City of San Clemente
Proposed
Inland Residential and Rancho
San Clemente Industrial Runoff
Treatment Project
CPS-Mod™ & GITS™ Full Capture System Devices &
ARS-CL™ Curb-Opening Screens
Prepared For:

Orange County Transportation Authority
Measure M2, Tier 1 Grant Application
Environmental Cleanup Program (ECP)

OC GO PROJECT X
600 South Main Street
Orange, CA 92863-1584
(714) 560-5363
DĂLJϱ, 2025
Prepared By:

Niki Beach
City of San Clemente
910 Calle Negocio
San Clemente, CA 92673
$WWDFKPHQW4

TABLE OF CONTENTS

1. COVER 1

2. TABLE OF CONTENTS 2

3. APPLICATION
A. SECTION I: General Project Information 3
B. SECTION II: Detailed Project Information & Scoring 5 C. SECTION III: Additional Project Details 13

4. ATTACHMENTS 15
A. Calculations & Support Documentation for Question #2 and #3 16 B. Detailed Project Estimate & Warranty 22
C. Location Maps &
Project Site Photos
29 46
D. Detailed Project Schedule 76
E. Design Drawings & Product Information
Trash & Debris Capture and Design Flow
79 99
F. City Council Resolution 101
G. Project Drainage Areas, Priority Land Uses, BMP Locations, KMZ files 106 H. Vendor and Installer Qualifications
Reference Letters
Orange County Local Small Business Certificate
DBE & MBE Certifications
109
112
124
125
2 PROJECT X
2025 Tier 1 Call for Projects Application for Funding
2025 Project X Tier 1 Application Page 1 of 12

APPLICATION INSTRUCTIONS
Local Agencies applying for Project X ECP funds are required to complete and submit this application. Any projects not in compliance with the CTFP Guidelines will not be eligible for funding.

SECTION I: General Project Information
Applicant Information
Agency: City of San Clemente
Project Title: Inland Residential and Rancho San Clemente Industrial Runoff Treatment Project Device Type(s) &
Quantity:

G2 CPS-Mod FCS (119 devices), Grated Inlet Trash Screens FCS (4 devices) & ARS-CL systems (264 device screens in 119 CBs).

Project Manager: Niki Beach
Phone: (949) 361-8354
Email: [email protected]
Proposed Funding Summary
Total Project Cost: $705,000 Local Match:
(Cash Only, 20% minimum) $141,000
M2 ECP Funds
Request: $564,000
Project is Part of a
Larger Construction
Effort:

No
Project Readiness & Schedule
City Council Approval: (of Resolution) 5/20/2025
Design & Permitting (If Applicable) N/A
Award of Contract (Authorization by City Council) 10/15/2025 Construction/Installation (Start and Completion) Start: 11/17/2025 Completion: 1/28/2026
Application Checklist

YES N/A
A Environmental Documentation (As Applicable) ܆ 9
B Detailed Project Estimate 9 ܆
C Location Maps & Project Site Photos 9 ܆
D Detailed Project Schedule 9 ܆
E Design/Concept Drawings 9 ܆
F City Council Resolution 9 ܆
G Project Drainage Area(s), Priority Land Use(s), and BMP Location(s) shapefiles/KMZs 9 ܆
H Preliminary agreements with joint and/or third-party entities (As Applicable) ܆ 9

PROJECT X
2025 Tier 1 Call for Projects Application for Funding
2025 Project X Tier 1 Application Page 2 of 12
Project Description – Describe the project location and the Tier 1 type improvements proposed. If the project is included in an existing Integrated Water Management Plan, please provide details on why it was included. Use additional pages as needed.

The City’s proposed project is a continuation of trash capture devices located in priority land use areas, with this project focused on medium to high density residential communities inland of the I-5 freeway which passes through San Clemente parallel to the coastline. The project also includes a small section of industrial land uses at the southern terminus of the inland arterial Avenida La Pata. In total, the project will retrofit 123 catch basins (CBs) east of the I-5, which is an important but sometimes overlooked potential source of trash and bacterial pollution to the Pacific Ocean, no more than 3 miles from the most inland catch basin in this project.

This project location captures trash and debris on 284 acres of Priority Land Use (PLU), in primarily medium and high-density residential areas which are dispersed among lower density planned community developments, as well as a relatively remote portion of the City’s industrial land uses, which include light manufacturing and a regional animal shelter. This Rancho San Clemente Industrial Park is also adjacent to the City’s rather large Steed Park, which although not a PLU, may also be a source of trash which could migrate or be deposited in nearby streets within the industrial park. The project will fill in an important gap in the management of trash and related bacteria generated from streets within the Poche/Prima Deshecha watershed as well as the City’s southern coastal canyons, including some drainage to the largely undeveloped San Mateo Creek watershed.

The City proposes installing 3 types of devices in the City’s MS4 catch basins (CBs) to capture trash and debris.

The devices are designed, fabricated, and installed by G2 Construction, Inc. and are: 1) CPS-Mod™ connector pipe screen Full Capture System (FCS), 2) GITS™ grated inlet trash screen FCS in drop-inlets, and 3) ARSCL™ curb-opening screen. City staff believe G2’s CPS-Mod, ARS-CL and GITS systems will stop transportation related pollutants from entering our stormwater system and will improve water quality by meeting Clean Water Act standards for local waterways and beaches. G2’s storm water devices have a long track record of success in stopping pollutants and debris from entering CBs, the patented CPS-Mod and GITS devices are Full Capture System certified by the State Water Board, and their devices were very highly ranked by Orange County (OC) Public Works on both of their last two RFPs for Trash devices.

The project spans portions of the City’s Prima Deshecha watershed, which is largely developed and conveys stormwater to a concrete box channel, and its Coastal Canyons watersheds including the larger regional San Mateo Creek watershed, which are relatively undeveloped and drain to mostly natural canyons and creeks before connecting to the Pacific Ocean. In the northern reach of the project area, the City’s storm drain system directs water into the Prima Deshecha Canada Creek which runs parallel to the Camino de los Mares inland of the I-5, ultimately discharging to Poche Beach at the City’s northern boundary, and is Clean Water Action Section 303(d) listed for Indicator Bacteria, which can be correlated with trash loading. The San Clemente Coastal Canyons and San Mateo Creek are not currently 303(d) listed but are still subject to trash loading from the City’s higher density land uses east of El Camino Real and the I-5, and also its eastern industrial developments that drain to San Mateo Creek’s natural tributary canyons. See included maps. The targeted residential and industrial areas, along with the adjacent and heavily traveled corridors such as Camino de los Mares, attract high volumes of people and their vehicles, and even the inland areas have significant proximity and connectivity to I-5 and its on/off ramps.

The G2 CPS-Mod, ARS-CL and GITS devices are our selected Tier 1 BMPs because they provide two levels of pollutant filtration. The entire width of the CB curb-opening will be protected using the multiple-screen ARS-CL system. All 123 locations will have a CPS-Mod or GITS full capture system device installed in front of each discharge pipe to prevent everything 5mm or larger from escaping the CB and flowing downstream.

This project location and these Tier 1 type devices are selected because this project will deliver the greatest water quality improvement for the waters, land, and people of San Clemente available. No environmental documentation is required for this project. Attachments A-H are included.

PROJECT X
2025 Tier 1 Call for Projects Application for Funding
2025 Project X Tier 1 Application Page 3 of 12
SECTION II: Detailed Project Information & Scoring

1. Describe the need for the selected BMP(s), including nexus to transportation pollutants, and detail the benefits to water quality the BMP(s) will achieve. (up to 15 Points) The City of San Clemente needs the CPS-Mod™, ARS-CL™ and GITS devices for this project for multiple reasons. First, G2’s proprietary devices are custom designed, fabricated and fitted to the City’s existing MS4 catch basins (CBs) without the need for new concrete structures or excavation. These CBs are the best place to capture trash and pollutants flushed by rain events, wind or automobiles from roadways, properties, facilities, sidewalks, driveways and parking lots. All 123 catch basins for this project are in Priority Land Use (PLU) areas with a direct nexus to transportation pollutants.

Second, the ARS-CL™ curb-opening screen’s patented design stops pollutants ¾” or greater from entering the CBs during dry weather, and City street sweeping collects these pollutants. The top-hinge ARS-CL with G2’s CamLock Technology™ works with all of the City’s curb-opening inlets. Pollutants that make it into the catch basin are stopped by the second line of defense. The CPS-Mod™ have a patented design that stop 100% of particles 5mm or larger from exiting the CB and flowing downstream. This is also true of the GITS™ and both are certified Full Capture Systems by the California Water Board.

Third, all 3 devices are custom fabricated from 304 stainless steel and installed to fit each unique CB. The City believes installing these G2 devices is our best opportunity to stop the highest amount of transportationgenerated pollutants before they enter our stormwater system and travel downstream into the nearby Pacific Ocean. These BMPs also come with a 10-year warranty. G2’s inlet devices have a long track record of success in stopping pollutants and debris, and their devices were very highly ranked by Orange County (OC) Public Works on both of their two RFPs for Trash and Debris Capture Devices. The City will use G2 Construction’s Master Agreement with OCPW to get volume pricing discounts.

The project screens will be installed in key areas with land uses well documented to contribute to transportation-generated pollution, including suburban residential and industrial workplace destinations that are frequently driven to and from (See Project Description and Attached Maps). Notably, the COVID-19 pandemic increased the number of San Clemente residents who telecommute part or full-time and have more opportunities to drive to and from their homes to pick up a meal or run an errand between working hours and contribute to incidental trash generation.

The devices will benefit water quality through significant capture of pollutants flowing to 123 CBs. This will result in a reduction of trash and pollutants flowing into the Prima Deshecha Canada Creek and to the San Clemente Coastal Canyons and San Mateo Creek watersheds. San Clemente’s shoreline is 303(d) listed for Indicator Bacteria at Prima Deshecha Canada’s Poche Beach outlet. In both the Prima Deshecha Canada and Coastal Canyons and San Mateo Creek watersheds, the project will reduce visible pollutants, as well as the microscopic bacteria that often accompany trash, in the City’s creeks and beaches, while also reducing the harmful impacts to fish and wildlife of trash that makes its way to the ocean.

The City’s coastal water quality will also benefit from receiving significantly fewer loads of metals such as copper, lead and zinc from vehicles driving along these busy transportation routes and to concentrated commercial districts. Additionally, since the G2 CPS-Mod and GITS devices are approved Full Capture Systems they will also meet the State Trash Amendment requirement for these catch basins.

In summary, this project will install G2’s CPS-Mod™ and ARS-CL™ in the same 119 CBs; and GITS™ in 4 grated drop-inlet CBs. All 123 of these CBs will become Full Capture System compliant. In total, 264 unique ARS-CL screens will be installed in these 119 CBs. The project will cover 284 acres of PLU land. We have selected G2 Construction’s devices because they have been highly effective within the City and are approved by OCTA ECP and OCPW. These devices are the best value for the City’s water quality needs.

PROJECT X
2025 Tier 1 Call for Projects Application for Funding
2025 Project X Tier 1 Application Page 4 of 12

2. Based on information provided by the applicant, a cost/benefit calculation will be conducted to compare the total project cost to the area of priority land uses treated by the proposed BMP(s). Please complete the table below: (up to 16 points):

BMP(s)
Type 1 Type 2, etc.

Type(s) of BMP(s) proposed:

FULL CAPTURE
CPS-Mod™ &
GITS™ by G2
ARS-CL™
Curb-Opening
Screens by G2
Number of each BMP type: 123 264
Total drainage area(s) contributing to each BMP type: 284.8 279.4 Total
Drainage area(s) that is/are considered Priority Land Uses*: 284.8 279.4 284.8 Total Project Cost: $705,000
Cost/Benefit ($/ac of priority land uses): $2,475
Project Score (to be completed by OCTA):

Click to enter
text.
*Refer to City General Plans for general land use distribution/coverage information. Refer to the Statewide Trash Provisions for a complete definition of Priority Land Uses (e.g. high density residential, industrial, commercial, mixed urban, public transportation stations).

3. Pollutant Reduction Benefits: Project benefits will be based on treatment capacity and BMP type.

Applicant to provide the calculations used to determine the following scores: (up to 12 points):

Line Factor Points
Available Multiplier Line Score
A Fractional percent of 1-yr, 1-hr event peak flowrate treated by the BMP(s) 0 to 1 3 3 B Fractional percent of 85th percentile, 24-hr design event that is treated by the BMP(s) 0 to 1.5 3 4.5
C
BMP Multiplier:
0 to 1 6 0
•0 points if BMP is not low-impact development (LID) or treatment control •1/3 point for high-capacity systems
•2/3 point for filters/biofilters
•1 point for zero-discharge BMPs
Project Score: 7.5
Scoring Equation (Max 12 points): (Ax3) + (Bx3) + (Cx6) Calculations may be provided on a separate sheet

PROJECT X
2025 Tier 1 Call for Projects Application for Funding
2025 Project X Tier 1 Application Page 5 of 12

4. How effectively will the proposed project deal with the more visible forms of pollutants, such as litter and debris? (up to 10 points)
The City’s proposed project will have a very significant impact reducing visible forms of pollutants from entering the water systems and showing up in the waters downstream and on Orange County beaches. This project will utilize two very strong lines of defense that work to capture visible pollution before travelling downstream.

1.) The CPS-Mod™ and GITS™ Full Capture Systems will stop 100% of visible pollutants that get past an existing ARS or through a grate and enter the catch basin. The CPS-Mod and GITS devices will stop everything 5mm and larger from exiting the catch basin and entering the connector pipe and waterways. These pollutants such as plastic (small pieces of bottles, cups, bags, containers, straws, mylar, Styrofoam, etc.), cigarette butts, and more are screened from the water before ever entering the connector pipe and waterways.

2.) The ARS-CL™ curb-opening screens are designed to stop the most visible pollutants from ever entering our catch basins. The ARS-CL stops everything ¾” or larger, such as takeout food waste, Aluminum cans, glass and plastic bottles, and even leaf litter from entering the catch basin. The City’s street sweeping program then removes this debris on a prompt and regular basis. Also, the ARS screens close off the entire curb opening of each catch basin and physically prevent people from consciously or unconsciously putting trash into the catch basin. This acts as an excellent deterrent to polluters and reminds everyone that trash and pollutants should never be discarded into the storm drain system.

Through this two-prong approach, the City’s proposed CPS-Mod, GITS, and ARS-CL project is the most effective solution readily available for stopping the most visible forms of pollutants from entering the storm water system. Installation of these catch basin screens is also a very cost-effective retrofit project to prevent trash from traveling downstream, and their benefits continue to increase proportional to the number of devices that can be installed throughout the City.

The City of San Clemente also believes that educating the public is an important nonstructural BMP for protecting the coastal environment. When our residents see installed ARS-CL screens, they not only serve as a physical barrier for trash, but also promote the understanding that trash and other items should not be allowed into catch basins. The City anticipates that this visual reminder, especially in residential neighborhoods, will play a long-term role in reducing the amount of pollution that people generate, ultimately reducing the amount of capture and related maintenance required in its storm drain inlets.

PROJECT X
2025 Tier 1 Call for Projects Application for Funding
2025 Project X Tier 1 Application Page 6 of 12

5. What other BMP types were considered for this project? Why was the proposed BMP chosen? (5 points) The City has considered many alternative BMPs before selecting G2’s products.

1. Hydrodynamic separators have been installed in some coastal areas of the City. These are expensive projects ($500K+) that are required to be approved annually by the City Council during the budget process for the Capital Improvement Program. In order to install these large devices, the City needs to identify a location where there is an existing easement and where access to the site is feasible for a Vactor truck to conduct its cleaning. It was determined that no site was available for a separator that would capture debris from the area proposed in this project. And, due to the cost for purchase and installation of these products, the cost per acre for treatment is quite high.

2. The City has existing hanging filter baskets in some catch basins along the main thoroughfares, but they ultimately need to be removed and replaced because they are very difficult to clean and do not meet full capture equivalency per Water Board requirements. The ARS-CL devices in this project will solve much of the existing maintenance problems going forward since the larger debris can be collected by City maintenance or street sweeping vehicles prior to entering the catch basin vault, thus reducing the amount of debris that collects in the vault and needs to be vacuumed during maintenance. Meanwhile, the CPS-Mod units will function more effectively within the vault and meet full capture equivalency that is lacking in many of the other filter baskets.

3. Permeable pavement was considered, but these areas of the City were built many years ago and a retrofit of paved streets, especially including an increased maintenance schedule, would prove to be prohibitively expensive. Also, this alternative would not capture all visible pollutants, and would not be feasible in several portions of the project with privately owned streets that nonetheless drain to City storm drain inlets.

