AGENDA REPORT

CITY OF SAN CLEMENTE
City Council Meeting
Meeting Date: 8/15/2023 Agenda Item: 6N
Department: Public Works
Prepared By Kiel Koger, Public Works Director/City Engineer Subject:

CONSIDERATION OF A RESOLUTION RATIFYING A SECOND EMERGENCY CONSTRUCTION CONTRACT WITH ALLIANCE DIVERSIFIED ENTERPRISES, INC. FOR THE EMERGENCY

SLOPE STABILIZATION REPAIRS AT CASA ROMANTICA FOR A TOTAL CONTRACT AMOUNT NOT TO EXCEED $7,760,800
Fiscal Impact:

Yes. The emergency slope stabilization repairs will be completed for a not to exceed amount of $7,760,800, which includes a 10% contingency. The work is being performed by force account (time and materials) due to the uncertain condition at the site and will be funded from Account Number # 001-481-43470-000-23502 (Casa Romantica Stabilization).

Summary:

A landslide on April 27, 2023, at the City owned Casa Romantica facility necessitated an emergency response to ensure that more damage was not caused to an adjacent condominium building and the railroad tracks located at the bottom of the failed slope. The initial temporary repairs including regrading and reshaping the site did not stabilize the slope and more substantial repairs were needed immediately to secure the building and site to protect life and property prior to the upcoming winter rain season. The proposed resolution ratifies a second emergency construction contract with Alliance Diversified Enterprises, Inc. (ADEI) for the emergency slope stabilization repairs at Casa Romantica.

Background:

The western slope at Casa Romantica above the railroad tracks failed on the afternoon of April 27, 2023. The landslide deposited debris and soil near the railroad tracks below the site to the west and against the condominium building to the north. The City hired ADEI who specializes in emergency slope stability and foundation repairs, to mobilize to the site on Friday, May 12, 2023 to start the repairs under the supervision of a local geotechnical engineering firm, LGC Geotechnical, Inc. The emergency work was initially completed on June 2, 2023 but the slope continued to move over the next 2 days even with additional shaping and grading. The slope started moving again on June 5, 2023 and continued to slowly creep, necessitating more substantial repairs to secure the building and site to protect life and property prior to the winter rain season.

Surveying and design work has already started on the next phase of work to include the installation of tiebacks and grade beams along the slope beneath the Casa Romantica building to secure the unstable slope. The tiebacks will be drilled 6 feet on center in rows across the slope and founded approximately 70-110 feet into the slope and secured with grade beams. As the tiebacks and grade beams are installed, the slope will be excavated from the top to the bottom. The slope will then be reconstructed in front of the grade beams with the use of geogrid reinforcement placed within the compacted soil backfill. The landslide soil mass will be need to be excavated, hauled off site and CITY OF SAN CLEMENTE Page 1 of 3 Printed on 8/10/2023
powered by Legistar™ 1
Attachment 3
910 Calle Negocio
2nd Floor
San Clemente, California
www.san-clemente.org
Meeting Date: 8/15/2023 Agenda Item: 6N
compacted soil backfill. The landslide soil mass will be need to be excavated, hauled off site and blended with other soil material and then brought back to the site to be placed and compacted in lifts to rebuild the slope. The exact amount of soil that needs to be excavated and then replaced and compacted is unknown due to the possible presence of another landslide mass at the base of slope near the railroad tracks.

The City will continue to work closely with OCTA and Metrolink on coordination of the work as well as keep the California Coastal Commission updated on our progress to stabilize the slope and seek out alternative funding sources.

Council Options:
· Adopt Resolution No. 23-84, ratifying an emergency construction contract with Alliance Diversified Enterprises, Inc. for emergency slope stabilization repairs at Casa Romantica for a total contract amount not to exceed $7,760,800.
· Modify and adopt Resolution No. 23-84.
· Continue the item with direction to provide additional information.

Environmental Review/Analysis:

Under the State CEQA Guidelines, an emergency is defined as a sudden, unexpected occurrence, involving a clear and imminent danger, demanding immediate action to prevent or mitigate loss of, or damage to life, health, property, or essential public services and includes fire, flood, earthquake, or other soil or geologic movements, as well as such occurrences as riot, accident or sabotage. This work meets the definition of an emergency.

Before proceeding with the temporary repairs, staff determined that the project qualified for an exemption pursuant to Section 15269(c) of the State CEQA Guidelines as specific actions necessary to prevent or mitigate an emergency. The City Council made the same finding with respect to the future planned repairs on July 18, 2023.

The California Coastal Commission was notified on May 11, 2023 and June 8, 2023 of the immediate emergency action needed to stabilize the slope. A meeting with the CCC on July 6, 2023 was also held to discuss the work required going forward.

Recommended Actions:

Staff Recommendation
STAFF RECOMMENDS THAT the City Council adopt Resolution No. 23-84, which would:

1. Ratify an Emergency Construction Contract with Alliance Diversified Enterprises, Inc. on a time and materials basis for an amount not to exceed $7,760,800 for the emergency slope stabilization repairs at Casa Romantica to include construction of tiebacks and grade beams as well as reconstructing the slope with geogrid reinforcement and compacted soil backfill.

CITY OF SAN CLEMENTE Page 2 of 3 Printed on 8/10/2023
powered by Legistar™ 2
Meeting Date: 8/15/2023 Agenda Item: 6N
Attachment:

1. Resolution No. 23-84

2. Construction Contract
Notification:

Casa Romantica, OCTA/Metrolink, Reef Gate HOA
CITY OF SAN CLEMENTE Page 3 of 3 Printed on 8/10/2023
powered by Legistar™ 3
ATTACHMENT 1
RESOLUTION NO. 23-84

A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF

SAN CLEMENTE, CALIFORNIA, RATIFYING A SECOND

EMERGENCY CONSTRUCTION CONTRACT WITH
ALLIANCE DIVERSIFIED ENTERPRISES, INC. FOR THE

EMERGENCY SLOPE STABILIZATION REPAIRS AT CASA

ROMANTICA FOR A TOTAL CONTRACT AMOUNT NOT
TO EXCEED $7,760,800
WHEREAS, a landslide on April 27, 2023 necessitated an emergency response to ensure that more damage was not caused to a condominium building and railroad tracks adjacent to the failed slope; and
WHEREAS, the initial temporary repairs completed on June 4, 2023 including regrading and reshaping the site did not stabilize the slope and the slope continued to creep slowly; and
WHEREAS, in order to protect public health and safety, more substantial repairs were needed immediately to secure the building and site to protect life and property prior to the upcoming winter rain season; and
WHEREAS, the next phase of work includes the installation of tiebacks and grade beams along the slope beneath the Casa Romantica building to secure the unstable slope; and
WHEREAS, the tiebacks will be drilled 6 feet on center in rows across the slope and founded approximately 70-110 feet into the slope and secured with grade beams; and WHEREAS, as the tiebacks and grade beams are installed, the slope will be excavated from the top to the bottom. The slope will then be reconstructed in front of the grade beams with the use of geogrid reinforcement placed within the compacted soil backfill; and
WHEREAS, the landslide soil mass will be need to be excavated, hauled off site and blended with other soil material and then brought back to the site to be placed and compacted in lifts to rebuild the slope; and
WHEREAS, the exact amount of soil that needs to be excavated and then replaced and compacted is unknown due to the possible presence of another landslide mass at the base of slope near the railroad tracks; and
WHEREAS, on July 18, 2023, the City Council determined that an emergency exists due to the potential failure of an existing slope and that the situation requires immediate action to prevent or mitigate impairment to property and public services that 4 Resolution No. 23-84 Page 2
might otherwise occur if the City were required to incur delays attributed to the typical engineering analysis and competitive bidding process; and WHEREAS, on July 18, 2023, the City Council also determined that the public interest and necessity demand the immediate expenditure of public funds to safeguard public health; and
WHEREAS, under the California Environmental Quality Act (CEQA) Guidelines, an emergency is defined as a sudden, unexpected occurrence, involving a clear and imminent danger, demanding immediate action to prevent or mitigate loss of, or damage to life, health, property, or essential public services and includes fire, flood, earthquake, or other soil or geologic movements, as well as such occurrences as riot, accident or sabotage; and
WHEREAS, on July 18, 2023, the City Council determined that this project meets the definition of an emergency and is exempt from CEQA pursuant to Section 15269(c) of the State CEQA Guidelines as specific actions necessary to prevent or mitigate an emergency; and
WHEREAS, on July 18, 2023, the City Council authorized and directed staff to take such actions as are necessary and proper to start immediately on the emergency slope stabilization repairs at Casa Romantica, including entering into a contract and bringing a future agenda item to City Council to ratify such; and
WHEREAS, on ________, 2023, the City Manager entered into an Emergency Construction Contract with Alliance Diversified Enterprises, Inc. on a time and materials basis for an amount not to exceed $7,760,800, which amount includes a 10% contingency, for the emergency slope stabilization repairs at Casa Romantica to include construction of tiebacks and grade beams as well as reconstructing the slope with geogrid reinforcement and compacted soil backfill.

NOW, THEREFORE, the City Council of the City of San Clemente hereby finds, resolves and determines as follows:

SECTION 1. That the foregoing recitals are true and accurate and are incorporated herein.

SECTION 2. That the second Emergency Construction Contract with Alliance Diversified Enterprises, Inc. on a time and materials basis for an amount not to exceed $7,760,800 which includes a 10% contingency for the emergency slope stabilization repairs at Casa Romantica to include construction of tiebacks and grade beams as well as reconstructing the slope with geogrid reinforcement and compacted soil backfill entered into by the City Manager on ________, 2023 is hereby ratified and approved.

SECTION 3. The City Clerk shall certify to the passage and adoption of this resolution and enter it into the book of original resolutions. 5 Resolution No. 23-84 Page 3
PASSED AND ADOPTED this _____ day of August, 2023.
_______________________
Mayor of the City of
San Clemente, California
ATTEST:
__________________________
CITY CLERK of the City of
San Clemente, California

STATE OF CALIFORNIA )
COUNTY OF ORANGE ) §

CITY OF SAN CLEMENTE )
I, LAURA CAMPAGNOLO, City Clerk of the City of San Clemente, California, do hereby certify that Resolution No. 23-84 was adopted at a regular meeting of the City Council of the City of San Clemente held on _______ day of August 2023, by the following vote:

AYES:

NOES:

ABSENT:

IN WITNESS WHEREOF, I have hereunto set my hand and affixed the official seal of the City of San Clemente, California, this _____ day of _________________, ________.
_______________________
CITY CLERK of the City of
San Clemente, California
Approved as to form:
___________________________
Elizabeth A. Mitchell, City Attorney
6 1
ATTACHMENT 2
7 CITY OF SAN CLEMENTE CONSTRUCTION CONTRACT

CASA ROMANTICA SLOPE STABILIZATION REPAIR

1. PARTIES AND DATE.

This Contract is made and entered into this __ day of August, 2023 by and between the City of San Clemente, a public agency of the State of California ("City") and Al liance Diversified Enterprises, Inc., a California corporation with its principal place of business at 665 Opper Street, Escondido, CA 92029 ("Contractor''). City and Contractor are sometimes individually referred to as "Party" and collectively as "Parties" in this Contract.

2. RECITALS.

2. 1 City. City is a public agency organized under the laws of the State of California, with power to contract for services necessary to achieve its purpose.

2.2 Contractor. Contractor desires to perform and assume responsibility for the provision of certain construction services required by the City on the terms and conditions set forth in this Contract. Contractor represents that it is duly licensed and experienced in providing shoring to include construction of tieback systems and grade beams as well as slope stabilization techniques and excavation/grading related construction services to public clients, that it and its employees or subcontractors have all necessary licenses and permits to perform the services in the State of California. The following license classifications are required for this Project: Class A - General Engineering.

2.3 Project. City desires to engage Contractor to render such services for the Casa Romantica Slope Stabilization Repairs ("Project") as set forth in this Contract.

2.4 Project Documents & Certifications. Contractor has obtained, and delivers concurrently herewith, a performance bond, a payment bond, and all insurance documentation, as required by the Contract.

3. TERMS

3.1 Incorporation of Documents. This Contract includes and hereby incorporates in full by reference the following documents, including all exhibits, drawings, specifications and documents therein, and attachments and addenda thereto:
• Services/Schedule (Exhibit "A")
• Plans and Specifications (Exhibit "B")
• Special Conditions (Exhibit "C")
• Contractor's Certificate Regarding Workers' Compensation (Exhibit "D") • Public Works Contractor Registration Certification (Exhibit "E") • Payment and Performance Bonds (Exhibit "F")
• Federal Requirements (Exhibit "G")- NIA
• Insurance Requirements (Exhibit "H)
8 3.2 Contractor's Basic Obligation; Scope of Work. Contractor promises and agrees, at its own cost and expense, to furnish to the City all labor, materials, tools, equipment, services, and incidental and customary work necessary to fully and adequately complete the Project, including all structures and facilities necessary for the Project or described in the Contract (hereinafter sometimes referred to as the "Work"), for a Total Contract Price as specified pursuant to this Contract. All Work shall be subject to, and performed in accordance with the above referenced documents, as well as the exhibits attached hereto and incorporated herein by reference. The plans and specifications for the Work are further described in Exhibit "B" attached hereto and incorporated herein by this referi nce. Special Conditions, if any, relating to the Worl< are described in Exhibit "C" attached hereto and incorporated herein by this reference.

3.2. ·1 Change in Scope of Work. Any change in the scope of the Work, method of performance, nature of materials or price thereof, or any other matter materially affecting the performance or nature of the Work shall not be paid for or accepted unless such change, addition or deletion is approved in writing by a change order executed by the City. Should Contractor request a change order due to unforeseen circumstances affecting the performance of the Work, such request shall be made within fi ve (5) business days of the date such circumstances are discovered or shall waive its right to request a change order due to such circumstances. If the Parties cannot agree on any change in price required by such change in the Work, the City may direct the Contractor to proceed with the performance of the change on a time and materials basis.

