both Parties.

3.17.19 Non-Waiver. None of the provisions of this Agreement shall be considered waived by either party, unless such waiver is specifically specified in writing.

3.17.20 City’s Right to Employ Other Contractors. City reserves right to employ other contractors in connection with this Project or other projects. [SIGNATURES ON NEXT PAGE]
55452.01510\32977834.2
20 IN WITNESS WHEREOF, the parties hereto have caused this Agreement to be duly executed on the respective dates set forth opposite of their signatures.

CITY OF SAN CLEMENTE
By:____________________________
Andy Hall, City Manager
ATTEST: Dated: _______________, 20____
_____________________________
CITY CLERK of the City of
San Clemente, California
APPROVED AS TO FORM:
_____________________________
Elizabeth A. Mitchell, City Attorney

APPROVED AS TO AVAILABILITY
OF FUNDING:
_____________________________
Finance Authorization

ROBERTSON INDUSTRIES,
INC., an Arizona corporation
(“CONTRACTOR”)

By:_____________________________
Thomas Discipio, CEO
Dated: __________________, 2025
By:_____________________________
William Stafford, CFO
Dated: __________________, 2025
55452.01510\32977834.2
21 EXHIBIT “A”

SERVICES / SCHEDULE
Continued on next page.

ROBERTSON INDUSTRIES, INC.

Corporate Office: 2140 East Cedar Street • Tempe, AZ 85281 Toll Free: (800) 858.0519 • Fax: (602) 340-0402
www.totturf.com
Description of Scope of Work:
• Provide Temp Fencing for duration of project.
• Remove and dispose of existing EWF materials.
• Remove and dispose of the existing ADA Concrete Ramp
• Furnish, install and properly compact an aggregate subbase for a new PIP surfacing installation • Furnish and install new IPEMA Certified PIP Rubberized Safety Surfacing per ADA, ASTM and IPEMA Standards.
• Approx 6,000 Total SF (4600 SF at 8’ / 1400 SF at 4’) • Color to be 50% Std. EPDM TBD mixed with 50% Black - Aromatic • Includes a Basic 3-Color(s) Design – TBD - Although Not Required • Includes a 5-Year Warranty
TOTAL COST: $144,595
Other Notes:

I. Addendums 1-3 are acknowledged.

II. Additional Options available via change order(s):
a. Less Black in color mix
b. Extensive design work
c. Tot Turf Advantage under Slide Exits and Swing Bays
d. Upgrade the Urethane to Aliphatic
Proposal # 23-38886
Robertson Industries, Inc.
2140 E. Cedar Street
Tempe, AZ 85281
(800) 858-0519
FAX: (602) 340-0402
www.totturf.com
Date Issued: 11/19/2024
Project Name: San Gorgonio Park - City of San Clemente
Address: 400 Linda Ln, San Clemente, CA 92672
Contact: Steve Fritzsch
Phone: +19492459292
Email: [email protected]
Sales Representative
Name: Vince Brantley
Phone: +17149048219
Email: [email protected]
PRICE EXPIRES: 02/18/2025

PRODUCT NAME DESCRIPTION QTY
UNIT
PRICE
TOTAL
Site Prep Opt. 1 - Site Prep Work per below 1 $40,850 $40,850.00 TotTurf Poured in Place Safety
Surfacing
Opt. 1 - Install IPEMA Certified Poured in Place Safety Surfacing
1 $103,745 $103,745
GRAND TOTAL $144,595
CONTRACT TYPE: Regular WAGE TYPE: State Prevailing UNION: No CA GRANT: No DETAILED SCOPE:

CA DIR Registration # 1000002700 - CA Contractors Lic. #667261 C/61 - D/12 PRICE BASED ON:

Prevailing Wages and apprenticeship requirements when applicable.

There are NO Union or Labor Agreements requirements included in our proposal. (add 15% if required) Performance and/or Payment Bonds are Not Included (add 2% if required) Proposal based on drawings, details and specifications provided by customer Includes addendum(s) 1-3

PROJECT OVERVIEW
Replace EWF with PIP Rubber Surfacing
Over Entire Playground
Approx 6000 Total SF (4600 SF at 8’ / 1400 SF at 4’)
50/50 Std. EPDM and Black Aromatic
3 color basic design
Includes a 5-Year Warranty
Customer responsible for securing the area which includes 72 hours of curing time.

