Change Order for Grand Well SCADA (RoviSys)

San Jacinto City Council
April 15, 2025

Document
Change Order for Grand Well SCADA (RoviSys)
Meeting
April 15, 2025
Body
San Jacinto City Council
Original file
724 KB
Text extracted from the city's file for reading and search. Open the original on sanjacintoca.iqm2.com. That file is the official record.

www.rovisys.com North America | Asia | Europe
City of San Jacinto
Grand Well and Treatment Improvements
For
Mathew Osborn
Water Utilities Superintendent
City of San Jacinto
270 Bissell Place, San Jacinto, CA 92582
P: 951.487.7330 x755 C: 951.537.7721
[email protected]
Prepared by
Mike Perez Aiden Hall
Proposal Number Project Engineer System Engineer
COSAJ24A02-A 919.387.1200 ext. 86356 562.447.3808
March 21, 2025 [email protected] [email protected] COSAJ24A02-A March 21, 2025
Grand Well and Treatment Improvements Page 2 of 27
Table of Contents
1 Project Proposal ....................................................................................................... 4

1.1 Project Overview .......................................................................................................................... 4

1.2 Basis for Proposal ....................................................................................................................... 5

1.3 Services Scope and Deliverables .................................................................................................. 7

1.4 RoviSys Assumptions ................................................................................................................ 24 2 Pricing ................................................................................................................... 25

2.1 Pricing Summary....................................................................................................................... 25

2.2 Fixed Services Breakout ............................................................................................................ 25

2.3 Outside Hardware and Services Total ........................................................................................ 26 3 Terms and Conditions ............................................................................................ 27 COSAJ24A02-A March 21, 2025
Grand Well and Treatment Improvements Page 3 of 27
Proposal Revision History
Rev Date Description
A March 21, 2025 Initial Revision
B -
NOTICE
This document contains RoviSys proprietary information and has been provided for the sole purpose of evaluation. Acceptance of the document constitutes agreement that the recipient shall not disclose RoviSys proprietary information to any third party in whole or in part or transmit any documents or copies thereof in whole or in part to any third party without the expressed written consent of The RoviSys Company.

All copyrights and trademarks remain the property of their respective owners.

COSAJ24A02-A March 21, 2025
Grand Well and Treatment Improvements Page 4 of 27
1 Project Proposal

1.1 Project Overview
City of San Jacinto has requested that RoviSys provide a proposal in response to the Construction of the New Grand Treatment Plant Facility and Equipping of the New Grand Well Project. Construction of the Grand Treatment Plant and Equipping of the New Grand Well effort will run in parallel with ongoing SCADA Migration. Construction of the Grand Treatment Plant and Equipping of the New Grand Well calls for Integrator (RoviSys) to:

Design Radio Communications
o 5 GHz radio and flat panel
integrator.

Design/build RTU-100 control panel
RTU-100 OIT (Operator Interface Terminal) Configuration o RTU-100 OIT will be part of VTScada plant wide SCADA instance. o If radio fails, thin client can still run RTU-100 locally.

RTU-100 PLC (Programmable Logic Controller) Configuration COSAJ24A02-A March 21, 2025
Grand Well and Treatment Improvements Page 5 of 27

1.2 Basis for Proposal
The information in the following sections reflects the estimated quantities used as the basis for this proposal. These quantities are derived from the data provided and are utilized for estimation purposes only. Final field quantities will be determined during the design portion of this control system project. This proposal is based on bid documents received from City of San Jacinto, and subsequent communications.

This Request for Proposal includes the following documents:

COSAJ24A02-A March 21, 2025
Grand Well and Treatment Improvements Page 6 of 27

1.2.1 I/O Quantities per P&ID Drawings
IO Type Hardwired to
RTU-100 Qty
Analog Inputs 10
Analog Outputs 3
Digital Inputs 24
Digital Outputs 6
Total Hardwired I/O 43
IO Type Soft IO from OEM Qty
Analog Inputs 12
Analog Outputs 7
Digital Inputs 58
Digital Outputs 54
Total Hardwired I/O 131

1.2.2 Graphics Quantities
An estimated total of 10 overview displays to be incorporated into RTU- COSAJ24A02-A March 21, 2025
Grand Well and Treatment Improvements Page 7 of 27

1.3 Services Scope and Deliverables
RoviSys will provide the following scope items to meet the project requirements for RTU-100 as defined in the specifications and drawings. All RoviSys scope is limited to called out sections located within Division 40 PROCESS of the bid specification, plus supporting sections called out: Division 01 GENERAL and Division 26 ELECTRICAL. These sections are identified below along with a summary of the scope that RoviSys will provide, as well as any exceptions/clarifications associated with that scope.