3.2.2 Substitutions/"Or Equal". Pursuant to Public Contract Code Section 3400(b), the City may make a finding that designates certain products, things, or services by specific brand or trade name. Unless specifically designated in this Contract, whenever any material, process, or article is indicated or specified by grade, patent, or proprietary name or by name of manufacturer, such Specifications shall be deemed to be used for the purpose of facilitating the description of the material, process or article desired and shall be deemed to be followed by the words "or equal."
Contractor may, unless otherwise stated, offer for substitution any material, process or article which shall be substantially equal or better in every respect to that so indicated or specified in this Contract. However, the City may have adopted certain uniform standards for certain materials, processes and articles. Contractor shall submit requests, together with substantiating data, for substitution of any "or equal" material, process or article no later than thirty-five (35) days after award of the Contract. To facilitate the construction schedule and sequencing, some requests may need to be submitted before thirty-five (35) days after award of Contract. Provisions regarding submission of "or equal" requests shall not in any way authorize an extension of time for performance of this Contract. If a proposed "or equal" substitution request is rejected, Contractor shall be responsible for providing the specified material, process or article.

The burden of proof as to the equality of any material, process or article shall rest with Contractor.

The City has the complete and sole discretion to determine if a material, process or article is an "or equal" material, process or article that may be substituted. Data required to substantiate requests for substitutions of an "or equal" material, process or article data shall include a signed affidavit from Contractor stating that, and describing how, the substituted "or equal" material, process or article is equivalent to that specified In every way except as listed on the affidavit. Substantiating data shall include any and all illustrations, specifications, and other relevant data including catalog information which describes the requested substituted "or equal" material, process or article, and substantiates that it is an "or equal" to the material, process or article. The substantiating data must also Include information regarding the durability and lifecycle 2 9
cost of the requested substituted "or equal" material, process or article. Failure to submit all the required substantiating data, including the signed affidavit, to the City in ;3 timely fashion will result in the rejection of the proposed substitution.

Contractor shall bear all of the City's costs associated with the review of substitution requests. Contractor shall be responsible for all costs related to a substituted "or equal" material, process or article. Contractor is directed to the Special Conditions (if any) to review any findings made pursuant to Public Contract Code section 3400.

3.3 Period of Perfonnance.

3.3.1 Contract Time. The term of this Agreement shall be from July 25, 2023 until the work is completed to the satisfaction of the City on a time and materials basis. Contractor shall perform its Worl< in strict accordance with any completion schedule, construction schedule or project milestones developed by the City. Such schedules or milestones may be included as part of Exhibits "A" or ''B" attached hereto, or may be provided separately in writing to Contractor.

3.3.2 Force Majeure. Neither City nor Contractor shall be considered in default of this Contract for delays in performance caused by circumstances beyond the reasonable control of the non-performing party. For purposes of this Contract, such circumstances include but are not limited to, abnormal weather conditions; floods; earthquakes; fire; pandemics or epidemics; war; riots and other civil disturbances; strikes, lockouts, work slowdowns, and other labor disturbances; sabotage or judicial restraint. Should such circumstances occur, the nonperforming party shall, within a reasonable time of being prevented from performing, give written notice to the. other party describing the circumstances preventing continued performance and the efforts being made to resume performance of this Contract. Contractor's exclusive remedy in the event of delay covered under this section shall be an extension of the Contract Time.

3.3.3 Liquidated Damages. [RESERVED.]

3.4 Standard of Performance: Performance of Employees. Contractor shall perform all Work under this Contract in a skillful and workmanlike manner, and consistent with the standards generally recognized as being employed by professionals in the same discipline in the State of California. Contractor represents and maintains that it is skilled in the professional calling necessary to perform the Work. Contractor warrants that all employees and subcontractors shall have sufficient skill and experience to perform the Work assigned to them. Finally, Contractor represents that it, its employees and subcontractors have all iicenses, permits, qualifications and approvals of whatever nature that are legally required to perform the Work, including any required business license, and that such licenses and approvals shall be maintained throughout the term of this Contract. As provided for in the indemnification provisions of this Contract, Contractor shall perform, at its own cost and expense and without reimbursement from the City, any work necessary to correct errors or omissions which are caused solely by Contractor's failure to comply with the standard of care provided for herein. Any employee who is determined by the City to be uncooperative, incompetent, a threat to the safety of persons or the Work, or any employee who fails or refuses to perform the Work in a manner consistent with the terms and conditions of this Agreement and acceptable to the City, shall be promptly removed from the Project by Contractor and shall not be re-employed on the Work.
3 10

3.5 Control and Payment of Subordinates; Contractual Relationship. City retains Contractor on an independent contractor basis and Contractor is not an employee of City. Any additional personnel performing the work governed by this Contract on behalf of Contractor shall at all times be under Contractor's exclusive direction and control. Contractor shall pay all wages, salaries, and other amounts due such personnel in connection with their performance under this Contract and as required by law. Contractor shall be responsible for all reports and obligations respecting such additional personnel, including, but not limited to: social security taxes, income tax withholding, unemployment insurance, and workers' compensation insurance.

3.6 City's Basic Obligation. City agrees to engage and does hereby engage Contractor as an independent contractor to furnish all materials and to perform all Work according to the temis and conditions herein contained for the sum set forth above. Except as otherwise provided in the Contract, the City shall pay to Contractor, as full consideration for the satisfactory performance by Contractor of the services and obligations required by this Contract, the below- referenced compensation in accordance with compensation provisions set forth in the Contract.

3.7 Compensation and Payment.

3. 7.1 Amount of Compensation. As consideration for performance of the Work required herein, City agrees to pay Contractor a Total Contract Price not to exceed Seven Million, Seven Hundred Sixty Thousand, Eight Hundred Dollars ($7,760,800} which includes a 10% contingency for unforeseen conditions. The work will be done by force account (time and materials) under the direction of the Public Works Director/City Engineer and LGC Geotechnical, Inc. The time and materials rate will be based upon the Caltrans force account costs, including allowable markups, and equipment costs, etc.
https://dot.ca.gov/-/media/dot-media/programs/construction/documents/equipment-rental-ratesand-labor-surcharge/book 2023.pdf ·

3. 7 .2 Payment of Compensation. If the Work is scheduled for completion in thirty (30) or less . calendar days, City will arrange for payment of the Total Contract Price upon completion and approval by City of the Work. If the Work is scheduled for completion in more than thirty (30) calendar days, City will pay Contractor on a monthly basis as provided for herein.

On or before the fifth (5th) day of each month, Contractor shall submit to the City an itemized application for payment in the fomiat supplied by the City Indicating the amount of Work completed since commencement of the Work or since the last progress payment. These applications shall be supported by evidence which is required by this Contract and such other documentation as the City may require. The Contractor shall certify that the Work for which payment is requested has been done and that the materials listed are stored where indicated. Contractor may be required to furnish a detailed schedule of values upon request of the City and in such detail and form as the City shall request, showing the quantities, unit prices, overhead, profit, and all other expenses involved in order to provide a basis for determining the amount of progress payments.

3.7.3 Prompt Payment. City shall review and pay all progress payment requests in accordance with the provisions set forth in Section 20104.50 of the California Public Contract Code. However, no progress payments will be made for Work not completed in accordance with this Contract. Contractor shall comply with all applicable laws, rules and regulations relating to the proper payment of Its employees, subcontractors, suppliers or others.

3.7.4 · Contract Retentions. From each approved progress estimate, five percent (5%) will be deducted and retained by the City, and the remainder will be paid to Contractor. All 4 11
Contract retention shall be released and paid to Contractor and subcontractors pursuant to Cal ifornia Public Contract Code Section 71 07.

3.7.5 Other Retentions. In addition to Contract retentions, the City may deduct from each progress payment upon written notice to Contractor and Contractor's failure within three (3) business days to commence and continue to cure or perform with di ligence and promptness, an amount necessary to protect City from loss because of: (1) liquidated damages which have accrued as of the date of the application for payment; (2) any sums expended by the City in performing any of Contractor's obligations under the Contract which Contractor has fa iled to perform or has performed inadequately; (3) defective Work not remedied; (4) stop notices as allowed by state law; (5) unsatisfactory prosecution of the Work by Contractor; (6) failure of Contractor to maintain or submit on a timely basis proper and sufficient documentation as required by the Contract or by City during the prosecution of the Work; (7) any sums representing expenses, losses, or damages as determined by the City, incurred by the City for which Contractor is liable under the Contract; and (8) any other sums which the City is entitled to recover from Contractor under the terms of the Contract or pursuant to state law, including Section 1727 of the California Labor Code. The failure by the City to deduct any of these sums from a progress payment shall not constitute a waiver of the City's right to such claims.

3.7.6 Substitutions for Contract Retentions. In accordance with California Public Contract Code Section 22300, the City will permit the substitution of securities for any monies withheld by the City to ensure performance under the Contract. At the request and expense of Contractor, securities equivalent to the amount withheld shall be deposited with the City, or with a state or federally chartered bank in California as the escrow agent, and thereafter the City shall then pay such monies to Contractor as they come due. Upon satisfactory completion of the Contract, the securities shall be returned to Contractor. For purposes of this Section and Section 22300 of the Public Contract Code, the term "satisfactory completion of the contract" shall mean the time the City has issued written final acceptance of the Work and filed a Notice of Completion as required by law and provisions of this Contract. Contractor shall be the beneficial owner of any securities substituted for monies withheld and shall receive any interest thereon. The escrow agreement used for the purposes of this Section shall be in the form provided by the City.

3.7.7 Title to Work. As security for partial, progress, or other payments, title to Work for which such payments are made shall pass to the City at the time of payment. To the extent that title has not previously been vested in the City by reason of payments, full title shall pass to the City at delivery of the Work at the destination and time specified In this Contract. Such transferred title shall in each case be good, free and clear from any and all security interests, liens, or other encumbrances. Contractor promises and agrees that it will not pledge, hypothecate, or otherwise encumber the items in any manner that would result in any lien, security interest, charge, or claim upon or against said items. Such transfer of title shall not imply acceptance by the City, nor relieve Contractor from the responsibility to strictly comply with the Contract, and shall not relieve Contractor of responsibility for any loss of or damage arising from any lien, security interest, charge or claims upon or against said items resulting solely from Contractor and consistent with the terms and conditions of this Agreement.

3.7.8 Labor and Material Releases. Contractor shall furnish City with labor and material releases from all subcontractors performirig work on, or furnishing materials for, the Work governed by this Contract prior to final payment by City.

Prevailing Wages. Contractor is aware of the requirements of California Labor Code Section 1720 et seq., and 1770 et seq., as well as California Code of Regulations, Title 8, Section 16000 et 5 12
seq., ("Prevailing Wage Laws"), which require the payment of prevailing wage rates and the performance of other requirements on "public works" and "maintenance" projects. Since the Services are being performed as part of an applicable "public worl<s" or "maintenance" project. as defined by the Prevailing Wage Laws, and since the total compensation is $1,000 or more, Contractor agrees to fully comply with such Prevailing Wage Laws. City shall provide Contractor with a copy of the prevailing rates of per diem wages in effect at the commencement of this Contract upon request. Contractor shall make copies of the prevailing rates of per diem wages for each craft, classification or type of worker needed to execute the Services available to interested parties upon request, and shall post copies at Contractor's principal place of business and at the project site. Contractor shall defend, indemnify and hold the City, its officials, officers, employees and agents free and harmless from any claim or liability arising out of any failure or alleged failure to comply with the Prevailing Wage Laws. Contractor and any subcontractor shall forfeit a penalty of up to $200 per calendar day or portion thereof for each worker paid less than the prevailing wage rates.

3.7.9 Apprenticeable Crafts. When Contractor employs workmen in an apprenticeable craft or trade, Contractor shall comply with the provisions of Section 1777 .5 of the California Labor Code with respect to the employment of properly registered apprentices upon public works . The primary responsibility for compliance with said section for all apprenticeable occupations shall be with Contractor. The Contractor or any subcontractor that is determined by the Labor Commissioner to have knowingly violated Section 1777 .5 shall forfeit as a civil penalty an amount not exceeding $100 for each full calendar day of noncompliance, or such greater amount as provided by law.

3.7.10 Hours of Work. Contractor is advised that eight (8) hours labor constitutes a legal day's work. Pursuant to Section 1813 of the California Labor Code, Contractor shall forfeit a penalty of $25. 00 per worker for each day that each worker is permitted to work more than eight (8) hours in any one calendar day and forty (40) hours in any one calendar week, except when payment for overtime is made at not less than one and one-half (1-1/2) times the basic rate for that worker.

3.7.11 Payroll Records. Contractor and each subcontractor shall keep an accurate payroll record, showing the name, address, social security number, work classification, straight time and overtime hours worked each day and week, and the actual per diem wages paid to each journeyman, apprentice, worker, or other employee employed by him or her in connection with the public work. The payroll records shall be certified and shall be available for inspection at all reasonable hours at the principal office of Contractor in the manner provided in Labor Code section 1776. In the event of noncompliance with the requirements of this section, Contractor shall have 10 days in which to comply subsequent to receipt of written notice specifying in what respects such Contractor must comply with this section. Should noncompliance still be evident after such 10-day period, Contractor shall, as a penalty to City, forfeit not more than $100.00 for each calendar day or portion thereof, for each worker, until strict compliance is effectuated. The amount of the forfeiture is to be determined by the Labor Commissioner. A contractor who is found to have violated the provisions of law regarding wages on Public Works with the intent to defraud shall be ineligible to bid on Public Works contracts for a period of one to three years as determined by the Labor Commissioner. Upon the request of the Division of Apprenticeship Standards or the Division of Labor Standards Enforcement, such penalties shall be withheld from progress payments then due. The responsibility for compliance with this section is on Contractor.

The requirement to submit certified payroll records directly to the Labor Commissioner under Labor Code section 1771.4 shall not apply to work performed on a public works project that is exempt pursuant to the small project exemption specified in Labor Code Section 1771.4. 6 13
Contractor and Subcontractor Registration. Pursuant to Labor Code sections 1725.5 and 1771 .1, all contractors and subcontractors that wish to bid on, be listed in a bid proposal, or enter into a contract to perform public work must be registered with the Department of Industrial Relations.

