July 28, 2025
City of San
Jacinto
CISJA.250440
3850 Vine Street, Suite 110 | Riverside, CA 92507 | 805.692.6921 Office | mnsengineers.com Construction Management Services for
Construction of the Grand Treatment
Plant and Equipping of the Grand Well
Project #22-010

PROPOSAL TO PROVIDE
3850 Vine Street, Sui | Address Line 2
555.555.5555 OFFICE
mnsengineers.com
July 28, 2025
City of San Jacinto
Attention: Selection Committee
595 S. San Jacinto Ave.

San Jacinto, CA 92583
SUBJECT: Proposal to Provide Construction Management Services for the Construction of Grand Treatment Plant and Equipping of Grand Well
Dear Selection Committee:

MNS Engineers, Inc. (MNS) appreciates the opportunity to submit this proposal to provide Construction Management (CM) Services for the Construction of Grand Treatment Plant and Equipping of Grand Well (Project) for the City of San Jacinto (City).

Since 1962, MNS has provided quality infrastructure consulting services to the water resource market throughout California. We specialize in the core services of construction management, civil engineering, and land surveying. Currently, MNS is providing CM professional services for numerous public agency water and wastewater projects within California. This invaluable experience provides us with a comprehensive project understanding and involvement from conception to completion.

MNS has assigned Aaron Singer, PE as the Project Contact/Project Manager.

He will serve as the City’s trusted advisor to bring this project through to completion. Additionally, we have selected LandMark Consultants, Inc., a Disadvantaged Business Enterprise (DBE) that will provide geotechnical and materials testing services (soils and concrete), along with another trusted Women’s Business Enterprise (WBE) teaming partner, Z&K Consultants, to facilitate the site observation. Aaron and his team have carefully reviewed the requirements of the RFP and project scope and alongside the contractor, are ready to deliver these core project elements: a new welded steel clarifier tank, equipped well, Pureflow treatment system, fabricated steel treatment enclosure building, FRP hypochlorite enclosure, generator, site piping and electrical, and demolition. Our team is excited to begin these services pending selection on August 5, 2025, and look forward to a successful completion come January 21,

MNS DETAILS

LEGAL NAME
MNS Engineers, Inc.

FIRM OWNERSHIP TYPE
C-Corporation

YEAR FIRM ESTABLISHED
1962

CALIFORNIA DEPARTMENT

OF INDUSTRIAL RELATIONS
DIR No. 1000003564

CORPORATE OFFICE
201 N. Calle Cesar Chavez,
Suite 300
Santa Barbara, CA 93103
805.692.6921 Office/Fax
mnsengineers.com

LOCAL OFFICE
3850 Vine Street, Suite 110
Riverside, CA 92507
805.692.6921 Corporate
Dispatch

PROJECT CONTACT
Aaron Singer, PE
Project Manager
424.392.5823
[email protected]

AUTHORIZED SIGNATURE
Joe Pope, PE, QSD/QSP
Vice President, CM Water
805.302.1624
[email protected]

STATEMENTS
This proposal will remain valid
for a 90-day period.

Appendices
A. 2-page Resumes
City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 2
2027. Our team is ready and prepared to expeditiously work alongside the City, the contractor, and the Engineer of Record (EOR) to deliver the Project.

MNS is confident our uniquely experienced and qualified team will provide quality services and ensure successful City project delivery. We look forward to building our working relationship with the City and being a part of your growth and improvement. Please contact me with any questions you may have about our submittal or if there is a desire to negotiate any of the items that are included here-in or within the Fee. Thank you for your consideration.

Sincerely,
MNS Engineers
Joe Pope, PE, QSD/QSP
Vice President, CM Water Resources

MNS DETAILS
Acknowledgments
Addendum #1 – July 14, 2025
Addendum #2 – July 15, 2025
Addendum #3 – July 15, 2025
FEE
Attached as a separate file, per
RFP requirements.

City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 3

TABLE OF CONTENTS
COVER LETTER 1-2

1. EXECUTIVE SUMMARY 4

2. QUALIFICATIONS AND EXPERIENCE 4-10
2A. SKILLS AND EXPERIENCE 4-5
2B. PROJECT TEAM AND COMPANY 5-9
2C YEARS IN OPERATION 10
2D. OUR EXPERIENCE 10

3. REFERENCES 11

4. SUBCONSULTANTS 13-14

5. PROPOSED METHOD TO ACCOMPLISH THE WORK 15
5A. PROJECT UNDERSTANDING 15
5B. PROJECT KEYS 16
5C. THE MNS APPROACH 20
5D. SCOPE OF WORK 22
5E. PROPOSED DRAFT SCHEDULE 35

6. CERTIFICATION OF PROPOSAL 36

7. FEE PROPOSAL 36
APPENDIX A: STAFF RESUMES 37
City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 4

1. Executive Summary
The City is seeking a firm to provide expeditious construction management services for the Grand Treatment Plant and Equipping of Grand Well Project. As a multidisciplinary infrastructure consultant, MNS has the resources to successfully deliver projects to our clients and has selected the right team for this project. As detailed within Section 2, the project will be spearheaded by Aaron Singer, PE and directly supported by Pat Hanify, PE. Aaron and Pat bring a dedicated local background to their construction management process as well as the technical know-how to deliver the project successfully. They will be supported as detailed in Sections 2 and 4 by Z&K Consultants (Z&K), an Inland Empire based trusted teaming partner, who is able to efficiently provide onsite observation to the City. A current teaming partner on several MNS projects, LandMark Consultants (LandMark) will facilitate the geotechnical and material testing onsite in a responsive manner. Our team has extensively reviewed the project documents and RFP files provided by the City, from review of the site along with available documentation accessible through the City’s website. It is this research and careful planning that has allowed us to assemble 15 project “keys” (detailed in Section 5), along with the comprehensive and tailored resources necessary to accomplish the scope of work. We are confident in our team and look forward to working alongside the City to deliver this successful project to the community.

2. Qualifications and Experience
2A. Skills and Experience
Water and Wastewater Construction Management (CM) Expertise MNS offers an experienced CM team with hands-on experience in the management of new and renovated water and wastewater facilities and infrastructure projects. Throughout the past decade alone, MNS has successfully managed over $1B of water and wastewater treatment and improvement projects.

Our construction management expertise includes:
• Complete construction management and
inspection
• Scheduling and Critical Path Method (CPM)
review
• Time impact analysis
• Risk management
• Claims and safety management, avoidance, and
mitigation
• Cost estimating
• Funding administration: local, state, and federal
• Contract administration and constructability
review
• Stormwater Pollution Prevention Plan (SWPPP)
compliance
• Multi-party and contractor coordination
• Plant startup and commissioning
• Permitting and coordination
MNS Team Overview
MNS offers an experienced and motivated team for construction management and inspection services for this critical project. Our team's substantial experience in managing similar projects provides a valuable understanding of critical project elements and potential issues. Our team has the following key objectives:
• Quality service and projects • Schedule and budget efficiency City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 5
• Adherence to QA/QC standards • Consistent communication • Application of technical and practical expertise
2B. Project Team
Our cohesive, talented team of experienced professionals meet all the specific elements and requirements for the Project. Figure 2.1 displays our team organization chart. This section provides a brief overview of the responsibilities and biographies for key team members. Appendix A contains two-page resumes for each team member.

Figure 2.1. Team Organization Chart
3850 Vine Street, Sui | Address Line 2
555.555.5555 OFFICE
mnsengineers.com
Aaron Singer, PE
Project Manager
Firm MNS
Years Exp 9
License Professional Civil Engineer, CA No. 94535
Certification OSHA 30 Hour Construction Safety and Health Training
As Project Manager, Mr. Singer will manage all
construction activities, administration of project
documentation, oversee the Construction Inspectors,
and coordinate construction activities with the
contractor. Aaron has nine years of construction and
engineering experience. His career has been shaped
by mentorship from industry leaders, allowing him to
build a strong track record in construction
management, inspection, and constructability reviews.

With a diverse background spanning heavy civil
construction, precast, and land development, he
excels in design drafting, field supervision, and clear project communication. Recently, Aaron’s focus has
been on managing water and wastewater
infrastructure projects, where his skills continue to
drive successful outcomes.

Joe Pope, PE, QSD/QSP
Principal-in-Charge
Firm MNS
Years Exp 27
License Professional Civil Engineer, CA No. 63553
Certification Qualified SWPPP Developer/Practitioner
(QSD/QSP) CA No. C63553
CalOES Safety Assessment Program
Lean Six Sigma Green Belt Certification
Mr. Pope is a collaborative civil engineer with over 27 years of progressive, executive management
experience leading large municipal and federal public
works organizations. Joe is a recognized visionary
leader in managing large interdisciplinary engineering, operations, and planning teams in the efficient
delivery of sustainable facilities, construction,
environmental, water, wastewater, and electrical
utilities. He is an exceptional problem solver with
excellent communication skills and an ethical and
inspirational leader.

Patrick Hanify, PE, CCM, QSD/QSP
QA Oversight and Technical Support –
Principal Construction Manager
Firm MNS
Years Exp 19
License Professional Civil Engineer, CA No. 79874
Certification Certified Construction Manager, CA No. 8612 Qualified SWPPP Practitioner (QSP), CA No.
20942
Qualified SWPPP Developer (QSD), CA No.