4. The installation of bioretention basin(s) continue to be reviewed City-wide, but presently, there is no suitable location in the City’s watersheds that would treat a similar PLU area due to lack of city property ownership, city easements, and the constraints of the already built out areas. Retention basins are desirable but are expensive and take significant time and cost to design, approve, and install. Therefore, the cost per location, as well as a lack of available space for placement, would make this BMP very difficult to pursue.

The City selected the CPS-Mod, GITS, and ARS-CL for this project because they deliver greater value than other existing BMP options, have a proven record of efficacy, are easy to install inside existing catch basins, and can be installed very quickly with minimal disruption to traffic or other City services. Effectiveness and affordability for these custom-fabricated and installed devices allows for a high number of catch basins to be retrofitted with significant pollutant reduction that is realized immediately following installation.

PROJECT X
2025 Tier 1 Call for Projects Application for Funding
2025 Project X Tier 1 Application Page 7 of 12

6. Provide information on proposed BMP performance efficiency and/or effectiveness, including pollutant capture, storage capacity, flow capacity, etc. (up to 6 points) According to G2 Construction, the designer and manufacturer of the CPS-Mod™, GITS™, and ARS-CL™ patented devices, these storm water screens have proven effective over the past 18 years, with over 30 thousand devices installed in California.

Performance Effectiveness:

CPS-Mod – 100% reduction in litter, debris and pollutants that are 5mm or larger. State Water Board certified as trash Full Capture System.

GITS – 100% reduction in litter, debris and pollutants that are 5mm or larger. State Water Board certified as trash Full Capture System.

ARS-CL prevents 85-95% of debris, trash, and pollutants from ever entering the waterway system from jurisdictional streets.

Storage Capacity:

CPS-Mod – 44 cubic feet (average; size of catch basin to the height of the CPS screen) GITS - 5 cubic feet (average)
ARS-CL – Blocks entry into CB. Unlimited capacity, but does not “store.” Collected by street sweeping or other street maintenance events.

Filtered Flow Rates in CFS (Cubic Feet per Second):

CPS-Mod: 4.2 sqft screen = 4.06 CFS @ 5mm;
CPS-Mod: 7.0 sqft screen = 6.76 CFS @ 5mm;
CPS-Mod: 11.0 sqft screen = 10.63 CFS @ 5mm;
GITS : 7.0 sqft screen = 6.76 CFS @ 5mm;
ARS-CL: 3.5’ = 1.45 CFS; 5’ = 2.13 CFS; 7’ = 2.93 CFS; 10’ = 4.31 CFS; 14’ = 6.02 CFS; 21’ = 8.99 CFS; 28’ = 12.08 CFS @ ¾” filter.

In 2005-2006 Laguna Hills participated in the Sulphur Solution Project with the City of Laguna Niguel. One key component of the project was to install automatic retractable screens (ARS) in catch basins across the City. In 2006, following installations, the City’s catch basins were cleaned and the trash, debris, soil and “muck” was measured and the data was analyzed.

Data analysis showed that ARS retrofitted catch basins had a 70% drop in the volume of trash and an 81% drop in the volume of soil/muck/sediment, as compared with similar catch basins with ARS screens.

Average volume in catch basins without ARS was 4.7 cubic feet, while average volume with ARS was 1.4 cubic feet, with a net reduction of 3.3 cubic feet per catch basin. The City’s street sweeper collected and removed debris prior to entry into the catch basin. This data was submitted to the San Diego Regional Water Quality Control Board that year.

The G2 ARS-CL is a more effective design, higher quality, and longer lasting than the 1st generation ARS installed in 2005-2006. It was tested by LACDPW at their BMP testing site at San Gabriel dam. A total of 10 tests were performed including water flow rates ranging from 0.25 to 5.0 CFS. The ARS-CL passed testing at all flow ranges and the Design Division concluded the device met all requirements for performance and safety. This product is approved throughout California.

G2 Construction’s ARS-CL is customized during fabrication to fit each specific catch basin, which is of particular benefit in a city like San Clemente with older and irregularly sized existing infrastructure. The ARS screens prevent all objects ¾” or larger from entering the catch basin and the current model ARS-CL prevents 85-95% of debris, trash, and pollutants from ever entering the stormwater collection system from City streets.

PROJECT X
2025 Tier 1 Call for Projects Application for Funding
2025 Project X Tier 1 Application Page 8 of 12

7. Project Readiness: How long after OCTA Board of Directors approval (anticipated August 2025) will the project be operational (select one)? (up to 6 points):
܈> 4 Months
6 Points
܆ 4 – 8 Months
4 Points
܆ 8 – 12 Months
2 Points
܆ < 12 Months
1 Point

8. Will the project provide any secondary benefits beyond water quality improvements (i.e., water-use efficiency, public awareness, flood control, recreation, habitat, sustainability)? (up to 5 points) Secondary benefits beyond water quality improvements include:

1. The protection of sensitive riparian habitats, aquatic and terrestrial life, local fisheries, and bird populations, among other natural resources, will benefit from the project’s CPS-Mod, GITS, and ARS-CL BMPs because they capture trash that can be mistaken for food or can break down and become microplastics embedded in the marine food chain. The project would also help prevent plastics and other trash from entangling or being swallowed by birds and other native wild animals.

2. Recreationally, San Clemente is very popular for surf and water sports. This project will improve the water quality and reduce dangerous and unsightly trash along both San Clemente City beaches and San Clemente and San Onofre State Beaches, known internationally -- and recently selected to host the 2028 Olympics -- for competitive surfing. Health and human safety protections for children and adults playing on the beach and in the water, and for surfers and their spectators, are a clear benefit of the reduction of sharp objects (metal, broken glass, etc.), cigarette butts, and bacteria on local beaches.

3. Similarly, the economic benefits of tourism are critical to the City’s vitality. The continued reduction of trash and pollution on beaches within or adjacent to the City will continue to grow the economy through a positive public image and increased tourism. San Clemente’s business community has historically depended on its clean beaches to attract residents, visitors, tourists and even surf contest sponsors to this particular stretch of shoreline. Without projects such as this proposal, persistent reports of trash or bacterial pollution at beaches may send visitors to coastal vacation or surf spots elsewhere.

4. As with increasing tourism, property values (and related tax revenues to the City) may also be increased in areas exhibiting ARS-CL and CPS-Mod stainless steel device installationss because of how they demonstrate the City’s efforts in environmental protection, and the related sense of civic pride, to existing owners and prospective buyers.

5. Public awareness that stormwater catch basins need to be protected from trash and pollutants is important. The City’s installation of ARS-CL and CPS-Mod throughout the City shows the public that maintaining a stormwater collection system to protect water quality is a very high priority. Seeing an ARS-CL in particular ca. Similarly, observations of trash recently trapped in front of an ARS-CL can encourage citizens to make more sustainable choices in purchasing disposable items, such as by avoiding single-use plastics. The project will make pollution less of an out-of-sight, out-of-mind problem.

6. Sustainable and proper functioning of the storm drain system -- with less trash and bacteria causing problems -- protects local neighborhoods, as well as stream beds and shorelines, from flooding or unnatural ponding that could be caused by obstructions in the conveyance system, and safeguards the quality of soils beneath and adjacent to the system, also reducing the introduction of pollutants into the terrestrial human and natural environments.

PROJECT X
2025 Tier 1 Call for Projects Application for Funding
2025 Project X Tier 1 Application Page 9 of 12

9. What is the methodology for measuring pollutant reduction before and after the BMP is implemented? How frequently will monitoring and performance assessment occur? (up to 10 points) The City’s methodology for measuring pollutant reduction and monitoring performance is planned as follows:

1. Trash and debris removed during the City’s catch basin cleanings will be measured and documented.

New data will be compared to prior data and the City will be able to quantify the effectiveness of the CPS-Mod or GITS and ARS-CL devices. The results can be reported to the Regional Water Quality Control Board as a part of the NPDES annual report.

2. The City street maintenance staff and utilities crew supervisor will visually observe the amount of pollutants and debris that build up in front of the ARS-CL screens. Staff will drive the streets routinely and provide input and feedback about the amount of pollution. Special attention will be paid to the installed locations before, during and after storms. When excess amounts are found in front of the ARS, or are reported by the public or other department staff, they will be promptly removed by street maintenance staff or the City’s contracted street sweepers.

3. Visual inspections of every CPS-Mod, ARS-CL, and GITS installed will be conducted at a minimum twice per year (an increase from once per year), and observations about trash and debris levels in front will be made.

4. Discussions and interviews with street sweeping and collections crews regarding the quantity and types of trash found in front of catch basins will continue to help build understanding of the types and quantity of pollution being intercepted. This will also help identify specific catch basins or areas that accumulate more amounts of debris. This information can help develop education programs that target specific areas where more debris is observed.

PROJECT X
2025 Tier 1 Call for Projects Application for Funding
2025 Project X Tier 1 Application Page 10 of 12

10. Provide an operations and maintenance plan for the lifespan of the proposed project. Include schedule of inspections, cleaning, removal and disposal of pollutants, repairs, etc. (up to 15 points) The City’s operations and maintenance plan for the proposed CPS-MOD, GITS, and ARS-CL screens includes regular inspections, cleanings, and maintenance for their ten-year lifespan. Services performed by the City will include:

1. Inspections of the CPS-Mod, GITS, and ARS-CL devices will be conducted a minimum of twice annually by the City’s collections maintenance team or outside contractor. Inspections will include visually checking both devices and mechanically checking the ARS. The locking system will be inspected annually as required by the manufacturer’s warranty. The inspection will either document any issues that need to be addressed, or verify the device(s)’ working order.

2. If repairs are needed after being identified during inspection and the City cannot easily fix, then these issues will be documented. The City will take photos, and provide a description and location. G2 Construction will evaluate the information and repair under their warranty.

3. Cleaning the front ARS-CL screen will at a minimum be performed weekly for arterial highways and every two weeks for residential streets by the City’s contracted street sweepers. As required, the ARS screens will be kept clean and not have mud or debris built up in from of it. Street sweeping is an approved cleaning method for ARS devices to ensure they function appropriately, in addition to helping effectively remove trash and objects before they enter the storm drain system.

4. The CPS-Mod and GITS in each catch basin will be cleaned three (3) times annually, as needed, and is typically scheduled in October prior to the rainy season, January and May (or prior to significant storm events). The ARS, CPS, and GITS screens are also cleaned off during this removal of trash and debris. The non-hazardous materials are collected and disposed of in the City’s street sweeping debris waste bin, which is considered by the County of Orange as a limited volume transfer station.

Any hazardous material will be contained and disposed of properly.

5. After each significant storm event, the City’s collections staff or contractor will visually inspect the ARS devices from the exterior of the catch basin to check for open, damaged, or clogged screens, as recommended by the manufacturer. This identifies any issue that may have been caused by the storm, and before the next street sweeping event. Crews will remove debris that may be preventing the ARS from fully closing and locking. The screen will be returned to its default locked position. If any problems are identified, then any fixes that are easy and will follow the manufacturer’s operations and maintenance guidelines will be completed. This will be the standard procedure after each significant storm event.

6. The City will request service under – and/or eventually, outside of -- warranty from G2 Construction as needed, in order to keep all installed devices on this project working effectively. This ensures that the City’s installation of full-capture systems, as required by the State, have a long-term and lasting benefit to water quality.

PROJECT X
2025 Tier 1 Call for Projects Application for Funding
2025 Project X Tier 1 Application Page 11 of 12

11. BONUS: Is the proposed local match over the 20% minimum cash match requirement? If yes, enter match rate here. (0.5 points for each 5% overmatch, up to 5 points) N/A
Note: In-kind services are not eligible as local match
SECTION III: Additional Project Details
Match Sources
Other Grants: Non-M2 competitive grants may be used as match. Any grants used as match must be dedicated to the project for match credit to be received. Please list the name and amount of match sources.

N/A
Supplanting or Replacing Funds
ECP funds are designed to supplement, not supplant, existing water quality programs. Proposed projects must improve and not replace existing pollution reduction efforts by an eligible party. Please clarify that the proposed project will not be supplanting any existing water quality programs or other obligations.

This proposed City project will not supplant any existing water quality program. This project will improve water quality and reduce pollution, and it will not replace any existing pollution reduction effort by the City or other any eligible party.

Joint Applicant Information (if applicable)
See program guidelines for details on joint applicant applications and enter the details below.

PROJECT X
2025 Tier 1 Call for Projects Application for Funding
2025 Project X Tier 1 Application Page 12 of 12
Local Agency: N/A Local Agency: Click to enter text.

Project Manager: Click to enter text. Project Manager: Click to enter text.

Phone: Click to enter text. Phone: Click to enter text.

Email: Click to enter text. Email: Click to enter text.

Additional Comments
Click here to enter text.

I hereby certify that the information provided herein this form is accurate and consistent with accompanying documentation. I further certify that the above information has been approved by Council resolution and that awarded funds will not be used outside of their intended purpose.

Niki Beach
Name (Print) Signature Date

May 5, 2025

ATTACHMENTS
A. Calculations & Support Documentation for Question # 2 and # 3 B. Detailed Project Estimate & Warranty
C. Location Maps & Project Site Photos
D. Detailed Project Schedule
E. Design Drawings
F. City Council Resolution
G. Project Drainage Areas, Priority Land Uses, BMP Location & KMZ Files H. Vendor and Installer Qualifications
15 A. Calculations & Support Documentation
for Questions #2 and #3
16 OCTA ECP PROJECT X - CALCULATIONS for Questions #2 and #3 Support Documentation City of San Clemente
Type 1 Type 2
Type(s) of BMP(s) proposed

FULL CAPTURE
CPS-Mod™ &
GITS™ by G2
ARS-CL™ CurbOpening Screens
by G2
Number of each BMP type: 123 264
Total drainage area(s) contributing to each BMP Type: (Acres) 284.8 279.4 Total Drainage area(s) considered Priority Land Uses: (Acres) 284.8 279.4 284.8 Total Project Cost $705,000
Cost / Benefit ($/acres of priority land uses): $2,475
Project Score
Line Factor Points Multiplier Line Score
A Fractional percent of 1-yr, 1-hr event peak flowrate
treated by the BMP(s) 1.0 3 3
B Fractional percent of 85th percentile, 24-hr design event that is treated by the BMP(s) 1.5 3 4.5
C BMP Multiplier 0
Project Score: 7.5
Analysis for G2 Construction's CPS-Mod™,
GITS™, and ARS CL™ devices

2. Cost / Benefit Calculation for priority land uses treated by proposed BMP(s). *Per City General Plans for land use and Statewide Trash Provisions (high density residential, industrial, commercial, mixed urban, public transportation stations).

BMP(s)

3. Pollutant Reduction Benefit: Treatment capacity and BMP Type:
17 OCTA ECP PROJECT X - CALCULATIONS for Questions #2 and #3 Support Documentation City of San Clemente

PROJECT SUMMARY
Land Use: Residential Medium-High Density, Industrial, & CommercialBMP: CPS-Mod™, GITS™, and ARS CL™ by G2 Construction, Inc. 123 FULL CAPTURE SYSTEM CPS-Mod™ or GITS™264 ARS-CL™ Curb-Opening Screens 284.8 Acres Total Drainage Area
284.8 Acres Priority Land Use Area

77.5% Land use impervious (est.)
Total project Cost:/ PLU Acre
PLU Land Use
Residential - Med-High DensityIndustrial - HeavyIndustrial - LightPublic ParkingCommercial Analysis for G2 Construction's CPS-Mod™, GITS™, and ARS CL™ devices $705,000
$2,475
18 OCTA ECP PROJECT X - CALCULATIONS for Questions #2 and #3 Support Documentation City of San Clemente Analysis for G2 Construction's CPS-Mod™, GITS™, and ARS CL™ devices

3.A. Fractional percent of 1-yr, 1-hr event peak flowrate treated by the BMPs: Mixed Flow/Volume BMPS BMP 1: FULL CAPTURE SYSTEM CPS-Mod™ & GITS™ by G2 BMP 2: ARS-CL™ Curb Opening Screens by G2 NOTE: ARS-CL filtration is in addition to Full Capture System filtration.