No bid will be accepted nor any contract entered into without proof of the contractor's and subcontractors' current registration with the Department of Industrial Relations to perform public work. Contractor is directed to review, fi ll out and execute the Public Works Contractor Registration Certification attached hereto as Exhibit "E" prior to contract execution.

Notwithstanding the foregoing, the contractor registration requirements mandated by Labor Code Sections 1725.5 and 1771.1 shall not apply to work performed on a public works project that is exempt pursuant to the small project exemption specified in Labor Code Sections 1725.5 and '1771.'1.

3.7.12 Labor Compliance; Stop Orders. This Project is subject to compliance monitoring and enforcement by the Department of Industrial Relations. It shall be the Contractor's sole responsibility to evaluate and pay the cost of complying with all labor compliance requirements under this Contract and applicable law. Any stop orders issued by the Department of Industrial Relations against Contractor or any subcontractor that affect Contractor's performance of Work, including any delay, shall be Contractor's sole responsibility. Any delay arising out of or resulting from such stop orders shall be considered Contractor caused delay subject to any applicable liquidated damages and shall not be compensable by the City.

Contractor shall defend, indemnify and hold the City, its officials, officers, employees and agents free and harmless from any claim or liability arising out of stop orders issued by the Department of Industrial Relations against Contractor or any subcontractor.

3.8 Performance of Work: Jobsite Obligations.
3:8.1 Water Quality Management and Compliance.

3.8.1.1 Water Quality Management and Compliance. Contractor shall keep itself and all subcontractors, staff, and employees fully informed of and in compliance with all local, state and federal laws, rules and regulations that may impact, or be implicated by the performance of the Work including, without limitation, all applicable provisions of the Federal Water Pollution Control Act (33 U.S.C. §§ 1300); the California Porter-Cologne Water Quality Control Act (Cal Water Code§§ 13000-14950); local ordinances regulating discharges of storm water; and any and all regulations, policies, or permits issued pursuant to any such authority regulating the discharge of pollutants, as that tenn is used in the Porter-Cologne Water Quality Control Act, to any ground or surface water in the State.

3.8.1 .2 Compliance with the Statewide Construction General Permit. Contractor shall comply with all conditions of the most recent iteration of the National Pollutant Discharge Elimination System General Permit for Storm Water Discharges Associated with Construction Activity, issued by the California State Water Resources Control Board ("Permit"). It shall be Contractor's sole responsibility to file a Notice of Intent and procure coverage under the Permit for all construction activity which results in the disturbance of more than one acre of total land area or which is part of a larger common area of development or sale. Prior to initiating work, Contractor shall be solely responsible for preparing and implementing a Storm Water Pollution Prevention Plan (SWPPP) as required by the Permit. Contractor shall be responsible for procuring, implementing and complying with the provisions of the Penn it and the SWPPP, including the standard provisions, and monitoring and reporting requirements as required by the Permit. The Permit requires the SWPPP to be a "living document" that changes as necessary to meet the conditions and requirements of the job site as it progresses through difference phases of construction and is subject to different weather conditions. It shall be 7 14
Contractor's sole responsibility to update the SWPPP as necessary to address conditions at the project site.

3.8.1.3 Other Water Quality Rules Regulations and Policies.

Contractor shall comply with the lawful requirements of any applicable municipality, drainage City, or local agency regarding discharges of storm water to separate storm drain systems or other watercourses under their jurisdiction, including applicable requirements in municipal storm water management programs.

3.8.1.4 Cost of Compliance. [Intentionally omitted).

3.8.1.5 Liability for Non-Compliance. Failure to comply with the Permit is a violation of federal and state law. Pursuant to the indemnification provisions of this Contract, Contractor hereby agrees to defend, indemnify and hold harmless the City and its officials, officers, employees, volunteers and agents for any alleged violations. In addition, City may seek damages from Contractor for any delay in completing the Work in accordance with the Contract, if such delay is caused by or related to Contractor's failure to comply yvith the Permit.

3.8.1.6 Reservation of Right to Defend. City reserves the right to defend any enforcement action brought against the City for Contractor's .failure to comply with the Permit or any other relevant water quality law, regulation, or policy. Pursuant to the indemnification provisions of this Contract, Contractor hereby agrees to be bound by, and to reimburse the City for the costs (including the City's attorney's fees) associated with, any settlement reached between the City and the relevant enforcement entity.

3.8.1.7 Training. In addition to the standard of performance requirements set forth In paragraph 3.4, Contractor warrants that all employees and subcontractors shall have sufficient skill and experience to perform the Work assigned to them without Impacting water quality in violation of the laws, regulations and policies described in paragraph 3.8.1 . Contractor further warrants that it, its employees and subcontractors will receive adequate training, as determined by City, regarding the requirements of the laws, regulations and policies described in paragraph 3.8.1 as they may relate to the Work provided under this Agreement. Upon request, City will provide the Contractor with a list of training programs that meet the requirements of this paragraph.

3.8.2 Safety. Contractor shall execute and maintain its work so as to avoid injury or damage to any person or property. Contractor shall comply with the requirements of the specifications relating to safety measures applicable in particular operations or kinds of work. In carrying out its Work, Contractor shall at all times be in compliance with all applicable local, state and federal laws, rules and regulations, and shall exercise all necessary precautions for the safety of employees appropriate to the nature of the Work and the conditions under which the Work is to be performed. Safety precautions as applicable shall include, but shall not be limited to, adequate life protection and lifesaving equipment; adequate illumination for underground and night operations; Instructions in accident prevention for all employees, such as machinery guards, safe walkways, scaffolds, ladders, bridges, gang planks, confined space procedures, trenching and shoring, fall protection and other safety devices, equipment and wearing apparel as are necessary or lawfully required to prevent accidents or injuries; and adequate facilities for the proper inspection and maintenance of all safety measures. Furthermore, Contractor shall prominently display the names and telephone numbers of at least two medical doctors practicing In the vicinity of the Project, as well as the telephone number of the local ambulance service, adjacent to all telephones at the Project site.
8 15

3.8.3 Laws and Regulations. Contractor shall keep itself fully informed of and in compliance with all local, state and federal laws, rules and regulations in any manner affecting the performance of the Contract or the Work, including· all Cal/OSHA requirements, and shall give all notices required by law. Contractor shall be liable for all violations of such laws and regulations in connection with Work. If Contractor observes that the drawings or specifications are at variance with any law, rule or regulation, it shall promptly notify the City in writing. Any necessary changes shall be made by written change order. If Contractor performs any worl< knowing it to be contrary to such laws, rules and regulations and without giving written notice to the City, Contractor shall be solely responsible for all costs arising therefrom. City is a public entity of the State of California subject to certain provisions of the Health & Safety Code, Government Code, Public Contract Code, and Labor Code of the State. It is stipulated and agreed that all provisions of the law applicable to the public contracts of a municipality are a part of this Contract to the same extent as though set forth herein and will be complied with. Contractor shall defend, indemnify and hold City, its officials, officers, employees and agents free and harmless, pursuant to the indemnification provisions of this Contract, from any claim or liability arising out of any failure or alleged failure to comply with such laws, rules or regulations.

3.8.4 Permits and Licenses. Contractor shall be responsible for securing City permits and licen·ses necessary to perform the Work described herein, including, but not limited to, any required business license. While Contractor will not be charged a fee for any City permits, Contractor shall pay the City's business license fee, if any. Any ineligible contractor or subcontractor pursuant to Labor Code Sections 1777 .1 and 1777. 7 may not perform worl< on this Project.

3.8.5 Trenching Work. If the Total Contract Price exceeds $25,000 and if the Work governed by this Contract entails excavation of any trench or trenches five (5) feet or more in depth, Contractor shall comply with all applicable provisions of the California Labor Code, including Section 6705. To this end, Contractor shall submit for City's review and approval a detailed plan showing the design of shoring, bracing, sloping, or other provisions to be made for worker protection from the hazard of caving ground during the excavation of such trench or trenches. If such plan varies from the shoring system standards, the plan shall be prepared by a registered civil or structural engineer.

3.8.6 Hazardous Materials and Differing Conditions. As required by California Public Contract Code Section 7104, if this Contract involves digging trenches or other excavations that extend deeper than four (4) feet below the surface, Contractor shall promptly, and prior to disturbance of any conditions, notify City of: ( 1) any material discovered in excavation that Contractor believes to be a hazardous waste that is required to be removed to a Class I, Class II or Class Ill disposal site; {2) subsurface or latent physical conditions at the site differing from those indicated by City; and {3) unknown physical conditions of an unusual nature at the site, significantly different from those ordinarily encountered in such contract work. Upon notification, City shall promptly Investigate the conditions to determine whether a change order is appropriate.

In the event of a dispute, Contractor shall not be excused from any scheduled completion date and shall proceed with all Work to be performed under the Contract, but shall retain all rights provided by the Contract or by law for making protests and resolving the dispute.

3.8.7 Underground Utility Facilities. To the extent required by Section 4215 of the California Government Code, City shall compensate Contractor for the costs of: { 1} locating and repairing damage to underground utility facilities not caused by the failure of Contractor to exercise reasonable care; (2) removing or relocating underground utility facilities not indicated in the construction drawings; and (3) equipment necessarily idled during such work. Contractor shall not be assessed liquidated damages for delay caused by failure of City to provide for removal or 9 16
relocation of such utility faci lities.

3.8.8 Air Quality. Contractor must fully comply with all applicable laws, rules and regulations in furnishing or using equipment and/or providing services, including, but not limited to, emissions limits and permitting requirements imposed by the California Air Resources Board (CARB). Although CARB limits and requirements are more broad, Contractor shall specifically be aware of their application to "portable equipment", which definition is considered by CARB to include any item of equipment with a fuel-powered engine. Contractor shall indemnify City against any fines or penalties imposed by CARB, or any other governmental or regulatory agency for violations of applicable laws, rules and/or regulations by Contractor, its subcontractors, or others for whom Contractor is responsible under its indemnity obligations provided for in this Agreement.

3.8.9 State Recycling Mandates. Contractor shall comply with State Recycling Mandates. Any recyclable materials/debris collected by the contractor that can be feasibly diverted via reuse or recycling must be hauled by the appropriate handler for reuse or recycling.

3.9 Completion of Work. When Contractor determines that it has completed the Work required herein, Contractor shall so notify City in writing and shall furnish all labor and material releases required by this Contract. City shall thereupon inspect the Work. If the Work is not acceptable to the City, the City shall indicate to Contractor in writing the specific portions or items of Work which are unsatisfactory or incomplete. Once Contractor determines that it has completed the incomplete or unsatisfactory Work, Contractor may request a reinspection by the City. Once the Work is acceptable to City, City shall pay to Contractor the Total Contract Price remaining to be paid, less any amount which City may be authorized or directed by law to retain.

Payment of retention proceeds due to Contractor shall be made in accordance with Section 7107 of the California Public Contract Code.

3.10 Claims: Government Code Claim Compliance.

3.10.1 Intent. Effective January 1, 1991, Section 20104 et seq., of the California Public Contract Code prescribes a process utilizing informal conferences, non-binding judicial supervised mediation, and judicial arbitration to resolve disputes on construction claims of $375,000 or less. Effective January 1, 2017, Section 9204 of the Public Contract Code prescribes a process for negotiation and mediation to resolve disputes on construction claims. The intent of this Section is to implement Sections 20104 et seq. and Section 9204 of the California Public Contract Code. This Section shall be construed to be consistent with said statutes.

3.10.2 Claims. For purposes of this Section, "Claim» means a separate demand by the Contractor, after a change order duly requested in accordance with the terms of this Contract has been denied by the City, for (A) a time extension, (B) payment of money or damages arising from Work done by or on behalf of the Contractor pursuant to the Contract, or (C) an amount the payment of which is disputed by the City. A "Claim" does not include any demand for payment for which the Contractor has failed to provide notice, request a change order, or otherwise failed to follow any procedures contained in the Contract Documents. Claims governed by this Section may not be filed unless and until the Contractor completes all proeedures for giving notice of delay or change and for the requesting of a time extension or change order, including but not necessarily limited to the change order procedures contained herein, and Contractor's request for a change has been denied in whole or in part. Claims governed by this Section must be filed no later than fourteen (14) days after a request for change has been denied in whole or in part or after any other event giving rise to the Claim. The Claim shall be submitted in writing to . the City and shall include on its first page the following in 16 point capital font: "THIS IS A CLAIM." Furthermore, the claim shall include the documents necessary to substantiate the claim. Nothing 10 17
in th is Section is intended to extend the time limit or supersede notice requirements otherwise provided by contract for the filing of claims, including all requirements pertaining to compensation or payment for extra Work, disputed Work, and/or changed conditions. Failure to follow such contractual requirements shall bar any claims or subsequent lawsuits for compensation or payment thereon.

3.10.3 Supportinq Documentation. The Contractor shall submit all claims in the following format:

3.10.3.1 Summary of claim merit and price, reference Contract Document provisions pursuant to which the claim is made

3.10.3.2 3.10.3.3

3.10.3.4 3.10.3.5

3.10.3.6 List of documents relating to claim:
(A) Specifications
(B) Drawings
(C) Clarifications (Requests for Information)
(D) Schedules
(E) Other
I
Chronology of events and correspondence
Analysis of claim merit
Analysis of claim cost
Time impact analysis in CPM format

3.10.3. 7 If Contractor's claim is based in whole or in part on an allegation of errors or omissions in the Drawings or Specifications for the Project, Contractor shall provide a summary of the percentage of the claim subject to design errors or omissions and shall obtain a certificate of merit in support of the claim of design errors and omissions.

3.10.3.8 Cover letter and certification of validity of the claim, including any claims from subcontractors of any tier, in accordance with Government Code section 12650 et seq.