Section Title Notes
40 00 00 INSTRUMENTATION GENERAL
REQUIREMENTS Excluded
40 05 13 COMMON WORK RESULTS FOR PRCOESS
PIPING Excluded
40 05 13.09 FLUSHING AND DISINFECTION Excluded
40 05 13.10 FLUSHING AND TESTING Excluded
40 05 13.11 LEAK TESTING OF PIPING Excluded
40 05 13.13 STEEL PROCESS PIPING (BLACK AND
GALVANIZED) Excluded
40 05 13.53 DUCTILE, MALLEABLE, AND CAST IRON
ALLOYS PROCESS PIPING Excluded
40 05 23 COMMON WORK RESULTS FOR PROCESS
VALVES Excluded
40 05 29 HANGERS AND SUPPORTS FOR PROCESS
PIPING SYSTEMS Excluded
40 80 01 TESTING, CALIBRATION AND
COMMISSIONING Excluded
40 90 00 INSTRUMENTATION AND CONTROLS FOR

PROCESS SYSTEMS
Included, see below
section for additional
details
40 91 19.29 PRESSURE TRANSMITTERS Excluded
40 91 19.30 PRESSURE AND DIFFERENTIAL PRESSURE
SWITCHES Excluded
40 91 23.35 FLOW PROCESS MEASUREMENT DEVICES
MAGNETIC Excluded
40 91 23.37 LEVEL PROCESS MEASUREMENT DEVICES
LEVEL SWITCHES Excluded
40 91 23.40 LEVEL PROCESS MEASUREMENT DEVICES
PRESSURE TYPE Excluded
COSAJ24A02-A March 21, 2025
Grand Well and Treatment Improvements Page 8 of 27
Section Title Notes
40 91 23.41 LEVEL PROCESS MEASUREMENT DEVICES
ULTRASONIC Excluded
40 91 23.42 LEVEL PROCESS MEASUREMENT DEVICESSUBMERSIBLE Excluded 40 91 23.55 LIMIT AND POSITION SWITCHES Excluded
40 96 36 PROCESS CONTROL DESCRIPTIONS
Included, see below
section for additional
details
01 00 00 GENERAL REQUIREMENTS Excluded
01 04 50 EXISTING FACILITIES Excluded
01 11 00 SUMMARY OF WORK Excluded
01 14 13 ACCESS TO SITE Excluded
01 14 16 COORDINATION WITH THE OWNER Excluded
01 14 19 USE OF SITE Excluded
01 20 00 PRICE AND PAYMENT PROCEDURES Excluded
01 31 19 PROJECT MEETINGS Excluded
01 32 16 CONSTRUCTION PROGRESS SCHEDULE Excluded
01 32 19 SUBMITTALS SCHEDULE
Included, see below
section for additional
details
01 33 00 SUBMITTAL PROCEDURES Excluded
01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND

SAMPLES
Included, see below
section for additional
details
01 40 00 QUALITY REQUIREMENTS Excluded
01 42 13 ABBREVIATIONS Excluded
01 42 19 REFERENCE STANDARDS Excluded
01 45 16 FIELD QUALITY CONTROL PROCEDURES Excluded
01 45 16.13 CONTRACTOR QUALITY CONTROL Excluded
01 51 00 TEMPORARY UTILITIES Excluded
01 52 19 SANITARY FACILITIES Excluded
01 55 26 TRAFFIC CONTROL Excluded
01 56 26 TEMPORARY FENCING Excluded
COSAJ24A02-A March 21, 2025
Grand Well and Treatment Improvements Page 9 of 27
Section Title Notes
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS Excluded
01 60 00 PRODUCT REQUIREMENTS Excluded
01 65 00 EQUIPMENT TESTING, TRAINING, AND