Criteria Value Unit Criteria Value Unit
C= (0.75 x imp) + 0.15 = 0.73125 C= (0.75 x imp) + 0.15 = 0.73125 i= 1-yr, 1hr intensity= 0.423 in/hr i= 1-yr, 1hr intensity= 0.423 in/hr Land Imperviousness 77.5% Land Imperviousness 77.5%
Acres 284.8 Acres 279.4
G2 Construction's CPS-Mod or GITS 123 screens G2 Construction's ARS-CL 264 screens A= Avg/ contrib. DA per CPS= 2.3 ac A= Avg/ contrib. DA per ARS screen= 1.1 ac Avg. 1-yr, 1-hr peak flowrate (Q) = 0.7 cfs Avg. 1-yr, 1-hr peak flowrate (Q) = 0.3 cfs CPS-Mod & GITS design flowrate average this project 5.2 cfs G2 ARS-CL design flowrate average this project 1.45 cfs Fractional percent of 1-yr, 1-hr event filtered by BMP (Calc). Max= 100% 727% Fractional percent of 1-yr, 1-hr event filtered by BMP (Calc). Max= 100% 443% Score (Max=1.0) = Score (Max=1.0) =
Q3.A Weighted Score:

All calculations based on OCTA Workshop presentation.
1 1
1 19
OCTA ECP PROJECT X - CALCULATIONS for Questions #2 and #3 Support Documentation City of San Clemente Analysis for G2 Construction's CPS-Mod™, GITS™, and ARS CL™ devices

3.B. Fractional percent of 85th percentile, 24-hr design event that is treated by the BMP Calculate the design flowrate equivalent to design volume:BMP 1: FULL CAPTURE SYSTEM CPS-Mod™ & GITS™ by G2 BMP 2: ARS-CL™ Curb Opening Screens by G2 NOTE: ARS-CL filtration is in addition to CPS-Mod filtration. Always in combo.

Criteria Value Unit Criteria Value Unit
C= (0.75 x imp) +.15 = 0.73125 C= (0.75 x imp) +.15 = 0.73125 i= equivalent BMP design intensity= 0.26 in/hr i= equivalent BMP design intensity= 0.26 in/hr Land Imperviousness 77.5% Land Imperviousness 77.5%
A= 284.8 ac A= 279.4 ac
Design Storm Flowrate (Q) = 54 cfs Design Storm Flowrate (Q) = 53 cfs G2 CPS-Mod & GITS design flowrate avg this project 5.2 cfs G2 ARS-CL design flowrate average this project 1.45 cfs Total FCS design flowrate (from manufacturer)= 641 cfs Total ARS-CL design flowrate (from manufacturer)= 383 cfs Fractional percent of 85th percentile, 24 hr event, that could be treated. 1183% cfs Fractional percent of 85th percentile, 24 hr event, that could be treated. 721% cfs Max Available Points Max Available PointsAll calculations based on OCTA Workshop presentation.

1.5 1.5
20 OCTA ECP PROJECT X - CALCULATIONS for Questions #2 and #3 Support Documentation City of San Clemente

3.A. Precipitation Intensity
Precipitation Intensity "i": 0.423 (0.355-0.507)
Source: NOAA Precip Frequency Estimates: CA

3.B. Design Storm Depth
Design Capture Storm Depth = .85"
Source:

Use multiplier to calculate the design storm intensity equivalent to the design storm depth:

Time of Concentration (Tc)
5 Min Modeled for High Intensity
Tc Multiplier 0.26 in/hrFraction of design storm entering the BMP 100% Equivalent BMP Design Intensity 0.26 in/hr
Analysis for G2 Construction's CPS-Mod™, GITS™, and ARS CL™ devices

3.B. Fractional percent of 85th percentile, 24-hr design event that is treated by the BMP 21 B. Detailed Project Estimate & Warranty
22 Lic. #801253 - A, C8, C60
1352 E. Borchard Ave.

Santa Ana, CA 92705
714.748.4242
Customer: City of San Clemente Date: 4/30/2025
910 Calle Negocio Quote No 250430-SC
San Clemente, CA 92673
Eric H. Taylor
Contacts: Niki Beach By: Eric H. Taylor
949.361.8354 VP, Bus Dev, G2 Construction, Inc.

[email protected] 714.679.2550
[email protected]
Products: G2 CPS-Mod™ patented connector pipe screen, 304 stainless steel, custom fab & install G2 GITS™ grated inlet trash screen, 304 stainless steel, custom fab & install G2 ARS-CL™ patented curb-opening screens, 304 stainless steel, custom fab & install Count
City
SWINL #
Land Use
Street Name Nearest X-Street Lat Long
Grates
Traffic
ControlG2 BMP 1: Full
Capture
System
G2 BMP 2:

Curb-Opening
Screen
ARS-CL™
Screens
1 10458 PLU Camino De Los Mares Portico Del Sur 33.46792 -117.6360 4 TC CPS-Mod™ ARS-CL™ -14x 4 2 10457 PLU Portico Del Sur Camino De Los
Mares 33.46795 -117.6362 TC CPS-Mod™ ARS-CL™ -10 2
3 10456 PLU Portico Del Sur Camino De Los
Mares 33.46792 -117.6363 TC CPS-Mod™ ARS-CL™ -10 2
4 10453 PLU Portico Del Sur Camino De Los
Mares 33.46897 -117.6367 TC CPS-Mod™ ARS-CL™ -07 2
OCTA ECP Tier 1 Grant Application '25-26
DBE, MBE & SBE Certified
QUOTE
City of San Clemente
CPS-Mod ™, GITS™, and/or ARS-CL™ for 123 PLU Catch Basins Inland Residential and Rancho San Clemente
Industrial Runoff Treatment Project
G2 will install 123 Full Capture Systems and 264 unique ARS-CL™ screens. Costs for required traffic control and catch basin cleaning are included.

OCPW / OCTA Master Agreement for Trash and Debris Capture Devices (Good until for 180 Days)

DESCRIPTION
G2 Construction (G2) proposes to custom fabricate and install our patented devices in 123 City catch basins (CBs).

The installed Full Capture System device counts are 119 CPS-Mod™ connector pipe screens and 4 GITS™ grated inlet trash screens systems. G2 will also fabricate and install 264 ARS-CL™ curb-opening screens in 119 of these City catch basins.

All 123 locations are in priority land use (PLU) areas: Residential Medium-High Density and Industrial primarily, and also Public Facilities.

This proposal utilizes the G2's master purchase agreement with OCPW / OCTA Master Agreement for Trash and Debris Capture Devices for the City of San Clemente's OCTA ECP Project X grant application for 2025-26. The City is eligible for this piggyback contract like all Orange County cities, which guarantees the best product, service, and pricing. 1 of 5 23
5 10452 PLU Calle Portada Portico Del Sur 33.46898 -117.6365 TC CPS-Mod™ ARS-CL™ -07 2 6 12792 PLU Calle Mandarina Calle Portada 33.46890 -117.6362 CPS-Mod™ ARS-CL™ -14x 4 7 10455 PLU Calle Vecino Calle Mandarina 33.46820 -117.6357 CPS-Mod™ ARS-CL™ -10 2 8 10454 PLU Calle Vecino Calle Mandarina 33.46815 -117.6356 CPS-Mod™ ARS-CL™ -10 2 9 10450 PLU Calle Clasico Calle Carmelita 33.46886 -117.6356 CPS-Mod™ ARS-CL™ -05 1 10 10451 PLU Calle Clasico Calle Carmelita 33.46881 -117.6359 CPS-Mod™ ARS-CL™ -05 1 11 10441 PLU Avenida Fortuna Portico Del Sur 33.46978 -117.6372 CPS-Mod™ ARS-CL™ -10 2 12 10442 PLU Avenida Fortuna Portico Del Sur 33.46989 -117.6373 CPS-Mod™ ARS-CL™ -10 2 13 10443 PLU Avenida Fortuna Portico Del Sur 33.46954 -117.6377 CPS-Mod™ ARS-CL™ -07 2 14 10444 PLU Avenida Fortuna Portico Del Sur 33.46923 -117.6378 CPS-Mod™ ARS-CL™ -07 2 15 10445 PLU Calle Prospero Avenida Fortuna 33.46936 -117.6376 CPS-Mod™ ARS-CL™ -07 2 16 10446 PLU Calle Prospero Avenida Fortuna 33.46925 -117.6376 CPS-Mod™ ARS-CL™ -07 2 17 10447 PLU Calle Prospero Avenida Fortuna 33.46873 -117.6374 CPS-Mod™ ARS-CL™ -10 2 18 10448 PLU Calle Prospero Avenida Fortuna 33.46870 -117.6373 CPS-Mod™ ARS-CL™ -07 2 19 10157 PLU Avenida Fortuna Portico Del Sur 33.46873 -117.6381 CPS-Mod™ ARS-CL™ -07 2 20 10158 PLU Avenida Fortuna Portico Del Sur 33.46838 -117.6382 CPS-Mod™ ARS-CL™ -07 2 21 10438 PLU Portico Del Sur Avenida Fortuna 33.47001 -117.6371 TC CPS-Mod™ ARS-CL™ -14x 4 22 10439 PLU Portico Del Sur Avenida Fortuna 33.47012 -117.6371 TC CPS-Mod™ ARS-CL™ -14x 4 23 10397 PLU Portico Del Sur Roberto 33.47125 -117.6364 TC CPS-Mod™ ARS-CL™ -05 1 24 12973 PLU Rosalinda Felipe 33.47046 -117.6362 CPS-Mod™ ARS-CL™ -10 2 25 12974 PLU Rosalinda Felipe 33.47035 -117.6362 CPS-Mod™ ARS-CL™ -10 2 26 10383 PLU Portico Del Sur Sombreado 33.47204 -117.6361 3 TC CPS-Mod™ ARS-CL™ -14x 4 27 10384 PLU Portico Del Sur Sombreado 33.47200 -117.6360 1 TC CPS-Mod™ ARS-CL™ -14x 4 28 10381 PLU Portico Del Sur Estampida 33.47444 -117.6363 3 TC CPS-Mod™ ARS-CL™ -10 2 29 10382 PLU Portico Del Sur Estampida 33.47445 -117.6362 TC CPS-Mod™ ARS-CL™ -10 2 30 10379 PLU Estampida Portico Del Sur 33.47437 -117.6360 CPS-Mod™ ARS-CL™ -21x 6 31 10380 PLU Estampida Portico Del Sur 33.47426 -117.6360 TC CPS-Mod™ ARS-CL™ -14x 4 32 10459 PLU Camino De Los Mares Portico Del Sur 33.46760 -117.6361 1 TC CPS-Mod™ ARS-CL™ -07 2 33 10465 PLU Camino De Los Mares Camino Vera Cruz 33.46926 -117.6334 1 TC CPS-Mod™ ARS-CL™ -10 2 34 10463 PLU Camino Vera Cruz Camino De Los
Mares 33.46928 -117.6335 1 TC CPS-Mod™ ARS-CL™ -07 2
35 10464 PLU Camino Vera Cruz Camino De Los
Mares 33.46919 -117.6337 1 TC CPS-Mod™ ARS-CL™ -07 2
36 10460 PLU Domador Camino Vera Cruz 33.46948 -117.6338 CPS-Mod™ ARS-CL™ -07 2 37 10462 PLU Domador Camino Vera Cruz 33.46978 -117.6332 CPS-Mod™ ARS-CL™ -10 2 38 10461 PLU Domador Camino Vera Cruz 33.46985 -117.6329 CPS-Mod™ ARS-CL™ -10 2 39 10489 PLU Camino Vera Cruz Camino De Los
Mares 33.46883 -117.6334 TC CPS-Mod™ ARS-CL™ -05 1
2 of 5 24
40 10488 PLU Camino Vera Cruz Camino De Los
Mares 33.46897 -117.6332 TC CPS-Mod™ ARS-CL™ -05 1
41 10485 PLU Camino Vera Cruz Las Posas 33.46852 -117.6328 TC CPS-Mod™ ARS-CL™ -05 1 42 10486 PLU Las Posas Camino Vera Cruz 33.46881 -117.6328 CPS-Mod™ ARS-CL™ -10 2 43 10487 PLU Las Posas Camino Vera Cruz 33.46862 -117.6327 CPS-Mod™ ARS-CL™ -14x 4 44 10483 PLU Calle Emilia Estancia 33.47006 -117.6302 CPS-Mod™ ARS-CL™ -05 1 45 10484 PLU Calle Emilia Estancia 33.47011 -117.6303 CPS-Mod™ ARS-CL™ -05 1 46 10430 PLU Camino De Los Mares Estancia 33.47110 -117.6300 TC CPS-Mod™ ARS-CL™ -07 2 47 10421 PLU Estancia Camino De Los
Mares 33.47119 -117.6303 1 CPS-Mod™ ARS-CL™ -10 2
48 10422 PLU Estancia Camino De Los
Mares 33.47127 -117.6302 1 TC CPS-Mod™ ARS-CL™ -10 2
49 10211 PLU Camino De Los Mares Ave. Vaquero 33.45728 -117.6440 1 TC CPS-Mod™ ARS-CL™ -07 2 50 10213 PLU Calle Campana Camino De Los
Mares 33.45655 -117.6451 TC CPS-Mod™ ARS-CL™ -05 1
51 10215 PLU Calle Campana Camino De Los
Mares 33.45644 -117.6452 1 TC CPS-Mod™ ARS-CL™ -14x 4
52 10214 PLU Calle Campana Camino De Los
Mares 33.45612 -117.6452 TC CPS-Mod™ ARS-CL™ -05 1
53 10623 PLU Calle Frontera Ave. Vista Hermosa 33.44666 -117.6288 TC CPS-Mod™ ARS-CL™ -07 2 54 10625 PLU Calle Frontera Ave. Vista Hermosa 33.44712 -117.6293 1 TC CPS-Mod™ ARS-CL™ -07 2 55 10626 PLU Calle Frontera Camino Faro 33.44753 -117.6309 1 CPS-Mod™ ARS-CL™ -10 2 56 10627 PLU Camino Faro Calle Frontera 33.44779 -117.6306 TC CPS-Mod™ ARS-CL™ -07 2 57 10579 PLU Camino Faro Calle Frontera 33.44819 -117.6305 1 TC CPS-Mod™ ARS-CL™ -07 2 58 10578 PLU Camino Faro Calle Frontera 33.44836 -117.6302 1 TC CPS-Mod™ ARS-CL™ -10 2 59 10575 PLU Calle Balandra Camino Faro 33.44868 -117.6299 1 CPS-Mod™ ARS-CL™ -14x 4 60 10574 PLU Camino Faro Calle Balandra 33.44901 -117.6300 1 CPS-Mod™ ARS-CL™ -14x 4 61 10573 PLU Camino Faro Calle Balandra 33.44904 -117.6298 1 TC CPS-Mod™ ARS-CL™ -07 2 62 10572 PLU Via Chalupa Camino Faro 33.44947 -117.6293 1 CPS-Mod™ ARS-CL™ -07 2 63 10571 PLU Camino Faro Via Chalupa 33.44959 -117.6293 1 CPS-Mod™ ARS-CL™ -07 2 64 10570 PLU Camino Faro Via Chalupa 33.44974 -117.6292 1 TC CPS-Mod™ ARS-CL™ -14x 4 65 10568 PLU Camino Faro Calle Almirante 33.44988 -117.6284 1 CPS-Mod™ ARS-CL™ -10 2 66 10566 PLU Calle Almirante Camino Faro 33.44970 -117.6282 TC CPS-Mod™ ARS-CL™ -07 2 67 10569 PLU Calle Almirante Camino Faro 33.44997 -117.6281 1 CPS-Mod™ ARS-CL™ -07 2 68 10567 PLU Camino Faro Calle Almirante 33.44977 -117.6280 TC CPS-Mod™ ARS-CL™ -05 1 69 10565 PLU Camino Faro Calle Almirante 33.44984 -117.6278 TC CPS-Mod™ ARS-CL™ -05 1 70 13154 PLU Avenida Vista Hermosa Camino Faro 33.44982 -117.6270 1 TC CPS-Mod™ ARS-CL™ -07 2 71 10564 PLU Avenida Vista Hermosa Camino Faro 33.44975 -117.6267 1 TC CPS-Mod™ ARS-CL™ -14x 4 72 10618 PLU Avenida Vista Hermosa Calle Frontera 33.44791 -117.6279 1 TC CPS-Mod™ ARS-CL™ -07 2 73 10620 PLU Avenida Vista Hermosa Calle Frontera 33.44772 -117.6277 1 TC CPS-Mod™ ARS-CL™ -07 2 74 11499 PLU Avenida Presidio I-5 Frwy 33.42744 -117.6101 TC CPS-Mod™ ARS-CL™ -14x 4 3 of 5 25
75 11500 PLU Avenida Presidio I-5 Frwy 33.42731 -117.6099 TC CPS-Mod™ ARS-CL™ -07 2 76 11521 PLU Vista Encanta N. La Esperanza 33.42598 -117.6087 CPS-Mod™ ARS-CL™ -07 2 77 11520 PLU Vista Del Ponto S. La Esperanza 33.42630 -117.6084 1 TC CPS-Mod™ ARS-CL™ -07 2 78 11519 PLU S. La Esperanza Vista Del Ponto 33.42644 -117.6080 TC CPS-Mod™ ARS-CL™ -05 1 79 11518 PLU S. La Esperanza Vista Del Ponto 33.42649 -117.6079 1 TC CPS-Mod™ ARS-CL™ -05 1 80 11549 PLU Vista Encanta Vista Del Ponto 33.42390 -117.6076 1 TC GITS™ NA- no curb opening 81 11547 PLU Vista Del Ponto Vista Encanto 33.42430 -117.6072 1 TC GITS™ NA- no curb opening 82 11546 PLU Calle Patricia S. La Esperanza 33.42460 -117.6068 TC CPS-Mod™ ARS-CL™ -07 2 83 11545 PLU Calle Patricia S. La Esperanza 33.42466 -117.6067 TC CPS-Mod™ ARS-CL™ -07 2 84 11934 PLU Avenida San Pablo Ave. Acapulco 33.41512 -117.5947 1 TC CPS-Mod™ ARS-CL™ -07 2 85 11927 PLU Avenida San Pablo Calle Cuervo 33.41833 -117.5946 2 TC CPS-Mod™ ARS-CL™ -07 2 86 11921 PLU Avenida San Pablo Calle Cuervo 33.41760 -117.5946 2 CPS-Mod™ ARS-CL™ -07 2 87 11930 PLU Avenida San Pablo Calle Cuervo 33.41593 -117.5946 2 CPS-Mod™ ARS-CL™ -10 2 88 11931 PLU Avenida San Pablo Calle Cuervo 33.41630 -117.5946 1 CPS-Mod™ ARS-CL™ -07 2 89 11920 PLU Calle Cuervo Ave. San Pablo 33.41783 -117.5945 3 TC CPS-Mod™ ARS-CL™ -10 2 90 11932 PLU Calle Cuervo Ave. San Pablo 33.41617 -117.5943 1 TC CPS-Mod™ ARS-CL™ -07 2 91 11933 PLU Calle Cuervo Ave. San Pablo 33.41608 -117.5943 2 TC CPS-Mod™ ARS-CL™ -10 2 92 12273 PLU Avenida Acapulco Ave. Adobe 33.41635 -117.5908 2 TC CPS-Mod™ ARS-CL™ -07 2 93 12274 PLU Avenida Acapulco Ave. Adobe 33.41622 -117.5908 3 TC CPS-Mod™ ARS-CL™ -10 2 94 12275 PLU Avenida Acapulco Ave. Adobe 33.41557 -117.5924 1 TC CPS-Mod™ ARS-CL™ -07 2 95 12276 PLU Avenida Acapulco Ave. Adobe 33.41547 -117.5924 TC CPS-Mod™ ARS-CL™ -05 1 96 11996 PLU Avenida Acapulco Ave. Adobe 33.41522 -117.5932 1 TC CPS-Mod™ ARS-CL™ -07 2 97 11937 PLU Avenida Adobe Ave. Acapulco 33.41505 -117.5931 2 TC CPS-Mod™ ARS-CL™ -07 2 98 11938 PLU Avenida Adobe Ave. Acapulco 33.41500 -117.5932 1 TC CPS-Mod™ ARS-CL™ -05 1 99 12277 PLU Avenida Baja Ave. Adobe 33.41487 -117.5915 1 TC CPS-Mod™ ARS-CL™ -05 1 100 12278 PLU Avenida Baja Ave. Adobe 33.41487 -117.5916 1 TC CPS-Mod™ ARS-CL™ -05 1 101 12282 PLU Avenida Adobe Ave. Baja 33.41304 -117.5900 1 TC CPS-Mod™ ARS-CL™ -07 2 102 12281 PLU Avenida Adobe Ave. Baja 33.41276 -117.5902 2 TC CPS-Mod™ ARS-CL™ -07 2 103 12286 PLU Avenida Adobe Calle Bahia 33.41242 -117.5915 1 TC CPS-Mod™ ARS-CL™ -07 2 104 12287 PLU Avenida Adobe Calle Bahia 33.41235 -117.5915 1 TC CPS-Mod™ ARS-CL™ -07 2 105 12201 PLU Avenida La Pata Calle Iglesia 33.44793 -117.5870 1 TC CPS-Mod™ ARS-CL™ -07 2 106 13571 PLU Avenida La Pata Calle Iglesia 33.44745 -117.5869 1 TC CPS-Mod™ ARS-CL™ -10 2 107 12203 PLU Avenida La Pata Steed Memorial Park 33.44644 -117.5857 1 TC CPS-Mod™ ARS-CL™ -05 1 108 13640 PLU Avenida La Pata Steed Memorial Park 33.44602 -117.5855 1 GITS™ (2x) NA- no curb opening 109 12204 PLU Steed Memorial Park Ave. La Pata 33.44575 -117.5843 1 TC GITS™ NA- no curb opening 4 of 5 26
110 12205 PLU Steed Memorial Park Ave. La Pata 33.44568 -117.5843 4 TC CPS-Mod™ ARS-CL™ -14x 4 111 12206 PLU Avenida La Pata Calle Extremo 33.44608 -117.5833 1 TC CPS-Mod™ ARS-CL™ -05 1 112 12207 PLU Avenida La Pata Calle Extremo 33.44594 -117.5833 1 TC CPS-Mod™ ARS-CL™ -05 1 113 12305 PLU Avenida La Pata Calle Extremo 33.44601 -117.5815 CPS-Mod™ ARS-CL™ -14x 4 114 12306 PLU Calle Extremo Ave. La Pata 33.44545 -117.5814 1 TC CPS-Mod™ ARS-CL™ -07 2 115 12307 PLU Calle Extremo Ave. La Pata 33.44542 -117.5815 1 TC CPS-Mod™ ARS-CL™ -07 2 116 12309 PLU Calle Extremo Avenida Fabricante 33.44354 -117.5815 1 TC CPS-Mod™ ARS-CL™ -07 2 117 12310 PLU Calle Extremo Avenida Fabricante 33.44353 -117.5814 1 TC CPS-Mod™ ARS-CL™ -14x 4 118 12311 PLU Calle Extremo Avenida Fabricante 33.43919 -117.5826 CPS-Mod™ ARS-CL™ -05 1 119 13419 PLU Avenida Fabricante Calle Extremo 33.44230 -117.5844 1 TC CPS-Mod™ ARS-CL™ -07 2 120 12238 PLU Avenida Fabricante Calle Extremo 33.44117 -117.5841 TC CPS-Mod™ ARS-CL™ -21x 6 121 12237 PLU Avenida Fabricante Calle Extremo 33.44122 -117.5840 TC CPS-Mod™ ARS-CL™ -21x 6 122 12312 PLU Avenida Fabricante Calle Extremo 33.44027 -117.5826 1 TC CPS-Mod™ ARS-CL™ -10 2 123 12313 PLU Avenida Fabricante Calle Extremo 33.44034 -117.5826 TC CPS-Mod™ ARS-CL™ -14x 4 DEVICES with Installation & CB Prep $622,748
Product Install Totals: Discounts (Quantity 101+ CBs) -$7,746 119 CPS-Mod™ Full Capture Systems Catch Basin & Inlet Cleaning $9,840 4 GITS™ Full Capture Systems Traffic Control $27,400
264 ARS-CL™ Screens Mobilization $35,000
Project Bonds $17,758
SUB-TOTAL $705,000
Contingency $0
TOTAL CONSTRUCTION COST : $705,000
Terms & Conditions:

Pricing based on OCPW/ OCTA Master Pricing with Volume Discounts.

Pricing does not include project licence or business fees.

Final design configurations and costs to be revised after final field evaluations.

Payment NET 30 days.

Thank You. We Appreciate Your Business!
5 of 5 27
Lic. #801253 - A, C8, C60
1352 E. Borchard Ave.

Santa Ana, CA 92705
714.748.4242
[email protected]
Date: April 24, 2025
CPS-Mod™, ARS-CL™ & GITS™

WARRANTY
Project: San Clemente - CPS-Mod™, ARS-CL™, & & GITS™ Screens City of San Clemente 2025-26 OCTA Measure M2’s Environmental Cleanup Program (ECP) Tier 1 – Project X
G2 Construction, Inc. hereby provides a product warranty of 10 years for the G2 CPS-Mod™ connector pipe screens, GITS™ grated inlet trash screen, and ARS-CL™ automatic retractable screens installed in catch basins for the project listed above. G2 guarantees the CPS-Mod™, GITS™, and ARS-CL™ will be manufactured and installed in accordance with the product drawings and specifications.

G2 Construction agrees to repair or replace any installed product that proves defective in its workmanship or material within one year of the project acceptance date. If an installed product proves defective within ten years, then G2 agrees to provide replacement parts at no cost.

Accidents, product modifications, vandalism, unusual use, or lack of standard cleaning may nullify a product’s warranty.

Requests for warranty service must be made by the product Owner, and should include photos and details.

John Alvarado, President
G2 Construction, Inc.
28 C. Location Maps & Project Site Photos
29 City of San Clemente
Project Sub-Map Areas
Inland Residential & Rancho San Clemente Industrial
Runoff Treatment Project
The proposed project’s specific catch basins receiving devices. 30 City of San Clemente PLU Map
Phase 5 – 2025
Inland Residential and Rancho San
Clemente Industrial Runoff
Treatment Project
31 City of San Clemente
Project Overview Map
Inland Residential & Rancho San Clemente Industrial
Runoff Treatment Project
The proposed project’s specific catch basins receiving devices. 1 2
3 4
5 6
32 City of San Clemente
PLU Sub-Area #1
Medium-High Density Residential
Inland Residential & Rancho San Clemente Industrial
Runoff Treatment Project
The proposed project’s specific catch basins receiving devices. 33 City of San Clemente
PLU Sub-Area #1 Drainage
Medium-High Density Residential
Inland Residential & Rancho San Clemente Industrial
Runoff Treatment Project
The proposed project’s specific catch basins receiving devices. 34 City of San Clemente
PLU Sub-Area #2
Medium-High Density Residential
Inland Residential & Rancho San Clemente Industrial
Runoff Treatment Project
The proposed project’s specific catch basins receiving devices. 35 City of San Clemente
PLU Sub-Area #2 Drainage
Medium-High Density Residential
Inland Residential & Rancho San Clemente Industrial
Runoff Treatment Project
The proposed project’s specific catch basins receiving devices. 36 City of San Clemente
PLU Sub-Area #3
Medium-High Density Residential
Inland Residential & Rancho San Clemente Industrial
Runoff Treatment Project
The proposed project’s specific catch basins receiving devices. 37 City of San Clemente
PLU Sub-Area #3 Drainage
Medium-High Density Residential
Inland Residential & Rancho San Clemente Industrial
Runoff Treatment Project
The proposed project’s specific catch basins receiving devices. 38 City of San Clemente
PLU Sub-Area #4
Median-High Density Res., Public, & Commercial
Inland Residential & Rancho San Clemente Industrial
Runoff Treatment Project
The proposed project’s specific catch basins receiving devices. 39 City of San Clemente
PLU Sub-Area #4 Drainage
Median-High Density Res., Public, & Commercial
Inland Residential & Rancho San Clemente Industrial
Runoff Treatment Project
The proposed project’s specific catch basins receiving devices. 40 City of San Clemente
PLU Sub-Area #5
Medium-High Density Residential
Inland Residential & Rancho San Clemente Industrial
Runoff Treatment Project
The proposed project’s specific catch basins receiving devices. 41 City of San Clemente
PLU Sub-Area #5 Drainage
Medium-High Density Residential
Inland Residential & Rancho San Clemente Industrial
Runoff Treatment Project
The proposed project’s specific catch basins receiving devices. 42 City of San Clemente
PLU Sub-Area #6
Rancho San Clemente Industrial
Inland Residential & Rancho San Clemente Industrial
Runoff Treatment Project
The proposed project’s specific catch basins receiving devices. 43 City of San Clemente
PLU Sub-Area #6 Drainage
Rancho San Clemente Industrial
Inland Residential & Rancho San Clemente Industrial
Runoff Treatment Project
The proposed project’s specific catch basins receiving devices. 44 City of San Clemente

WATERSHED MAP
Inland Residential & Rancho San Clemente Industrial
Runoff Treatment Project
A depiction of the City’s three largest watersheds, along with several smaller “Coastal Canyons,” is pictured below.

The proposed project is focused on capturing trash primarily from:
(1) the upper Prima Deshecha Canada Watershed from about 3 miles to 1 mile inland from the Pacific Ocean. The Camino de los Mares corridor connects with I-5 just downstream of this part of the project. (2) the San Clemente Coastal Canyons Watershed includes mostly natural canyons that collect drainage from the City’s center, including parts of the El Camino Real Corridor. (3) the San Mateo Creek Watershed, which is arguably the largest mostly undeveloped watershed south of Los Angeles, and accepts runoff from parts of the southernmost residential and all of the Rancho San Clemente Industrial Park near the City’s southeastern boundary.
45 PHOTOS of Catch Basins CITY of SAN CLEMENTE OCTA 2025 Project X CB ID# 10458 Camino De Los Mares North side East of Portico Del Sur CB ID# 10457 Portico Del Sur East side North of Camino De Los Mares CB ID# 10456 Portico Del Sur West side North of Camino De Los Mares CB ID# 10453 Portico Del Sur East side North of Camino De Los Mares 46 CB ID# 10452 Calle Portada North side East of Portico Del Sur CB ID# 12792 Calle Mandarina East side South of Calle Portada CB ID# 10455 Calle Vecino North side East of Calle Mandarina CB ID# 10454 Calle Vecino South side East of Calle Mandarina 47 CB ID# 10450 Calle Clasico East side West of Calle Carmelita CB ID# 10451 Calle Clasico West side West of Calle Carmelita CB ID# 10441 Avenida Fortuna South side West of Portico Del Sur CB ID# 10442 Avenida Fortuna North side West of Portico Del Sur 48 CB ID# 10438 Portico Del Sur West side North of Avenida Fortuna CB ID# 10439 Portico Del Sur West side North of Avenida Fortuna CB ID# 10397 Portico Del Sur East side North of Roberto CB ID# 12973 Rosalinda North side South of Felipe
49 PHOTOS of Catch Basins CITY of SAN CLEMENTE OCTA 2025 Project X CB ID# 12974 Rosalinda South side South of Felipe
CB ID# 10383 Portico Del Sur West side North of Sombreado CB ID# 10384 Portico Del Sur East side North of Sombreado CB ID# 10381 Portico Del Sur West side North of Estampida 50 CB ID# 10382 Portico Del Sur East side North of Estampida CB ID# 10379 Estampida North side East of Portico Del Sur CB ID# 10380 Estampida South side East of Portico Del Sur CB ID# 10459 Camino De Los Mares South side at Portico Del Sur 51 CB ID# 10465 Camino De Los Mares North side East of Camino Vera Cruz CB ID# 10463 Camino Vera Cruz East side North of Camino De Los Mares CB ID# 10464 Camino Vera Cruz West side North of Camino De Los Mares CB ID# 10460 Domador North side at Camino Vera Cruz
52 PHOTOS of Catch Basins CITY of SAN CLEMENTE OCTA 2025 Project X CB ID# 10462 Domador North side East of Camino Vera Cruz CB ID# 10461 Domador South side East of Camino Vera Cruz CB ID# 10489 Camino Vera Cruz West side South of Camino De Los Mares CB ID# 10488 Camino Vera Cruz East side South of Camino De Los Mares 53 CB ID# 10485 Camino Vera Cruz East side South of Las Posas CB ID# 10430 Camino De Los Mares South side East of Estancia CB ID# 10421 Estancia West side North of Camino De Los Mares CB ID# 10422 Estancia East side North of Camino De Los Mares 54 CB ID# 10213 Calle Campana East side South of Camino De Los Mares CB ID# 10215 Calle Campana West side South of Camino De Los Mares CB ID# 10214 Calle Campana West side South of Camino De Los Mares CB ID# 10211 Camino De Los Mares East side South of Ave. Vaquero 55 PHOTOS of Catch Basins CITY of SAN CLEMENTE OCTA 2025 Project X CB ID# 10623 Calle Frontera East side South of Ave. Vista Hermosa CB ID# 10625 Calle Frontera North side West of Ave. Vista Hermosa CB ID# 10626 Calle Frontera South side West of Camino Faro CB ID# 10627 Camino Faro East side North of Calle Frontera 56 CB ID# 10579 Camino Faro West side North of Calle Frontera CB ID# 10578 Camino Faro East side North of Calle Frontera CB ID# 10575 Calle Balandra South side East of Camino Faro CB ID# 10574 Camino Faro West side North of Calle Balandra 57 CB ID# 10573 Camino Faro East side North of Calle Balandra CB ID# 10572 Via Chalupa North side East of Camino Faro CB ID# 10571 Camino Faro East side North of Via Chalupa CB ID# 10570 Camino Faro West side North of Via Chalupa 58 CB ID# 10568 Camino Faro North side West of Calle Almirante CB ID# 10566 Calle Almirante East side South of Camino Faro CB ID# 10569 Calle Almirante East side North of Camino Faro CB ID# 10567 Camino Faro South side East of Calle Almirante 59 PHOTOS of Catch Basins CITY of SAN CLEMENTE OCTA 2025 Project X CB ID# 10565 Camino Faro North side East of Calle Almirante CB ID# 13154 Avenida Vista Hermosa West side North of Camino Faro CB ID# 10564 Avenida Vista Hermosa East side North of Camino Faro 60 CB ID# 10618 Avenida Vista Hermosa West side North of Calle Frontera CB ID# 10620 Avenida Vista Hermosa East side North of Calle Frontera 61 PHOTOS of Catch Basins CITY of SAN CLEMENTE OCTA 2025 Project X CB ID# 11499 Avenida Presidio North side East of I-5 Frwy CB ID# 11500 Avenida Presidio South side East of I-5 Frwy CB ID# 11521 Vista Encanta East side South of N. La Esperanza 62 CB ID# 11520 Vista Del Ponto East side South of S. La Esperanza CB ID# 11519 S. La Esperanza West side South of Vista Del Ponto CB ID# 11518 S. La Esperanza East side South of Vista Del Ponto CB ID# 11549 Vista Encanta South side West of Vista Del Ponto 63 CB ID# 11547 Vista Del Ponto East side East of Vista Encanto CB ID# 11546 Calle Patricia West side South of S. La Esperanza CB ID# 11545 Calle Patricia East side South of S. La Esperanza 64 PHOTOS of Catch Basins CITY of SAN CLEMENTE OCTA 2025 Project X CB ID# 11934 Avenida San Pablo East side North of Ave. Acapulco