3.10.4 City's Response. Upon receipt of a claim pursuant to this Section, City shall conduct a reasonable review of the claim and, within a period not to exceed 45 days, shall provide the Contractor a written statement identifying what portion of the claim is disputed and what portion is undisputed. Any payment due on an undisputed portion of the claim will be processed and made within 60 days after the public entity issues its written statement.

3.10.4.1 If City needs approval from its governing body to provide the Contractor a written statement identifying the disputed portion and the undisputed portion of the claim, and the governing body does not meet within the 45 days or within the mutually agreed to 11 18
extension of time following receipt of a claim sent by registered mail or certified mail, return receipt requested, City shall have up to three days following the next duly publicly noticed meeting of the governing body after the 45-day period, or extension, expires to provide the Contractor a written statement identifying the disputed portion and the undisputed portion.

3.10.4.2 Within 30 days of receipt of a claim, City may request in writing additional documentation supporting the claim or relating to defenses or claims City may have against the Contractor. If additional information is thereafter required, it shall be requested and provided pursuant to this subdivision, upon mutual agreement of City and the Contractor.

3.10.4.3 City's written response to the claim, as further documented, shall be submitted to the Contractor within 30 days (if the claim is less than $50,000, within 15 days) after receipt of the further documentation, or within a period of time no greater than that taken by the Contractor in producing the additional information or requested documentation, whichever is greater.

3.10.5 Meet and Confer. If the Contractor disputes City's written response, or City fails to respond within the time prescribed, the Contractor may so notify City, in writing, either within 15 days of receipt of City's response or within 15 days of City's failure to respond within the time prescribed, respectively, and demand an informal conference to meet and confer for settlement of the issues in dispute. Upon receipt of a demand, City shall schedule a meet and confer conference within 30 days for settlement of the dispute.

3.10.6 Mediation. Within 10 business days following the conclusion of the. meet and confer conference, if the claim or any portion of the claim remains in dispute, City shall provide the Contractor a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed. Any payment due on an undisputed portion of the claim shall be processed and made within 60 days after City issues its written statement. Any disputed portion of the claim, as identified by the Contractor in writing, shall be submitted to nonbinding mediation, with City and the Contractor sharing the associated costs equally. City and Contractor shall mutually agree to a mediator within 10 business days after the disputed portion of the claim has been identified in writing, unless the parties agree to select a mediator at a later time.

3.10.6.1 If the Parties cannot agree upon a mediator, each Party shall select a mediator and those mediators shall select a qualified neutral third party to mediate with regard to the disputed portion of the claim. Each Party shall bear the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator.

3.10.6.2 For purposes of this section, mediation includes any nonbinding process, including, but not limited to, neutral evaluation or a dispute review board, in which an independent third party or board assists the Parties in dispute resolution through negotiation or by issuance of an evaluation. Any mediation utilized shall conform to the timeframes in this section.

3.10.6.3 Unless otherwise agreed to by City and the Contractor in writing, the mediation conducted pursuant to this section shall excuse any further obligation under Section 20104.4 to mediate after litigation has been commenced.

3.10.6.4 The mediation shall be held no earlier than the date the Contractor completes the Work or the date that the Contractor last performs Work, whichever is earlier. All unresolved claims shall be considered jointly In a single mediation, unless a new unrelated claim arises after mediation is completed.
12 19

3.10. 7 Procedures After Mediation. If following the mediation, the claim or any portion remains in dispute, the Contractor must fi le a claim pursuant to Chapter 1 (commencing with Section 900) and Chapter 2 ( commencing with Section 910) of Part 3 of Division 3.6 of Title 1 of the Government Code. For purposes of those provisions, the running of the period of time within which a claim must be filed shall be tolled from the time the Contractor submits his or her written claim pursuant to subdivision (a) until the time the claim is denied, including any period of time utilized by the meet and confer conference or mediation.

3.10.8 Civil Actions. The following procedures are established for all civil actions filed to resolve claims subject to this Section:

3.10.8.1 Within 60 days, but no earlier than 30 days, following the fil ing or respons ive pleadings, the court shall submit the matter to non-binding mediation unless waived by mutual stipulation of both parties or unless mediation was held prior to commencement of the action in accordance with Public Contract Code section 9204 and the terms of these procedures .. The mediation process shall provide for the selection within 15 days by both parties of a disinterested third person as mediator, shall be commenced within 30 days of the submittal, and shall be concluded within 15 days from the commencement of the mediation unless a time requirement is extended upon a good cause showing to the court.

3.1 0.8.2 If the matter remains in dispute, the case shall be submitted to judicial arbitration pursuant to Chapter 2.5 ( commencing with Section 1141 .10) of Title 3 of Part 3 of the Code of Civil Procedure, notwithstanding Section 111 4. 11 of that code. The Civil Discovery Act of 1986 (Article 3 (commencing with Section 2016) of Chapter 3 of Title 3 of Part 4 of the Code of Civil Procedure) shall apply to any proceeding brought under this subdivision consistent with the rules pertaining to judicial arbitration.

3.1 0.8.3 In addition to Chapter 2.5 (commencing with Section 1141 .10) of Title 3 of Part 3 of the Code of Civil Procedure, (A) arbitrators shall, when possible, be experienced in construction law, and (B) any party appealing an arbitration award who does not obtain a more favorable judgment shall, in addition to payment of costs and fees under that chapter, also pay the attorney's fees on appeal of the other party.

3.10.9 Government Code Claims. In addition to any and all contract requirements pertaining to notices of and requests for compensation or payment for extra work, disputed work, claims and/or changed conditions, Contractor must comply with the claim procedures set forth in Government Code sections 900 et seq. prior to filing any lawsuit against the City. Such Government Code claims and any subsequent lawsuit based upon the Government Code claims shall be limited to those matters that remain unresolved after all procedures pertaining to extra work, disputed work, claims, and/or changed conditions have been followed by Contractor. If no such Government Code claim is submitted, or if any prerequisite contractual requirements are not otherwise satisfied as specified herein, Contractor shall be barred from bringing and maintaining a valid lawsuit against the City. A Government Code claim must be filed no earlier than the date the work Is completed or the date the Contractor last performs work on the Project, whichever occurs first. A Government Code claim shall be inclusive of all unresolved claims unless a new unrelated claim arises after the Government Code claim is submitted.

3.10.10 Non-Waiver. City's failure to respond to a claim from the Contractor within the time periods described in this Section or to otherwise meet the time requirements of this Section shall result in the claim being deemed rejected in its entirety. City's failure to respond shall not waive City's rights to any subsequent procedures for the resolution of disputed claims. 13 20

3.11 Loss and Damage. Except as may otherwise be limited by law and subject to the provisions set forth in 3.12.3 herein, Contractor shall be responsible for all loss and damage which may arise out of the nature of the Work agreed to herein, or from the action of the elements, or from any unforeseen difficulties which may arise or be encountered in the prosecution of the Work until the same is fully completed and accepted by City. In the event of damage proximately caused by an Act of God, as defined by Section 7'105 of the Public Contract Code, the City may terminate this Contract pursuant to Section 3.1 7.3.

3. -12 Indemnification.

3.12.1 Scope of Indemnity. To the fullest extent permitted by law, Contractor shall defend (with counsel reasonably approved by City), indemnify and hold the City, its officials, employees, agents and authorized volunteers free and harmless from any and all claims, demands, causes of action, suits, actions, proceedings, costs, expenses, liability, judgments, awards, decrees, settlements, loss, damage or injury of any kind, in law or equity, to property or persons, including wrongful death, (collectively, "Claims") in any manner arising out of, pertaining to, or incident to any negligence or willful misconduct of Contractor, its officials, officers, employees, subcontractors, consultants or agents in connection with the performance of the Contractor's services under this Agreement, including without limitation the payment of all consequential damages, expert witness fees and attorneys' fees and other related costs and expenses. Notwithstanding the foregoing, to the extent required by Civil Code section 2782, Contractor's indemnity obligation shall not apply to liability for damages for death or bodily injury to persons, injury to property, or any other loss, damage or expense arising from the sole or active negligence or willful misconduct of the City or the City's agents, servants, or Independent contractors who are directly responsible to the City, or for defects in design furnished by those persons.

3.12.2 Additional Indemnity Obligations. In addition, Contractor shall pay and satisfy any judgment, award or decree that may be rendered against City or its officials, employees, agents and authorized volunteers as part of any such claim, suit, action or other proceeding arising from Contractor's indemnity provisions set forth in section 3.12.1 herein.

Contractor shall also reimburse City for the cost of any settlement paid by City or its officials, employees, agents and authorized volunteers as part of any such claim, suit, action or other proceeding. Such reimbursement shall include payment for City's attorney's fees and costs, including expert witness fees. Contractor shall reimburse City and its officials, employees, agents and authorized volunteers, for any and all legal expenses and costs incurred by each of them in connection therewith or in enforcing the indemnity herein provided. Contractor's obligation to indemnify shall not be restricted to insurance proceeds, if any, received by the City, its officials, employees, agents and authorized volunteers.

3.12.3 City Indemnity Obligations. To the fullest extent permitted by law, City shall defend (with counsel reasonably approved by Contractor), indemnify and hold the Contractor, its officials, employees, agents and authorized volunteers ( collectively "Contractor lndemnitees") free and harmless from any and all claims, demands, causes of action, suits, actions, proceedings, costs, expenses, liability, judgments, awards, decrees, settlements, loss, damage or injury of any kind, in law or equity, to property or persons, including wrongful death, ( collectively, "Claims") in any manner arising out of, pertaining to, or incident to the landslide which gave rise to the Work of Contractor under this Agreement and the services provided by Contractor herein, any alleged acts, errors or omissions, or willful misconduct of City, its officials, officers, employees, subcontractors, consultants or agents related thereto, including such claims of the property owner, adjacent property owners and/or the Claims related to the railroad and its related 14 21
or affiliated entities, including without limitation the payment of all consequential damages, expert witness fees and attorneys' fees and other related costs and expenses, except to the extent caused by the negligence or willful misconduct of Contractor lndemnitees. Notwithstanding the foregoing, to the extent required by Civil Code section 2782, City's indemnity obligation shall not apply to liability for damages for death or bodily injury to persons, injury to property, or any other loss, damage or expense arising from the sole or active negligence or willful misconduct of the Contractor or the Contractor's agents, servants, or independent contractors who are directly responsible to the Contractor, or for defects in design furnished by those persons.

3.12.4 Both acknowledge and agree that to the fullest extent permitted by law, their respective duty to defend is broader than the duty to indemnify under the above provision. Depending on the claim, the defense obligation may include an obligation to provide independent defense counsel in any form or at any stage of an action or proceeding, whether or not liability is established. An allegation or determination that persons or entities other than the indemnifying party are responsible for the claim does not relieve the indemnifying party from its separate and distinct obligation to defend even if the indemnifying party or any third parties assert that liability is caused in part by the negligence or willful misconduct of the indemnified parties. If it is finally adjudicated that liability was caused by the negligence or willful misconduct of the indemnified party, the indemnifying party may submit a claim to the indemnified party for reimbursement of reasonable attorneys' fees and defense costs in proportion to the parties_' comparative liability.

3.13 Insurance. Contractor agrees to procure and maintain, at Contractor's expense all insurance specified in Exhibit "H" attached hereto and by this reference incorporated herein.

Contractor shall require all subcontractors to carry the same policies and limits of insurance that the Contractor is required to maintain, unless otherwise approved in writing by the City.

3.14 Bond Requirements . .

3. 14.1 Payment Bond. If required by law or otherwise specifically requested by City in Exhibit "C" attached hereto and incorporated herein by reference, Contractor shall execute and provide to City concurrently with this Contract a Payment Bond in an amount required by the City and in a form provided or approved by the City. If such bond is required, no payment will be made to Contractor until the bond has been received and approved by the City.

3.14.1 Payment Bond. If required by law or otherwise specifically requested by City in Exhibit "C" attached hereto and incorporated herein by reference, Contractor shall execute and provide to City concurrently with this Contract a Payment Bond in an amount required by the City and in a form provided or approved by the City. If such bond is required, no payment will be made to Contractor until the bond has been received and approved by the City.

3.14.2 Performance Bond. If specifically requested by City in Exhibit "C" attached hereto and incorporated herein by reference, Contractor shall execute and provide to City concurrently with this Contract a Performance Bond in an amount required by the City and in a form provided or approved by the City. If such bond is required, no payment will be made to Contractor until the bond has been received and approved by the City.

3.14.3 Bond Provisions. Should, in City's sole opinion, any bond become insufficient or any sorely be found to be unsatisfactory, Contractor shall renew or replace the effected bond within (ten) 1 O days of receiving notice from City. In the event the surety or 15 22
Contractor intends to reduce or cancel any required bond, at least thirty (30) days prior written notice shall be given to the City, and Contractor shall post acceptable replacement bonds at least ten (1 O) days prior to expiration of the original bonds. No further payments shall be deemed due or will be made under this Contract until any replacement bonds required by this Section are accepted by the City. To the extent, if any, that the Total Contract Price is increased in accordance with the Contract, Contractor shall, upon request of the City, cause the amount of the bond to be increased accordingly and shall promptly deliver satisfactory evidence of such increase to the City. If Contractor fails to furnish any required bond, the City may term inate the Contract for cause.

3.14.4 Surety Qualifications. Only bonds executed by an admitted surety insurer, as defined in California Code of Civil Procedure Section 995.120, shall be accepted. If a California-adm itted surety insurer issuing bonds does not meet these requirements, the insurer will be considered qualified if it is in conformance with Section 995.660 of the California Code of Civil Procedure, and proof of such is provided to the City.