C79874
OSHA 30-Hour
With over 19 years of experience in construction
management, project management, inspection,
resident engineering, owners' engineering, and owner
representation, Mr. Hanify has played a key role in
many Southern California public works and
infrastructure projects. Patrick’s expertise spans water and wastewater treatment facilities, large-scale public works, and complex land development projects. All of
Patrick’s projects are executed with strict adherence
to labor regulations and quality standards. Serving a
diverse client base that includes public and private
utilities, joint powers authorities, land developers,
municipalities, and state agencies, he excels at
managing stakeholder relationships and navigating
regulatory challenges.

Known for delivering projects on time and within
budget, Patrick combines proactive problem-solving
City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 7
with a deep knowledge of local, state, and federal
regulations to provide clients with efficient and
effective solutions. His skills in drafting ensure clear communication throughout the life of each project,
reducing conflicts while boosting efficiency—making
him a trusted partner from start to finish.

Carlos Gaytan, D3
Senior Construction Observer
Firm Z&K
Years Exp 30
Certification SWRCB Water Distribution Operator D3,
Operator #14889
Bilingual in English and Spanish
30 Cal/OSHA
Confined Space Training
Fall Protection
Traffic Control Safety
Mr. Gaytan will serve as the Senior Construction
Observer for the City of San Jacinto Grand Well Site
project. With more than 30 years of experience in
public works construction, underground utilities, and
water infrastructure, Carlos brings extensive field
knowledge and a disciplined approach to observing
and documenting all aspects of construction activities
for potable water systems. Carlos has supported a
wide variety of water and sewer infrastructure
projects, including well equipping, manhole
rehabilitation, confined space operations, bypass
pumping coordination, and trench restoration. He has
observed and documented work related to
excavation, backfill, pipe installation, structural
concrete, treatment system components, coatings,
pressure testing, traffic control, and ADA-compliant
surface restoration. He is well-versed in monitoring
contractor performance for compliance with plans,
specifications, CEQA mitigation measures, and
SWPPP best practices.

As a certified Water Distribution Operator (D3), Carlos offers technical expertise in pipeline construction,
potable water system installation, and inspection of
structural and mechanical components. He is
proficient in maintaining detailed daily field reports, capturing photographic documentation, and facilitating
coordination between the contractor, engineers, utility companies, and City personnel. Carlos’ bilingual
communication skills (English and Spanish) help
ensure clear and prompt issue resolution in the field.

His dedication to quality, safety, and schedule
adherence—combined with his familiarity with public
agency standards and regulatory compliance—makes
him a trusted observer for complex water
infrastructure projects.

Ed Nylund
Senior Construction Observer
(Alternate)
Firm Z&K
Years Exp 34
Certification Water Treatment Operator – Grade 2 |
Certificate No. 17150
Water Distribution Operator – Grade 3 |
Certificate No. 4903
QSP Certificate No. 26356
Traffic Signal Senior Field Technician III
Certificate No. 97687
Traffic Signal Inspector Certificate No. SI97687
Ed Nylund is a highly experienced Senior
Construction Observer with over 34 years of hands-on
expertise in public works inspection, utility
construction, and field supervision throughout
Southern California. Ed’s background spans a wide
array of water and wastewater infrastructure,
including potable and recycled water pipelines, sewer
and storm drain systems, pump stations, reservoirs,
and major utility coordination.

For more than 20 years, Ed served as the Lead Public
Inspector for the City of Chino, where he oversaw
City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 8
daily inspection operations for capital improvement
projects involving waterline and sewer main
replacements, grading, encroachment permits, fiber
optics, traffic signal systems, and ADA-compliant
improvements. He regularly collaborated with City
engineers and contractors to ensure construction met
all applicable codes, safety regulations, and
specifications.

Ed brings additional value through his leadership in
inspector training. He served as the lead instructor for the Maintenance Superintendents Association’s
(MSA) 12-week online Public Works Inspector
Training Program in 2024, developed a 16-week
Traffic Signal Inspection Training Program for the City of Chino in 2019, and delivered a tailored best
practices session for the City of San Bernardino in
2025. With certifications in Water Treatment (Grade
2), Water Distribution (Grade 3), Traffic Signal
Inspection, and Field Supervision, Ed brings
unmatched technical depth and communication skills
to his observer role.

As Alternate Senior Construction Observer, Ed is
prepared to step in seamlessly to maintain project
continuity, review inspection documentation,
coordinate field activity, and uphold the highest
standards of quality and compliance on the Grand
Well Site project.

Sandra Lee
Labor Compliance
Firm MNS
Years Exp 13
Certification US Department of Labor Davis-Bacon Act
Prevailing Wage
US Department of Housing and Urban
Development Section 3
US Department of Industrial Relations
Prevailing Wage
Ms. Lee has extensive experience providing quality
project compliance monitoring and reporting services
to various public agencies including cities, counties,
and housing authorities. Throughout Sandra's career,
she has demonstrated strong communication skills, a
strong work ethic, and unwavering trustworthiness.

Sandra's expertise lies in maintaining professional
relationships with public agencies that have remained
her clients for many years. She understands the
importance of effective communication and
consistently delivers accurate and timely reports to
ensure compliance with regulatory requirements.

Sandra is knowledgeable in federal Community
Development Block Grant (CDBG), HOME Investment
Partnerships Program (HOME) entitlement, HOME
American Rescue Plan Program (HOME-ARP),
Emergency Services Grant (ESG), Homekey, and
Permanent Local Housing Allocation (PLHA)
guidelines to ensure project and its contractors follow the reporting requirements. Her dedication to
excellence is evident in her meticulous approach to
monitoring projects and ensuring all necessary
documentation is complete. Sandra's commitment to
professionalism has earned her a reputation as a
reliable partner for public agencies seeking
comprehensive compliance services. With Sandra's
proven track record of success, she continues to be a
trusted resource for public agencies needing project
compliance monitoring and reporting services. She
works closely with public agencies to ensure each
project’s audit is cleared by HUD and Los Angeles
County Development Authority.

Estella Wells
Onsite Compliance Coordinator
Firm MNS
Years Exp 20
Ms. Wells is an exceptional leader with a wealth of
experience in housing and project management
spanning over 20 years. Throughout her career, she
has demonstrated a strong commitment to overseeing
City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 9
affordable housing units and ensuring their successful
implementation. One of Estella's key strengths lies in
her extensive knowledge of various programs related
to housing and economic development. She
possesses a deep understanding of HOME,
Neighborhood Stabilization Program, and Tax Credit
compliance monitoring. Additionally, she is wellversed in the intricacies of other federal, state, or local programs that are relevant to the field. With her
expertise in these areas, Estella consistently ensures
all projects under her supervision comply with the
necessary regulations and guidelines. Her meticulous
approach to monitoring affordable housing units
guarantees they meet the required standards for
affordability and accessibility. Estella's leadership
skills combined with her comprehensive
understanding of housing programs make her an
invaluable asset in any housing or project
management endeavor.

Chris Cooper, CPII
Optional Field/Shop Coating Inspector
Firm MNS
Years Exp 22
Certification NACE Level 1 Basic Coatings Inspector, No. 115694
Certified Public Infrastructure Inspector, APWA
ACI Concrete Field Testing Technician-Grade
1, No. 01057304
ICC Pre-Stressed Concrete Special Inspector,
No. 5312076-92
ICC Reinforced Concrete Special Inspector,
No. 5312076-49
ICC Soils Special Inspector, No. 5312076-EC
ICC Spray Applied Fire Proofing Special
Inspector, No. 5312076-86
ICC Structural Masonry Special Inspector, No.
5312076-84
ICC Structural Steel and Bolting, No. 5312076-
S1
Caltrans CTM 105, 125, 125AC, 125AGG,
125PCC, 201, 202, 216, 217, 226, 227, 231,
504, 518, 523, 533, 539, 540, 556, 577
Radiation Safety Officer, APNGA
Defensive Driving
ProCPR Adult CPR/AED and First Aid
Certificate, No. 159811010523201
Mr. Cooper has over 22 years of experience as a
construction inspector and materials technician
working on highway/roadway improvements and
potable and non-potable water infrastructure. Chris’
expertise includes concrete and hot mix asphalt
(HMA) placement inspection, masonry, bolting, prestressed concrete, soils and geotechnical testing, and framing and nailing inspection, soils and geotechnical
testing, and coating. He has provided field quality
control and quality assurance in both structure and
infrastructure projects.

Donny Spates
Optional Field/Shop Coating Inspector
Firm MNS
Years Exp 37
Certification Certified Public Infrastructure Inspector, APWA NACE Coating Inspector, Level 1
ACI Concrete Field Testing Technician, Grade I
ICC Reinforced Concrete Special Inspector
10-hour Construction Safety, Cal/OSHA
Confined Space Awareness
Defensive Driving
CPR and First Aid
Mr. Spates has over 37 years of experience in project
supervision and inspection in water and wastewater
facilities, reinforced concrete, structural steel,
roadways, and underground piping. Donny is skilled
at interpreting plans and specifications to mitigate
cost and schedule risks. He is an excellent project
team supervisor and strives to implement resourcesaving solutions. 3850 Vine Street, Sui | Address Line 2
555.555.5555 OFFICE
mnsengineers.com
2C. Years in Business
Established in 1962 as a C-Corporation, MNS has provided 63 years of quality infrastructure consulting services to the water resources, transportation, and government service markets throughout California.