CB ID# 11927 Avenida San Pablo East side North of Calle Cuervo CB ID# 11921 Avenida San Pablo East side South of Calle Cuervo CB ID# 11930 Avenida San Pablo East side South of Calle Cuervo 65 CB ID# 11931 Avenida San Pablo East side North of Calle Cuervo

CB ID# 11920 Calle Cuervo North side East of Ave. San Pablo

CB ID# 11932 Calle Cuervo North side East of Ave. San Pablo

CB ID# 11933 Calle Cuervo South side East of Ave. San Pablo 66 CB ID# 12273 Avenida Acapulco North side West of Ave. Adobe CB ID# 12274 Avenida Acapulco South side West of Ave. Adobe CB ID# 12275 Avenida Acapulco North side East of Ave. Adobe CB ID# 12276 Avenida Acapulco South side East of Ave. Adobe 67 PHOTOS of Catch Basins CITY of SAN CLEMENTE OCTA 2025 Project X CB ID# 11996 Avenida Acapulco North side at Ave. Adobe
CB ID# 11937 Avenida Adobe East side South of Ave. Acapulco CB ID# 11938 Avenida Adobe West side South of Ave. Acapulco CB ID# 12277 Avenida Baja East side West of Ave. Adobe
68 CB ID# 12278 Avenida Baja West side West of Ave. Adobe CB ID# 12282 Avenida Adobe West side South of Ave. Baja CB ID# 12281 Avenida Adobe East side South of Ave. Baja

69 CB ID# 12286 Avenida Adobe North side East of Calle Bahia CB ID# 12287 Avenida Adobe South side East of Calle Bahia 70 PHOTOS of Catch Basins CITY of SAN CLEMENTE OCTA 2025 Project X CB ID# 12201 Avenida La Pata North side East of Calle Iglesia CB ID# 13571 Avenida La Pata South side East of Calle Iglesia CB ID# 12203 Avenida La Pata North-Median West of Steed Memorial Park CB ID# 13640 Avenida La Pata South side West of Steed Memorial Park 71 CB ID# 12204 Steed Memorial Park East side North of Ave. La Pata

CB ID# 12205 Steed Memorial Park East side North of Ave. La Pata

CB ID# 12206 Avenida La Pata North side West of Calle Extremo

CB ID# 12207 Avenida La Pata North-Median West of Calle Extremo

72 CB ID# 12305 Avenida La Pata West side North of Calle Extremo CB ID# 12306 Calle Extremo East side South of Ave. La Pata CB ID# 12307 Calle Extremo West side South of Ave. La Pata CB ID# 12309 Calle Extremo West side North of Avenida Fabricante 73 PHOTOS of Catch Basins CITY of SAN CLEMENTE OCTA 2025 Project X CB ID# 12310 Calle Extremo East side North of Avenida Fabricante CB ID# 13419 Avenida Fabricante South side West of Calle Extremo CB ID# 12238 Avenida Fabricante South side West of Calle Extremo 74 CB ID# 12237 Avenida Fabricante North side West of Calle Extremo CB ID# 12312 Avenida Fabricante South side West of Calle Extremo CB ID# 12313 Avenida Fabricante North side West of Calle Extremo 75 D. Detailed Project Schedule
76 City Council Approval of Resolution May 20, 2025
OCTA & City Agreement Letter Signed August 1, 2025
City Council Approval of Contract October 15, 2025
City Award of Contract to Contractor November 3, 2025
START - Contractor
Construction/Installation November 17, 2025
COMPLETION - Contractor
Construction/Installation January 28, 2026

DETAILED PROJECT SCHEDULE
OCTA ECP Project X 2025-26

CITY OF SAN CLEMENTE
77 Lic. #801253 - A, C8, C60
1352 E. Borchard Ave.

Santa Ana, CA 92705
714.748.4242
[email protected]
Installation Schedule
City of San Clemente
2025-26 OCTA ECP, Project X
April 30, 2025
Action Time (from signed
contract & NTP)

1. Evaluate all catch basins and take detailed
measurements.
4 weeks

2. Fabricate custom CPS-Mod™, GITS™ & ARS-CL™

3. Install custom fitted G2 Devices 8 weeks

4. Inspection and sign-off
TOTAL PROJECT (start to finish) 12 WEEKS
78 E. Design Drawings
79 CPS-Mod™
Patented
CPS Modular Series
CA State Water Board Certified - FULL CAPTURE SYSTEM _____________________________________________________________________________________________________________________________ G2 CPS-Mod™ Full-Capture 5mm perforated screens with
patented modular design for easy installation inside catch basins.

Approved by the California State Water Board, LACDPW, OCPW, OCTA, SF Bay RWQCB & agencies everywhere. The CPSMod™ prevents trash, pollutants, and debris from entering waterways through the catch basin outlet pipe.
x Made from 304 Stainless Steel for extended life.
x Sized to meet or exceed 1-year, 1-hour storm.
x Modular to easily fit all catch basin types.
x Custom designed and fabricated to each catch basin to ensure compliance of no gaps > 5mm in size.
x Professionally installed by G2 or a trained & certified installer. x Quick Release Removable (optional)
x Mosquito & Vector Abatement Deflector (where required) Recommended with G2’s ARS CamLock Series™
80 CPS-Mod™
Patented
CPS Modular Series
FULL CAPTURE SYSTEM Certified by
California State Water Board & Regional Water Quality Control Boards G2 CPS-Mod™ Connector Pipe Screen
Function:
x Captures all pollutants 5mm and larger that enter the catch basin. x Pollutants prevented from exiting the catch basin:
¾ Primary: plastics (food containers, bags, bottles, straws); trash (paper, cigarette butts, cans); vegetative debris (leaves, branches, landscaping); other all other objects. ¾ Secondary: pollutants absorbed by or attached to the Primary pollutants. Including from vehicles (hydrocarbons, fluids, copper, cadmium, zinc, tires, etc.), pathogens / bacteria, pesticides, nutrients, organic compounds, sediment toxicity, etc.

Design, Flexibility, & Approval:
x Custom designed and fabricated for each catch basin and its unique features. x Fits any standard catch basin with discharge pipe on front, back, or side wall. x Approved by State Waterboard, Los Angeles County DPW, City of LA, Orange County DPW, OCTA, San Francisco Bay Area Water Resource Board, and agencies everywhere.

Material & Fabrication:
x Made of 304 stainless steel; 14 gauge with 5mm holes. x “Made in California, USA”
Value:
x Low initial capital investment relative to other storm water quality BMPs. Lower long-term and total lifetime costs vs. any water quality BMP or taking no action. x Requires no replacement filters or parts.
x G2’s CPS-Mod™ in combination with the G2’s ARS-CL™ creates the most effective BMP system and greatest value.

Public Outreach:
x Residents aware of the CPS-Mod™ installed in their local catch basin perceive it to be an environmental benefit and demonstrates an environmentally conscious community.

Recommended with G2’s ARS CamLock Series™ screens, for the most complete full capture system. 81 CPS-Mod™
Patented
CPS Modular Series FULL CAPTURE SYSTEM
82 NOTES:

TOP DEFLECTOR, AS NEEDED
SUPPORT BRACKET WHEN A 48".

BOTTOM TRIM SIZED TO FIT, AS NEEDED,
SEE SHEET #3.
2 G2 Construction, Inc.

Connector Pipe Screen (CPS)

NOT TO SCALE
A
*Hb
*Hs
A*
B*
(typ)
*Hs/2
(typ)
*Hs/2
(typ)
Full Capture Model: G2 CPS - Modular
Patented
VI
A
5 mm Opening Screen 14 Gauge
A
*L = A
5 mm Opening Screen 14 Gauge
*L = A+2B
B (typ)
A
5 mm Opening Screen 14 Gauge
*L = A+B
B
3 3
1 2
1 Screen made of 304 Stainless Steel
14 gauge, with 5 mm openings.

Manufactured and Installed Exclusively by:

Office (714) 748- 4242
CA Lic. # 801253 A, C-8, C-60
G2 Construction, Inc. [email protected]
1352 E. Borchard Avenue
Santa Ana, CA 92705
83 _
GITS™ Drop-In CPS
Grated Inlet Trash Screen
___________________________________________________________________________________________ State Water Board Certified

FULL CAPTURE SYSTEM
G2 GITS™ grated inlet trash screen is a Full Capture
System with 5mm perforations.
x Made from 304 Stainless Steel for extended life.
x Fits under any size inlet grate.
x Custom designed, fabricated & fitted to each grated
inlet. “Made in California, USA”
x Sized to meet or exceed 1-year, 1-hour storm*.
x Professionally installed by G2 or by the customer.

Recommended for grated inlets.
84 GITS™ Drop-In CPS
Grated Inlet Trash Screen
FULL CAPTURE SYSTEM Certified by the
CA State Water Board & Regional Water Quality Control Boards GITS™ Under Grate Trash Capture Device
Function:
x Captures all pollutants 5mm and larger that enter the inlet through the grate. x Meets CA State Water Board trash regulation Track 1 requirements. x Easy to install, clean and maintain.
x Pollutants prevented from exiting the inlet:
¾ Primary: plastics (food containers, bags, bottles, straws); trash (paper, cigarette butts, cans); vegetative debris (leaves, branches, landscaping); other all other objects. ¾ Secondary: pollutants absorbed by or attached to the Primary pollutants. Including from vehicles (hydrocarbons, fluids, copper, cadmium, zinc, tires, etc.), pathogens / bacteria, pesticides, nutrients, organic compounds, sediment toxicity, etc.

Design, Flexibility, & Approval:
x Custom designed and fabricated for each inlet and its unique features. Fits any grated inlet. x Approved by State Water Board, Orange County DPW, OCTA, and agencies everywhere.

Material & Fabrication:
x Made of 304 stainless steel; 14 gauge with 5mm holes. x “Made in California, USA”
Value:
x Low initial capital investment relative to other storm water quality BMPs. Lower long-term and total lifetime costs vs. any water quality BMP or taking no action. x Requires no replacement filters or parts.

Public Outreach:
x Residents aware of the GITS installed in their local grated inlet perceive it to be an environmental benefit and demonstrates an environmentally conscious community. 85 _____________________________________________________________________________________ [email protected] www.G2construction.com Santa Ana 714.748.4242 DBE, MBE & SBE Certified California
GITS™ Drop-In CPS
Grated Inlet Trash Screen
FULL CAPTURE SYSTEM Certified by the
CA State Water Board & Regional Water Quality Control Boards 86 18.00
End View Side View Top View

25.75 8.09 25.75

27.7523.75

10.00 3.50

3.50 10.09

8.09 17.75

39.00 .00

5.00 G2 Construction, Inc.

TM
GITS Full Capture System 3DWHQW3HQGLQJ
Grated Inlet Trash Screen Model :
18" x 40" with 10" Basket
1 4
1 1
2 3
3 Full Capture System for
Drop Inlets with grate
covers 18" x 40"
1 3
4 304 SS - 16 gauge Rim Assembly 304 SS 14 gauge, 5mm perforated material 304 SS solid round bar 18" dia. used to trim off
top of basket. Makes for no sharp edge. 2 304 SS Solid round bar 14" dia. , each baskets has 6 support members.

Manufactured and Installed Exclusively by:

Office (714) 748- 4242
CA Lic. # 801253 A, C-8, C-60
G2 Construction, Inc. [email protected]
1352 E. Borchard Avenue
Santa Ana, CA 92705
6$03/('5$:,1*
87 88
ARS-CL™
Patented
ARS CamLock Series ___________________________________________________________________________________________ G2’s ARS-CL™ automatic retractable screen with CamLock
technology prevents trash and debris from entering catch basins through the curb opening. Approved by LACDPW,
OCTA, OCPW, SF Bay ABAG, and most agencies.

Approved for Trash Amendment TRACK 2 compliance.

Reduces catch basin cleaning costs and CPS maintenance.

Prevents up to 95% of trash and debris from entering the catch basin.
x Made from 304 Stainless Steel for extended life.
x Custom designed, fabricated & fitted to each curb
opening. “Made in California, USA”
x Independent ARS-CL™ devices open and lock between
all catch basin support bolts.
x Sized to meet or exceed 1-year, 1-hour storm*.
x Professionally installed by G2.

Recommended with G2’s CPS-Mod Series™
89 ARS-CL™
Patented
ARS CamLock Series _________________________________________________________________________________________ ARS-CL™ Automatic Retractable Screen
Function:
x Stops all pollutants ¾ inches and larger from entering catch basins and water systems. x Significantly reduces cleaning frequency for catch basins and CPS-Mod™ maintenance. x Pollutants prevented from entering the catch basin:
¾ Primary: plastics (food containers, bags, bottles); trash (paper, cigarette butts, cans); vegetative debris (leaves, branches, landscaping); other objects (balls, toys). ¾ Secondary: pollutants absorbed by or attached to the Primary pollutants. Including from vehicles (hydrocarbons, fluids, copper, cadmium, zinc, tires, etc.), pathogens / bacteria, pesticides, nutrients, organic compounds, sediment toxicity, etc.
x Automatically unlocks and opens during storm events to prevent street flooding. x Automatically re-locks in the closed position to prevent pollutant access. x Low maintenance. Prevents 85-95% of trash and debris from entering the catch basin.

Design, Flexibility, & Approval:
x Custom designed and fabricated for each catch basin’s curb opening. x Fits any standard curb-face catch basin opening.
x Approved by Los Angeles County DPW, City of LA, Orange County DPW, OCTA, San Francisco Bay Area Water Quality Board, Contra Costa County DPW, and Agencies nationally.

Material & Fabrication:
x 100% stainless steel device.
x Fabricated in Orange County. “Made in California, USA” Value:
x Significantly reduces catch basin cleaning requirements and costs. x Low initial capital investment relative to other storm water quality BMPs. Lower long-term and total lifetime costs vs. any water quality BMP or taking no action. x Requires no replacement filters or parts.
x Works in harmony with regular street sweeping programs.

Aesthetics & Environmentalism:
x Beautiful stainless steel devices add aesthetic value to streets and neighborhoods. x Residents perceive the ARS-CL™ to be an environmental benefit and demonstrates an environmentally conscious community.

Recommended with G2’s CPS-Mod Series™ screens, for the most complete full capture system. 90 ARS-CL™
Patented
ARS CamLock Series __________________________________________________________________________________________ 91 Device Filtered Flow Rate Calculation
What are the filtered flow rates for G2 Construction devices, and how are they determined? G2 Construction (G2) reports filtered flow rates based on hydrology modeling and testing with water flows.

Our design team applies the same formula used by the Los Angeles County Department of Public Works (LACDPW) to calculate filtered CFS (cubic feet per second) in their TECHNICAL REPORT on Connector Pipe Screen Design and Full Capture TMDL Compliance (April 2007). This technical report was submitted and approved by the Los Angeles Regional Water Quality Control Board.

CPS-Mod ™ CFS Formula:

Where:

Qscreen= Max CFS filtered thru screen.
c = Coeficent of the screen orifice for friction & turbulence.

A = Area of the screen.
g = Gravity.
h = Differential head of upstream vs. downstream side of screen.