EXCLUSIONS:

Curbing/Borders, Drainage and Equipment Installation
Temp Fencing and overnight Security unless noted above
HIC/Gmax Testing
INSTALLATION NOTES:

Material ordering lead time is 8-12 weeks for premium colors Typical Scheduling Lead Time is 3-4 Weeks
Staging and Access to be within 100 LF and no stairs unless noted above COMMENTS:

SECURITY:

SIGNATURE: DATE:

Printed Name: Title:

Company Name:

Address:

BILLING Contact Name:

BILLING Email: Phone: Fax:

Issue all POs, Contracts, and payments to ROBERTSON INDUSTRIES, INC.

Send ALL completed forms back to your Sales Representative:

Vince Brantley: [email protected]
CLICK HERE TO PAY WITH A CREDIT CARD: PAY NOW!
Proposal # 23-38886
TERMS & CONDITIONS:

1. Quote is based on the information provided here within and is subject to change based on final installation unless otherwise indicated in writing.

Any changes or additions to this proposal will affect pricing.

2. Changes to the proposed scope not agreed to here within or separately in writing may result in additional charges (change order). Work cannot commence until Change Order(s) are fully executed.

3. ANY additional site work not included here within, including sub base, is the responsibility of the owner.

4. Job site access must be at a maximum of 25' for trucks and mixer, with no stairs. Irrigation, sprinkler, and/or water systems must be shut off 24 hours before install and remain off until 24 hours after the installation has completed.

5. Charges for downtime/stand-by may be assessed in the event that installation is delayed due to the site not being ready as scheduled or if installation is interrupted for reasons other than those related to weather or general public emergencies.

6. Security during install and upon completion is the responsibility of the owner, unless specified otherwise in Project Scope.

7. Excess material at the job site upon completion is property of Robertson Industries, Inc., unless otherwise noted here within.

8. Installations scheduled after 90 days of proposal acceptance may be subject to price adjustments.

9. Scheduling and crew deployment is subject to local weather conditions.

10. Warranty will NOT be issued unless "Completion Sheet" is signed.

11. All projects over $2,500.00 will be issued a preliminary lien.

Force Majeure: No Party to this Agreement shall be responsible for any delays or failure to perform any obligation under this Agreement due to acts of God, outbreaks, epidemic/pandemic or the spreading of disease or contagion strikes or other disturbances, including, without limitation, war, insurrection, embargoes, governmental restrictions, acts of governments or governmental authorities, and any other cause beyond the control of such party. During an event of force majeure, the Parties' duty to perform obligations shall be suspended.

PROPOSAL ACCEPTANCE: I agree to the scope and details as provided for the above mentioned proposal as well as the terms outlined in this agreement. I am duly authorized to approve and accept this proposal as stated.

CONTRACT to follow PURCHASE ORDER to follow ACCEPT THIS AS OUR AGREEMENT PAYMENT TERMS:

Payment is due upon receipt, and payment may be made via Check, ACH or Credit Card. Customers requesting credit terms may be required to submit a credit application and/or a deposit. Credit applications can be obtained from your sales representative. If credit terms are extended, payment terms are due Net 30 days from date of invoice.

Please attach a copy of your TAX EXEMPT CERTIFICATE if you or your company is claiming tax exemption.

TOTAL PURCHASE AMOUNT: $144,595
Scheduling/Site Contact: Steve
Phone: +19492459292 Email: [email protected]
Estimated Install Date:

Dec

INITIALS
Robertson Industries, Inc: 2140 East Cedar Street, Tempe, AZ 85281 ~ (800) 858-0519, FX: (602) 340-0402 AZ: ROC091920, CLASS L-05 ~ CA: 667261, CLASS C/61 D/12 ~ NV: 42331, CLASS C25 C40 CALIFORNIA PWC REGISTRATION NUMBER: 1000002700 (DIR#)
The PlayCore Surfacing Division Includes: Robertson Industries, Inc, Sports Surface Specialties, Rubber Designs and American Recycling Center
EXHIBIT “B”

PLANS AND SPECIFICATIONS
Continued on next page.
12/2022
SECTION 32 18 16.13

PLAYGROUND RESILIENT SURFACING

TOTTURF POURED IN PLACE (PIP) EPDM
PART 1 - GENERAL

1.01 WORK SCOPE
A. Furnish labor, material, and equipment necessary to install the poured-in-place, resilient surfacing system as shown on the drawings and specified herein. a. Work shall include, but not be limited to the following: layout; excavation; backfill; furnishing and installing of base material; furnishing and installing of poured-inplace, resilient surfacing and all other incidental work to provide a complete resilient surfacing system.
b. Poured in place playground surfacing shall consist of a polyurethane binder mixed with recycled rubber, which will make up the attenuation cushion layer. The attenuation cushion layer is capped with EPDM granules, mixed with a polyurethane binder creating the Wear Course.
c. Surfaces shall comply with ADA and CPSC guidelines as well as ASTM Standards.