3.15 Warranty. Contractor warrants all Work under the Contract (which for purposes of this Section shall be deemed to include unauthorized work which has not been removed and any non-conforming materials incorporated into the Work) to be of good quality and free from any defective or faulty material and workmanship. Contractor agrees that for the period of time specified elsewhere in the Contract or in any guarantee or warranty provided by any manufacturer or supplier of equipment or materials incorporated into the Work, whichever is later) after the date offinal acceptance, Contractor shall within ten (10) days after being notified In writing by the City of any defect in the Work or non-conformance of the Work to the Contract, commence and prosecute with due diligence all Work necessary to fulfill the terms of the warranty at its sole cost and expense. Contractor shall act sooner as requested by· the City in response to an emergency. In addition, Contractor shall, at its sole cost and expense, repair and replace any portions of the Work damaged by its defective Work or which becomes damaged in the course of repairing or replacing defective Work. For any Work so corrected, Contractor shall perform such tests as the City may require to verify that any corrective actions, including, without limitation, redesign, repairs, and replacements comply with the requirements of the Contract. All costs associated with such corrective actions and testing, including the removal, replacement, and reinstitution of equipment and materials necessary to gain access, shall be the sole responsibility of Contractor. All warranties and guarantees of subcontractors, suppliers and manufacturers with respect to any portion of the Work, whether express or i111plied, are deemed to be obtained by Contractor for the benefit of the City, regardless of whether or not such warranties and guarantees have been transferred or assigned to the City by separate agreement and Contractor agrees to enforce such warranties and guarantees, if necessary, on behalf of the City. In the event that Contractor falls to perform its obligations under this Section, or under any other warranty or guaranty under this Contract, to the reasonable satisfaction of the City, the City shall have the right to correct and replace any defective or non-conforming Work and any work damaged by such work or the replacement or correction thereof at Contractor's sole expense. Contractor shall be obligated to fully reimburse the City for any expenses incurred hereunder upon demand.

3.16 Employee/Labor Certifications.

3.16.1 Contractor's Labor Certification. By its signature hereunder, Contractor certifies that he is aware of the provisions of Section 3700 of the California Labor Code which require every employer to be insured against liability for Worker's Compensation or to undertake self-insurance in accordance with the provisions of that Code, and agrees to comply with such provisions before commencing the performance of the Work. A certification form for this purpose, which is attached to this Contract as Exhibit "D" and incorporated herein 16 23
by reference, shall be executed simultaneously with this Contract.

3.16.2 Equal Opportunity Employment. Contractor represents that it is an equal opportunity employer and that it shall not discriminate against any employee or applicant for employment because of race, religion, color, national origin, ancestry, sex, age or other interests protected by the State or Federal Constitutions. Such non-discrimination shall include, but not be limited to, all activities related to initial employment, upgrading, demotion, transfer, recruitment or recruitment advertising, layoff or termination.

3.16.3 Verification of Employment Eligibility. By executing this Contract, Contractor verifies that it fully complies with all requirements and restrictions of state and federal law respecting the employment of undocumented aliens, including, but not limited to, the Immigration Reform and Control Act of 1986, as may be amended from time to time, and shall require all subcontractors and sub-subcontractors to comply with the same.

3.17 General Provisions.

3.17.1 City's Representative. The City hereby designates the General Manager, or his or her designee, to act as its representative for the performance of this Contract ("City's Representative"). City's Representative shall have the power to act on behalf of the City for all purposes under this Contract. Contractor shall not accept direction or orders from any person other than the City's Representative or his or her designee.

3.17.2 Contractor's Representative. Before starting the Work, Contractor shall submit in writing the name, qualifications and experience of its proposed representative who shall be subject to the review and approval of the City ('"Contractor's Representative").

Following approval by the City, Contractor's Representative shall have full authority to represent and act on behalf of Contractor for all purposes under this Contract. Contractor's Representative shall supervise and direct the Work, using his best skill and attention, and shall be responsible for all construction means, methods, techniques, sequences and procedures and for the satisfactory coordination of all portions of the Work under this Contract. Contractor's Representative shall devote full lime to the Project and either he or his designee, who shall be acceptable to the City, shall be present at the Work site at all times that any Work is in progress and at any time that any employee or subcontractor of Contractor is present at the Work site. Arrangements for responsible supervision, acceptable to the City, shall be made for emergency Work which may be required. Should Contractor desire to change its Contractor's Representative, Contractor shall provide the information specified above and obtain the City's written approval.

3.17.3 Termination. This Contract may be terminated by City at any time, either with our without cause, by giving Contractor three (3) days advance written notice. In the event of termination by City for any reason othe,r than the fault of Contractor, City shall pay Contractor for all Work performed up to that time as provided herein. In the event of breach of the Contract by Contractor, City may upon two (2) business days written notice from City and failure of Contractor to commence and continue correction of such breach with diligence and promptness, terminate the Contract, may reduce payment to Contractor in the amount necessary to offset City's resulting damages, and may pursue any other available recourse again.st Contractor. Contractor may not terminate this Contract except for cause. In the event this Contract is terminated in whole or in part as provided, City may procure, upon such terms and in such manner as it may determine appropriate, services similar to those terminated. Further, if this Contract is terminated as provided, City may require Contractor to provide all finished or unfinished documents, data, diagrams, drawings, materials or other matter prepared or built by Contractor in connection with its 17 24
performance of this Contract.
3:17.4 Contract Interpretation. Should any question arise regarding the. meaning or import of any of the provisions of this Contract or written or oral instructions from City, the matter shall be referred to City's Representative, whose decision shall be binding upon Contractor.

3."17.5 Anti-Trust Claims. This provision shall be operative if this Contract is applicable to California Public Contract Code Section 7·103.5. In entering into this Contract to supply goods, services or materials, Contractor hereby offers and agrees to assign to the City all rights, title, and interest in and to all causes of action it may have under Section 4 of the Clayton Act (1 5 U.S.C. Section 15) or under the Cartwright Act (Chapter 2, commencing with Section 16700, of Part 2 of Division 7 of the Business and Professions Code) arising from purchases of goods, services, or materials pursuant to the Contract. This assignment shall be made and become effective at the time the City tender final payment to Contractor, without further acl<nowledgment by the Parties.

3.17 .6 Notices. All notices hereunder and communications regarding interpretation of the terms of the Contract or changes thereto shall be provided by the mailing thereof by registered or certified mail, return receipt requested, postage prepaid and addressed as follows:

CONTRACTOR:

CITY:

Alliance Diversified Enterprises, Inc.
665 Opper Street
Escondido, CA 92029
Attn: Rian Grenke, Vice President of Operations
City of San Clemente
91 O Calle Negocio
San Clemente, CA 92673
Attn: Kiel Koger, Public Works Director/City Engineer
Any notice so given shall be considered received by the other Party three (3) days after deposit in the U.S. Mail as stated above and addressed to the Party at the above address. Actual notice shall be deemed adequate notice on the date actual notice occurred, regardless of the method of service. ·

3.17. 7 Time of Essence. Time is of the essence to all Parties to this Agreement in the performance of this Contract.

3.17 .8 Assignment Forbidden. Contractor shall not, either voluntarily or by action of law, assign or transfer this Contract or any obligation, right, title or interest assumed by Contractor herein without the prior written consent of City. If Contractor attempts an assignment or transfer of this Contract or any obligation, right, title or interest herein, City may, at its option, terminate and revoke the Contract and shall thereupon be relieved from any and all obligations to Contractor or its assignee or transferee.

3.17.9 No Third Party Beneficiaries. There are no intended third party beneficiaries of any right or obligation assumed by the Parties. 18 25

3.17.10 Laws, Venue, and Attorneys' Fees. This Agreement shall be interpreted in accordance with the laws of the State of California. If any action is brought to interpret or enforce any term of this Agreement, the action shall be brought in a state or federal court situated in the County of Orange, State of California.

3.17.1 'I Counterparts. This Contract may be executed in counterparts, each of which shall constitute an original.

3.17.12 Successors. The Parties do for themselves, their heirs, executors, administrators, successors, and assigns agree to the full pe1iormance of all of the provisions contained in this Contract.

3.17.13 (Reserved)

3.17.14 Solicitation. Contractor maintains and warrants that it has not employed nor retained any company or person, other than a bona fide employee working solely for Contractor, to solicit or secure this Contract. Further, Contractor warrants that it has not paid nor has it agreed to pay any company or person, other than a bona fide employee working solely for Contractor, any fee, commission, percentage, brokerage fee, gift or other consideration contingent upon or resulting from the award or mal<ing of this Contract. For breach or violation of this warranty, City shall have the right to terminate this Contract without liability.

3.17.15 Conflict of Interest. Contractor maintains and warrants that it has not employed nor retained any company or person, other than a bona fide employee working solely for Contractor, to solicit or secure this Agreement. Further, Contractor warrants that it has not paid nor has it agreed to pay any company or person, other than a bona fide employee working solely for Contractor, any fee, commission, percentage, brokerage fee, gift or other consideration contingent upon or resulting from the award or making of this Agreement. For breach or violation of this warranty, City shall have the right to rescind this Agreement without liability. For the term of this Contract, no official, officer or employee of City, during the term of his or her service with City, shall have any direct interest in this Contract, or obtain any present or anticipated material benefit arising therefrom. In addition, Contractor agrees to file, or to cause its employees or subcontractors to file, a Statement of Economic Interest with the City's Filing Officer as required under state law in the performance of the Work.

3.1 7.16 Certification of License.

3.17.16.1 Contractor certifies that as of the date of execution of this Contract, Contractor has a current contractor's license of the classification indicated below under Contractor's signature.

3.17 .16.2 Contractors are required by law to be licensed and regulated by the Contractors' State License Board which has jurisdiction to investigate complaints against contractors if a complaint regarding a patent act or omission is filed within four (4) years of the date of the alleged violation. A complaint regarding a latent act or omission pertaining to structural defects must be filed within ten (10) years of the date of the alleged violation. Any questions concerning a contractor may be referred to the Registrar, Contractors' State License Board, P.O.

Box 26000, Sacramento, California 95826.

3.17.17 Authority to Enter Contract. Each Party warrants that the individuals 19 26
who have signed this Contract have the legal power, right and authority to mal<e this Contract and bind each respective Party.
3:17: 18 Entire Contract: Modification. This Contract contains the entire agreement of the Parties with respect to the subject matter hereof, and supersedes all prior negotiations, understandings or agreements. This Contract may only be modified by a writing signed by both Parties.

3. ·17.19 Non-Waiver. None of the provisions of this Agreement shall be considered waived by efther party, unless such waiver is specifically specified in writing.

3.17.20 City's Right to Employ Other Contractors. City reserves right to employ other contractors in connection with this Project or other projects.

3.17.21 Federal Provisions. When funding for the Services is provided, in whole or in part, by an agency of the federal government, Contractor shall also fully and adequately comply with the provisions included in Exhibit "G" (Federal Requirements) attached hereto and incorporated herein by reference ("Federal Requirements"). With respect to any conflict between such Federal Requirements and the terms of this Agreement and/or the provisions of state law, the more stringent requirement shall control. [SIGNATURES ON NEXT PAGE]
20 27
IN WITNESS WHEREOF, the parties hereto have caused this Agreement to be duly executed on the respective dates set forth opposite of their signatures.

CITY CI:ERK of the City o
San Clemente, California
0 AVAILABILITY
2 1
Andy Hall,
Dated: B/ 8 , 2023 -----;--,-"----
A~~\ce Diversified Enterprises, Inc
C~~\00) tM 1 U
By: Joan Grenke
Its: Chief Executive Officer/Secretary
Dated: 3: .. ~ , 2023
Alliance
~
Diversified Enterprises, Inc.

By: Evan Grenke
Its: Chief Financial Officer
Dated: ~ - '-/ , 2023
28 EXHIBIT "A"

SERVICES / SCHEDULE
In accordance with the attached Slope Repair Budgetary Proposal for Casa Romantica Landslide Repair (4 pages) dated July 11, 2023 from Alliance Diversified Enterprises, Inc. (with Contractor acting as the "Prime Contractor" under the attached standard conditions), and as directed by the Director of Public Works and LGC Geotechnical, Inc.
22 29
Date:

To:

Attn :

Project:

Gentlemen:

SLOPE REPAIR BUDGETARY PROPOSAL
Ju ly 11, 2023
City of Sa n Clemente
Kiel Koger, Publi c Works Directo r City Engineer
Casa Roma ntica Landslid e Repair
Alliance Diversified Enterprises, Inc. appreciates the opportunity to provide this Proposa l for construction of th e above referenced project. ADEi Is a full service contra ctor speciali zing in the design and installation of foundation, shoring and underpinning systems.

We have reviewed the following information as a basis for our pricing:
t Per cross sections & sketch provided by LGC
,. Soils Report to be finali zed by LGC
Specifications to be designed by ADEi
SCOPE OF WORI<:
,, Design to be provided by ADEi
;; Provide required submlttals
;, One mobilization included
i; Slope Repair for approximately 25,500 sqft (per attached sketch) , 4 rows of tiebacks and grade beams
i; Geogrid reinforced slope
/; All material to be stockpiled on site or at location provided by others {Old City Hall) ,, No civil plans have been provided, Elevations and areas to be verified

SCHEDULE OF PRICES
The work will be done by force account (time and materials) with time and materials rates based upon the Caltrans force account costs. Total compensation including contingency, shall not exceed:

Item I Description I Unit I Quantity I Unit Price Extended Price l Jscope I LS I 1 I s 7,760,800.00 $ 7,760,800.00
Total $ 7,760,800.00
. ' • ; I' ., • •• , , , .· •• . -, . . . . .
30 Exclusions
Geotechnlcal Tes ting
" Su rvey Contro l and layout
Water pollution control plan (SWPPP)
Traffic Control
Disposa l of spoils offsite
F Monitoring, test ing and/ or inspection
i: Temp. power & water; surveying, utility work, dewatering Permits, fees; third party Inspections, costs & fees
,., Waterproofing
,, 5% rete ntion maximum
i• Rock pockets
1: OCIP deduct
Load ce lls
Hydroseeding
,: Irrigation
Prices Based on our standard terms and conditions 2 pages attached.