Using this formula, G2 calculates the filtered CFS for different designs, and with different assumptions. Catch basin discharge pipes are designed and sized to transport the area’s stormwater from the catch basin. G2 designs each CPS-Mod™ based on the size and location of the discharge pipe, and size and configuration of the catch basin.

In addition to modeling filtered CFS with formulas, G2 has tested our devices with flowing water.

Results found that actual flowing water CFS rates were 90-95% of the modeled formulas.

However, G2 realizes there are many factors that can reduce filtration rates not included in the formulas. We take a conservative approach by applying a size factor that calculates filtration rates for a smaller device that estimated, typically 85%. This provides a safety factor.

G2 knows there are real world variables that will reduce flow rates, and screen blockage is the most common issue. For that reason, G2 designs assume that a percentage of the screen will be blocked with trash or debris, and our designs typically assume between 10-30% of the screen cannot pass water. This directly reduces the assumed filtration rates.

Each of G2’s ARS-CL™ screens varies in curb opening width between 3.5’ to 5’, and is designed to unlock and open when 4” of water pools in front of the catch basin. The same formula is used to determine device filtered flow rates. Similarly, our designed filtered flow rates for the closed ARSCL™ screen assumes there is some screen blockage. LACDPW has performed hydrology tests on the ARS-CL™ at the San Gabriel dam test facility and has approved the design.

Device Filtered Flow Rate Testing with Water
G2’s devices have been testing using flowing water to simulate real-world conditions. Attached is a report of filtration testing performed on the patented CPS-Mod™. This test and the results were included in G2’s application to the State Waterboard that resulted in the certification of G2’s CPSMod™ and GITS™ devices as Full Capture Systems. 92 &ŝůƚĞƌĞĚ&ůŽǁZĂƚĞdĞƐƚŝŶŐͲ'ϮW^ͲDŽĚ:ĂŶ͘ϮϬϭϵ ϭ
),/7(5(')/2:5$7(7(67,1*
'HYLFH7HVWHG
*&RQVWUXFWLRQ±&360RGŒ
)LOWHUHG)ORZUDWH
&)6
7HVWLQJIRU*&360RGŒ
6XPPDU\
/DEWHVWLQJRI*&360RGŒZDVSHUIRUPHGWRGHWHUPLQHILOWHUHGIORZUDWHV &)6
LQD
VLPXODWHGLQKRXVHFDWFKEDVLQV\VWHP5HVXOWVVKRZHGWKDWDQDYHUDJHVL]HG*&36 VTIWVFUHHQ

ZLOOILOWHUPRUHWKDQ&)6RIZDWHUZKHQFOHDQ7KLVILOWHUHGIORZUDWHH[FHHGVWKHSHDNIORZUDWHRIWKH RQH\HDURQHKRXUVWRUPHYHQWIRUPRVWFDWFKEDVLQVZLWKGLVFKDUJHSLSHOHVVWKDQ´5HVXOWVDOVR VKRZHGWKDWZKHQRIWKHVFUHHQLVEORFNHGLWZLOOFRQWLQXHWRILOWHUDWOHDVW&)6 7KHSULPDU\OLPLWDWLRQRIWKHWHVWLQJZDVGXHWROLPLWHGVXSSO\RIZDWHU

JDOORQV
ZKLFKZDVUHF\FOHG
GXULQJWHVWLQJ)RUDOOWHVWVWKH*&36VXFFHVVIXOO\ILOWHUHGDOOZDWHUIORZVZLWKRXWRYHUIORZLQJWKH VFUHHQ,IKLJKHU&)6IORZUDWHVZHUHDYDLODEOHGXULQJWHVWLQJWKHQKLJKHUPD[LPXPILOWHUHGIORZUDWHV ZRXOGKDYHUHVXOWHG
0HWKRGRORJ\
*EXLOWDQLQKRXVHZDWHUIORZV\VWHPZLWKWKUHHFKDPEHUV 
 :DWHU6RXUFH&KDPEHUKROGVXSWRFXELFIHHWRIZDWHU

JDOORQV

 7HVW&KDPEHULVDVLPXODWHGFDWFKEDVLQZKHUHWKHWHVWHG&36ZDVLQVWDOOHG  5HF\FOH7DQNFROOHFWVWHVWHGZDWHU
FXELFIW

JDO
ZKHUHLWLVSXPSHGEDFNXSWRWKH
VRXUFHFKDPEHU
7HVW&KDPEHU'LPHQVLRQV

 
7HVWHG*&360RGŒGHYLFH

 
7KLV&36ZDVWHVWHGXQGHUWZRVFHQDULRV

 VFUHHQEORFNDJH
 EORFNDJH7KHERWWRPRIWKHVFUHHQZDVWLJKWO\FRYHUHGZLWKLPSHUPHDEOHSODVWLF EDUULHU
93 &ŝůƚĞƌĞĚ&ůŽǁZĂƚĞdĞƐƚŝŶŐͲ'ϮW^ͲDŽĚ:ĂŶ͘ϮϬϭϵ Ϯ
)RUHDFKWHVWXSWRFXELFIHHWIORZHGIURPWKHZDWHUVRXUFHFKDPEHULQWRWKHWHVWFKDPEHUDQG WKURXJKWKH&36
7HVW5HVXOWV

 
,QDOOWHVWVFHQDULRVWKH*&36ILOWHUHGRIWKHZDWHUZLWKRXWZDWHUULVLQJDQGRYHUIORZLQJWKHVFUHHQ $QDO\VLV
7KH&36FRXOGKDYHILOWHUHGPRUHZDWHULILWZDVDYDLODEOHZLWKRXWRYHUIORZLQJ7KHWHVWHG* &36KDGDILOWHUHGIORZUDWHWKDWH[FHHGHG&)6SHUVTXDUHIRRWRIVFUHHQ &RQFOXVLRQ
7HVWLQJVKRZHGWKDW*¶V&36RIDYHUDJHVL]H
VTIWVFUHHQ
ILOWHUVZDWHULQH[FHVVRI
&)67KLVUDWHH[FHHGVWKHIXOOFDSWXUHUHTXLUHPHQWVRIPRVWFDWFKEDVLQVZLWKDGLVFKDUJHSLSHGLDPHWHU OHVVWKDQ´7KHSULPDU\OLPLWDWLRQRIWKLVWHVWZDVWKHLQDELOLW\WRVXSSO\KLJKHUZDWHUYROXPHVDQGIORZ UDWHV)XUWKHUWHVWLQJLVUHFRPPHQGHG
3KRWRVRI&)67HVWV

*&)67HVWHU
FKDPEHUV\VWHP
:DWHU6RXUFH&KDPEHU &)
*DOORQV

 
94 &ŝůƚĞƌĞĚ&ůŽǁZĂƚĞdĞƐƚŝŶŐͲ'ϮW^ͲDŽĚ:ĂŶ͘ϮϬϭϵ ϯ
6FHQDULR
%ORFNDJHRI6FUHHQ6FHQDULR %ORFNHGZLWKSODVWLF
 
%HIRUH7HVW

7HVW&KDPEHU'LVFKDUJH3LSH  
'XULQJ7HVW
 
95 ),/7(5(')/2:5$7(6/$%7(67**UDWHG,QOHW7UDVK6FUHHQ )LOWHUHG)ORZUDWH
&)6
7HVWLQJIRU**,76[
6XPPDU\

/DEWHVWLQJRIWKH**,76ZDVSHUIRUPHGWRGHWHUPLQHILOWHUHGIORZUDWHV &)6
LQDVLPXODWHGLQKRXVH
VWRUPZDWHULQOHW7KUHHVFHQDULRVZHUHWHVWHGXVLQJWKHVWDQGDUG**,76[ 
VTIWVFUHHQ


VFUHHQEORFNDJHVFUHHQEORFNDJHDQGVFUHHQEORFNDJH5HVXOWVVKRZHGWKDW &)6IORZUDWH
ZDVVXFFHVVIXOO\ILOWHUHGDFURVVRQDOOWHVWVDQGSURMHFWHGPD[LPXP&)6RIWKHXQEORFNHG*,76LV KLJKHUWKDQ&)67KLVLVDFRQVHUYDWLYHHVWLPDWH7KH*,76ILOWHUHGIORZUDWHVTXDOLI\LWDVDIXOO FDSWXUHV\VWHP
0HWKRGRORJ\

*EXLOWDQLQKRXVHZDWHUIORZV\VWHPWRVLPXODWHDVWRUPHYHQWIRUDJUDWHGLQOHW 
 :DWHU6RXUFH&KDPEHUKROGVXSWRFXELFIHHWRIZDWHU

JDOORQV

 7HVW&KDPEHULVDVLPXODWHGLQOHWZKHUHWKHWHVWHG*,76ZDVLQVWDOOHG )RU7HVWWKH*,76WUDVKFROOHFWLRQEDVNHW¶VVFUHHQZDVFRPSOHWHO\RSHQ)RU7HVWDQGWKLFN ZDWHUSURRIWDSHZDVDSSOLHGWRERWKWKHLQVLGHDQGRXWVLGHRIWKHVFUHHQWRPDNHLWFRPSOHWHO\ LPSHUPHDEOH7HVW
EORFNDJH
ZDVFRQGXFWHGDIWHUWKH*,76ERWWRPZDVEORFNHGFRPSOHWHO\DQG DOOVLGHVZHUHZUDSSHGXSWRDKHLJKWRIWKHFROOHFWLRQEDVNHW7HVW EORFNDJH
ZDV
FRQGXFWHGDIWHUWKH*,76ERWWRPZDVEORFNHGFRPSOHWHO\DQGRIVLGHVZHUHZUDSSHGFRPSOHWHO\7KLV OHIWRQHVLGHRSHQ

RIWKHVFUHHQVXUIDFH

5HVXOWVDQG$QDO\VLV

7HVW
EORFNDJHZLWK
&)6ZDWHUIORZUHVXOWHGLQILOWUDWLRQWKURXJKWKHVFUHHQZLWKRXWRYHUIORZ :DWHUH[LWHGIURPWKHERWWRPDQGPLGGOHRIWKHVFUHHQEXWWKHXSSHUSRUWLRQRIWKHILOWUDWLRQEDVNHWZDVQRW XWLOL]HGLQGLFDWLQJWKHUHZDVPRUHFDSDFLW\,IKLJKHU&)6IORZUDWHVZHUHDYDLODEOHGXULQJWKLVWHVWWKHQ KLJKHUPD[LPXPILOWHUHGIORZUDWHVZRXOGKDYHUHVXOWHG 7KLV &)6ILOWHUHGIORZUDWHH[FHHGVWKHSHDN
IORZUDWHRIWKHRQH\HDURQHKRXUVWRUPHYHQWIRUPRVWLQOHWVZLWK´E\´JUDWHV 7HVW
EORFNDJHZLWK
&)6UHVXOWHGLQILOWUDWLRQWKURXJKWKHVFUHHQZLWKRXWRYHUIORZ7KH SURMHFWHGPD[LPXP&)6RIDQXQEORFNHG*,76EDVHGRQWKLVWHVWLV&)6 7HVW
EORFNDJHZLWK
&)6UHVXOWHGLQILOWUDWLRQWKURXJKWKHVFUHHQZLWKRXWRYHUIORZ7KH SURMHFWHGPD[LPXP&)6RIDQXQEORFNHG*,76EDVHGRQWKLVWHVWLV&)67KHILOWHUHGIORZUDWHRIWKLV WHVWH[FHHGHG&)6SHUVTXDUHIRRWRIVFUHHQ
&RQFOXVLRQ

7HVWLQJVKRZHGWKDW*¶V*,76[

VTIWVFUHHQ
VXFFHVVIXOO\ILOWHUVZDWHUIORZRI
&)63URMHFWHG
&)6H[FHHGV&)6
7HVW
DQGPD\UHDFK&)6
7HVW
7KH*,76ILOWHUHGIORZUDWHVTXDOLI\LWDVD
IXOOFDSWXUHV\VWHP7KHSULPDU\OLPLWDWLRQRIWKLVWHVWZDVWKHLQDELOLW\WRVXSSO\KLJKHUZDWHUYROXPHVDQG IORZUDWHV

96 *&)67HVW&KDPEHU
BBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBB 7(676
6FHQDULR
%ORFNDJHRI6FUHHQ
3UH7HVW6HWXS 'XULQJ7HVW
,PDJHDW0D[&)6 1R2YHUIORZ

2 97
6FHQDULR
%ORFNDJHRI6FUHHQ

7RSKDOIRSHQ
ERWWRPDQGKDOIRIVLGHVEORFNHG

3UH7HVW6HWXS 'XULQJ7HVW
,PDJHDW0D[&)6 1R2YHUIORZ

BBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBB 6FHQDULR

%ORFNDJHRI6FUHHQ

)URQWVLGHRSHQ
VLGHVDQGERWWRPEORFNHG

3UH7HVW6HWXS 'XULQJ7HVW
,PDJHDW0D[&)6 1R2YHUIORZ

3 98
Catch Basin receiving ARS-CL™ and CPS-Mod™ FCS
ARS-CL CPS-Mod
w ARS
CB "W"
(ft)
ARS-CL
CB Count
Linear Feet (LF) of
Curb Opening
CPS-Mod
CB Count
Cubic Ft/
LF
Cubic Ft/
LF
Cubic Ft Trash/
Debris Captured

3.5 22 77 22 6 4 770
7 50 350 50 6 3 3,150
10 26 260 26 6 3 2,340
14 18 252 18 6 3 2,268
21 3 63 3 6 2.5 536
28 0 0 0 6 2 0
774.5
Linear Feet (LF) of
Curb Opening
Catch Basin drop-inlets receiving GITS™ FCS
Grate
Size CB Count SQFT of Grate
Opening
Cubic Ft Trash/
Debris Captured
40" x 24" 4 26.7 107
TOTAL 123 9,170
CB Count Cubic Ft Trash/ Debris
Captured per Year
Cubic Ft/ SQFT
4 Inland Residential and Rancho San Clemente
Industrial Runoff Treatment Project 2025-26

CITY OF SAN CLEMENTE

TRASH & DEBRIS CAPTURE
Cubic Foot Estimate

ASSUMPTIONS

ASSUMPTIONS
99 G2 Construction, Inc.

Full Capture System Devices
Device Device
Quantity
Device Filtration
SQFT (avg)

PROJECT
Filtration
Total SQFT
Design Flow
Rate Max per
Device
CPS-Mod 6.0 64 4.75 304 6.12
CPS-Mod 9.0 45 7.25 326.25 9.34
CPS-Mod 11.0 10 10 100 12.88
GITS 40x24 3 6.9 20.7 8.89
GITS 40x24 (double) 1 13.8 13.8 17.78
TOTALS 123 730.3
Weighted Average CFS 8.01
per Device (0% screen blockage)
Device Filter Size 5.94 SQFT (avg)
Device Max Filtration 8.01 CFS (avg)
Screen Blockage 35% (Max. anticipated blockage between CB Cleanings) (conservative option)
DESIGN FLOWRATE 5.21 CFS FILTERED (avg)
TOTAL DESIGN 640.4 CFS FILTERED
Curb-Opening Device Screens
Device Quantity Device Linear
Feet Total SQFT
Design Flow
Rate Max per
Device
ARS-CL Screens 264 3.5 924 1.45
TOTALS 264 924 1.45
DESIGN FLOWRATE 1.45 CFS (avg)
TOTAL DESIGN 382.8 CFS FILTERED

DESIGN FLOW

CITY OF SAN CLEMENTE
Inland Residential and Rancho San Clemente Industrial
Runoff Treatment Project 2025
100

F. City Council Resolution Dra ft
(San Clemente City Council to
approve on May 20, 2025)

101
ATTACHMENT 1
RESOLUTION NO.

A RESOLUTION OF THE CITY COUNCIL OF THE CITY

OF SAN CLEMENTE, CALIFORNIA, AUTHORIZING AN

APPLICATION FOR FUNDS FOR THE
ENVIRONMENTAL CLEANUP, TIER 1 GRANT

PROGRAM UNDER ORANGE COUNTY LOCAL
TRANSPORTATION ORIDANANCE NO. 3 FOR THE

INLAND RESIDENTIAL AND RANCHO SAN

CLEMENTE INDUSTRIAL RUNOFF TREATMENT

PROJECT
WHEREAS, Orange County Local Transportation Ordinance No.3, dated July 24, 2006, is known and cited as the Renewed Measure M Transportation Ordinance and Investment Plan and makes funds available through the Environmental Cleanup Program to help protect Orange County beaches and waterways from transportation-generated pollution (urban runoff) and improve overall water quality; and
WHEREAS, the Environmental Cleanup, Tier 1 Grant Program consists of funding purchases and installation to catch basins with Best Management Practices, such as screens, filters, inserts, and other "street-scale" low flow diversion projects; and WHEREAS, OCTA has established the procedures and criteria for reviewing proposals; and
WHEREAS, the City of San Clemente possesses authority to nominate water quality improvement projects that have a transportation pollution nexus to finance and construct the proposed project; and
WHEREAS, by formal action the City Council authorizes the nomination of the Inland Residential and Rancho San Clemente Industrial Runoff Treatment Project, including all understanding and assurances contained therein, and authorizes the person identified as the official representative of the City of San Clemente to act in connection with the nomination and to provide such additional information as may be required; and WHEREAS, the City of San Clemente will maintain and operate the equipment acquired and installed; and
WHEREAS, the City of San Clemente will give OCTA's representatives access to and the right to examine all records, books, papers or documents related to the funded Tier 1 Grant Project; and
WHEREAS, the City of San Clemente will cause work on the project to be commenced within a reasonable time after receipt of notification from OCTA and that the 102
Resolution No. Page 2
project will be carried to completion with reasonable diligence; and WHEREAS, the City of San Clemente will comply where applicable with provisions of the California Environmental Quality Act, the National Environmental Policy Act, the American with Disabilities Act, and any other federal, state, and/or local laws, rules and/or regulations; and
WHEREAS, the City of San Clemente must include all projects funded by Net Revenues in the seven-year Capital Improvement Program as part of the Renewed Measure M Ordinance eligibility requirement; and
WHEREAS, the City of San Clemente authorizes a formal amendment to the seven-year Capital Improvement Program to add projects approved for funding upon approval from the Orange County Transportation Authority Board of Directors; and WHEREAS, the City of San Clemente will provide a minimum of 20% in matching funds for the Inland Residential and Rancho San Clemente Industrial Runoff Treatment Project as required by the Orange County Comprehensive Transportation Funding Program Guidelines.