Specializing in the core services of construction management, civil engineering, and land surveying, MNS' reputation has been built on clear and direct communication and quality services. 2D. Our Experience
As detailed above, MNS and members of the CM team have successfully delivered construction management services for many similar projects. A sample of MNS' recent, proven, and recognized experience is provided below:

Project Project Features Client Dates
Mountain View Well No. 5
Equipping
Active Plant Work and Phasing, Chemical
Treatment, Well Modification and Equipping,
Welded Steel Pipe, Genset, Site Demolition.

Golden State Water
Company
2022-
current
*Del Monte Treatment Plant
Improvements
Active Plant Work and Phasing, Owner
provided GAC Treatment System, Chemical
Treatment, Well Modification and Equipping,
Booster Station, Bolted Steel Backwash
Tank, Welded Steel Pipe, Genset, Site
Demolition.

Golden State Water
Company
2022-2024
*Kiowa Plant Well Equipping, Chemical Treatment, 0.54
MG Welded Steel Tank, Booster Station,
Genset
Golden State Water
Company
2020-2022
Mojave Plant 0.40 MG Welded Steel Tank, Welded Steel
Pipe, Booster Station, Genset
Golden State Water
Company
2023-
current
Bear Valley Plant Phase 3
(Booster Station)
Active Plant Work and Phasing, Booster
Station, Welded Steel Pipe, Genset,
Demolition
Golden State Water
Company
2022-
current
SP2684 Treatment Plant
Upgrades and SP2678
Groundwater Injection Well
SM-11i and Monitoring Wells
MWi-2 and MWi-3 Drilling and
Equipping
Active Plant Work and Phasing, Dual Well
Equipping, Pressure Filter Vesel Platforms
City of Santa Monica 2024-
current
Olympic Well Field
Restoration and Arcadia WTP
Expansion Project
Active Plant Work and Phasing, UV-AOP
and Granulated Activated Carbon
Treatment, Treatment Plant facilities
expansion & optimization
City of Santa Monica 2021-
current
Beltz 12 Aquifer Storage and
Recovery Project (ASR)
Active Plant Work and Phasing, Well Reequipping and Modifications, Steel Pipe City of Santa Cruz 2024-
current
City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 11
Valley Pumping Plant Booster
Station Rehabilitation
Green Sand Filtration, Reverse Osmosis
Treatment, Storage Tanks, Drilling of New
Well, Solids Settling System
City of Burbank 2021-2024
North Pleasant Valley
Groundwater Desalter Project
Green Sand Filtration, Reverse Osmosis
Treatment, Storage Tanks, Drilling of New
Well, Solids Settling System
City of Camarillo 2019-2022
*Completed by Aaron Singer, PE and Pat Hanify, PE prior to Contract Transfer to MNS.

3. References – Clients and Projects
PROJECT Del Monte Treatment Plant Improvements*
OWNER Golden State Water Company
CLIENT

CONTACT
Roman Silvestre, PE
626.485.9613
[email protected]
DATES 2022-2023
This project improved a treatment plant by installing a booster station, rehabilitating a well, installing an
arsenic treatment system, and constructing a steel
bolted backwash tank and chemical building with the
capacity of 3,200 gallons-per-minute (GPM). Concrete
mortar lined and coated (CML&C) piping and ductile
iron piping were installed. Additionally, the project
added a new Southern California Edison service
antenna that was integrated into the existing SCADA
system and modifications to site grading, paving, and
drainage were made to plant. This plant contained
two welded steel reservoirs and boosters. These
reservoirs and boosters were demolished upon
completion of the new booster station. Patrick was
responsible for leading bi-weekly project meetings
and preparing minutes, handling submittals and
Requests for Information (RFIs), processing monthly
payment recommendations, reviewing change orders
and submitting recommendations to the GSWC,
preparing and managing project records and closeout documents, reviewing schedules, and processing job control documents.
*Project performed by Pat Hanify & Aaron Singer while at Michael Baker International prior to transfer of GSWC Contract to MNS Engineers, Inc.

PROJECT Kiowa Plant Project*
OWNER Golden State Water Company
CLIENT

CONTACT
Ben Jimenez, PE
310.413.5518
[email protected]
DATES 2020-2022
This project involved the construction of a welded
steel tank, installation of a booster pump station
equipped with a backup generator, along with well
equipping with chemical treatment. Key components
included building a concrete ring wall foundation, out
fitting the tank with necessary appurtenances,
preparing building pads, and providing chlorination
and disinfection. The scope also covered testing and
site cleanup, installation of new yard piping, as well as electrical work for lighting and other site systems. Site enhancements were made by constructing an asphalt
concrete (AC) access road and concrete drainage
structures to effectively manage stormwater run-off.

City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 12
*Project performed by Pat Hanify & Aaron Singer while at Michael Baker International prior to transfer of GSWC Contract to MNS Engineers, Inc.

PROJECT Mojave Plant
OWNER Golden State Water Company
CLIENT

CONTACT
Octavio Verduzco, PE
626.261.3913
[email protected]
DATES 2023-current
This project involved
the construction of a

0.40 MG welded
steel tank, welded
steel pipe, booster
station, site
retention, and
Genset. Key components included building a concrete
ring wall foundation, outfitting the tank with necessary appurtenances, preparing the tank pad for the Boost,
and providing chlorination and disinfection. The scope
also covered testing and site cleanup, installation of
new yard piping, as well as electrical work for lighting and other site systems. Site enhancements were
made by constructing an AC ring road and
hardscaping and concrete drainage structures to
effectively manage stormwater run-off.

PROJECT Mountain View Well Equipping
OWNER Golden State Water Company
CLIENT

CONTACT
Roman Silvestre, PE
626.485.9613
[email protected]
DATES 2022-current
This project involved
the construction of a
well equipped, welded
steel pipe, installation
of chemical treatment,
site retention, and
pump to waste. Key
components included building a concrete ring wall
foundation, outfitting the tank with necessary
appurtenances, preparing building pads, and
providing chlorination and disinfection. The scope
also covered testing and site cleanup, installation of
new yard piping, and electrical work for lighting and
other site systems. Site enhancements were made by
constructing an AC access road and concrete
drainage structures to effectively manage stormwater
run-off.

PROJECT North Pleasant Valley Groundwater
Desalter Project
OWNER City of Camarillo
CLIENT

CONTACT
David Klotzle, PE
805.383.5642
[email protected]
DATES 2019-2022
The $66M facility
processes
approximately 4,500
acre-feet per year of
groundwater,
producing about
3,800 acre-feet of
drinking water per year. The resulting brine waste of
approximately 700 acre-feet per year will be
discharged to the Calleguas Regional Salinity
Management Pipeline (SMP), Phase 2C. The SMP
conveys brine waste to the Pacific Ocean. The North
Pleasant Valley Desalter project site is located within the 4.7-acre treatment plant and will treat brackish
groundwater for use as potable water. Construction
management responsibilities included construction
contract administration and constructability review;
progress payment review; monthly as-built and
baseline schedule review; coordination of permits;
process and facility treatment field inspections
conforming to drawings and specifications;
coordination with specialty inspectors; construction
safety oversight; traffic control implementation;
identification of potential utility conflicts; startup and City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 13
commissioning oversight; post construction activities;
and record drawing collection.

PROJECT Olympic Well Field Restoration and
Arcadia WTP Expansion Project
OWNER City of Santa Monica
CLIENT

CONTACT
Carlos Rosales
310.458.8271 x2620
[email protected]
DATES 2021-2024
The City of Santa
Monica is
undertaking a
progressive
design/build
project that will
involve an approximate $72M expansion and upgrade
of the Santa Monica Arcadia Water Treatment Plant
(AWTP) located in the City of Los Angeles. This
project includes the restoration of the Olympic Well
Field's pumping capacity by adding and/or improving
new treatment facilities (Olympic Advanced Water
Treatment Facility) within the AWTP, which will also
allow the additional use of a new raw water source
from the Olympic Well Field. This advanced treatment
will require additional treatment processes, including
UV-AOP and granulated activated carbon (GAC), to
remove several contaminants found in the well water.

This work will also require additional yard piping and
electrical upgrades within the boundaries of the
AWTP. Another major component of this project is the
upgrade and expansion of the AWTP to increase the
current reverse osmosis treatment system’s overall
recovery to 90% by using new flow reversal (FFRO)
technology. The overall goal is to increase raw water
treatment efficiency and capacity from reversal
gallons per day (MGD) to 13 MGD while maximizing
local water supplies and reducing reliance on
imported water supplies. Appurtenant electrical and
control systems additions and upgrades are also part
of these plant modifications. MNS is providing
construction inspection and teamed with Z&K to
provide these services.