STARTUP
Included, see below
section for additional
details
01 66 00 PRODUCT STORAGE AND HANDLING
REQUIREMENTS Excluded
01 71 13 MOBILIZATION Excluded
01 71 18 SITE ACCESS AND STORAGE Excluded
01 71 23 CONSTRUCTION SURVEYING Excluded
01 71 31 PROTECTION OF EXISTING FACILITIES Excluded
01 73 50 TESTING, DISINFECTION OF WATER
FACILITIES Excluded
01 77 00 CLOSEOUT PROCEDURES
Included, see below
section for additional
details
01 78 23 OPERATION AND MAINTENANCE DATA
Included, see below
section for additional
details
01 78 39 PROJECT RECORD DOCUMENTS
Included, see below
section for additional
details
01 79 00 FINAL ACCEPTANCE TESTING
Included, see below
section for additional
details
26 00 00 GENERAL ELECTRICAL REQUIREMENTS
Included, see below
section for additional
details
26 00 01 PACKAGED SYSTEM AND CONTROL PANELS
Included, see below
section for additional
details
26 00 60 ELECTRICAL DEMOLITION Excluded
26 01 27 ELECTRICAL ACCEPTANCE TESTING Excluded
26 05 19 LOW VOLTAGE ELECTRICAL POWER

CONDUCTORS AND CABLES
Included, see below
section for additional
details
COSAJ24A02-A March 21, 2025
Grand Well and Treatment Improvements Page 10 of 27
Section Title Notes
26 05 26 GROUNDING AND BONDING FOR ELECTRICAL
SYSTEMS Excluded
26 05 33 PULLBOXES FOR ELECTRICAL SYSTEMS Excluded
26 05 35 CONDUIT FOR ELECTRICAL SYSTEMS Excluded
26 05 53 IDENTIFICATION FOR ELECTRICAL SYSTEMS Excluded 26 05 73 POWER SYSTEM STUDY Excluded
26 05 83 WIRING CONNECTIONS
Included, see below
section for additional
details
26 05 90 ENCLOSURES GENERAL GRAND NOT
PROVIDED. Excluded.
26 09 13 ELECTRICAL POWER MONITORING Excluded
26 09 16 ELECTRICAL CONTROLS AND RELAYS Excluded
26 21 00 LOW VOLTAGE ELECTRICAL SERVICE
ENTRANCE Excluded
26 22 13 LOW VOLTAGE DISTRIBUTION
TRANSFORMERS Excluded
26 22 20 MINI POWER CENTERS Excluded
26 24 13 SWITCHBOARDS Excluded
26 24 16 PANELBOARDS Excluded
26 24 19 MOTOR CONTROL CENTER Excluded
26 27 26 WIRING DEVICES Excluded
26 27 27 WEATHERPROOF WHILE IN USE OUTLET
ENCLOSURES Excluded
26 28 17 ENCLOSED SWITCHES Excluded
26 29 13 MOTOR STARTERS Excluded
26 29 23 VARIABLE FREQUENCY MOTOR
CONTROLLERS Excluded
26 32 26 ENGINE DRIVEN GENERATOR SET Excluded
26 36 23 AUTOMATIC TRANSFER SWITCH Excluded
26 43 00 SURGE PROTECTIVE DEVICES Excluded
26 50 00 LIGHTING Excluded
COSAJ24A02-A March 21, 2025
Grand Well and Treatment Improvements Page 11 of 27
Section Title Notes
26 05 09 LOW VOLTAGE MOTORS UP TO 500
HORSEPOWER Excluded
01 32 19 Submittals Schedule
RoviSys accepts all the responsibilities identified in this section, with inclusions/exclusions noted below.

Inclusions:

1. RoviSys to expect 10-15 calendar days after receipt by the Owner for review of each submittal, including re-submittals.

2. RoviSys submittal cover sheets to include name, address, telephone number, submittal number, date, contract title / number, subcontractor information if applicable.

3. Each RoviSys submittal includes applicable drawings and specification references.

Exclusions:

1. CONTRACTOR responsible for all other requirements in this specification.

COSAJ24A02-A March 21, 2025
Grand Well and Treatment Improvements Page 12 of 27
01 33 23 Shop Drawings, Product Data & Samples
RoviSys accepts all the responsibilities identified in this section, with inclusions/exclusions noted below.