NOW, THEREFORE, the City Council of the City of San Clemente hereby finds, determines and resolves as follows:

SECTION 1. The recitals above are true and correct and incorporated fully herein as findings.

SECTION 2. The application submitted on May 8, 2025 to the Orange County Transportation Authority (OCTA) Project X Environmental Cleanup Program, Tier 1 Grant Program, for the Inland Residential and Rancho San Clemente Industrial Runoff Treatment Project is hereby approved.

SECTION 3. The City Manager, or his designee, as the official representative of the City of San Clemente, is hereby authorized and directed to accept funds for the Environmental Cleanup, Tier 1 Grant Program for the Inland Residential and Rancho San Clemente Industrial Runoff Treatment Project from OCTA.

SECTION 4. The City Manager, or his designee, is hereby authorized and directed to agree to fund the City's share of the project costs and any additional costs over the identified programmed amount for the Inland Residential and Rancho San Clemente Industrial Runoff Treatment Project.

SECTION 5. Staff is hereby authorized and directed to take such other and further actions and execute and submit such documents as may be necessary and proper to accomplish the purposes of this resolution.
103
Resolution No. Page 3
SECTION 6. The City Clerk shall certify to the passage and adoption of this resolution and enter it into the book of original resolutions.

PASSED AND ADOPTED this _____ day of May, 2025.
_______________________
Mayor of the City of
San Clemente, California
ATTEST:
__________________________
CITY CLERK of the City of
San Clemente, California
104
Resolution No. Page 4

STATE OF CALIFORNIA )
COUNTY OF ORANGE ) §

CITY OF SAN CLEMENTE )
I, LAURA CAMPAGNOLO, City Clerk of the City of San Clemente, California, do hereby certify that Resolution No. _________ was adopted at a regular meeting of the City Council of the City of San Clemente held on _______ day of April 2023, by the following vote:

AYES:

NOES:

ABSENT:
_______________________
CITY CLERK of the City of
San Clemente, California
Approved as to form:
_____________________________
Elizabeth A. Mitchell, City Attorney
105
G. Project Drainage Areas, Priority Land Uses,
BMP Location & KMZ Files
106
CITY OF SAN CLEMENTE 2025
PROJECT DRAINAGE ACRES + IMPERVIOUS SURFACE

PRIORITY LAND USE (PLU) DRAINAGE AREAS
Drainage
Area
Area Name Drainage
Acres Land Use
Imperviousness
*
Imperv
Acres
1 1. PLU - Res Med Density 69.9 Residential HD (24du/acre) 74% 51.7 2 2. PLU - Res Med Density 12.5 Residential HD (24du/acre) 74% 9.3 3 3. PLU - Res Med Density 41.6 Residential HD (24du/acre) 74% 30.8

4.1 4.1 PLU - Res Med Density 27.0 Residential HD (24du/acre) 74% 20.0

4.2 4.2 PLU - Public Facility 4.0 Office - Public 88% 3.5

4.3 4.3 PLU - Commercial - Church 6.9 Commercial 88% 6.0 5 5. PLU - Res Med Density 64.2 Residential HD (24du/acre) 74% 47.5

6.1 6.1 PLU - Light Industrial 18.9 Industrial - Light 81% 15.3

6.2 6.2 PLU - Heavy Industrial 33.0 Industrial - Heavy 91% 30.0

6.3 6.3 PLU - Public Parking 6.9 Public Parking 95% 6.5 Total PLU Acres 284.8
TOTAL ACRES: 284.8 TOTAL IMPERV ACRES: 220.6
IMPERVIOUSNESS*: 77.5%
*Source: ISC
PLU TOTAL ACRES 284.80
Total Project Cost: $705,000
Cost Per PLU Acre: $2,475
107
City of San Clemente
KMZ Files & Drainage
2 5 6
1 3
4 108
H. Vendor and Installer Qualifications
109

CREDENTIALS & QUALIFICATIONS
Background & Experience
G2 Construction started operations in Orange County in 2001 with strong foundations in welding, concrete construction, shop fabrication, and field work. The company began designing, fabricating, and installing catch basin curb opening automatic retractable screens (ARS) and full-capture connector pipe screens (CPS) and other stormwater protection devices for Los Angeles County Department of Public Works (LACDPW) and southern California municipalities in 2002.

Since then, G2 has fabricated and installed tens of thousands of approved catch basin inserts and screen covers on hundreds of stormwater projects in the Orange County and Los Angeles area. G2 offers complete solutions by performing project evaluation and consultation on stormwater devices and then designing, fabricating, and installing highly effective devices to meet and exceed specifications.

G2’s General Credentials
x Orange County Public Works (OCPW) and OCTA M2 Environmental Cleanup Program approved storm water quality devices:
o CPS-Mod™ patented Full Capture System approved by State Waterboard. o GITS™ grated inlet trash screen Full Capture System approved by State Waterboard.
o ARS-CL™ patented automatic retractable screen.
x OCPW ranks G2 Construction as their #1 stormwater device provider (2020 RFP & 2014 RFP). Awarded Master Purchase Agreements covering 2015 - 2025. x Los Angeles County Dept. of Public Works & City of Los Angeles Bureau of Sanitation approved products: ARS-CL™& CPS-Mod™
x Association of Bay Area Governments (ABAG) Approved products (all) x California Contractor Licenses: A (General Contractor), C-8 (Concrete), C60 (Welding) x Orange County Local Small Businss (OCLSB) certified. [see Attached] x Disadvantaged Business Entity (DBE) certified. [see Attached] x Minority Business Entity (MBE) certified. [see Attached] x Small Business Entity (SBE) certified.
110
G2’s Technical Expertise
G2 Construction is at the forefront of the stormwater device industry. G2 has designed and fabricated the most advanced stormwater protection devices to solve the needs of public agencies and private developers. Our advanced methodologies for fabrication and installation have made G2 the industry leader in providing custom-fitted stainless steel catch basin inserts and curb opening screen covers.

G2 has developed a high degree of technical expertise by incorporating all phases (evaluation, consulting, design, fabrication, installation, reporting) of stormwater projects, and learning from hundreds of installed projects over the years. We have become extremely familiar with all the procedures required for success.

Our depth of knowledge and technical experience has been the result of solving many dozens of challenges and constraints of projects over two decades. This includes, among many others, solving for all the various catch basin types and sizes and conditions that we face in the field.

We’ve learned something new from most projects and most clients. Our experiences with cities in Orange County and throughout southern California have been very good for many years.

Because many cities have developed an advanced knowledge of the industry and recognize quality and value, it makes G2’s work more effective, efficient, and valuable.

Fortunately, G2’s strong culture for project management helps us to organize projects effectively and manage diverse teams. This has enabled G2 to have a 100% rate of success for completing projects and within budget.

G2 provides its technical expertise and installation services throughout California and focuses on the Orange County and Los Angeles County regions.

Letters of Reference
G2’s customers provide additional insights into our qualifications. Attached are a few letters of our customer letters of recommendation.
111

CITY OF LAGUNA HILLS
24035 El Toro Road •Laguna Hills, California 92653 • (949) 707-2600 • FAX (949) 707-2633 Website: www.LagunaHillsCA.gov
Feb. 3, 2025
Orange County Public Works
Procurement Services
601 North Ross Street
Santa Ana, CA 92701
SUBJECT: City of Laguna Hills – Letter of Recommendation for G2 Construction, Inc.

TRASH AND DEBRIS CAPTURE DEVICES – RFP# 080-2736403-WH
To Whom It May Concern:

The City of Laguna Hills has contracted with G2 Construction (G2) since 2007 to design, fabricate, and install their ARS-CL and CPS-Mod trash and debris screens throughout the City. Between 2012 - 2024, G2 installed 11 annual City projects that won OCTA Environmental Cleanup Program’s Project X grant funds. They have installed over 2,000 ARS screens and 370 CPS devices in our catch basins.

The City continues to select G2 Construction because their devices successfully prevent trash, debris, and vegetation from entering our storm drain system and watershed. The City plans to work with G2 again this year to install our Phase XII OCTA grant.

For each project G2 has provided a simple end-to-end solution that includes field evaluations and measurements of catch basins, custom design and fabrication of their devices, installation, photos, support documentation, and warranty. G2’s work has always been on schedule, on budget, and performed without any problems.

G2 has also assisted the City with an inventory of catch basin devices, and provided information critical to our Project X applications.

I am pleased to offer this letter of recommendation for G2 Construction. The City finds their trash and debris devices to be very effective and of good value, and their installation work to be of high quality. The company has been very professional and dependable in their interactions with the City. We look forward to working with G2 Construction on future projects.

You may contact me with any questions at [email protected] or 949/707-2655.

Sincerely,
Joe Ames, P.E., T.E.

Public Works Director/City Engineer
Joe Ames, P.E., T.E
112
City of Mission Viejo
Public Works Department
200 Civic Center x Mission Viejo, California 92691 949/470-3056 http://www.cityofmissionviejo.org
Bob Ruesch
Mayor
Wendy Bucknum
Mayor Pro Tem
Brian Goodell
Councilmember
Trish Kelley
Councilmember
Cynthia Vasquez
Councilmember
January 17, 2025
Subject: G2 Construction
To Whom It May Concern:

G2 Construction has consistently provided quality services for the City of Mission Viejo since 2014 when it first installed Trash and Debris Capture Devices in Mission Viejo’s catch basins.

Since then, the City has contracted with G2 every year to install more G2 devices and will again in 2025.

G2 provides the Full Capture System CPS devices and ARS curb-opening screens the City prefers to prevent pollutants and debris from entering its storm drain systems. G2 is a full-service entity providing everything from field evaluations to custom device design, device fabrication, and installation. G2 is also instrumental in assisting the City with grant funding applications and the preparation of grant reimbursement requests.

G2 Construction is professional, experienced, expedient and reliable. Work is always performed quickly and efficiently and within budget.

They are a pleasure to work with and the City looks forward to many more projects with G2 Construction.

Regards,

MARK CHAGNON
City Of Mission Viejo
Director Of Public Works
113
CITY HALL 211 EIGHTH STREET
SEAL BEACH, CALIFORNIA 90740
(562) 431-2527 • www.sealbeachca.gov
October 23, 2024
Orange County Public Works
Procurement Services
601 N. Ross Street
Santa Ana, CA 92701
SUBJECT: TRASH AND DEBRIS CAPTURE DEVICES – REQUEST FOR PROPOSAL City of Seal Beach – Recommendation Letter
To Whom It May Concern:

This letter of recommendation is in response to Orange County Public Works’ Trash and Debris Capture Devices RFP. In my current capacity as the City of Seal Beach’s Public Works Director, I have had the pleasure of working with G2 Construction, Inc. (G2) for the installation of multiple capture devices.

OCPW’s master agreement in partnership with OCTA’s Environmental Cleanup Program has allowed many local agencies mitigate transportation-related pollutants. Through this, G2 has provided a seamless approach to successful project delivery, which I have no reservations recommending. The following is a recent list of services performed under my purview:
x 2023 Seal Beach CPS -Mod (170 systems) + ARS (48 screens) x 2020 Seal Beach CPS-Mod (53 systems) + ARS (95 screens) x 2019 Seal Beach CPS-Mod (55 systems) + ARS (127 screens) Should you have any questions regarding G2’s performance, please feel free to reach out at (562) 431- 2527, x1322 or [email protected].

Sincerely,
Iris Lee
Director of Public Works
114
&,7<2))8//(5721
BBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBB 3XEOLF:RUNV'HSDUWPHQW±(QJLQHHULQJ'LYLVLRQ
7+(('8&$7,21&20081,7<
:HVW&RPPRQZHDOWK$YHQXH)XOOHUWRQ&DOLIRUQLD



‡ZZZFLW\RIIXOOHUWRQFRP
EŽǀĞŵďĞƌϳ͕ϮϬϮϰ
Z
͗ KƌĂŶŐĞŽƵŶƚLJdƌĂŶƐƉŽƌƚĂƚŝŽŶƵƚŚŽƌŝƚLJDĞĂƐƵƌĞDϮ
ŶǀŝƌŽŶŵĞŶƚĂůůĞĂŶƵƉdŝĞƌϭ'ƌĂŶƚ
WƌŽŐƌĂŵ&ŝƐĐĂůzĞĂƌϮϬϮϰͲϮϬϮϱ
 ŝƚLJŽĨ&ƵůůĞƌƚŽŶͲ>ĞƚƚĞƌŽĨZĞĐŽŵŵĞŶĚĂƚŝŽŶ
dŚĞŝƚLJŽĨ&ƵůůĞƌƚŽŶ;ŝƚLJͿŚĂƐǁŽƌŬĞĚǁŝƚŚ'ϮŽŶƐƚƌƵĐƚŝŽŶ/ŶĐ;'ϮͿŽŶĞǀĞƌLJKƌĂŶŐĞŽƵŶƚLJ dƌĂŶƐƉŽƌƚĂƚŝŽŶƵƚŚŽƌŝƚLJDĞĂƐƵƌĞDϮ
ŶǀŝƌŽŶŵĞŶƚĂůůĞĂŶƵƉdŝĞƌϭ'ƌĂŶƚƚŚĞŝƚLJŚĂƐĂƉƉůŝĞĚƚŽƐŝŶĐĞ ϮϬϭϰ͘ƐƚŚĞŝƚLJ͛ƐƉƌŝŵĂƌLJĐŽŶƚƌĂĐƚŽƌĨŽƌŝŶƐƚĂůůŝŶŐƚŚĞĨƵůůĐĂƉƚƵƌĞƚƌĂƐŚĂŶĚĚĞďƌŝƐĚĞǀŝĐĞƐ͕'ϮŚĂƐ ŝŶƐƚĂůůĞĚĂƉƉƌŽdžŝŵĂƚĞůLJϰϵϱĨƵůůĐĂƉƚƵƌĞƚƌĂƐŚĂŶĚĚĞďƌŝƐĚĞǀŝĐĞƐƚŽĚĂƚĞǁŝƚŚŝŶƚŚĞŝƚLJ͘ KǀĞƌƚŚĞLJĞĂƌƐ͕'ϮŚĂƐĨĂƌĞdžĐĞĞĚĞĚƚŚĞŝƚLJ͛ƐĞdžƉĞĐƚĂƚŝŽŶĂŶĚƉƌŽǀĞŶƚŽďĞƉƌŽĨĞƐƐŝŽŶĂůĂŶĚŵĂƐƚĞƌƐŽĨ ƚŚĞŝƌĐƌĂĨƚ͘tŝƚŚĞĂĐŚƉƌŽũĞĐƚ͕'ϮĐŽŶƚŝŶƵĞƐƚŽƉƌŽǀŝĚĞŐƌĞĂƚƐĞƌǀŝĐĞŝŶĐůƵĚŝŶŐĚĞƚĂŝůĞĚĨŝĞůĚƌĞǀŝĞǁƐ͕ ƉŚŽƚŽƐĂŶĚƐƵƉƉŽƌƚŝŶŐĚŽĐƵŵĞŶƚĂƚŝŽŶ͕ĂŶĚĐŽŶƚŝŶƵŽƵƐĐŽŵŵƵŶŝĐĂƚŝŽŶ͘ ĂĐŚƉƌŽũĞĐƚŝƐĐŽŵƉůĞƚĞĚŽŶ
ƚŝŵĞĂŶĚǁŝƚŚŝŶďƵĚŐĞƚ͘
&ƵƌƚŚĞƌŵŽƌĞ͕/ĂŵŝŵƉƌĞƐƐĞĚǁŝƚŚƚŚĞƐĞƌǀŝĐĞ'ϮƉƌŽǀŝĚĞƐĂŶĚ/ĂŵƉůĞĂƐĞĚƚŽƌĞĐŽŵŵĞŶĚ'Ϯ ŽŶƐƚƌƵĐƚŝŽŶ͕/ŶĐ͘dŚĞŝƚLJŝƐůŽŽŬŝŶŐĨŽƌǁĂƌĚƚŽǁŽƌŬŝŶŐǁŝƚŚ'ϮŽŶŶĞdžƚLJĞĂƌ͛ƐĂƚĐŚĂƐŝŶŽŶŶĞĐƚŽƌ WŝƉĞ^ĐƌĞĞŶWƌŽũĞĐƚ͘
&ĞĞůĨƌĞĞƌĞĂĐŚŽƵƚƚŽŵĞĨŽƌĂŶLJƋƵĞƐƚŝŽŶƐďLJƉŚŽŶĞϳϭϰͲϳϯϴͲϲϴϴϲŽƌďLJĞŵĂŝů DĞůŝƐƐĂ͘ZĞŶĚŽŶΛĐŝƚLJŽĨĨƵůůĞƌƚŽŶ͘ĐŽŵ͘
^ŝŶĐĞƌĞůLJ͕
DĞůŝƐƐĂZĞŶĚŽŶ͕W͘
͘
ŝǀŝů
ŶŐŝŶĞĞƌ
ŝƚLJŽĨ&ƵůůĞƌƚŽŶ
WƵďůŝĐtŽƌŬƐ
ŶŐŝŶĞĞƌŝŶŐĞƉĂƌƚŵĞŶƚ
115
116