4. Subconsultants
For this project, we have partnered with the following subconsultants to tailor a team that provides a local presence and value:

Z&K Consultants, Inc (Z&K) - Construction Observation
Founded in 2009, Z&K is a certified small business specializing in construction management, inspection, and project support services for public works and utility infrastructure projects across Southern California. Our team brings decades of experience supporting capital improvement programs involving water, wastewater, stormwater, and transportation systems.

Z&K offers proven expertise in well-equipped pump stations, reservoirs, treatment facilities, pipeline installation, SWPPP compliance, traffic signal systems, ADA upgrades, and roadway rehabilitation. Their staff includes certified professionals in water distribution and treatment, confined space safety, traffic control, and public works inspection.

They are known for their responsive field support, accurate documentation, and collaborative coordination with contractors, engineers, and agency staff. They aim to help agencies deliver safe, compliant, and high-quality infrastructure projects with confidence and efficiency.

City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 14
MNS is teaming with Z&K due to their specialized expertise, geographic proximity, and proven availability to meet project needs. While MNS can and does provide these services in-house, we recognize that teaming with Z&K allows us to field the right personnel in the right locations to ensure optimal service and coverage.

Furthermore, our past successful teaming efforts with Z&K have demonstrated strong collaboration and reliable performance. MNS’ primary goal is to assemble the best team possible for project success, and Z&K's capabilities and local presence make them a valuable partner in achieving that objective.

LandMark Consultants, Inc (LandMark) - Materials Testing (Geotechnical and Concrete) LandMark is a small geoscience engineering firm. They have established offices/laboratories in Palm Desert and El Centro, California and are a MBE owned (American Indian Cherokee Nation) firm as certified by State of California, Department of Transportation (CALTRANS). Their facilities are certified by State of California DSA and CALTRANS and accredited by the American Association of State Highway and Transportation Officials (AASHTO). LandMark has provided geotechnical consulting and materials testing and inspection services in the Inland Empire area of Southern California since 1987.

LandMark offers a broad range of consulting services on diverse projects in both the public and private sectors. The firm specializes in geotechnical engineering, engineering geology, soils and construction materials testing, and inspection services. Typical clients include water agencies, municipalities, industrial plants, power generation companies, commercial and subdivision developers, architects, engineers, the military, and construction companies.

MNS has teamed with LandMark due to their specialized geotechnical and materials testing services that are outside the scope of what MNS provides in-house. Their location within the Inland Empire and long-standing presence in the region ensures localized expertise and responsiveness. As a small firm, LandMark is nimble, efficient, and able to adapt quickly to project needs. This partnership allows MNS to deliver a more complete and geographically responsive service offering, aligning with our commitment to assembling the best team possible for project success.

City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 15

5. Proposed Method to Accomplish the Work
5A. Project Understanding
After review of the RFP, city agendas, City website resources, bidding records, submitted proposals and other details we could procure, MNS understands the Grand Well and Treatment Plant Project represents a key infrastructure initiative aimed at addressing the City’s long-term water system needs—particularly emergency flow capacity through maximizing the new well’s full 2500 GPM, and to provide system relief by balancing out the City’s water sourcing to limiting use of pumping of water from the eastern wells. Treatment design was engaged to provide iron and manganese removal and to address taste, color, and odor of the extracted well water. This project began with replacement of the existing Grand Well, built in
1992. This effort found its funding through the
American Rescue Plan Act of 2021 and the
Infrastructure Investment and Jobs Act of 2021 and
led to the completion of the Grand Well drilled in
2022 by Yellow Jack Drilling. However, the project
timelines were impacted due to the necessary
reallocations of funding to prioritize the Bath Well
Treatment Plant Design and Construction. The
Project continued along into design after Council
acceptance of Civiltec on December 5, 2023, and
additional funding sources were identified to
complete the Grand Well facilities. The design
contract schedule anticipated a target date of the
bidding release of July 24, 2024; however, the
construction RFP was not released until February
2, 2025 with subsequent City Council approval on
April 15, 2025, awarding these efforts to Pacific
Hydrotech, who is currently building the Bath Well
Treatment Plant Design and Construction. The
contractor Notice-to-Proceed (NTP) for construction
of the Project was Issued July 1, 2025. Total
construction duration, as understood by the
construction schedule provided within the RFP, has
commenced in July and is anticipated to run to
January 2027. The detailed construction duration in
total is anticipated to be 400 working days.

City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 16
Regarding project site specifics, the project includes construction of a new welded steel clarifier tank, well equipping, installation of owner procured Pureflow treatment system, new fabricated steel treatment enclosure building, fabricated hypochlorite system, new generator, site piping and electrical, and demolition and removal of prior equipment and structures. It is understood that the existing site’s treatment equipment and clarifier tank are currently offline and pose no operationally intensive impact for removal. The existing tank, booster station, and generator, however, are critical items that must be sequenced properly and performed within strict timelines.
5B. Project Keys
Quick Start As was communicated within the on-site pre-proposal meeting, the City is looking to expeditiously have the contract issued to have the construction management begin. Our team will work to coordinate with the City and contractor to strike off as many open items to bring the project back towards the contractor’s included schedule.

Additionally, it was communicated that the contractor was already issuing submittals which, at the time of onboarding, may be nearly 30 days in queue for review. We assume that most of these submittals are Pacific Hydrotech’s critical long lead procurement items. Given that the Design Engineer included engineering services during construction in Task 5 of their proposal (refer to Civiltec’s design proposal scope), we would highly recommend having the EOR begin the process of review while selections are made. Document control regarding these items can be handled at a later date, during onboarding of the CM consultant.

Contractor Sequencing
and Procurement
Our team will connect at the start of the project to coordinate with the contractor for an updated schedule and clear timelines for the long lead procurement items. These start with physically received purchase orders indicating the manufacturer’s production timelines. Once these are provided and the updated schedule is received, we will look to review discrepancies.

Per the demolition plan, the contractor is to provide a clear sequencing plan that minimizes downtime of the site operations. These efforts are not detailed on the schedule. Once submitted, we will coordinate with the Operations staff to determine the acceptability of such tasks before any activities on-site begin.

Electrical and Power
Equipment Lead Times
We have found that without a
purchase order and submitted and
reviewed shop drawings, the
timeline for the critical electrical
equipment is generally
underestimated by the contractor.

We are hopeful that the contractor
has achieved their due diligence;
however, the City should be ready
City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 17
for potential delivery of up to 18 months from the time the supplier is released to perform procurement and construction of the equipment (generally after review of submittal). The highest priority discussions at the time of the project start will be for these items: MCC, switchboard, MPZ-100, and generator. Should there be delays, we will look to work with the contractor on how they plan to mitigate the impacts of such delays and continue with the site improvements and work onsite to make all things ready for receipt of this equipment.

Coordination of 2MG
Tank and Existing
Booster Shutdown
Plans
It is not uncommon for these plans to become an afterthought to contractors when the priority is to keep crews busy and to keep work moving onsite.

Reviewing the contractor’s schedule, there are no line items for critical efforts such as the shutdown requirements for the site. Per the contract, the shutdown of the tank necessitates a two-week advance notice, and a limitation of four hours. In addition, the contractor appears to have these efforts aligned to occur during August of 2026. The plans specifically call for work to be limited to the winter months during low demand.

There is, however, a bit of conflict
between the notes on Page C7/Note 3
and that of the plan page C2/Demolition Phasing Note 3, as plant page C7 does not call for limiting the
work to four-hour windows. We will work
with the City operations team prior to
beginning these discussions with the
contractor prior to mobilization, as it is
highly likely they may desire to rearrange their schedule to accommodate these efforts sooner rather than later as intended.

Coordination with
Edison
The plans indicated that the process for site power turnover is to keep the existing service in place prior to tie over and start-up of the new electrical power. We will look to work with the City and the contractor to coordinate with Edison if this is an acceptable option, as we have found Edison does not typically like to provide an interim condition of two live services for a singular site requiring only one metered service. If such an option is not feasible, we will work with the contractor to coordinate alternative options for site power for interim conditions.

Pre-Fabricated
Products
There are a few prefabricated assemblies for the project in addition to the typical power equipment. These items additionally can have very long lead times from the design, production, and assembly process. Additionally, it is not uncommon for these assemblies to have the majority of all requested deviations on a project, which will generally lead to delays in the submittal process. Therefore, it will be critical for our team to understand where these items are in the process of submission, and to expedite them to the position of procurement.

City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 18
Owner Procured
Materials
In the pre-proposal meeting, it was detailed that the owner-procured materials would be ready for receipt come this October and November. This is great news, and generally, such expeditious delivery before construction is not common. We are hopeful that Pureflow’s timelines remain on track.

Given such early delivery, we will ensure the contractor is clear that they have received all necessary parts with the delivery at the time of arrival and take the necessary measures to protect and secure the materials onsite.

Additionally, we will look to coordinate another review a few months prior to installation to confirm no materials were displaced during the time awaiting installation.

Availability of Asphalt
Cutbacks
We have provided CM services for a few recent welded tank projects. Most of these projects required a different mixture of oil sand that did not include either an SC250 or SC70 cutback. One of the recent projects required these cutbacks for prime coating for the asphalt concrete paving; however, we were unable to have these cutbacks provided as refinery availability for production, given the product’s undesirable environmental characteristics, hindered provision. We will look to address this early in the project to clarify that these impacts are no longer of concern. If they are, we will coordinate with the City and the EOR for an alternative.