Inclusions:

1. Panel drawings shall be produced using AutoCAD.

2. 3. Panel drawings shall include external panel details, internal panel details, power distribution, PLC schematics, loop/interconnect drawings, and network architecture details. A symbol distribution legend shall be provided as required.

4. Custom title block shall be produced with
a. Drawing number, date, title, revision, number, and sheet number b. Name of CONTRACTOR
c. Contract number.
d. Subcontractor/manufacturer name (if applicable)
e. Name of installation location

5. Product data shall be provided. Applicable submittals shall have a technical literature section to illustrate/describe each BOM item.

6. Model number and serial numbers shall be provided in the O&M manual. Hardware Factory Acceptance Testing shall provide steps to record all serial numbers.

Exclusions:

1. Elevation view drawings with conduit details not included.

2. No samples to be provided by RoviSys.

3. Certificate of compliance to be produced by others.

4. Contract sheet number, contract page number will be provided in respective specification check sections in submittals, not title blocks.

5. Seismic studies to be provided by others.

COSAJ24A02-A March 21, 2025
Grand Well and Treatment Improvements Page 13 of 27
01 65 00 Equipment Testing, Training, and Startup
RoviSys accepts all the responsibilities identified in this section, with inclusions/exclusions noted below.

Inclusions:

1. per District approved design drawing packages. RoviSys panel testing is conducted by the project engineers during fabrication and upon final completion of the panels.

Panel testing will be documented in the Hardware Factory Acceptance Testing report with pictures.

2. RoviSys shall provide proposed dates for training, site acceptance testing, and operations/maintenance training that relate to RTU-100.

3. Training shall not commence until O&M manuals have been accepted.

Exclusions:

1. Video recordings shall be coordinated and provided by others for training. 01 77 00 - Closeout Procedures
RoviSys accepts all the responsibilities identified in this section, with inclusions/exclusions noted below.

Inclusions:

1. CONTRACTOR to submit all approved submittals to District prior to formal closeout in a transmittal format. RoviSys shall provide all as built material to CONTRACTOR prior to close out.

Exclusions:

1. Construction cleanup to be done by others.

COSAJ24A02-A March 21, 2025
Grand Well and Treatment Improvements Page 14 of 27
01 78 23 Operation and Maintenance Data
RoviSys accepts all the responsibilities identified in this section, with inclusions/exclusions noted below.

Inclusions:

1. RoviSys shall produce an Operation and Maintenance (O&M) Manual submittal for review/approval in an electronic format.

Exclusions:

1. Hard copy prints with binders shall be provided by others.

2. Soft copy backups via USB/CD shall be provided by others.

SECTION 01 78 39 PROJECT RECORD DOCUMENTS
RoviSys accepts all the responsibilities identified in this section, with inclusions/exclusions noted below.

Inclusions:

1. Installation, testing and startup reports shall be included in the final O&M submittal.

2. As built drawings shall be included in the final O&M submittal. Both pdf and dwg formats shall be provided.

3. Final payment shall be granted once final O&M submittal is approved.

Exclusions:

1. Certificates of inspection and acceptance by local governing agencies to be provided by others.

2. Others to submit Record Drawings to Safeway Vons DC on behalf of RoviSys.

COSAJ24A02-A March 21, 2025
Grand Well and Treatment Improvements Page 15 of 27
SECTION 01 79 00 FINAL ACCEPTANCE TESTING
RoviSys accepts all the responsibilities identified in this section, with inclusions/exclusions noted below.

Inclusions:

1. Approval of hardware SAT report submittal and software SAT report submittal indicate that all system availability requirements and final system acceptance have been met.

2. As built drawings shall be included in the final O&M submittal. Both pdf and dwg formats shall be provided.

3. Final payment shall be granted once final O&M submittal is approved.

Exclusions:

1. Certificates of inspection and acceptance by local governing agencies to be provided by others.

2. Others to submit Record Drawings to Safeway Vons DC on behalf of RoviSys.

COSAJ24A02-A March 21, 2025
Grand Well and Treatment Improvements Page 16 of 27
SECTION 26 00 00 GENERAL ELECTRICAL REQUIREMENTS
RoviSys accepts all the responsibilities identified in this section, with inclusions/exclusions noted below.