Prices contingent on material pricing all Increases will be passed to the customer If fuel goes 10% above average fuel cost at the time of this proposal there will be a surcharge Gt:r, Op pt!r St. t:!\Condido, c:A. !,17.() 2~
7UO."i,!,\. l!i0/i P il\O .n:H) .\! f"i i t
CSLB/i 9l9~J.8 ·1 DIR# 100001(M,n
31 Exhibit A · Co111i1111 c<l ALLIA NCE DIVERSIFIED ENTI,;R1'111SES INC

STANDARD COND ITIO NS SHORING AND UNDERPINNING
This proposnl is bnscd upon lhc fo llowing conditions, exclusions nnd requirements I. II shall be the responsibility of lhc Prime Conlmclor lo coordinnle lhc work of nil olher conlraclors, subconlraclors, nnd malerinl suppliers so ns nol 10 hinder, interfere with or delay ALLIANCE DIVERSIFIED ENTERPRISES fNC work.

2. IL shnll be the resJJonsibilily of the Prime Cont rnclor 10 provide safe access for nil personnel, cq11ipme111 , mnlerinl nnd concrete trucks moving under their own power lo nnd from ench ALLIANCE DIVERS IFIED
ENTERPRISES INC work locnlion. Access includes lndders and slnirwnys, as well ns furn ishing, placing and maintai ning dry, level, fim1 benches, ramps, mals, gravel, clc., or olhcr surfa ce mnlerinls throughout lhe project, J. II slrnll be 1hc resJJonsib iliry of the Prime Comrnclor lo provide hoisting of mnlerinls nnd equip111 enl, if required, due lo lack of ndeq unle access. ,1, II shall be lhe responsibility of lhe Prime Conlrnclor lo provide all required field engineerin g, survey in g •nd ln)'Otrl, includi11g clenrly 1t1nrkcd center lines, grade, offset slakes, and elcvnlions al eac h hole locnlion and mai11tennnce of same.

5. II shnll be lhe responsibility of lire Prime Conlrnclor lo provide all required soil, concrete nn<l mnterinls lesting, inspeclion and/or system moniloring, perm its, surveys, casemenls, permiss ion Lo encroach, report s, ns-lrnill drowings, nil required notices, licenses nnd bonds,

6. II shall be lhe responsibility of the Prime Conlrnclor lo provide suilnble onsile orcas for ALLIANCE DIVERSJr-lED ENTERPRISES INC omce, slornge ofmalerinls and equipment and fabrication ofmnlerinls.

7. II shnll be lhe responsibility of lhe Prime Conlroclor lo provide lhc protection, location, relocation, rcmovnl, rerouting and/or repair ol' all pavement, sidewalks, and utilities, underground or overhcnd, overhead wires, ducts, pipelines, conduits, nnd olher ohslruclions, etc., in lh~ project nrea nnd on adjncenl property, so ns lo prevent any interference with nny phase of ALLIANCE DIVERSIFIED ENTERPRISES INC work.

8. II shall be lhe responsibility of lhe Prime Conlrnclor lo provide continuous removal and disposal of •II spoils ond wnsle mnleria ls, debris, excess concrete and dunnage, so ns 1101 lo interfere wilh or deluy the progress of ALLIANCE DIVERSIFIED ENTERPRISES INC work.
9, ALLIANCE DIVERSIFIED ENTERPRISES INC shall nol provide services with regard lo the removal or disposal of' hazardous substnnces or contaminated mntoriols. Owner nnd/or Prime Conlrnclor shnll have sole responsibility for invcslignting the existence and location of ha,.1rdous substances or contaminated malcriols al the project site and furnishing ull tests, inspections, warnings, notices, or posting required by law.

The encountering of any hnznrdous substances or contaminated rnaleririls sholl be n di!Tering si le condition. If n hazardous substance or conlarninnled mnlerial is discovered, ALLIANCE DIVERSIFIED ENTERPRISES INC shall slop lhe work affected, notify lhe Owner nnd/or Prime Conlrnclor, and have no oblignlion lo perform invcsligntion or remedial work. The Owner and/or Prime Conlroclor shall promptly inveslignlc lhe condition and make all required dclerminalions. If ALLIANCE DtVERSIFIED ENTERPRISES INC agrees Jo proceed, the Owner and/or Prime Con1roc1or shall provide insurance with rnulunlly agreed upon policy limits and give written direction lo ALLIANCE DIVERSIFIED ENTERPRISES INC relnling lo completion of work under the Contract. ALLIANCE DIVERSIFIED ENTERPRISES fNC shall be enliiled lo a lime extension for lhe delay and compensation for all costs incurred, including bul nol limited lo lhe udditional costs of perfonning conlracl work, extra work, delays, suspension of work, safely measures, etc.

Owner agrees lo indemnify, hold harmless, nnd defend ALLIANCE DIVERSIFIED ENTERPRISES fNC and its owners, officers, employees, ng~nls, subcontractors of any lier, suppliers, vendors, consuhnnls nnd represenlalives from ond against any liubility, claim, loss. penally, clarnnge, expense (including legal nnd expert expenses) or legnl or odrninislrnlive proceeding brought by any other party including any governmcnlal or regulatory authority nrising oul of the exislcncc, encountering, handling, 1rnnsportalion, disposnl, relcosc, response, remediation, or removal of the hnznrdous substance or conlnminalcd material.

As used herein, hazardous substance or conlaminoled material shall bo inlcrpretccl broadly lo mean nny suhstnncc. mnlerial, or wnste ent.:ourllered during lhc course of pcrforrrrnncc defined or dcsignu1ed ns hilZn rdnus, toxic, or otherwise dangerous lo humnn health, property, or lhc environrnenl by ilny govcmrnentnl or regulatory authority
I 0. II shnll be lhe responsibility of lhc Prime l'onlrnc1or 1n provide si!C clcwn1cring prior lo lhe slnrl of work so ns lo prevent hydrostatic hend and/or nol delay the progress or ALL IANCE DIVERSIFIED ENTERPRISES INC. work. When ALLl;\ NCE [)J VERS IFlr-.D ENTERPRISES INC is pu111ping water 1111d /or dri llin g nuids from any excavation , it shall be 1he responsihility of lhc h ral,;r Prime Conlrnctor 10 provide a sum p within 100 lcel of encl, locnlion. Should lnnks or desilling basins he required, lhey ore lo be furnished nnd clcnned, nnd lhc rnntcrinl conlnined therein removed by <ll hers nl no cosl 10 ALL IANCC DIVUlSIFIED ENTERl'IUSL:S INl'

11. It shall be the responsibility or the Owner and/or Prime Conlrnclo r lo provide trnflic co ntrol and protection incl11d ing nil lnhor /nilgpersons. nashers. elc I and equipment , s1rce1 cleaning, hurricndes, fences, or handrails, n1clud11rg rclocalion ns m1uircd.

12. IL shall be lhe responsibility of lhe Prime Contrnclor 10 provide all wnler, lighting, lclephone service, snnilnry fncililics nnd cleclricnl power, in such quanlily nnd qunlily ns required by ALLIANCE DIVERSIFIED ENTER l'RISES INC wi thin 200 re el of each work locatro11 .

I J. Unless specified otherwise, only convenlionill nugcr lools will be supplied Work items such as rock dril ling, coring, dcwnlering, hand min ing, hnnd cleaning, cosing of shnl1s, and shoring of bells. as well ns the 1cpnir of drill rigs, drill tools, nnd cnsing (dnmngcd ns n result of rock drilling or coring) will be exlrn work.
1,1. Unless otherwise specified, lhc removal of obslruclinns 1h111 1n1erfere with ALLIANCE DIVERSlrIED ENTERPRISES INC: work shilll l:c c,1ra 11ork Obs1ruc1lons nre defined ns nny material which cnnnol be drilled 111 n rn1e of I fool In one minute with II conventionnl ea rth 11uger and/or under-reaming IOOI.

The use of specia l rock nugers, core barrels, nir tools, blasting, hand cxcnvntion nnd/or other 111e1hods of excnvnlion. if necessary. will he extra work,

15. Slrucluml concrcle 10 be pl aced per ACI 336.1: nonslruclurnl will be plnced by the free-foll method. Unless otherwise specified. placemen I or concrete by pump is excluded.

16. In order to eliminnle unsnfe conditions, nil shnns which nre 1101 complc1dy filled wilh concrete nre Jo he covered by other.,. Also. ALLIANC:F.

DIVERSIFIED ENTERPRISES INC shall nol be responsible for any portion of n shan lcn open or not hucklillcd. lo include top of concrele cutoff below grade, in which case lhc furnishing nnd plncemenl of bnckflll mnleriol is required. All of lhe foregoing work is lo be done by others at no cost lo

ALLIANCE DIVERSIFIED ENTERPRISES INC
32 ALLIANCE 0IVEHS!fol Im GNTERPRISES INC STAND,\ RD COND ITI ONS SI-IOHING AND UNOt,;Rl'INN ING

17. Coordinnlion of mnss cxcavulion shall he lhe responsibility of lhc Prime Conlrnclor, so as lo prevent unsafe over- excava tion.

18. ALLIANCE DI VERSIFIED ENTERPRISES INC assumes no responsi bility for stnb illly or 11minlennnce of excnval ion or for excessive cuncrelc ovcrb rcnk . ALLIANCE DIVERSW IED ENTERPRISES INC is 11 01 rcsp,insibl c for lhc hnckftl ling oi' over- excnvnlion caused by olhc1s.

19. Mass excavation nnd trimming of omtcrinl 10 lhc fnc c of soldier pi les or to lhc foc c or logging, whichever is further, will be done by others sons 1,01 10 interfere with or dclny ALLIA NCE DIVERS IFIED ENTER PRISES INC work.

20. Excavalion for lagging and lagging inslullntion shal l 1101 exceed 5 fool verticnl lins. Soil conditions may dictate 1hnt lins be less 1hnn S feet. 2 1. When existi ng foundations urc to be underpinned, sequen tial excavat ion lo the bollom of ex isting foundations is to be done by others nl no cost 10

ALLIANCE DIVERSIFIED ENTERPRISES INC

22. Horizontal lolernnccs for cxcavalion support systems shn ll be wilhin I¾ of the ve rt ical heigh t or as speciried under special conditions, whichever is grentcr.

23. Un less pcnnnnenl licbncks ore required, shoring, tiebacks and nni ls arc tempora ry. Pcrmonenl slruclurcs must be co11s1ruc1cd fo r ru1ure s1abili1y and lateral support.

24. Unless negligent, ALLIA NCE DIVERSIFIED ENTERPRISES INC nssumes no res ponslbilily or liubility for cracking or selllemcnl of nny cxi.sling strcels, sidewalks, curbs, gulters, 111l lilics, pavement, buildings or other lmprovemenls or nny other damages which may occur during performance of the work or which may be cnused by vibration or machinery or equipment.

25. The 1cmoval ofony materials once installed is excluded, unless such work is covered by bid item.

26. All work by ALLIANCE DIVERSWIED ENTERPRISES INC will be done on n stmighl-limc basis; directed overtime work will be performed only If costs nre paid by others.

27. This proposal price is based on perfonning our work in one co nt inuous, unin1cm1pled operntion with only one move on and arr the site. Each ndditionnl rnobilizn1ion will be charged nt I 0% of ihe lotnl project cost.

28. Should conditions be encountered in the performnnce of ALLIA NCE DIVERSIFIED ENTERPRISES INC work wh ich differ from those (A) indicoled by the Contrnct documents or soils dnla furnished to ALLIANCE DIVERSIFIED ENTBRPRJSES INC which nre nol part of the Contract documents, or (B) ordinarily encountered and generally recognized as inherent in work of lhe character provided in the Conlrocl, nn equitable adjustment and time extension will be made to cover the resulling cost.

29. No charges of any kind lo ALLIANCE DIVERSIFIED ENTERPRISES INC will be accepted unless agreed to and signed for by an nulhorizcd representative of ALLIANCE DIVERSIFIED ENTERPRISES INC on 11 doily basis.

30. Unless specifically staled in writing herein, this quotation does 1101 include any local, stole, fcdcrnl or other governmental ngency taxes, including sales tnx .

31. ALLIANCE DIVERSIFIED ENTERPRISES rNC shall Indemnify and Owner with respect to ony clnim which nrises directly rrom the negligence, if any, of ALLIANCE DIVERSIFIED ENTERPRISES INC in performnncc of its work hereunder, but the exlcnl or such Indemnity shall be only In proportion lo ALLIANCE! DIVERSIPIED ENTERPRISES INC share of ihe total fault causing the loss or damage on which such cluim is bnsed.

ALLIANCE DIVERSIFIED ENTERPRISES INC shall hove no other responsibility to defend, indemnify or provide insurance for Prime Contrnctor (if any), Owner or others wilh respecl to clnims arising from or related 10 ALLIANCE! DIVERSIFIED ENTERPRISES INC work hereunder.

32. 33. ALLIANCE DIVERSIFIED ENTERPRISES INC shall ,nnlntain in place, during the performance of Its work hereunder, worke~s compensation coverage as required by lnw, nnd bodily injury nnd property damage liability Insurance (XCU exclusion deleied), with o cnmbincd single limit of Si million. "Addilio1111 I insured" coverage thereunder is limited 10 ALLIANCE IJIVERSIF IED ENTERPRISES INC proportionate share or the 101nl l'aull causinc the loss or dnnrngc on which such claim is b,1scd.

J•I No liquidnled Jamnges moy be assessed wi1hou1 ALLIANCF. DIVERSIFIED ENTERPRISES INC specifically ngreeing in writing. ALL IANCE DIVERS IFIED ENTERPRISES INC shall 1101 be responsible li>1 any eonsequcnl ial or inc1dentnl damages.

JS. Modili cntions 10 these ~ondilions or exclusions must be speci li cally descri bed nnd initialed by nn n11 1hmi1,ed represe111 a1ivc of ALLI ANCE

IJIVERSIFIED ENTERPR ISES INC
J6. Unless specified otherwise, extra wo,k nntl items of wo1k specifically excluded but perfonncd by ALLIANCE DIVERSIP IED ENTcRPRISES INC, or delays resulting rro111 inlcrfert!m::c or nonpcrformimc~ or ntht: rs. shnl I be invoiced nl cosl plus 20¾.