)%H

'%$H
(*"
)H
",;B,?FH
H
H
%?,;20H<B;AFH&B-94.H+<?8@H
#<0HB;AH(0;4<?H$,;,20:0;AH;,9F@AH
'010?0;.0H1<?H
H<;@A?B.A4<;H





)30H4AFH<1H B0;,H&,?8H3,@HD<?80/HD4A3H
H<;@A?B.A4<;H@4;.0H

HA<H4;@A,99H&(H'(H ,;/H

)(H/0C4.0@H<;H@A<?:H/?,4;@HA3?<B23<BAHA30H4AF@H=B-94.H?423A<1D,F H)30H4AFH3,@H:,4;A,4;0/H ,H 2<</HD<?84;2H ?09,A4<;@34=HD4A3H
H<;@A?B.A4<;H/B?4;2HA3,AHA4:0H ,;/H <B?H=?<50.A@H 3,C0H-00;H .<:=90A0/H <;H A4:0H ,;/H ,AH :,E4:B:H C,9B0H A<H A30H 4AF H !H .,;H ?0.<::0;/H
H <;@A?B.A4<;H 1<?H
1BAB?0H=?<50.A@HD4A3HF<B?H<?H<A30?H<?2,;4G,A4<;@H-,@0/H<;H<B?H0E=0?40;.0@ H+0H3,C0H.<:=90A0/HH
=?<60.A@HD4A3H
H<;@A?B.A4<;H?0@B9A4;2H4;H<C0?H


H@.?00;@H4;@A,990/
H
B;AH(0;4<?H$,;,20:0;AH;,9F@AH
73B;A-B0;,>,?8
.<:H

H0,.3H9C/H
B0;,H&,?8HH
H

HH
117
zero waste • zero wasted water
%2$5'2)38%/,&:25.6
0(0%(56
9$+,'.+256$1'
35(6,'(17
-(11<&+$9(=
9,&(35(6,'(17
-2+1*5$17
35(6,'(173527(0325(
67(9(6.$1*
&200,66,21(5
)$,7+,0,7&+(//
&200,66,21(5
(/<6(0$7621
(;(&87,9(2)),&(5

CITY OF LOS ANGELES

CALIFORNIA
.$5(1%$66
0$<25
%85($82)6$1,7$7,21
%$5%$5$520(52
',5(&725$1'*(1(5$/0$1$*(5
9$&$17
&+,()23(5$7,1*2)),&(5
6$5$,%+$*$
&+,()),1$1&,$/2)),&(5
-8/,($//(1
1,&2/(%(51621
0$6'2-,5,
$/(;$1'(5(+(/28
52%(573277(5
$66,67$17',5(&7256
+,6$1*.,0
$&7,1*+<3(5,21(;(&87,9(3/$170$1$*(5
±± 
6287+%52$':$<
7+)/225
/26$1*(/(6&$

7(/



:::/$&,7<6$125*
$1(48$/(03/2<0(1723325781,7<(03/2<(5
Recyclable and made from recycled waste


  
  
     

)HEUXDU\
(/(&7521,&0$,/
7R:KRP,W0D\&RQFHUQ

/(77(52)5(&200(1'$7,21)25*&216758&7,21,1& 
* &RQVWUXFWLRQ
*
 KDV GHVLJQHG IDEULFDWHG DQG LQVWDOOHG WKRXVDQGV RI WKHLU WUDVK FDSWXUH GHYLFHVLQWKH&LW\ RI/RV$QJHOHV VLQFHWKH EXUHDX RI 6DQLWDWLRQ DQG(QYLURQPHQW /$6$1

DSSURYHG WKHLU &36 LQVHUWV DQG $56 FXUE RSHQLQJ VFUHHQV LQ   *¶V GHYLFHV DUH YHU\ HIIHFWLYH DW FDSWXULQJ WUDVK WKHLU LQVWDOODWLRQV DUH RI KLJK TXDOLW\ DQG WKH FRPSDQ\ LV SURIHVVLRQDODQGUHOLDEOH
,Q/$6$1DZDUGHG*&RQVWUXFWLRQD\HDUFRQWUDFWWRIDEULFDWHDQGLQVWDOO )XOO&DSWXUH&DWFK%DVLQ ,QVHUWVDQG&XUE2SHQLQJ6FUHHQ&RYHUV *¶V&360RGDQG$56
&/ GHYLFHV
 * LV RQH RI RQO\ WZR DSSURYHG YHQGRUV WKDW /$6$1 KDV IRXQG DFFHSWDEOH WR SURYLGH ERWK WKH FDWFK EDVLQ FRQQHFWRU SLSH VFUHHQV &36
 DQG DXWRPDWLF UHWUDFWDEOH VFUHHQV

$56
LQ&LW\RI/RV$QJHOHVSXEOLFULJKWRIZD\FDWFKEDVLQV *¶VLQVWDOODWLRQFUHZVDUH KLJKO\ VNLOOHGDQGFRPPXQLFDWHZHOOZLWKLQVSHFWRUVWKHLUZRUNLV SHUIRUPHG RQWLPHDQGZLWKLQ EXGJHWDQGWKHLU SURMHFWPDQDJHPHQW KDV EHHQHIILFLHQW7KHLU SHUVRQQHODUHYHU\JRRGDWSURYLGLQJDOOUHTXLUHGGRFXPHQWDWLRQDQGPDNLQJWKHSURFHVVHDV\ 7KHDSSURYDORI*GHYLFHVE\/$6$1OHDGWRWKHLQVWDOODWLRQRIWKHLU&360RGDQG$56&/ GHYLFHVRQLPSRUWDQW&LW\SURMHFWVVXFKDV

LA World Airports Roadways (LAWA RUE). 2024
LA Metro Westside Purple Line. 2024
LA Metro Regional Connector Corridor. 2023
LA Metro LAX Corridor Project. 2021
Port of Los Angeles. 2020
Hyperion Treatment Plant Screens. 2016
Branford Dry Well project. 2016
City of LA TMDLS – Machado Lake. 2015-16
LA Metro Exposition Rail Line. 2015
I-405 Widening Project. 2014
118
/HWWHURI5HFRPPHQGDWLRQ±*&RQVWUXFWLRQ

3DJH1R
, DP SOHDVHG WR RIIHU WKLV OHWWHU RI UHFRPPHQGDWLRQ IRU * &RQVWUXFWLRQ  %DVHG RQ RXU H[SHULHQFHZLWK*&RQVWUXFWLRQ,FDQUHFRPPHQGWKHLUSURGXFWVDQGVHUYLFHV  6LQFHUHO\
 -21$7+$1%$//
 $VVLVWDQW'LYLVLRQ0DQDJHU
 :DWHUVKHG3URWHFWLRQ'LYLVLRQ
 /$6DQLWDWLRQDQG(QYLURQPHQW
--%ME  
F
 0DUVD&KDQ/$6$1
119
120
121
February 14, 2025
Re: Letter of Recommendation for G2 Construction, Inc.

To Whom It May Concern,
G2 Construction has been awarded 6 contracts by the City of San Marino to install their ARSCL and CPS-Mod Full Capture System devices between 2020 and December 2024. Their projects were all successfully completed on time and within budget. G2’s work has been performed professionally, quickly, and with effective communication of their schedule, project status, and solutions to issues.

The City has been pleased with the quality of their installed devices, and G2’s CPS-Mod connector pipe screen is certified as a trash Full Capture System by the State Water Resources Control Board. Both their CPS and ARS devices are approved by LACDPW and will likely be installed in San Marino’s County-owned catch basins in the future.

G2 Construction’s personnel are easy to work with, and very responsive to the City’s requests.

My experience has been very positive, and the company has delivered on their promises to the City.

Based on our experience with G2 Construction, I can recommend their products and services.

Sincerely,
Amber Shah, P.E.

Parks & Public Works Director/City Engineer
2200 Huntington Drive
San Marino, CA 91108
[email protected]
P: (626) 300-0787
122
5050 N. Clark Avenue x Lakewood, California 90712 x (562) 866-9771 February 6, 2025
Orange County Public Works
Procurement Services
601 North Ross Street
Santa Ana, CA 92701
SUBJECT: G2 Construction, Inc. – Letter of Recommendation To Whom It May Concern:

The City of Lakewood contracted with G2 Construction on three (3) projects to install State Water Board certified CPS-Mod connector pipe screens and GITS grated inlet trash screens.

G2 successfully installed their products in 2016, 2018, and 2023 as part of the City’s FullCapture Catch Basin Insert Program to the satisfaction of the City. G2’s personnel have been very capable, and both projects installed as scheduled.

Our experience with G2 has been very positive, and I can recommend their products and services. Their team has been very professional and responsive to our needs, and they were quick to provide field evaluations of our catch basins and recommendations for our project.

Some of the City’s catch basins were unique and G2 was able to manufacture customized CPSMod devices that allowed us to meet regulations and the City’s water quality objectives.

Please feel free to contact me if you have any additional questions.

Sincerely,
Ms. Konya Vivanti
Environmental Programs Manager
City of Lakewood
5050 Clark Avenue
Lakewood CA, 90712
(562) 866-9771 ext. 2507
[email protected]
123
OCLSB CERTIFICATE EXPIRATION DATE: 10/31/2026
CERTIFICATE ID: 2017839
LEGAL COMPANY NAME: G2 Construction Inc
DOING BUSINESS AS (DBA) NAME 1:

DOING BUSINESS AS (DBA) NAME 2: G2 CONSTRUCTION INC
COMPANY HEADQUARTERS ADDRESS: 1352 East Borchard Ave.

Santa Ana, CA 92705
COMPANY PHONE NUMBER: 714/748-4242
COMPANY EMAIL: [email protected]
COMPANY FAX NUMBER:

COMPANY WEB ADDRESS www.g2construction.com
SERVICE AREA Orange
CONGRATULATIONS – Print and Save your OCLSB Certificate! Your business is now certified and ready to compete in a County competitive solicitation process as an Orange County Local Small Business.

THE COMPANY LISTED ON THIS CERTIFICATE MEETS THE

COUNTY OF ORANGE CERTIFICATION REQUIREMENTS AS AN
OCLSB
Click here to get help

*&RQVWUXFWLRQ,QF
124
March 28, 2024 CUCP# 41740
Metro File #6371
MR. JOHN ALVARADO
G2 Construction, Inc.
1352 East Borchard Ave
Santa Ana, CA 92705-4413
Subject: Disadvantaged Business Enterprise Certification Dear MR. JOHN ALVARADO:

We are pleased to advise you that after careful review of your application and supporting documentation, the Los Angeles County Metropolitan Transportation Authority (Metro) has determined that your firm meets the eligibility standards to be certified as a Disadvantaged Business Enterprise (DBE) as required under the U.S. Department of Transportation (U.S. DOT) Regulation 49 CFR Part 26, as amended. This certification will be recognized by all of the U.S. DOT recipients in California. Your firm will be listed in the California Unified Certification Program (CUCP) database of certified DBEs under the following specific area(s) of expertise that you have identified on the NAICS codes form of the application package:

NAICS 331491: NONFERROUS METAL (EXCEPT COPPER AND ALUMINUM) ROLLING, DRAWING, AND EXTRUDING NAICS 237310: HIGHWAY, STREET, AND BRIDGE CONSTRUCTION
NAICS 332313: PLATE WORK MANUFACTURING
Your DBE certification applies only for the above code(s). You may review your firms information in the CUCP DBE database which can be accessed at the CUCP website at https://californiaucp.dbesystem.com. Any additions and revisions must be submitted to Metro for review and approval.

In order to ensure your continuing DBE status, you are required to submit an annual update along with supporting documentation. If no changes are noted, then your DBE status remains current. If there are changes, Metro will review to determine continued DBE eligibility. Please note, your DBE status remains in effect unless Metro notifies you otherwise.

Also, should any changes occur that could affect your certification status prior to receipt of the annual update, such as changes in your firm's name, business/mailing address, ownership, management or control, or failure to meet the applicable business size standards or personal net worth standard, please notify Metro immediately. Failure to submit forms and/or change of information will be deemed a failure to cooperate under Section 26.109 of the Regulations.

Metro reserves the right to withdraw this certification if at any time it is determined that it was knowingly obtained by false, misleading, or incorrect information. Your DBE certification is subject to review at any time. The firm thereby consents to the examination of its books, records and documents by Metro.

Congratulations, and thank you for your interest in the DBE program. Should you have any questions, please contact us at (213) 922-2600. For information on Metro contracting opportunities, please visit our website at www.metro.net/connect.

Sincerely,
125
Ramon Ortiz
Director, Certification & Economic Development
126
March 28, 2024 Metro File #6371
MR. JOHN ALVARADO
G2 Construction, Inc.
1352 East Borchard Ave
Santa Ana, CA 92705-4413
Subject: Small Business Enterprise Certification
Dear MR. JOHN ALVARADO:

We are pleased to advise you that after careful review of your application and supporting documentation, the Los Angeles County Metropolitan Transportation Authority (Metro) has determined that your firm meets the eligibility standards to be certified as a Small Business Enterprise (SBE) as required under Metro's SBE Program. Your firm will be listed in Metro's SBE database of certified SBEs under the following specific areas of expertise:

NAICS 331491: NONFERROUS METAL (EXCEPT COPPER AND ALUMINUM) ROLLING, DRAWING, AND EXTRUDING NAICS 237310: HIGHWAY, STREET, AND BRIDGE CONSTRUCTION
NAICS 332313: PLATE WORK MANUFACTURING
Your SBE certification is valid for five years from the date of this letter and applies only for the above NAICS code(s). Any additions and revisions must be submitted to Metro for review and approval.

In order to ensure your continuing SBE status, you are required to submit an annual update along with supporting documentation. If no changes are noted, then your SBE status remains current. If there are changes, Metro will review to determine continued SBE eligibility. Please note, your SBE status remains in effect unless Metro notifies you otherwise.

After the five-year certification period, your entire file will be reviewed in order to ascertain continued SBE certification status. You will be notified of the pending SBE status review and any documentation updates necessary prior to the expiration date.

Also, should any changes occur that could affect your certification status prior to receipt of the annual update application, such as changes in your firm's name, business/mailing address, ownership, management or control, or failure to meet the applicable business size standards or personal net worth standard, please notify Metro immediately.

Metro reserves the right to withdraw this certification if at any time it is determined that it was knowingly obtained by false, misleading, or incorrect information. Your SBE certification is subject to review at any time. The firm thereby consents to the examination of its books, records, and documents by Metro.

Congratulations, and thank you for your interest in Metro's SBE Program. Should you have any questions, please contact us at (213) 922-2600. For information on Metro contracting opportunities, please visit our website at www.metro.net/connect.

Sincerely,
Ramon Ortiz
Director, Certification & Economic Development