Manufacturer is to be certified by IPEMA, a third-party testing organization for playground surfaces and equipment.

1.02 PERFORMANCE REQUIREMENTS
A. Area Safety: Poured in place within playground use zones shall meet or exceed the performance requirements of the CPSC, ADA and Fall Height Test ASTM F1292-18.

The surface must yield both a peak deceleration of no more than 200 G-max and a Head Injury Criteria (HIC) value of no more than 1,000 for a head-first fall from the highest accessible portion of play equipment being installed as shown on drawings.

IPEMA certification is required. (ASTM F1292-18, section 15 The laboratory test used to determine critical fall height shall have been conducted on surfacing material samples identical in design, materials, components, and thickness and manufactured as the installed playground surface).

Accessibility: NOTE: Children’s outdoor play areas shall be in compliance with the Uniform Federal Accessibility Standards (UFAS) FED-STD-795 and the Architectural B.
©2020 Robertson Recreational Surfaces, A PlayCore Company. 800-858-0519 www.totturf.com All rights reserved. All information contained is subject to change without notice. 1 12/2022
and Engineer Instructions (9AEI) Design Criteria.

C. The requirements of the Americans with Disabilities Act. Accessibility Guidelines (ADAAG) 28 CFR Part 36 that provide equal or greater accessibility than the requirements of UFAS must also be met in children’s outdoor play areas.

D. Poured in place surfaces intended to serve as accessible paths of travel for persons with disabilities shall be firm, stable and slip resistant, and shall meet the requirements of ASTM F 1951-14 and ASTM F1292-18.

1.03 APPLICABLE STANDARDS
A. ASTM International
B. ASTM D2047- Standard test method for determining the static coefficient of friction of ceramic tile and other like surfaces by the horizontal dynamometer pull meter method.

This standard replaces ASTM C1028.

C. ASTM D412 – Standard test methods for vulcanized rubber and thermoplastic rubbers and thermoplastic elastomers-tension.

D. ASTM D624 - Standard test method for tear strength of conventional vulcanized rubber and thermoplastic elastomers.

E. ASTM D2859 – Standard test method for flammability of finished textile floor covering materials.

F. ASTM E303 – Standard test method for measuring surfacing frictional properties using the British Pendulum tester.

G. ASTM F1292-18 – Standard specification for impact attenuation of surface systems under and around playground equipment.

ASTM F1951 – Standard specification for determination of accessibility of surface systems under and around playground equipment.

H.
©2020 Robertson Recreational Surfaces, A PlayCore Company. 800-858-0519 www.totturf.com All rights reserved. All information contained is subject to change without notice. 2 12/2022

1.04 Poured in place surfaces shall be manufactured and installed by trained, experienced company employees or certified installers who have successfully completed the “Certified Installers Training Program” required by Robertson Industries Inc.

1.05 SUBMITTALS: THE FOLLOWING SHALL BE SUBMITTED
A. The Contractor shall submit a complete set of the material submittals, as required, including manufacturer’s name and address, specific trade names, catalog and model numbers, illustrations and descriptive material, and samples of the proposed material for this project clearly marked as to proposed items for approval by the Owner’s representative.

B. Products submitted as equal must include hard copies of manufactures written specifications, warranty, purchase and use of materials.

C. Manufacturer’s descriptive data and installation instructions.

D. Manufacturer’s details showing depths of wear course and sub-base materials, anchoring systems and edge details.

E. Upon request, a listing of at least five installations where products similar to these proposed for use have been installed and have been in service for a minimum period of three years. The list shall include owner or purchaser, address of installation, date of installation, contact person, and phone number.

F. A signed statement by an authorized official certifying that the surfacing system meets the requirements of ASTM F1292-18, section 15 for a head-first fall from the highest accessible portion of the specified playground equipment.

G. A signed statement from the manufacturer of the poured in place surfacing attesting that all materials under this section shall be installed only by the Manufacturer’s Trained Installers.