37. During th e WOik , progress pnymcnls nre to be m,lllc IJ1- 11,onlhly. These progress payments sholl include cosls for oil malcrinls purchased and/or fabri cated . hul not installed. lnleresl or lnte fees will be clmgcd on all past d11c ncco11111 s, ul the m11 xin111111 rnlc 11 lluw11ble by law. Ful l paymc11 1 for ALLIANCE DIVERS IF IED ENTER PRISES INC work is 10 he mnde wi1hin JO days nl\cr s111Js1an1iol completion of 0 111 work. There is 10 be no rc1c111io11 withheld l'rom 1h1s final pny111c111. If there are phases or ramp removals, lhey shall be !rented ns sernrnlc jobs wilh nn ngrccd-Jo vnluc withheld.

J8. Unless specified otherwise. th is bi<l quotation slmll no l r<milin 1n crtcc1 al\ei IO clnys of the bid date t1 nless ncccpled i11 wri1 i11u or hy Conlrncl

39. If shotcre1e is used, 1hc quan lily included is lhe theorelicnl quantity plus 1Q ___ ¾. Quan lilies placed above Ihm 111110111\1 wi ll be invoiced nt $ ill..QQ Icy ns veriried by delivery lickels. 33 EXHIBIT "B"
PLANS AND SPECtFICATtONS

IN ACCORDANCE WITH THE ATTACHED DRAFT GEOTECHNCIAL MAP AND DRAFT CROSS SECTION A-A' FROM LGC GEOTECHNICAL, INC. DATED JULY 2023 .
55452.01510\32977834.2
34 ·I· ;,•,
' ' I,...

I ' .

I
I
GC
Gco~cnnlc:011 Inc.

LGC Geotechnica/, Inc.
131 Calle Iglesia, Ste. 200
San Clemente, CA 92672
TEL l'")J,MU1 FAX("t),I Mf.11
Geotechnica/ Map
aro
Ols~cTrvE
Qt
Tc
LGC-BA-2
T.D. • ~ 99·
LEGEND
~rtlnclal rl.11 - Older, Clrdcd \'\/here Euned
Quaternary Lanasllde, Cirdea Where Buned
Ou:::nemory Terrn.e:e Deposits, Circied \Micrc Buned
Toni.1,y Capl!itrano Form;1110n - Clrcied VVhere Buned
Approic:1mote Loi::o.tJon or Sonngs by LGC Geotechmcal. With Tolci OcpL'1 in Feel
/ Appro,amate LoC?ticn of Geologic Contact Coned VVhere Burled. Queneti 'Mlere Uncertain
A' L--i Gco10CM1C4l Cro:;s.Secuon Alignment
Apprcxlm.110 Locbon of Propo?:cd Gradebcam:; For Ro'N ol TiobJeC ----
PROJECT NAME Cily of San Clomsnte - Casa Romant;co
PROJECT NO. 23076--01
ENG.IGEOL BTZ IKBC
SCALE
DATE Ju/>/ 2023
SHEET
1 of 2
35 ::J'
Cf)
c~
0 Q) :;:::: > ell 0
> .0
Cl) <(
w a5
Q)
!:!::..
80 -
Railroad
Tracks
4 o - -1--afoQ --
- 40
0 l
· al Inc. LGC Geotech1:1cs!e 200
131 Calle /gles,aCA 92672
San Clemente~"'"!,.,_.,., TEL (U9)J&Ul41 ~ 4/)
N61E ::----
t. n Orientation
Sec 10 ________ _
-?
Apprpximate
-Rerii~airu
Profil~
80 160
Hanz . ontal Distance (Feet)
Cross-Sec tI ·on A-A'
LGIC-Sl-1
-+O
-40
City of San Clemente - Casa RomanUca ~ r' J·
23016-01 ___ 1 SHEET BTZIKBC 2 f 2 1" = 20' O
July 2023
36 EXHIBIT "C"

SPECIAL CONDITIONS
ARTICLE 1. BONDS
As soon as possible and in any event within 24 hours of starting work, the Contractor shall deliver to the City four identical counterparts of the Performance Bond and Payment Bond on the forms supplied by the City and included as Exhibit "F" to the Contract. The surety supplying the bond must be an admitted surety insurer, as defined in Code of Civil Procedure Section 995. ·120, authorized to do business as such in the State of California and satisfactory to the City. The Performance Bond and the Payment Bond shall be for one hundred percent (100%) of the Total Contract Price.
- 24-
55452.015 I 0\32977834.2
37 EXHIBIT "D"

WORKERS COMPENSATION INSURANCE CERTIFICATION

WORKERS' COMPENSATION DECLARATION
I hereby affirm under penalty of perjury one of the following declarations:
(ONE OF THE BOXES BELOW MUST BE CHECKED) □ n I have and will maintain a certificate of consent from the California Labor Commission to self-insure for workers' compensation, as provided for by Section 3700 of the Labor Code, for the performance of the work to be performed under this contract. I have and will maintain workers' compensation insurance, as required by Section 3700 of the Labor Code, for the performance of the work to be performed under this contract. My workers' compensation insurance carrier and policy number are: camfil_ -+- /l+-=c~e _.:_ll___ci_122L-Yt-~ ...-.~,.,_a~ X~ ,,uo.=--=- ~ -=-- -C:u ~ - Policy Number C S:--/ L ~ g ..S 7' -/ I certify that, in the performance of the work under this Agreement, I shall not employ any person in any manner so as to become subject to the workers' compensation laws of California, and I hereby agree to indemnify, defend, and hold harmless the City of San Clemente and all of its officials, employees, and agents from and against any and all claims, liabilities, and losses relating to personal injury or death, economic losses, and property damage arising out of my failure to provide such worker's compensation insurance. I further agree that, if I should become subject to the workers' compensation provisions of Section 3700 of the Labor Code, I shall forthwith comply with those provisions.

WARNING: FAILURE TO SECURE WORKERS' COMPENSATION COVERAGE IS

UNLAWFUL, AND SHALL SUBJECT AN EMPLOYER TO CRIMINAL PENALTIES AND CIVIL FINES UP TO ONE HUNDRED THOUSAND DOLLARS ($100,000), IN

ADDITION TO THE COST OF COMPENSATION, DAMAGES AS PROVIDED FOR IN SECTION 3706 OF THE LABOR CODE, INTEREST, AND ATTORNEY'S FEES. - 25 -
55452.01510\32977834.2
38 Dated: ~ -- z:5
Consultant
By:

Address
- 26 -
55452.01 510\32977834.2
39 EXHIBIT "E"

PUBLIC WORKS CONTRACTOR REGISTRATION CERTIFICATION
Pursuant to Labor Code sections 1725.5 and 1771. 1, all contractors and subcontractors that wish to bid on, be listed in a bid proposal, or enter into a contract to perform public work must be registered with the Department of Industrial Relations. See http://www.dir.ca.gov/PublicWorks/PublicWorks.html for additional information.

No bid will be accepted nor any contract entered into without proof of the contractor's and subcontractors' current registration with the.Department of Industrial Relations to perform public work.

Contractor hereby certifies that it is aware of the registration requirements set forth in Labor Code sections 1725.5 and 1771.1 and is currently registered as a contractor with the Department of Industrial Relations.1
Name of Contractor:____;, /+____;,{..:;_ ~ _ !__.....i....(=--_____ _ DIR Registration Number: /o:00 j Lf& /
DIR Registration Expiration: () 4 / 30 / 2RJ 2--~ r J
Small Project Exemption: __ Yes or X- No
Unless Contractor is exempt pursu-ant to the small project exemption, Contractor further acknowledges:
• Contractor shall maintain a current DIR registration for the duration of the project. • Contractor shall include the requirements of Labor Code sections 1725.5 and 1771.1 in its contract with subcontractors and ensure that all subcontractors are registered at the time of bid opening and maintain registration status for the duration of the project. • Failure to submit this form or comply with any of the above requirements may result in a finding that the bid is non-responsive.

NameofContractor ;4.fl~~ {),-v~t"'i.;fr,1 £',,.)- T"'lc.- Signature
Name and Title ~ i~ c,..~"" k '(
Dated 8 --8- 3>
1 If the Project is exempt from the contractor registration requirements pursuant to the small project exemption under Labor Code Sections 1725.5 and 1771.1, please mark "Yes" in response to "Small Project Exemption."
- 27 -
55452.0 I 510\32977834.2
40 55452.01510\32977834.2
EXHIBIT "F"

PAYMENTANDPERFORMANCEBONDS
- 28 -
41 PERFORMANCE BOND
l<NOW ALL PERSONS BY THESE PRESENTS:

THAT WHEREAS, the City of San Clemente (hereinafter referred to as "City") has awarded to ________ _ , (hereinafter referred to as the "Contractor") an agreement for
(hereinafter referred to as the "Project").

WHER AS, the work to be performed by the Contractor is more particularly set forth in the Contract Documents for the Project dated ______ _ , (hereinafter referred to as "Contract Documents"), the terms and conditions of which are expressly incorporated herein by reference; and
WHEREAS, the Contractor is required by said Contract Documents to perform the terms thereof and to furnish a bond for the fa ithful performance of said Contract Documents.

NOW, THEREFORE, we, _ ______ the undersigned Contractor and _ ________ __________ as Surety, a corporation organized and duly authorized to transact business under the laws of the State of California, are held and firmly bound unto the City in the sum of _ ________ __ DOLLARS, {$ _____ ), said sum being not less than one hundred percent ( 100%) of the total amount of the Contract, for which amount well and truly to be made, we bind ourselves, our heirs, executors and administrators, successors and assigns, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION IS SUCH, that, if the Contractor, his or its heirs, executors, administrators, successors or assigns, shall in all things stand to and abide by, and well and truly keep and perform the covenants, conditions and agreements in the Contract Documents and any alteration thereof made as therein provided, on its part, to be kept and performed at the time and in the manner therein specified, and in all respects according to their intent and meaning; and shall faithfully fulfill all obligations including the one~year guarantee of all materials and workmanship; . and shall indemnify and save hamiless the City, its officers and agents, as stipulated in said Contract Documents, then this obligation shall become null and void; otherwise it shall be and remain in full force and effect.

As a condition precedent to the satisfactory completion of the Contract Documents, unless otherwise provided for in the Contract Documents, the above obligation shall hold good for a period of one (1) year after the acceptance of the work by City, during which time if Contractor shall fail to make full, complete, and satisfactory repair and replacements and totally protect the City from loss or damage resulting from or caused by defective materials or faulty workmanship, Surety shall undertake and faithfully fulfill all such obligations. The obligations of Surety hereunder shall continue so long as any obligation of Contractor remains. Nothing herein shall limit the City's rights or the Contractor or Surety's obligations under the Contract, law or equity, including, but not limited to, California Code of Civil Procedure section 337.15.

Whenever Contractor shall be, and is declared by the City to be, in default under the Contract Documents, the Surety shall remedy the default pursuant to the Contract Documents, or shall promptly, at the City's option:
- 29 - 55452.0 I 5 I0\32977834.2
42 ('I) Take over and complete the Project in accordance with all terms and conditions In the Contract Documents; or
(2) Obtain a bid or bids for completing the Project in accordance with all terms and conditions in the Contract Documents and upon determination by Surety of the lowest responsive and responsible bidder, arrange for a Contract between such bidder, the Surety and the City, and make available as work progresses sufficient funds to pay the cost of completion of the Project, less the balance of the contract price, including other costs and damages for which Surety may be liable. The term "balance of the contract price" as used in this paragraph shall mean the total amount payable to Contractor by the City under the Contract and any modification thereto, less any amount previously paid by the City to the Contractor and any other set offs pursuant to the Contract Documents.
(3) Permit the City to complete the Project in any manner consistent with local, California and federal law and make available as work progresses sufficient funds to pay the cost of completion of the Project, less the balance of the contract price, including other costs and damages for which Surety may be liable. The term "balance of the contract price" as used in this paragraph shall mean the total amount payable to Contractor by the City under the Contract and any modification thereto, less any amount previously paid by the City to the Contractor and any other set offs pursuant to the Contract Documents.

Surety expressly agrees that the City may reject any contractor or subcontractor which may be proposed by Surety in fulfillment of its obligations in the event of default by the Contractor.

Surety shall not utilize Contractor in completing the Project nor shall Surety accept a bid from Contractor for completion of the Project if the City, when declaring the Contractor in default, notifies Surety of the City's objection to Contractor's further participation in the completion of the Project.

The Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Contract Documents or to the Project to be performed thereunder shall in any way affect its obligations on this bond, and it does hereby waive notice of any such c:;hange, extension of time, a)teration or addition to the terms of the Contract Documents or to the Project, including but not limited to the provisions of sections 2819 and 2845 of the California Civil Code.

IN WITNESS WHEREOF, we have hereunto set our hands and seals this ___ day of _____ , 20_).
(Corporate Seal)
Contractor/ Principal
By _____________ _
Title ____________ _
- 30 - 55452.01510\32977834.2
43 (Corporate Seal) Surety
By -------------- Attorney-in-Fact
Signatures of those signing for the Contractor and Surety must be notarized and evidence of corporate authority attached.
(Attach Attorney-in-Fact Certificate) Title ____________ _ The rate of premium on th is bond is _____ per thousand. The total amount of premium charges, $ ____________ _
(The above must be filled in by corporate attorney.)

THIS IS A REQUIRED FORM
Any claims under this bond may be addressed to:
(Name and Address of Surety)
(Name and Address of Agent or
Representative for service of
process in California, if different
from above)
(Telephone number of Surety and
Agent or Representative for service
of process in California)
NOTE: A copy of the Power-of-Attorney authorizing the person signing on behalf of the Surety to do so must be attached hereto.
- 31 - 55452.0l 510\32977834.2
44 Notary Acknowledgment
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.

STATE OF CALIFORNIA
COUNTY OF ____ _
On _ _ _____ ____. 20_ , before me, ______________ , Notary Public, personally appeared , who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the Instrument.
l certify under PENAL TY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.

WITNESS my hand and official seal.

Signature of Notary

OPTIONAL
Though /he Information below Is no/ required by law, ii may prove valuable to persons relying on /he document and could prevent fraudulent removal and reattachment of /his form to anolher document.

