AGENDA REPORT

CITY OF SAN CLEMENTE

CITY COUNCIL MEETING

CITY OF SAN CLEMENTE
Meeting Date: October 1, 2024 Agenda Item: 11H
Submitted By: Public Works
Prepared By: Belgin Cuhadaroglu, Senior Civil Engineer
Subject:
..titl e

CONSIDERATION OF A RESOLUTION AWARDING A CONSTRUCTION CONTRACT TO DIAMOND CONSTRUCTION & DESIGN FOR THE STORM DRAIN GRAVITY MAIN SWGM16135 REPAIRS, PROJECT NO. 26001; APPROVING A SUPPLEMENTAL APPROPRIATION IN THE AMOUNT OF $735,000 FROM THE STORM DRAIN FUND INTO ACCOUNT NO. 059- 553-43420-000-26001; AUTHORIZING THE CITY MANAGER TO EXECUTE THE CONSTRUCTION CONTRACT IN AN AMOUNT NOT TO EXCEED $573,637; AND FINDING

THE PROJECT CATEGORICALLY EXEMPT FROM THE CALIFORNIA ENVIRONMENTAL QUALITY ..body ACT
Fiscal Impact:

The total estimated construction cost for the Storm Drain Gravity Main SWGM-16135 Repairs is $735,000, funded from the Storm Drain Fund Depreciation Reserve / Storm Drain Rehabilitation, Account No. 059-553-43420-000-26001, which has a current account balance of $99,700. To provide funding for this storm drain repair, staff is recommending a supplemental appropriation in the amount of $735,000 from the Storm Drain Fund into Account No. 059-553-43420-000-26001, which will be funded by a loan from the Local Drainage Facilities Fund in an amount up to $735,000 from the Catch Basin and Strom Drain projects.

Summary:

Due to heavy rains during the winter months of 2024, a 30-inch corrugated storm drain metal pipe (CMP), as shown below, was corroded and failed, forming a 28-foot deep sinkhole at the bottom of the slope adjacent to Caltrans right-of-way. To circumvent further damage to the storm drain, staff is recommending replacement of a section of the storm drain line at a nominal depth and installation of a new manhole. A bid package was prepared and advertised, and competitive bids were received on September 18, 2024.

Sinkhole
38’x38’x28’ (Deep)
1 ( PROJECT
\,, LOCATION
Attachment 3
Meeting Date: October 1, 2024 Agenda Item: 11H

CITY OF SAN CLEMENTE
To make the repair, staff is recommending that the City Council award a construction contract (Attachment 2) to Diamond Construction & Design in an amount not to exceed $573,637 and approve a 19% project contingency for the Storm Drain Gravity Main SWGM-16135 Repairs, Project No. 26001.

Background:

Based on a Closed Circuit TV (CCTV) inspection of this storm drain pipe, staff found a corroded section of 30-inch corrugated storm drain metal pipe (CMP) between Camino de Los Mares and Interstate five that failed, and a 28-foot deep sinkhole was formed at the bottom of the slope. The project will backfill the sinkhole and replace approximately 230 linear feet of the corroded CMP pipe with a corrugated plastic pipe with at a normal depth of approximately five feet, instead of nearly 30 feet. An alternate bid item is included that provides construction of an additional 15 feet of storm drain pipe at the top of the slope connection, as needed, to be determined during construction when the existing pipe is exposed.

Staff prepared a bid package, notified local contractors, and advertised the project for competitive bidding on the PlanetBids website and in the SC Times. On September 18, 2024, the City received four (4) bids, Base Bids ranging from $558,637 to $930,950, as shown on the table below.
2 Meeting Date: October 1, 2024 Agenda Item: 11H.

CITY OF SAN CLEMENTE
Vendor Name City Base Bid
Amount
Base Bid and
Alternate
Diamond Construction & Design San Clemente $558,637 $573,637 HZS Engineering, Inc. Orange $577,006 $597,006
ZECO, Inc. Santa Ana $740,114 $784,114
GCI Construction, Inc. San Clemente $930,950 $970,950
Based on the lowest Base Bid plus the Alternate, the total estimated project construction cost is summarized below:

Construction Administration, Management $ 22,363
Geotechnical Construction Support Services. 30,000
Construction Contract 573,637
Contingency (19%) 109,000
Total Estimated Construction Cost $735,000
As required by state law and City policy, the contractor will be required to provide performance and payment bonds simultaneously with execution of the construction contract. Project plans and specifications are on file in the City Clerk’s office.

Council Options:
 Adopt Resolution No. 24-155 (Attachment 1), approving a supplemental appropriation in the amount of $735,000 from the Storm Drain Fund into Account No. 059-553-43420-000-26001; awarding the Storm Drain Gravity Main SWGM-16135 Repairs to Diamond Construction & Design; authorizing the City Manager to execute a construction contract in an amount not to exceed $573,637; approving a 19% project contingency of $109,000; and finding the project categorically exempt from CEQA under Class 2 (Replacement or Reconstruction, 14 CCR section 15302) of the State CEQA Guidelines.
 Modify and adopt Resolution 24-155.
 Continue the item and direct staff to provide additional information.  Do not adopt Resolution No. 24-155 and put the project on hold.

Environmental Review/Analysis:

This project is categorically exempt from the California Environmental Quality Act (CEQA) as it pertains a replacement of an existing storm drain line under Class 2 of the state CEQA Guidelines, Section 15302 - Replacement or Reconstruction. A notice of exemption will be filed for this project.
3 Meeting Date: October 1, 2024 Agenda Item: 11H

CITY OF SAN CLEMENTE
Recommended Actions:

Staff recommends that the City Council adopt Resolution No. 24-155, which will:
..recommendation

1. Approve a supplemental appropriation in the amount of $735,000 from the Storm Drain Fund into Account No. 059-553-43420-000-26001, which will be by a loan from the Local Drainage Fund in an amount up to $735,000 from the Catch Basin and Storm Drain projects;

2. Award a contract to Diamond Construction & Design, as the lowest responsible and responsive bidder, for the Storm Drain Gravity Main SWGM-16135 Repairs, Project No. 26001;

3. Authorize the City Manager to execute a contract with Diamond Construction & Design in an amount not to exceed $573,637 in a form substantially similar to Contract No. 24-56 (Attachment 2) for the Storm Drain Gravity Main SWGM-16135 Repairs, Project No. 26001;

4. Approve a 19% construction contingency of $109,000 for this Project; and

5. Find the Storm Drain Gravity Main SWGM-16135 Repairs, Project No. 26001, categorically exempt from the CEQA under Class 2 (Replacement or Reconstruction, 14 CCR section 15302) of the State CEQA Guidelines.
..end
Attachment:

1. Resolution No. 24-155

2. Contract No. C24-56 (without attachments)
Notification:

All bidders.