A Certificate of Insurance shall be provided by the Manufacturer for poured in place surfacing for use as playground safety surfacing, covering general and product liability, of not less than $1,000,000 for each occurrence, $2,000,000 general aggregate, with an excess/umbrella liability of $25,000,000. The issuing underwrite shall be AA rated.

H.

I. IPEMA Certification mandatory
©2020 Robertson Recreational Surfaces, A PlayCore Company. 800-858-0519 www.totturf.com All rights reserved. All information contained is subject to change without notice. 3 12/2022

1.06 Delivery, Storage and Handling: Materials and equipment shall be delivered and stored in accordance with the manufacturer’s recommendations.

1.07 Project Site Conditions: Poured in Place surfacing must be installed on a dry subsurface, with no prospect of rain within the initial drying period, and within the recommend temperature range of the manufacturer. Installation in weather condition of extreme heat, cold (less than 55°F), and/or high humidity may affect cure time, and the structural integrity of the final product. Immediate surrounding sites must be reasonably free of dust conditions or this could affect the final surface look.

1.08 Sequencing and Scheduling: Poured in Place surfacing shall be installed after all playground equipment, shade structures, signs and any other items that will be within the surfacing area. Coordinate with General Contractor.

1.09 Surface installation coordinated by manufacturer representative.

1.10 Warranty: Poured in Place surface shall maintain required impact attenuation characteristics and be guaranteed against defects in workmanship AND material for a limited five-year period or as specified and agreed upon per alternate contract.

Warranty will be specific to maintenance requirements and performance standards of completed product. Warranty is void if not installed by Manufacturers Trained and Certified Poured in Place Surfacing Installers.

1.11 Testing: NOTE: Critical Fall Height Four feet through 10 feet have been tested in accordance with Section 15 – Critical Fall Height Test Procedure of ASTM F1292-18.

PART 2 – PRODUCTS

2.01 Safety surfacing shall consist of both recycled and synthetic materials meeting the requirements of this specification. The type of safety surfacing shall be Robertson Industries Inc., manufactured and installed by Robertson Industries Inc., or it’s Certified Installers. Telephone: (800) 858-0519.

2.02 PRODUCT SCOPE
A. Poured in Place Surface: The poured in place surface shall consist of recycled rubber mixed with a polyurethane binder, then capped with EPDM granules mixed with an aliphatic binder or aromatic binder.
©2020 Robertson Recreational Surfaces, A PlayCore Company. 800-858-0519 www.totturf.com All rights reserved. All information contained is subject to change without notice. 4 12/2022
B. It shall consist of a uniform material manufactured in such a way that the top portion meets the requirements specified herein for wear surface.

C. The type of safety surfacing shall be a poured-in-place system and shall be indicated on the drawings.

2.03 ATTENUATION CUSHION LAYER SECTION
A. Impact attenuation cushion layer consists of these materials; recycled styrene butadiene rubber (SBR) and/or cryogenic crumb rubber and/or pre consumer postindustrial reclaimed scrap rubber adhered with a 100% solids polyurethane binder to form a resilient porous material.

B. Strands of SBR may vary from 0.5 mm – 2.0 mm in thickness by 3.0 mm – 20 mm in length.

Chunk Premium Black Rubber Granules are 5/8” granules: This rubber is pre-consumer, post-industrial, reclaimed rubber, granulated through a 5/8” screen and contains less than 2% dust.

C.

D. SBR Crumb Rubber (5-9 Mesh) using sieve analysis ASTM D5644 with a fiber content of .1% or less mixed in.

E. Binder shall be between 7-12% of the total weight of the material and shall provide 100 % coating of the particles.

The attenuation cushion layer shall be compatible with the wear course and must meet requirements herein for impact attenuation.

F.

2.04 WEAR COURSE
A. Wear course shall consist of Ethylene Propylene Diene Monomer (EPDM) granules with polyurethane binder formulated to produce an even, uniform, seamless surface.

Installation of surfacing shall be seamless (unless otherwise agreed upon by owner).

B. EPDM shall be peroxide cured with an EPDM content of 26% and shall include a processing aid to prevent hardness with 26% poly content to maintain dynamic testing characteristics, weatherization and UV stability.
©2020 Robertson Recreational Surfaces, A PlayCore Company. 800-858-0519 www.totturf.com All rights reserved. All information contained is subject to change without notice. 5 12/2022
C. ASTM D2240 (Shore A) hardness of 55-65, not less than 26 percent rubber hydrocarbons.

D. Size of EPDM granules shall be 1-4mm across. Binder shall be not less than 20% of total weight of rubber used in the wear surface and shall provide 100% coating of the particles.