Pump-to-Waste
Capacity
At 2500 GPM, the capacity of
the sludge drying pit may be
limited to facilitate contractual
flushing/ pumping to waste of
the well. We estimate that the
current timeline to fill would be
around 35 minutes.

Subsequently, testing will also
be dependent on percolation rate. This may introduce another factor to consider. We will work with the City and contractor prior to getting to these efforts to determine the best route forward.

Wire Mesh Screen
Between Flange
Eventually, the
existing 2MG
tank will require
a recoat to
extend the life of
the tank in
excess of that
intended at the
isolated inlet
and outlet of this
project. We
have observed where blast media found its way into the tank overflow.

Subsequently, this material was trapped by the mesh, hindering overflow.

Luckily, at this particular tank, the mesh was banded to the exterior of the pipe and the mesh pulled away from the water pressure. However, in the City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 19
orientation of the tank here, this type of occurrence would lead to very poor outcomes. Although this occurrence was solely the product of the contractor’s errors, such an occurrence would fall upon the City to address when the risk would be easy to mitigate. As such, we would recommend reconsidering this outlet orientation, or at a minimum, accounting for this grate and its need for removal prior to any recoating.

Concrete Encasement
of PTW Pipe
We have performed a few plant work operations where we have encountered significant impacts to plant modifications incurred by large encasements poured beyond the limits necessary. We will work with the contractor to ensure the limits do not go beyond what is necessary for the project.

Epoxy Anchorage
Deviations
We have worked with a few
pump and well companies that
have attempted to deviate from
the anchorage requirements as
stipulated within the plans.

Often, epoxy is requested
because of the generally
reduced effort to install;
however, this is not advised as
from our experience, the epoxy
anchor ESR reports do not
provide clear provisions of the
acceptability of this anchorage
method under vibration loading. We will remind the contractor that contract requirements will be enforced regarding the type of anchors.

Coordination of
Recycling of Waste
Concrete and Asphalt
The contract documents (Plan Page C-3, Compaction Notes) include provisions for the recycling of removed concrete and asphalt concrete that are part of the project. It is unclear if the contractor is anticipating such requirements from the schedule; however, we will work with the City and the contractor with the desired location of this materials application and ensure the contractor is compliant.

Location of
Downspouts
The steel building details indicated that the downspouts are to be placed at the north; however, there are man doors located at both these locations, with site drainage detailed to flow from north to south. We would recommend relocation of these downspouts to the south to mitigate storm flowing across the path of access to the electrical room/interior of the treatment building.

City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 20
Bollards outside of RollUp DoorsDetail I14/A10 shows bollards desired to be placed outside the jambs of the roll-up
overhead doorways six inches from the wall
face. Detail A1/S6 would appear to show the
footings eight inches below the surface and
thus would be in the way of such an
installation. However, the layout plan (S1)
shows these outside the building pier
foundations. Details generally govern layout
plans, so it will be important to clearly detail that the layout with the bollards outside the footing below is the proper location.
5C. The MNS Approach
MNS provides proven professional
construction management techniques that
support the safe construction of a highquality project delivered on time and within budget. This is achieved by establishing
systems and procedures that promote
effective project controls. The MNS
Construction Manager (CM) will facilitate
communication among all parties regarding roles and responsibilities, including the City (project management and operations), the Design Engineer, Pacific Hydrotech, and the MNS Team.

Time Management
Time management uses scheduling to accurately manage and track the restrictive elements of time and resources throughout the project. A properly developed, implemented, and maintained schedule is a critical management tool. MNS will review the contractor’s baseline schedule to ensure it is accurate and reasonable. Activity durations and logic ties will be examined for accuracy and constructability. The earned value approach will be utilized to manage the progress of the contractor to achieve the project schedule milestones.

Our team has extensive experience in dealing with changes from unforeseen conditions, owner-initiated changes, and other types of delays. We will require the contractor to submit a time impact analysis for any issue with the potential to delay the overall progress of the work, and we will seek ways to mitigate the delay as the first course of action. The MNS team will strive to foster an ongoing positive working relationship between the team members to facilitate creative solutions to time management concerns.

Information Management – Procore
Proper information flow is crucial to the success of a project. A construction project generates a large amount of information which must be promptly disseminated to all parties. The source of this information will cover the full spectrum, including contracts, meeting minutes, drawings and Construction management tools utilized to meet
project objectives include Time Management,
Information Management, Cost Management,
QA/QC, and Contractor Management.

City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 21
specifications, submittals, requests for information (RFIs), pay requests, invoices, inspection reports, and so forth. MNS has successfully used Procore on prior projects, has team members familiar with its terminology and procedures, and will quickly implement the City’s procedures at the onset of the project.

MNS, as your CM, will act as the hub for the management of all information flow, including document control using Procore project management software. Documents include letters, memoranda, submittals, RFIs, meeting minutes, drawings, and any other data transmitted electronically or by mail. MNS has extensive experience providing web-based document management solutions.

Our approach to information management also
includes building a communication framework to
continually foster partnering and teamwork
relationships for all the project stakeholders; the
key component is holding regular project
progress meetings. MNS builds this framework
from the start of the project with an all-inclusive
kick-off meeting where the lines of
communication and project responsibilities will be
clearly explained to all project stakeholders.

Cost Management
MNS will take the lead to ensure a cost management system is properly implemented and maintained. MNS’ cost management role will be twofold: 1) MNS will track the value of the completed work to ensure accurate and detailed monthly progress billing by the contractor; and 2) MNS will proactively manage the change order process. The Procore cost management module will be utilized for budget management, potential change orders (PCOs), field orders, contract change orders (CCOs), and monthly invoice billings reviews.

Each month, our CM will review and approve the updated cost-loaded CPM and verify that work activities and material deliveries are assigned the correct completion percentage by the contractor. If necessary, the contractor will revise and resubmit the schedule of values. This process ensures the Owner is accurately billed for the completed work each month.

Quality Assurance and Quality Control
MNS is experienced in all aspects of quality management and understands our role in providing quality assurance to help the City receive a high-quality finished product. While the contractor is responsible for quality control, the MNS observation team will monitor work to verify conformance with project specifications and industry standards. Quality issues will be addressed as they occur in the field, with follow-up and resolution tracked through ongoing communication and during weekly progress meetings.

MNS will review the contractor’s quality control procedures for adequacy, and a deficiencies and corrective items list will be maintained and updated regularly based on the contractor’s progress.

Contractor Management
MNS has experience using a variety of webbased document management platforms. For example, we have successfully used Procore
to support document control on several multimillion dollar public works projects, including pipeline installations, new treatment plant
construction, and retrofit projects.

City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 22
MNS has executed numerous construction projects and has worked with a wide range of contractors to successfully deliver them. We are currently working with and have worked with Pacific Hydrotech on several projects and are familiar with their operations, management style, and field approach. In addition, we have worked directly with several of their key subcontractors, including Best Drilling and Crosno Construction, further strengthening our understanding of their broader project teams.

Even highly capable contractors can face challenges when their subcontractors or suppliers fall behind or struggle with documentation and coordination. These delays, especially with long-lead materials or complex scopes, can hinder progress and lead to administrative bottlenecks. Our team understands how to navigate these dynamics and maintain focus on delivering a quality project.

These outcomes begin with clearly defined scopes, plans, and specifications that reduce ambiguity during construction. We also recognize that the management style of a contractor’s on-site leadership, whether collaborative or confrontational, can significantly influence project outcomes. With this in mind, MNS uses a team-oriented approach to build trust and foster synergy, which often results in fewer claims and more successful projects.

The City utilizes Procore extensively to manage its projects. MNS, as well as the contractor, are expected to do the same to promote efficiency and transparency. MNS will monitor and enforce all Procore-related requirements to support consistent project documentation and communication. 5D. Project Scope
MNS has reviewed and understands the City’s construction management requirements for this important project.

Task 1. Coordination between the City, Project Stakeholders, and the Contractor MNS will provide comprehensive coordination services to ensure seamless execution of all construction activities among the Project Engineers, treatment equipment manufacturer, general contractor (Pacific Hydrotech), subcontractors, the City, and other relevant stakeholders. Coordination efforts will be focused on maintaining alignment across the project team, minimizing disruptions, and ensuring timely and efficient decision-making throughout the duration of the project.

MNS will serve as the central point of contact for all construction-related communications and will oversee the alignment of project work with contract documents, scheduled milestones, and field operations. To support this, MNS will actively manage interface points between trades and disciplines, facilitate daily collaboration between construction crews and technical support personnel, and monitor field activities to identify and resolve conflicts early.

Project coordination will include review and monitoring of sequencing and phasing plans, tracking critical dependencies between vendors and trades, and ensuring lead times for long-lead equipment are understood and incorporated into the construction schedule. This coordination will be informed by regular review of the Contractor’s schedule and three-week look-aheads, which will be discussed during the proposed weekly City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 23
construction meetings. MNS will also coordinate directly with the City and its operations staff to mitigate any impacts to plant operations or access during construction.