Inclusions:

1. Panel shall be fabricated at a UL listed panel shop.

2. Panel drawings shall include external panel details, internal panel details, power distribution, PLC schematics, loop/interconnect drawings, and network architecture details. A symbol distribution legend shall be provided as required.

3. Wire labels and numbers to be provided in panel drawings.

4. Contractor to provide all applicable vendor submittals related to field wiring for RTU-100 to RoviSys.

5. Final payment shall be granted once final O&M submittal is approved.

6. Power up, power down procedures to be provided in O&M submittals.

7. Loop/interconnect drawings for RTU-100 will only show power/controls/networking interconnects to hardwired field devices. Circuit numbers, conduit sizes, number of conductors, and major junction boxes (if any) shall be shown.

8. Nameplates, labels, and legend plates to be provided.

9. Control wire markers to be provided by panel manufacturer.

10. Heating/cooling calculations shall consider the site conditions provided in spec.

11. Multiple sources of power hazard sign and general electrical danger signs to be provided.

Exclusions:

1. Anchoring devices and supports to be provided by others.

2. Utility coordination to be executed by others.

3. Concrete pad or foundations to be provided and installed by others.

4. Seismic studies to be provided by others.

5. Conduits and any accessories to be installed/provided by others.

6. Arc flash studies to be provided by others.

COSAJ24A02-A March 21, 2025
Grand Well and Treatment Improvements Page 17 of 27
26 00 01 Packaged System and Control Panels
RoviSys accepts all the responsibilities identified in this section, with inclusions/exclusions noted below.

Inclusions:

1. Panel drawings to show power & controls interconnects to hard IO connected to RTU-100.

2. Follow hardware requirements called out.

Exclusions:

1. No control/power interconnects drawings to be provided outside of P&ID drawing Sheets 1,2, 4, 5.
26 05 19 Low Voltage Electrical Power Conductors and Cables RoviSys accepts all the responsibilities identified in this section, with inclusions/exclusions noted below.

Inclusions:

1. Panel drawings shall follow 20 05 19 for internal controls, power, and networking cabling.

2. Follow hardware requirements called out.

Exclusions:

1. Field wiring and conduits provided by others.

2. Wire pulling provided by others.

3. Cable pulling calculations by others.
26 05 83 Wiring Connections
RoviSys accepts all the responsibilities identified in this section, with inclusions/exclusions noted below.

Inclusions:

1. Follow hardware requirements called out for power/controls terminal blocks, fuse holders, terminal strips, grounding blocks, and ancillary terminal strip details.

Exclusions:

1. n/a
COSAJ24A02-A March 21, 2025
Grand Well and Treatment Improvements Page 18 of 27
40 90 00 Instrumentation & Controls for Process Systems RoviSys accepts all the responsibilities identified in this section, with inclusion/exclusions noted below.

Inclusions:

1. RTU-100 hardware and software submittals.

2. RTU-100 hardware FATs and SATs.

3. Provide FAT procedure for factory inspection,

4. Programming methodology, control strategies, and ancillary application software to be provided in software submittal. Applicable for OIT and PLC configurations.

5. Equipment shall received 120VAC to power enclosure.

6. Calculate temperature based on indoor and outdoor provided data.

7. Power supplies shall be 24VDC, 10A minimum.

8. Signal isolators / surge protection shall be provided for analog 4-20mA signals.

9. Interposing relays shall be provided as needed all discrete signals (input/outputs).

10. Dual power supplies and UPS shall be provided and shall be monitored by PLC.

11. integrator.

12. System validation shall be provided for RTU-100 at panel shop and in the field.

Exclusions:

1. Printing of O&M manuals by others.

2. Power monitor meters from 26 09 13 are not in scope. P&IDs do not show hard/soft IO needs to be incorporated into SCADA.

3. Programming/design of FCP-100 control panel, HMI, and PLC.

4. RoviSys will NOT perform any of the following services as part of this contract:

Installation of control panels or instrumentation.