E. Thickness of wear course shall be a minimum .5” (12.7 mm).

F. The wear course shall be porous.

2.05 BINDER
A. No Toluene Diphenyl Isocyanate (TDI) shall be used.

B. No filler materials shall be used in urethane such as plasticizers and the catalyzing agent shall contain no heavy metals.

C. Weight of polyurethane shall be no less than 8.5 lbs. /gal (1.02 Kg/1) and no more than

9.5 lbs. /gal (1.14 Kg/1).

D. Manufacturer is permitted to modify the type of urethane required to match extreme weather conditions. Substitutions must be equal to or exceed original quality.

2.06 TOT TURF ADVANTAGE INSERTS
A. Insert – Thermal Plastic Vulcanized angular granules with a (Shore A) hardness of 65° A ± 5 and particle size between .5-1.5 mm shall be used.

B. Thickness of the Insert shall be .5”
C. Insert shall be porous.

D. Aliphatic urethane to be used as a binder.
©2020 Robertson Recreational Surfaces, A PlayCore Company. 800-858-0519 www.totturf.com All rights reserved. All information contained is subject to change without notice. 6 12/2022
E. Location –Insert to be installed under swings, swing bays, slide exits (unless otherwise noted in drawings). Customer to approve location of wear mat inserts.

F. Standard Color .5-1.5mm to be used. Colors include four standard colors: Terra Cotta Red, Blue, Green, and Beige.

G. Size: Swing bay use locations shall have TPV Inserts inclusive of all outside bay structure poles. Singular swings and slide exits shall be 4’x4’x.5” in thickness.

2.07 MATERIALS
A. Wear Course - EPDM Granules
Manufacturers: EPDM Granules
Robertson Industries Inc. (800) 858-0519
Playground Area
As Distributed by:

Location Used:

B. Attenuation cushion layer – Robertson Industries Inc. Shredded and/or Chunk Rubber
As Distributed by:

Location Used:

Robertson Industries Inc. (800) 858-0519
Playground Area
C. Binder – Aromatic VORAMER MR Products
Manufacturer:

As Distributed by:

Location Used:

DOW Chemical
Robertson Industries Inc. (800) 858-0519
Playground Area
D. Binder – Aromatic Urethane Stobielast® S 1020
Manufacturer:

As Distributed by:

Location Used:

Stockmeier Urethanes, USA, Inc.

Robertson Industries, Inc. (800) 858-0519
Playground Area
E. Binder – Aliphatic Urethane Premium, Non-Ambering
Manufacturer:

As Distributed by:

Location Used:

Accella Polyurethane Systems
Robertson Industries Inc. (800) 858-0519
Playground Area
F. Chunk Premium Black Rubber Granules
Manufacturer: American Recycling Center, Inc. (989) 725-5100 655 Wabassee Drive
©2020 Robertson Recreational Surfaces, A PlayCore Company. 800-858-0519 www.totturf.com All rights reserved. All information contained is subject to change without notice. 7 12/2022
Owosso, MI 48867
Robertson Industries Inc. (800) 858-0519
Playground Area
As Distributed by:

Location Used:

PART 3 – EXECUTION

3.01 SITE PREPARATION
A. Finished Grade/Slope: Verify that finished elevations or adjacent areas are as indicated on the architectural or site plans, that the appropriate sub-grade elevation has been established for the safety surface to be installed, and that the subsurface has been installed per architectural, site or equipment plans while meeting accessibility and use zones requirements.

B. Aggregate Sub Base: Tolerance of aggregate sub-base shall be within .5” in depth.

Verify that aggregate sub-base has been fully compacted. Per ADA Guidelines:
compacted Aggregate sub-base – 4” of .75” minus irregular stone with fines compacted to 95% in 2” watered lifts.

C. Concrete Sub-Base: Tolerance of concrete or bituminous sub-base shall be with .125” (3.0 mm) in 10’ (3050 mm). Per ADA Guidelines: Concrete a minimum of 3’ – 4’ at a minimum 2500 PSI. Concrete must cure for 7 days prior to application of attenuation cushion layer. Concrete must cure 21 days if wear course is to be applied directly to concrete surface. If poured in place surfacing is installed, verify that the concrete subbase has cured (all areas appear white in color usually at 7 days) and that all concrete curing compounds and other deleterious substances that might adversely affect adhesion have been removed. Surface shall be clean and dry.