To ensure issues are promptly addressed, MNS will initiate coordination meetings as needed between the contractor, City representatives, and subject matter experts, including the treatment equipment manufacturer, to resolve field issues, clarify design intent, and support timely procurement and installation of materials. MNS will track all coordination-related action items, assignments, and deadlines through the Procore platform, ensuring full transparency for the City and project team members.

In conjunction with other related tasks (e.g., document control, materials testing, change management), MNS will integrate these coordination services to support a responsive, well-organized construction management process and maintain clear communication channels throughout the project duration.

Task 2. Document Control
Procore
We understand the City, along with Pacific Hydrotech, use the Procore project management software extensively to manage its capital projects and it is understood that this project will adopt the Procore application for our use during the project. MNS will utilize the Procore platform to coordinate, review, upload, and access all construction-related documents, including RFIs, RFQs, submittals, shop drawings, inspection reports, change orders, and photos.

MNS will document all relevant project communication and promptly distribute it to the City and applicable parties using Procore web-based project management software (furnished by the City or contractor).

Throughout the project, MNS will maintain accurate records of all project documentation using various modules of Procore. We will furnish all original project documents and final project reports to the City within 30 calendar days following the filing of the notice of completion for the project. These documents and reports can also be furnished in electronic format on flash drives at the conclusion of the project to the City, if desired. At the start of the project, MNS will develop a communications matrix to clearly define who needs to receive specific information and the timing for those communications.

Procore includes logs for tracking both submittals and RFIs. All submittals and RFIs will be tracked and discussed at the progress meetings with the contractor to ensure each issue is resolved quickly. MNS will monitor the logs and coordinate with the City as needed to ensure a timely response to RFIs and submittals.

RFI and Submittal Review
One of the most critical aspects of successfully managing a construction project requires the timely review and processing of submittals and responses to RFIs. MNS understands, per the RFP Q&A, that the City expects the CM to facilitate these responses. We also recognize that the EOR’s Grand Well Design proposal (dated October 25 and approved December 5, 2023) includes submittal and RFI support under Task 5 for Construction Support.

City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 24
To maximize value for the City, MNS will minimize EOR involvement where feasible. However, if the City prefers the engineer to continue providing this support through our team, we see value of streamlining such reviews along with the preservation of CM budget, should contract timelines persist beyond January of 2027.

Regardless, MNS will collaborate with the
contractor to prioritize critical submittals and
RFIs and seek early input from the City on
such priority submittals and long lead items.

Acting as the gatekeeper, we will ensure
responses align with contract intent. When
further input is needed, we’ll coordinate with
the City to limit EOR involvement. If EOR
input becomes necessary, we will consult the
City before proceeding.

MNS will also work with the City and Design Engineer to issue any major design changes or clarifications needed to resolve technical issues.

MNS Assumes:
• Review of up to 71 total submittals, including resubmittals, based on the contractor’s schedule. Our review will be limited to contract conformance only. We assume all technical reviews will be performed by the City or EOR and are therefore not included in our fee. A 10-working-day turnaround is assumed, excluding City or EOR review time if required.
• No more than 20 total RFIs shall be submitted by the contractor. MNS assumes no technical review to be necessary and that review will be solely in conformance with the contract requirements or EOR/City issued changes - thus no deviations, substitutions, or ”or-equals” will be reviewed. Time for review is assumed to be five working days and does not include City or EOR review time, should it be necessary.

Optional Service:
• During our conversations with Procore,
we were informed Pacific Hydrotech
currently holds an active Procore license
for this project. Based on that information,
we have assumed shared access will be
provided directly through the contractor,
which would mitigate the need for the City
to procure its own license. However,
should the City require separate licensing,
we have obtained project-specific pricing
from Procore. Please refer to the Fee Schedule for a breakdown of these services. The proposed rates include a one-time training session, which City staff are welcome to attend virtually.

Potential Savings: MNS sees potential savings
in either direction if the City desires the EOR to
provide their services from Task 5 of the design
contract, or should the City determine to not use
this previously allocated funding and in lieu have
the CM prioritize the review.

Potential Savings: Based on our discussions
with Procore, the MNS team was informed that
joint access to the platform can be provided
through the contractor’s existing license. This
presents a potential cost savings opportunity for
the City by avoiding overlapping licensing fees.

City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 25
‒ Alternatively, MNS can provide access to our own proprietary CMIS web-based service at no cost to the project.

Task 3. Materials Testing (Geotechnical and Concrete)
MNS will perform general observation on the job site for materials and workmanship as indicated with Task 6.

The additional responsibilities include disallowing any deviations from the contract documents unless proper approvals have been obtained from the City and/or EOR, verifying only conforming materials are incorporated into the work, and scheduling required materials testing.

MNS, with and through our materials testing subconsultant, LandMark, will be responsible for quality assurance material and soil sampling, field analysis, and laboratory testing as noted in the contract documents. MNS will coordinate these services with LandMark to ensure the materials incorporated into the project meet the specified requirements. We will upload and share all materials testing reports with the City on Procore.

MNS Assumes:
• Specialty inspections beyond Geotechnical Observation and Testing and Concrete Observation, Collection, and Testing are not to be provided as per the clarifications detailed within the Q&A. However, LandMark is fully fit to provide such inspections if desired by the City. • Services included within our scope and fee include:
‒ Rough grading observation and testing
‒ Compaction testing of trenches, C&G, subgrade and basegrade, driveway approaches and sidewalk ‒ Concrete inspection, including onsite inspection of the reinforcement, and collection and testing of concrete cylinders
‒ 3 maximum density/optimum moisture tests will be performed. ‒ 25 concrete cylinders are assumed to be collected and tested. ‒ 20 half-time and 10 full-time site visits by a Soil Technician, and 10 full-time ICC concrete inspections ‒ Visits to site are subject to a two-hour surcharge for the respective staff assigned ‒ A two-hour minimum will be charged for all field work and thereafter in four-hour increments ‒ No night work is assumed. Requests for night work will be subject to the availability of personnel, will require no less than five working days’ notice, and will be charged at premium time of no less than

1.5x the standard rate and that required by law.

Value-Added Optional Service:

MNS has included an optional service for coating inspection for the tanks, covering both field and shop operations, which we recommend the City consider incorporating into the project. Coating inspection is a common practice for tank installations, as it helps ensure long-term performance, protects structural integrity, and verifies compliance with specifications during both fabrication and on-site application. This level of oversight is particularly valuable for welded steel tanks, where shop-applied coatings must meet strict quality City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 26
standards before delivery to the field. We have experience working with Crosno Construction, the tank subcontractor identified in the proposal, and understand the importance of verifying coating quality at both their facility and during field operations. Please refer to the attached Fee Schedule for detailed costs related to this optional service.

Task 4. Meetings
MNS will schedule regular and ad hoc project meetings. MNS will develop the agenda and meeting minutes to have a written record of any agreements and action items. A list of anticipated routine meetings expected during this project includes the following:
• Internal Kick-Off: Immediately after receiving a CM contract NTP, MNS will hold an internal kick-off meeting with all key stakeholders to go over project goals and key intermediate milestones to meet the project cost, quality, and schedule objectives.
‒ MNS assumes a single one-hour virtual recorded meeting attended by the Construction Manager and Observer.
• Pre-Construction: This is one of the most comprehensive meetings and is held with all key project stakeholders and the contractor immediately after the award of the construction contract. It covers scope, plant operations disruptions, submittal procedures, bonds and insurance, certified payroll verification, safety, invoicing, and associated forms and/or software to be utilized throughout the project. MNS will develop the agenda with City concurrence and will lead the conference as well as develop the meeting minutes for the team.
‒ MNS assumes a single hour and a half virtual recorded meeting attended by the Construction Manager, Technical Support and Labor Compliance.
• Weekly Construction Meetings: This important weekly meeting includes MNS, the City, Design Engineer, contractor, and its main subconsultants/subcontractors and will address the day-to-day issues on- and off-site, including procurement issues. MNS develops the agenda, leads the meeting, and distributes the minutes. At this meeting, the schedule, permitting, scope changes, submittals, safety, onsite coordination, and logistic issues will be addressed. The contractor will also review the three-week look-ahead schedule with the team.
‒ MNS assumes up to 75 one-hour virtual progress meetings. These meetings will be recorded and attended by the Construction Manager. Technical support staff are assumed to participate in no more than 16 of these meetings. Additionally, MNS assumes up to four one-hour onsite meetings, to be held during the Observer’s scheduled half-time shift. The Observer will attend meetings the first week of Mobilization.
‒ MNS assumes four such one-hour meetings on-site by the Construction Manager and Observer. The time of meeting will be during the Observer’s half-time shift on-site.

Task 5. Contractor’s Construction Schedule Review
MNS anticipates the general schedule included in this proposal, adapted from the contractor’s schedule provided within the RFP, will serve as the framework for core project milestones and guide our construction management services. As part of our role in supporting the City’s requirement to maintain the master City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 27
construction schedule, MNS will monitor, review, and evaluate the contractor’s baseline schedule and subsequent updates to help keep the project aligned with overall goals.