Installation of electrical conduit.

Pulling of wiring or cables.

Field device or control panel wire terminations.

COSAJ24A02-A March 21, 2025
Grand Well and Treatment Improvements Page 19 of 27
40 96 36 Process Control Descriptions
RoviSys accepts all the responsibilities identified in this section, with inclusion/exclusions noted below.

Inclusions:

1. RTU-100 HMI and OIT shall be configured per process narratives mentioned in 40 96 36.

Exclusions:

1. Programming/design of FCP-100 control panel, HMI, and PLC.

COSAJ24A02-A March 21, 2025
Grand Well and Treatment Improvements Page 20 of 27
See estimated deliverables below
Items in blue are SCADA project, no cost to this project.

Items in red
modifications.

Submittal
Number
Submittal Name Descriptions
1 RTU-100 Control Panel
Design Submittal
Bill of Materials
Enclosure hardware
Subpanel hardware
Schneider PLC
Technical Literature
Power Load Study
Heat Load Study
loop & interconnect drawings relative to
RTU-100
Hard IO list
Procure and build once submittal is
approved.
2 Grand Well Radio Design
Submittal
Design/procure 5GHz radio and flat panel
antenna.

Procure radio and flat panel once submittal
is approved.

Updates to Cybervision instance from
server, updates to Cisco 3300 switch.
3 RTU-100 Hardware FAT
Protocol
Panel Shop Energized/Non-Energized
steps, including:

IP Pings
Simulated discrete/analog values
using Fluke
4 RTU-100 Hardware FAT
Report
Pictures
Signatures (remotely or in person)
Redlined drawings, As Built drawings
Serial numbers
5 RTU-100 Software Design
Submittal
PLC & OIT Functional Specification
(modifications to ongoing Grand Well FS
docs)
Soft IO List: Data sharing spreadsheet
(RTU-100 to Filter FCP-100 panel)
OIT Configuration and Screen Graphics
RTU 100
PLC configuration RTU 100 (add-on
configurations)
COSAJ24A02-A March 21, 2025
Grand Well and Treatment Improvements Page 21 of 27
IP addresses
6 RTU-100 Software FAT
Protocol
Using simulated values in remote environment or panel
shop:

Test Operational Logic
Test Failure responses
Test Adjustable Setpoints
Test Interlocks
Test Calculated Variables
Test Alarms
Test Graphic Displays
7 RTU-100 Software FAT
Report
Pictures/screenshots and signed forms by all parties
(remotely or in person)
8 RTU-100 Hardware SAT
Protocol
Once all field wiring has been terminated and energized:

IP Pings
De-Energized and Energized checks
Loop checks of hardwired discrete/analog
values
Soft IO loop check
9 RTU-100 Hardware SAT
Report
Pictures and signed forms by all parties (remotely or in person)
10 RTU-100 Software SAT
Protocol
Using real values:

Test Operational Logic
Test Failure responses
Test Adjustable Setpoints
Test Interlocks
Test Calculated Variables
Test Alarms
Test Graphic Displays
11 RTU-100 Software SAT
Report
Pictures and signed forms by all parties (remotely or in person)
12 RTU-100 Final O&M Includes final as built RTU-100 drawing COSAJ24A02-A March 21, 2025
Grand Well and Treatment Improvements Page 22 of 27

1.3.1 Project Meetings
The following table is a summary of the quantity of meetings proposed for this project. Below the table describes the purpose of each meeting type.

Meeting Description Qty Duration
RoviSys
Resources
Location
Weekly Client Project Status Meetings
(Civeltec/SAJ) 6 1-Hr 2 Remote
Weekly Internal Status Meetings 3 30-Min 3 RoviSys
Internal
Design Review Meetings 3 1.5-Hr 1 Remote or
In Person
RoviSys will conduct regularly scheduled project status review meetings with City of San Jacinto project personnel to review progress and address issues.

Items that will be reviewed during these meetings include:

Review of previous meeting minutes and project action item log Review of project schedule and/or planning documents
Review & status of scheduled deliverables
Review of technical and design topics
The agenda of these meetings will be flexible throughout the course of project to address current and upcoming tasks. For example, when the project is close to the on-site phase, the project status meeting will focus on planning and coordination of the on-site activities.