D. Asphalt Sub-Base: Asphalt cure time requires 21-28 days. Once the new asphalt has cured, it must be pressure washed prior to the surfacing being installed. The contractor shall be responsible for flooding the pad to ensure proper slope and tolerance. Any areas holding enough water to cover a flat nickel shall be patched prior to the arrival of our installation crews.

E. Drainage: Verify that sub-surfacing drainage, if required, has been installed to provide positive drainage.
©2020 Robertson Recreational Surfaces, A PlayCore Company. 800-858-0519 www.totturf.com All rights reserved. All information contained is subject to change without notice. 8 12/2022

3.02 INSTALLATION
A. Poured in Place Surfacing: Components of the poured in place surfacing shall be mixed on site in a rotating tumbler to ensure components are thoroughly mixed and are in accordance with manufactures recommendations. Installation of surfacing shall be seamless up to 2,000 square feet per day. Material shall cover all foundations and fill around all elements penetrating the surface.

B. Attenuation Cushion Layer: Whenever practical, attenuation cushion layer of surfacing material shall be installed in one continuous pour on the same day of up to 2,000 square feet. When a second pour is required, step the seam (see detail) and fully coat the step of the previous work with polyurethane binder to ensure 100% bond with new work. Apply adhesive in small quantities so that new attenuation cushion layer can be placed before the adhesive dries.

C. Wear Course: Wear course must be quality peroxide cured EPDM granules. wear surface shall be bonded to attenuation cushion layer. If necessary, additional primer will be used between the attenuation cushion layer and wear course. Apply adhesive to attenuation cushion layer in small quantities allowing the wear course to be applied before adhesive dries. Surface shall be hand troweled to a smooth, even finish. Expect continuous and seamless up to 2,000 square feet per day (contact sales representative for seamless in excess of 2,000 square feet). Where seams are required due to color change, size or adverse weather, a step configuration will be constructed to maintain wear course integrity. The edge of initial pour shall be coated with adhesive and wearing surface mixture shall be immediately applied. Pads with multiple seams are encouraged to include a topcoat of urethane before being placed into use. Butt joint seams are not acceptable except for repairs. Under special conditions and with Owners written approval seams may be permitted in same color pad. Consult with Manufacturer for specific applications.

Perimeter: For installations over existing concrete, the perimeter shall be saw cut to provide a keyway 1” deep x 1” wide, or formed during the pour, with surfacing rolled down into the void. Primer adhesive must be applied to all sides of the void. When connecting to a concrete curb or border, the inside vertical edge shall be primed with adhesive and the final 2” of the attenuation cushion layer shall be tapered to allow the wear surface material to be 1.5”– 2” thick where it joins the concrete.

Asphalt: When installing over new asphalt, a curb or other type of border is recommended around the entire pad to separate the new surface from other ground materials. Primer adhesive must be applied to the inside vertical edge of the border before poured in place surface installation.

D.

E.
©2020 Robertson Recreational Surfaces, A PlayCore Company. 800-858-0519 www.totturf.com All rights reserved. All information contained is subject to change without notice. 9 12/2022
F. Asphalt: When installing over existing asphalt, a keyway cut of 1” deep by 1” side for the poured in place to taper into and terminate with required ADA slope.

G. Thickness: Construction methods such as the use of measured screeds or guides shall be employed to ensure that the full depth of specified surfacing material is installed.

Surfacing system thickness throughout the playground equipment use zone shall be as required to meet the impact attenuation requirements specified herein.

H. Clean Up: Manufacturer installers shall work to minimize excessive adhesive on adjacent surfaces or play equipment. Spills of excess adhesive shall be promptly cleaned.

I. Protection: The safety surface shall be allowed to fully cure in accordance with Manufacturer’s instructions. The surface shall be protected by the owner from all traffic during the curing period of at a minimum of 48 hours or as instructed by the Manufacturer.

J. Manufacturer Services: For poured in place safety surfacing, a Manufacturer’s representative who is experienced in the installation of playground safety surfacing shall be provided. The representative shall supervise the installation to ensure that the system meets the impact attenuation requirements as specified herein.

3.03 SITE AREA CLEAN UP
The site shall be kept clean and free of tools, trash, and debris and installation materials daily. Products may be stored on site during installation with appropriate protective measures and approval by the Owner’s representative.

END OF SECTION
©2020 Robertson Recreational Surfaces, A PlayCore Company. 800-858-0519 www.totturf.com All rights reserved. All information contained is subject to change without notice. 10

← All documents from this meeting