The Monthly Progress Report, prepared by MNS, will include the current schedule status, identifying any activities on the critical path and noting risks to milestone completion. Should delays arise, we will request detailed recovery plans from the contractor and assist the City in evaluating the adequacy of proposed adjustments. MNS will also assess productivity trends and sequencing to help identify any early warning signs of schedule slippage.

We understand that contractors typically utilize scheduling platforms such as Microsoft Project or Primavera P6, and our team is experienced in interpreting and analyzing these tools. While the contractor is responsible for maintaining their construction schedule, MNS will provide timely reviews and recommendations to the City in support of keeping the overall master schedule on track.

As noted in the “Project Keys” section of the Approach, we have already completed a cursory review of the contractor’s schedule included with the RFP and identified several items requiring immediate attention. Prior to mobilization, we will work with both the City and the contractor to resolve these inconsistencies and develop a coordinated approach that sets the project on solid footing from the outset.

Task 6. Construction Observation
MNS’ CM and our observation subconsultant, Z&K, will enforce all contractual requirements of the scope performed by the contractor. Z&K’s seasoned construction observers will proactively monitor the quality and conformance of the work during construction to minimize any non-compliant activities whenever feasible.

Recognizing that construction can involve unforeseen tasks or short-notice schedule changes, MNS and Z&K have proactively arranged for additional local observers to ensure adequate coverage and meet the project’s observation needs.

MNS understands the value of photo documentation and will utilize it for the City’s benefit in any disputes and claims against the contractor. Our inspectors will document the construction progress daily. These project progress photos will be uploaded to Procore for easy project stakeholder access.

MNS Assumes:

To provide the City with efficient and cost-effective field support, half-time (maximum of four hours per day including portal-to-portal) construction observation will be provided from mobilization (November 7, 2025) through project closeout (January 21, 2027) – a total of 300 working days. This flexible, part-time observation model is structured to meet project needs while maintaining budget discipline. Any site visits that conclude without requiring further inspection or are canceled same-day will be billed at a minimum of four hours.

This approach represents another value-add for the City, as it allows for targeted observation during critical construction activities without the cost of full-time, on-site staffing. To support this model, MNS has teamed with Z&K—a trusted partner with the right staff geographically located to provide responsive and reliable observation services. Z&K’s proximity and availability help us ensure timely support while maximizing City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 28
efficiency and minimizing unnecessary travel costs. Their familiarity with local practices and our successful history of collaboration further strengthens our ability to deliver a high-quality project outcome. All costs associated with cancellations with less than one working day’s notice provided by the contractor will be paid for by the contractor but billed through the consultant contract to the City.

Value Added Optional Service:
• MNS has included an optional service available to the City of Shop and Coating Observation. Please refer to the attached Fee and associated resumes.
• As part of our proposed approach for the Grand Treatment Plant and Equipping of Grand Well Project , MNS is offering part-time construction observation, which we believe is the most appropriate and costeffective solution given the scope, duration, and nature of the work. While full-time inspection services are available if requested by the City, our experience suggests that part-time observation is the preferred and most efficient course for this type of project. We are currently working with Pacific Hydrotech on another project where part-time inspection is being successfully implemented. This model provides the flexibility to monitor key construction activities while managing costs and resources effectively. Should the project conditions change or the City prefer full-time observation, our team is fully capable of adjusting staffing to meet that need.

Task 7. Site Maintenance and Best Management Practices
As part of its CM responsibilities, MNS will monitor the implementation of required Best Management Practices (BMPs) to ensure compliance with the project's environmental obligations, including California Environmental Quality Act (CEQA) requirements and the approved Stormwater Pollution Prevention Plan (SWPPP). MNS will compile the documented observations, maintain compliance records, and communicate any corrective actions required to the contractor and the City to ensure continued environmental compliance throughout the project duration.

MNS Assumes:
• SWPPP creation, monitoring, and uploading will be provided by others. • MNS assumes the contractor is solely responsible for compliance with the SWPPP, including the installation, maintenance, inspection, and reporting of all BMPs. • MNS will not be responsible for preparing, certifying, updating, or amending the SWPPP or any CEQArelated documentation or permits. • MNS assumes the SWPPP and all CEQA mitigation measures have been fully approved by the City and applicable regulatory agencies prior to the start of construction. • MNS will not be liable for any enforcement actions, penalties, or violations related to SWPPP compliance, CEQA mitigation measures, or environmental permit conditions. • MNS will not perform sampling, laboratory analysis, or water quality testing. Any such services, if required, must be contracted separately.

City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 29
• MNS assumes no archaeological, cultural resource, or biological monitoring responsibilities unless explicitly directed by the City through a separate agreement.

Task 8. Reports
MNS will provide all key project stakeholders with weekly working day statements (WDS) detailing general project progress, milestones accomplished since the last report, challenges, and interface coordination points needing assistance. Risks are monitored and discussed for what the project team must do to minimize negative risk impacts. The City and MNS can discuss the format and deliverables during the internal kick-off meeting.

At the onset of construction, Each MNS Inspector is required to submit an inspector’s daily report to document the work being performed, labor and equipment, materials, item quantities, and significant conversations or events. The MNS CM will review these reports to ensure accuracy and will have the subject daily reports uploaded to Procore within three business days for project stakeholder access.

MNS Assumes:
• 77 WDS will be provided as per the times set forth by the contract. • Daily reports will be provided by the Construction Observers for efforts performed onsite and will be provided in digital format only.
• Procore will serve as the onsite repository for all construction documentation for project stakeholder access.

Task 9. Project Cost Control and Certified Payroll
Cash flow is the lifeline of the contractor. For the contractor to execute the job effectively, they must be paid on a timely basis, yet too many contractors do not submit their monthly invoices on time. Beginning with a proper schedule of values (not allowing the contractor to front-load it), MNS will work closely with the contractor to ensure timely monthly progress payments.

Aaron will work with our construction observers to evaluate the actual work completed during the previous billing period before recommending payment approval to the City. Extra work and supplemental work costs will be tracked and compared against the authorized change order amounts.

MNS will monitor and update the status of the project costs and budget throughout the project. MNS will track and monitor the actual construction costs of a project including contract item payments and quantities, contract change orders, and extra work. The project contingency balance will be verified as part of the monthly progress pay estimate review.

MNS will additionally provide certified payroll in accordance with the RFP requirements. The following defines the task that will be performed to meet such requirements:

9.1 Pre-Construction Services
City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 30
Pre-Construction Meeting. MNS will attend/participate in a pre-construction meeting to present local State Labor Compliance requirements to contractors of all tiers. MNS will also obtain signatures from contractors to confirm they have been informed of the project’s compliance requirements and forms. This may be in the form of a sign-in sheet or a confirmation form that MNS will create and utilize with the City’s approval.

Prior to the meeting and with the City’s approval, MNS will create a Labor Compliance Reporting packet that contains all applicable Federal and State Labor Compliance documents. This package will provide a detailed explanation of each form and instructions on how to complete it and when to submit. Also, MNS will acquire the City’s approval to include language in the Compliance Reporting Packet that no lower tier subcontractors shall be allowed to work without timely notification to the City and verification of contractor eligibility. The categories of documents to be included in the Welcome Package include:

I. First-Time One-Time Documents
II. During Construction Documents – weekly, monthly and if applicable, quarterly III. Close-Out Labor Compliance Documents

9.2 Construction Phase Services
Certified Payroll Reporting. MNS will request, obtain and review weekly payrolls from each contractor on the project; this will include all lower tier subcontractors. MNS will ensure payrolls have been properly completed and reflect correct information such as trade/classification and group/period number, appropriate wage rates, fringe benefits, and deductions.

MNS will ensure all contractors are employing and working apprentices in ratios that conform to the apprenticeship regulations. From each apprentice reported on payroll, documentation will be obtained to prove apprentices and trainees are registered with an approved apprenticeship program.

Site Visits. MNS will conduct verifications of contractors working onsite. We will keep a log of verifications to confirm all contractors are submitting labor compliance documents and payrolls. MNS will also conduct onsite craftworker interviews to ensure craftworkers believe they are being paid the appropriate wage rate and fringe benefits for their trade/classification. MNS will conduct follow-up interviews with the same craftworkers to confirm the wages/fringes being paid are no less than the applicable wage determination. MNS will ensure at least 10% of each contractor’s work crew for each trade is interviewed.

Status Report. MNS will provide a monthly Labor Compliance Status Report that will outline each contractor’s compliance status with the project. The report will contain detailed descriptions of contractors’ delinquencies, discrepancies (suspected violation), clearance of issues and recommendation for payment withhold for outstanding discrepancy/delinquencies. Withholding of payment will be recommended when a contractor fails to respond and submit documents in a timely manner.

MNS will provide reports to the City’s Project Manager and prime contractor. MNS will follow up with the prime contractor to discuss remedy of Labor Compliance issues and coordinate deadline to remedy issues.

MNS will provide a final Labor Compliance Report to the City’s Project Manager and prime contractor to confirm when all contractors have properly closed out their compliance requirements for the project.