CAPACITY CLAIMED BY SIGNER
□ Individual
□ Corporate Officer
□ Partner( s)
D Attorney-In-Fact
D Trustee(s)
D Guardian/Conservator
Other:

Signer Is representing:

Name Of Person(s) Or
4875-3807-1395 v4
55452.0 [510\32977834.2
□ Limited
D General

DESCRIPTION OF ATTACHED DOCUMENT
Title or Type of
Number of
Date of
Slgner(s) Other Than Named Above
- 32 -
45 PAYMENT BOND
f<NOW ALL MEN BY THESE PRESENTS That
WHEREAS, the City of San Clemente (hereinafter designated as the "City"), by action taken or a resolution passed _______ , 20_ has awarded to ________ _ hereina~er designated as the "Principal," a contract for the work described as follows:
______________________ (the "Project"); and
WHEREAS, the work to be perfonned by the Principal is more particularly set forth in the Contract Documents for the Project dated ________ ("Contract Documents"), the terms and conditions of which are expressly incorporated by reference; and WHEREAS, said Principal is required to furnish a bond in connection with said contract; providing that if said Principal or any of its Subcontractors shall fail to pay for any materials, provisions, provender, equipment, or other supplies used in, upon, for or about the perfonnance of the work contracted to be done, or for any worl< or labor done thereon of any kind, or for amounts due under the Unemployment Insurance Code or for any amounts required to be deducted, withheld, and paid over to the Employment Development Department from the wages of employees of said Principal and its Subcontractors with respect to such work or labor the Surety on this bond will pay for the same to the extent hereinafter set forth.

NOW THEREFORE, we, the Principal and ___________ as Surety, are held and firmly bound unto the City in the penal sum of _ _______ ____ _ _______ Dollars ($ _____ ) lawful money of the United States of America, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION IS SUCH that if said Principal, his or its subcontractors, heirs, executors, administrators, successors or assigns, shall fail to pay any of the persons named in Section 9100 of the Civil Code, fall to pay for any materials, provisions or other supplies, used in, upon, for or about the performance of the work contracted to be done, or for any work or labor thereon of any kind, or amounts due under the Unemployment Insurance Code with respect to work or labor perfonned under the contract, or for any amounts required to be deducted, w_ithheld, and paid over to the Employment Development Department or Franchise Tax Board from the wages of employees of the contractor and his subcontractors pursuant to Section 18663 of the Revenue and Taxation Code, with respect to such work and labor the Surety or Sureties will pay for the same, in an amount not exceeding the si.Jm herein above specified.

This bond shall inure to the benefit of any of the persons named in Section 9100 of the Civil Code so as to give a right of action to such persons or their assigns in any suit brought upon this bond.

It Is further stipulated and agreed that the Surety on this bond shall not be exonerated or released from the obligation of this bond by any change, extension of time for performance, addition, alteration or modification in, to, or of any contract, plans, specifications, or agreement pertaining or relating to any scheme or work of improvement herein above described, or pertaining or relating to the furnishing of labor, materials, or equipment therefore, nor by any change or modification of any terms of payment or extension of the time for any payment pertaining or relating to any scheme or work of improvement herein above described, nor by any rescission or attempted rescission of the contract, agreement or bond, nor by any conditions precedent or - 33-
55452.01510\32977834.2
46 subsequent in the bond attempting to limit the right of recovery of claimants otherwise entitled to recover under any such contract or agreement or under the bond, nor by any fraud practiced by any person other than the claimant seeking to recover on the bond and that this bond be construed most strongly against the Surety and in favor of all persons for whose benefit such bond is given, and under no circumstances shall Surety be released from liability to those for whose benefit such bond has been given, by reason of any breach of contract between the owner or City and original contractor or on the part of any obligee named in such bond, but the sole conditions of recovery shall be that claimant is a person described in Section 9100 of the Civil Code, and has not been paid the full amount of his claim and that Surety does hereby waive notice of any such change, extension of time, addition, alteration or modification herein mentioned and the provisions of sections 2819 and 2845 of the California Civil Code. ·
IN WITNESS WHEREOF, we have hereunto set our hands and seals this ___ day of ------' 20_ .
(Corporate Seal)
Contractor/ Principal
By _______ ______ _
Title ____________ _
(Corporate Seal) Surety
By-------------- Attorney-in-Fact
Title ____________ _
Signatures of those signing for the Contractor and Surety must be notarized and evidence of corporate authority attached. A Power-of-Attorney authorizing the person signing on behalf of the Surety to do so must be attached hereto .
. NOTE: A copy of the Power-of-Attorney authorizing the person signing on behalf of the Surety to do so must be attached hereto.
- 34 - 55452.01510\32977834.2
47 Notary -Acknowledgment
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.

STATE OF CALIFORNIA
COUNTY OF _ _ __ _
On -------~ 20_ , before me, _ _ ____________ , Notary Public, personally appeared , who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.

I certify under PENAL TY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.

WITNESS my hand and official seal.

Signature of Notary

OPTIONAL
Though the information below ts not required by law, it may prove valuable to persons relying on the document and could pravent fraudulent removal and reattachment of this fonn to another document.

CAPACITY CLAIMED BY SIGNER
□ Individual
□ Corporate Officer
□ Partner(s)
□ Attorney-In-Fact
□ Trustee(s)
□ Guardian/Conservator
Other:

Signer Is representing:

Name Of Person(s) Or
4860-7008-9059 v1
55452.01510\32977834.2
□ Limited
□ General

DESCRIPTION OF ATTACHED DOCUMENT
Title or Type of
Number of
Date of
Slgner(s) Other Than Named Above
- 35 -
48 NOT APPLICABLE
55452,01510\'32977834,2
EXHIBIT "G"

FEDERAL REQUIREMENTS
- 36 -
49 3.13 Insurance.

EXHIBIT "H"

INSURANCE REQUIREMENTS

3.13.1 Time. for Compliance. Contractor shall not commence work under this Contract until it has provided evidence satisfactory to the City that it has secured all insurance required under this section. In addition, Contractor shall not allow any subcontractor to commence work on any subcontract as required in section 1.1 .12 of this agreement. 3: 13.2 Types of Insurance Required. As a condition precedent to the effectiveness of this Contract for work to be performed hereunder, and without limiting the indemnity provisions of the Contract, the Contractor, in partial performance of its obligations under such Contract, shall procure and maintain in full force and effect during the term of the Contract the following policies of insurance. If the existing policies do not meet the insurance requirements set forth herein, Contractor agrees to amend, supplement or endorse the policies to do so. (A) Commercial General Liability: Commercial General Liability Insurance which affords coverage at least as broad as Insurance Services Office "occurrence" form CG 0001, or the exact equivalent, and shall be no less than $2,000,000 per occurrence and no less than $4,000,000 in the general aggregate. Defense costs shall be paid in addition to the limits.

The policy shall contain no endorsements or provisions limiting coverage for (1) contractual liability; (2) cross liability exclusion for claims or suits by one insured against another; or (3) contain any other exclusion contrary to the Contract.
(B) Automobile Liability Insurance: Automobile Liability Insurance with coverage at least as broad as Insurance Services Office Form CA 0001 covering "Any Auto" (Symbol 1 ), or the exact equivalent, covering bodily injury and property damage for all activities shall be in an amount of not less than $1,000,000 combined limit for each occurrence. (C) Workers' Compensation: Workers' Compensation Insurance, as required by the State of California and Employer's Liability Insurance with a limit of not less than $1,000,000 per accident for bodily injury and disease.
(D) Builder's Risk Insurance ["All Risk"]: The City has obtained Builder's Risk [" All Risk"] extended coverage insurance for the Project. Contractor shall NOT procure Builder's Risk ["All Risk"] insurance for this Project, and shall NOT include the-cost of said coverage in its bid price/the Contract Price.
(E) Contractors Pollution Liability: Contractors Pollution Liability Insurance covering all of the Contractor's operations to include onsite and offsite coverage for bodily injury (including death and mental anguish), property damage, defense costs and cleanup costs with limits not less than $2,000,000 per loss and $4,000,000 total all losses. The policy shall contain no endorsements or provisions limiting contractual liability or coverage for cross liability of claims or suits by one Insured against another. If coverage is written on a claims-made basis, the retroactive date shall precede the effective date of the initial Contract and continuous coverage will be maintained or an extended reporting period will be exercised for a period of at least three (3) years from termination or expiration of this Contract. - 37 - 55452.01510132977834.2
50 3. 13.3 Endorsements. Required insurance policies shall contain the following provisions, or Contractor shall provide endorsements on forms approved by the City to add the following provisions to the insurance poli cies:
(A) Commercial General Liability and Contractor's Pollution Liability:
(1) Additional Insured: The City, its officials, officers, employees, agents, and volunteers shall be additional insureds with regard to liability and defense of suits or claims arising out of the performance of the Contract.

Additional Insured Endorsements shall not (1) be restricted to "ongoing operations"; (2) exclude "contractual liability"; (3) restrict coverage to "sole" liability of Contractor; or (4) contain any other exclusions contrary to the terms of purposes of this Contract. For all policies of Commercial General Liability insurance, Contractor shall provide endorsements in the form of ISO CG 20 10 10 01 and 20 37 10 01 (or endorsements providing the exact same coverage) to effectuate this requirement.
(2) Cancellation: Required insurance policies shall not be canceled or the coverage reduced until a thirty (30) day written notice of cancellation has been served upon the City except ten (10) days shall be allowed for non-payment of premium. (B) Automobile Liability:
(1) Cancellation: Required insurance policies shall not be canceled or the coverage reduced until a·thirty (30) day written notice of cancellation has been served upon the City except ten (10) days shall be allowed for non-payment of premium. (C) Workers' Compensation:
(1) Waiver of Subrogation: A waiver of subrogation stating that the insurer waives all rights of subrogation against the City, its officials, officers, employees, agents and volunteers.
(2) Cancellation: Required insurance policies shall not be canceled or the coverage reduced until a thirty (30) day written notice of cancellation has been served upon the City except ten (10) days shall be allowed for non-payment of premium.

3.13.4 Primary and Non-Contributing Insurance. All policies of Commercial General Liability, Automobile Liability insurance (if required) shall be primary and any other Insurance, deductible, or self-insurance maintained by the City, its officials, officers, employees agents or volunteers shall not contribute with this primary insurance. Policies shall contain or be endorsed to contain such provisions.

3.13.5 Waiver of Subrogation. All policies of Commercial General Liability, Automobile Liability insurance (if required) shall contain o.r be endorsed to waive subrogation against the City, its officials, officers, employees, agents, and volunteers or shall specifically allow Contractor or others providing insurance evidence in compliance with these specifications to waive their right of recovery prior to a loss. Contractor hereby waives its own right of recovery against City, and shall require similar written express waivers and insurance clauses from each of its subcontractors. - 38 - 55452.01510\32977834.2
51 3.13.6 Deductibles and Self-Insured Retentions. Any deductible or self-insured retention in excess of $5,000 must be approved in writing by the City and shall protect the City, its officials, officers, employees, agents and volunteers in the same manner and to the same extent as they would have been protected had the policy or policies not contained a deductible or self-insured retention.
3:13.7 Evidence of Insurance. The Contractor, concurrently with the execution of the Contract, and as a condition precedent to the effectiveness thereof, shall deliver either certified copies of the required policies, or original certificates on forms approved by the City, together with all endorsements affecting each policy. Required insurance policies shall not be in compliance if they include any limiting provision or endorsement that has not been submitted to the City for approval. The certificates and endorsements for each insurance policy shall be signed by a person authorized by that insurer to bind coverage on its behalf. At least fifteen (15 days) prior to the expiration of any such policy, evidence of insurance showing that such insurance coverage has been renewed or extended shall be fi led with the City. If such coverage is cancelled or reduced, and not replaced immediately so as to avoid a lapse in the required coverage, Contractor shall, within ten (10) days after receipt of written notice of such cancellation or reduction of coverage, file with the City evidence of insurance showing that the required insurance has been reinstated or has been provided through another insurance company or companies.

3.13.8 Failure to Maintain Coverage. In the event any policy of insurance required under this Contract does not comply with these specifications or is canceled and not replaced immediately so as t!) avoid a lapse in the required coverage, City has the right but not the duty to obtain the insurance it deems necessary and any premium paid by City will be promptly reimbursed by Contractor or City will withhold amounts sufficient to pay premium from Contractor payments. In the alternative, City may cancel this Contract, effective upon notice.

3.13.9 Acceptability of Insurers. Each such policy shall be from a company or companies with a current A.M. Best's rating of no less than A- VII and authorized to transact business of insurance in the State of California, or otherwise allowed to place insurance through surplus line brokers under applicable provisions of the California Insurance Code or any federal law.

3.13.10 Enforcement of Contract Provisions (non estoppel}. Contractor acknowledges and agrees that actual or alleged failure on the part of the City to inform Contractor of non-compliance with any requirement imposes no additional obligation on the City nor does it waive any rights hereunder.

3.13.11 Requirements Not Limiting . Requirement of specific coverage or minim um limits contained in this Appendix are not intended as a limitation on coverage, limits, or other requirement, or a waiver of any coverage normally provided by any insurance.

3.13.12 Insurance for Subcontractors. Contractor shall include all Subcontractors as additional insureds under the Contractor's policies, or the Contractor shall be responsible for causing Subcontractors to purchase the appropriate insurance in compliance with the terms of these Insurance Requirements, including adding the City, its officials, officers, employees, agents and volunteers as additional insureds to the Subcontractor's policies. All policies of Commercial General Liability insurance provided by Subcontractors shall be endorsed to name the City, its officials, officers, employees, agents and volunteers as additional insureds using endorsement form ISO CG 20 38 04 13. Contractor shall not allow any Subcontractor to commence work until it has received satisfactory evidence of Subcontractor's. compliance with all insurance - 39 - 55452.01510\32977834.2
52 requirements under this Contract, to the extent applicable. The Contractor shall provide satisfactory evidence of compliance with this section upon request of the City. - 40-
55452.01510\32977834.2