RESOLUTION NO. 25-113
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
SAN CLEMENTE, CALIFORNIA, AWARDING A
CONSTRUCTION CONTRACT TO ALLIANCE DIVERSIFIED
ENTERPRISES, INC. FOR THE MARQUITA SLOPE
INTERIM RECONSTRUCT CIP PROJECT NO. 21208 IN AN
AMOUNT NOT TO EXCEED$ 2,149,870, APPROVING A
SUPPLEMENTAL APPROPRIATION IN THE AMOUNT OF
$500,190, AND AUTHORIZING THE CITY MANAGER TO
EXECUTE THE CONTRACT, AND FINDING THE PROJECT
CATEGORICALLY EXEMPT FROM THE CALIFORNIA
ENVIRONMENTAL QUALITY ACT (CEQA) UNDER CLASS
1 (EXISTING FACILITIES, 14 CCR SECTION 153019) OF
THE STATE CEQA GUIDELINES
WHEREAS, on March 7· 2025, the City of San Clemente was granted an Emergency Development Coastal Permit for the Marquita Slope Interim Reconstruct CIP Project No. 21208;and
WHEREAS, in order to protect public health and safety, repairs are needed immediately to secure the Linda Lane Pump Station to protect life and property prior to the upcoming winter rain season; and
WHEREAS, on July 30, 2025, the City received two (2) responsive bids ranging from $2,149,870 to $5,509,690 for the project; and
WHEREAS, Alliance Diversified Enterprises, Inc. was the lowest responsive and responsible bidder with a bid of $2,149,870.
NOW, THEREFORE, the City Council of the City of San Clemente does hereby find, determine, and resolve as follows:
SECTION 1. That the above recitations are true and correct and fully incorporated herein.
SECTION 2. That based upon substantial evidence in the record as a whole, the Project is categorically exempt from the California Environmental Quality Act (CEQA) under Class 1 (Existing Facilities, 14 CCR section 15301) of the State CEQA Guidelines because it consists of repairs to existing City facilities, involves negligible or no expansion of existing or former use and there is no possibility of a direct or reasonably foreseeable indirect effect on the environment.
SECTION 3. That the supplemental appropriation in the amount of $500,190 into account No. 054-476-43470-000-21208 from the sewer depreciation fund is hereby approved.
SECTION 4. That the Construction Contract Agreement for the Marquita Slope Attachment 3
Resolution No. 25-113 Page2
Interim Reconstruct, CIP Project No. 21208, is hereby awarded to Alliance Diversified Enterprises, Inc., contingent upon a finalized right of entry agreement for the work SECTION 5. That the City Manager is authorized and directed to execute a construction contract for the Marquita Slope Interim Reconstruct, CIP Project No. 21208, with Alliance Diversified Enterprises, Inc., in an amount not to exceed $2,149,870, in a form substantially similar to that presented to City Council on August 5, 2025.
SECTION 6. That the City Manager is authorized and directed to negotiate and finalize a right of entry agreement For The Marquita slope reconstruction work.
SECTION 7. That the City Manager is authorized and directed to take such other and further actions as are necessary and proper to accomplish the purposes of this resolution and complete the project.
SECTION 8. That the City Clerk shall certify to the passage and adoption of this resolution and enter it into the book of original resolutions.
PASSED AND ADOPTED this 5th day of August, 2025.
Cit le of the City of
San Clemente, California
Steve Kc;i!;ayor of the
City of San Clemente, California
------
Resolution No. 25-113 Page 3
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) §
CITY OF SAN CLEMENTE )
I, LAURA CAMPAGNOLO, City Clerk of the City of San Clemente, California, do hereby certify that Resolution No. 25-113 was adopted at a special and regular meeting of the City Council of the City of San Clemente held on the 5th day of August, 2025, by the following vote:
AYES: CABRAL, ENMEIER, LOEFFLER, WU, MAYOR KNOBLOCK
NOES: NONE
ABSENT: NONE
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the official seal of the City of San Clemente, California, this \ '((f'\ day of August, 2025. ' Approved as to form:
Elizageth A Mitchell, City Attorney
LERK of the City of
Clemente, California