1.3.1.1 Design Review Meetings
Design Reviews are performed by the project teams to ensure that project implementation is meeting project objectives and user requirements. The RoviSys lead engineer will conduct these meetings either on-site at City of San Jacinto or via web conference. Three Design review meetings are allocated for the following:

Workshop soft IO details with Filter PLC OEM (Pureflow).

Workshop software design specifications with district.

Workshop updated telemetry design with the district.

COSAJ24A02-A March 21, 2025
Grand Well and Treatment Improvements Page 23 of 27

1.3.2 Project Closeout

1.3.2 RoviSys will assemble a turn-over package for City of San Jacinto once the project has been successfully delivered. The project turnover package will include electronic copies of the last transmitted version of every document supplied by RoviSys. The project turnover package will also include the as-installed software configuration files.

The Project Closeout Activities will include a lessons-learned meeting attended by the appropriate RoviSys and City of San Jacinto project and management personnel.

COSAJ24A02-A March 21, 2025
Grand Well and Treatment Improvements Page 24 of 27

1.4 RoviSys Assumptions
This proposal is based upon the following assumptions:

1. This proposal is based on quantities detailed in the Basis for Proposal section.

2. RoviSys has assumed that equipment and systems will be available when required to support the scheduled field activities without causing any delays. Delays of system availability may impact project schedules or resource availability, as well as price.

3. Field devices including instrumentation, transmitters, sensors, switches or other networking interfaces, network cables, all field wiring, VFDs, motor starters and drives will be procured and installed by others.

4. The programming of field instruments or the verification of field instrument wiring and calibration will be provided by others.

5. Physical installation of control system hardware, wiring, instrumentation, field panels, and HMIs will be performed by others.

6. Grand RTU-100 new cabinet shall replace the former SCADAPack PLC cabinet. Once the enclosure requires relocation to the new location per bid drawings, existing conduit holes shall be capped.

COSAJ24A02-A March 21, 2025
Grand Well and Treatment Improvements Page 25 of 27
2 Pricing
RoviSys has estimated, in good faith, the effort and cost of this project. The fixed cost estimate is based on the information provided by City of San Jacinto and on our experience in defining and implementing projects of similar scope and complexity.

2.1 Pricing Summary
Pricing Summary Table
Scope Item Price
Engineering Services - Fixed $80,369
Engineering Services - T&M $0
Outside Purchased Equipment, Software & Services $36,892 Travel and Living Expenses (estimated) $3,147
Tax on OPE (estimated) $1,875
Bond Pricing $1,834
Proposal Total $124,117

2.2 Fixed Services Breakout
Engineering Services Pricing Table
Services Scope - Fixed Price Price
Project Management $8,720
Meetings $3,795
Design Documents $5,064
Electrical Design $6,993
Infrastructure Configuration $860
Graphics Configuration $9,600
Control Configuration $10,560
Test Documents $3,072
In-House Testing $6,400
Site Support - Install & Loop Checks $9,464
Site Support - Commissioning $6,552
Training $3,640
As Built Documentation $1,274
Travel Hours $4,375
Fixed Price Services Subtotal $80,369
COSAJ24A02-A March 21, 2025
Grand Well and Treatment Improvements Page 26 of 27

2.3 Outside Hardware and Services Total

2.3 Outside Purchased Services Pricing Table
Outside Purchased Services Price Tax
Panel Build $10,615 $0
Outside Purchased Services Subtotal $10,615 $0
Outside Purchased Equipment & Software Pricing Table
Outside Purchased Equipment & Software Price Tax
Controls Hardware $21,084 $1,845
Network Hardware $345 $30
Software and Licenses $4,848 $0
Outside Purchased Equipment Subtotal $26,277 $1,875
COSAJ24A02-A March 21, 2025
Grand Well and Treatment Improvements Page 27 of 27
3 Terms and Conditions
This proposal is valid for 90 days.

Preferred rates have been applied for this project.

If RoviSys is selected for this work please send the purchase order to [email protected]
Approvals to Proceed with Changes
The RoviSys Company City of San Jacinto
Signature Signature
Printed
Name
Printed
Name
Title Title
Date Date