City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 31
Project Files. All written documentation provided by MNS for the purpose of Labor Compliance reporting to the City will be concise and organized in a manner that will be easily understood. All files related to the assigned project will be organized and ready to submit at the request from the City. The Labor Compliance files for projects will generally be organized as follows:
• First-time One-Time documents
‒ Worker’s Compensation Certification
‒ Certificate of Authorization and Understanding (authorized signer of payrolls and compliance documents)
‒ DAS 140 and 142 (for each trade that will be utilized for the project) with proof of transmittal ‒ Fringe Benefit Statement
• During Construction documents – weekly, monthly and quarterly (if applicable) ‒ Weekly Certified Payrolls with Statement of Compliance or Statement of Non-Performance with DIR eCPR confirmation
‒ Apprenticeship Certificate (State certificate for each new apprentice reported on payroll) ‒ Authorization for Payroll Deduction (for each new deduction reported on payroll for each craftworker) ‒ Revised payrolls with proof of restitution payment and Confirmation of Receiving Restitution signed by affected craftworker
‒ Monthly Apprenticeship Training Funds Report with proof of payment ‒ Monthly Labor Compliance Reports (sorted in date descending order) ‒ Craftworker Interview forms
‒ Conditional and Unconditional Lien Releases
• Close-Out Labor Compliance documents
‒ Final Certified Payroll with Statement of Compliance or Statement of Non-Performance with DIR eCPR confirmation
‒ Apprenticeship Declaration (signed by contractor to certify that all apprentice hours reported on payrolls are true and conformed to the apprenticeship regulations) ‒ Final Labor Compliance Certificate (signed by the contractor to certify that all compliance documents and payrolls submitted to the City are true and correct) LCP Tracker and Other File Upload Website. If LCP Tracker is provided by the City or the prime contractor, MNS will utilize the online submittal portal as MNS is very experienced in navigating the website. MNS is also experienced in using Elations and QuickBase. We will download all documents from the website to review and file into the project compliance files.

Electronic Submittal Process. For this project, MNS will share the company’s Box file sharing website and upload links. The Box website is secure and free of charge for contractors and the City to utilize. MNS will download each document from Box to review files into the Project Compliance files.

9.3 Post-Construction Services
City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 32
Once the construction has been completed, MNS’ compliance staff will work with contractors to properly close out their Labor Compliance requirements for the project. If any issues arise during the time of compliance close-out, MNS will notify the City Project Manager and prime contractor. MNS will work with contractors to remedy issues and assist contractors to submit their final compliance documents in a timely manner.

Once the Labor Compliance files are complete, MNS will submit a request form for file review and schedule the meeting. At the file review meeting, MNS will present the Labor Compliance files and walk the auditor though the entire project and answer any questions. If the auditor requests any additional documentation, MNS will gather the information and submit it to the auditor for final file review approval. Once final approval is received, MNS will deliver the entire Labor Compliance files to the City by City’s desired method of delivery.

MNS will provide Labor Compliance monitoring in a manner that minimizes the demands placed on City staff.

In addition to Labor Compliance monitoring, MNS staff will make certain that all required agency reports are submitted to the appropriate agencies prior to their due dates to ensure compliance and timeliness.

MNS Assumes:
• 18 complete progress payment packages (progress payment estimate, all unconditional and conditional waivers) submissions and subsequent reviews with no resubmissions from the contractor. • The City has conducted and filed the contractor verifications at the time of project award (pre-construction phase). If the City wishes for MNS to conduct and file the contractor verification files, MNS can perform this service for additional fee.
• If the City receives a Request for Public Information, it is assumed the City will prepare the response. If the City wishes for MNS to prepare the response, MNS can perform this service for additional fee. • MNS will provide pre-construction meeting Labor Compliance notes or recordings, compliance reporting and onsite posting package to contractors, and applicable prevailing wage determination and booklet in electronic format to contractors.
• All labor compliance documentation will be uploaded by the contractor (or City) to its file repository system, Box.
• MNS will provide all compiled contractor files – originals with wet signature and in electronic format by online shared drive Box, craftworker interview forms, and Labor Compliance status reports. • MNS will provide one final Labor Compliance Status Report, and complete project files for closeout after the cessation of all work onsite. It is assumed the contractor will provide all documentation organized as necessary.
• The project is funded with local funds, such as CIP and direct bank loans. Project is subject to State Department of Industrial Relations (DIR) prevailing wage and State Labor Compliance. Project is not subject to Federal Funding Requirements.
• If LCP Tracker is provided, MNS will utilize the software program to maintain project compliance files.

Task 10. Change Order and Claims Review
City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 33
As one of the highest priority CM tasks, potential claims and change orders will be reviewed and addressed by our CM. The MNS team will review the proposed change order entitlement and amount justified, if any, and make a specific recommendation to the City.

All CCOs must have a defined project scope of work and limits and comply with the project documents. Upon reaching an agreement of the change, a detailed scope, and independent cost analysis and time impact analysis will be prepared. This will form the basis for evaluating the contractor’s submitted costs and time impact analysis for the changed work and negotiating a change order with the contractor. Once finalized, MNS will compile the negotiated details on the City’s change order form, issue for signature, and will return to the City for execution and processing.

A discussion of changes and potential changes will be a key agenda item for the weekly coordination meetings with the contractor to ensure the proper monitoring for changed work and effective mitigation of impacts to the project. Any potential claims associated with changes to the work will be addressed before becoming actual claims. MNS will bring its lessons learned knowledge of resolving disputes and claims at the lowest level in the chain of command for the project.

MNS Assumes:
• Coordination and review of four complete contractor potential change orders with no requested revisions. • Coordination, review, and issuance upon City authorization of two CCOs with no requested revisions. • No project claims will be submitted by the contractor.

Task 11. Start-Up Coordination, Observation, and System Documents The contractor’s team of subcontractors, as well as equipment vendors, will provide startup assistance and training for the City operations staff. MNS’ Construction Observer will provide onsite observation of the testing, pre-final, and final stages of startup alongside the contractor’s representatives and City Operations team. As part of the project handover phase tasks, the contractor will provide the O&M Manuals to the City. MNS will review these O&M Manuals for the entire project to ensure they meet the contractual obligations. In addition, MNS will ensure the contractor has provided actual spare parts called for in the contract or a list suggesting the need for critical spare parts and normal spare parts and tracked in an agreed master list.

Task 12. Notice of Completion
Following confirmation from the City that all construction work has been satisfactorily completed and accepted, MNS will initiate the Notice of Completion (NOC) process. This begins with MNS preparing a draft NOC that includes all required project details such as the project title, contract number, location, contractor’s name, completion date, and a concise description of the work performed.

MNS will then submit the draft to City staff for review and approval. Once approved, MNS will coordinate with the appropriate City representative—typically the City Engineer or Director of Public Works—to obtain an authorized signature and notarization.

City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 34
After notarization, MNS will proceed to record the NOC with the Riverside County Recorder’s Office electronically. Upon successful recording, MNS will obtain a certified copy of the recorded document and provide it to the City for its records. MNS will also document the official recording date, which initiates the statutory lien period, and notify the contractor and other relevant parties that the NOC has been filed. This process is included as part of the overall project closeout responsibilities managed by MNS.

MNS Assumes:
• The City will provide the authorized signature and notarization. • The City is an eRecording Vendor with the County of Riverside.

Task 13. Closeout
MNS understands the value of meticulous records and project information that ultimately will be handed over to the City for long-term use. MNS will ensure the contractor adequately addresses all closeout requirements such as equipment warranties, spare parts lists, record-set of drawings, and training are adequately addressed. MNS will determine when substantial completion is achieved (generally after beneficial use of water is achieved) and coordinate with the City to issue the notice of substantial completion if so desired.

MNS will develop a punch list for the work performed, distribute to the City’s operations team for concurrence, and subsequently notify the contractor, and re-inspect the completed work. A final walk-through of the project will be scheduled with the City, the contractor, and any other party the City may wish to attend (we anticipate Pureflow and the EOR). MNS will evaluate the contractor’s completion of work and make a final acceptance recommendation to the City.

MNS will prepare a final report detailing the work completed, costs, changes, warranties, and documentation provided to the City. The report will also include a section on future suggestions and lessons learned and an evaluation on overall performance. MNS will additionally provide a contractor evaluation on the City’s form, if so desired.

As per the construction contract terms, the contractor is required to maintain the latest set of plans and specifications on-site. MNS will ensure the contractor is recording any field modifications on the redline drawings during onsite observations; full-time construction observers will track and record as-built conditions.

At the conclusion of construction, the contractor will furnish to the City with the complete set of plans and specifications updated to reflect actual construction via Procore.

MNS Assumes:
• One project close-out report will be provided to the City in electronic format via Procore.

City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 35
5E. Proposal Draft Schedule
From the schedule as provided by the contractor and included within the RFP, the below is an anticipated abbreviated draft schedule. From thorough review, our understanding is that this schedule will need to be revised and updated by the contractor to reflect secured procurement timelines, shutdown requirements, demolition sequencing, availability of temporary power, and testing/training requirements. Additionally, many of the contractor’s critical submittal dates are before or shortly thereafter the onboarding of the CM consultant, so impacts to the Critical Path should likely be anticipated by the City.

ABBREVIATED CONSTRUCTION TIMELINE
Preconstruction Phase 7/1/25 11/6/25
Contractor NTP 7/1/25 7/1/25
Construction Management Contract NTP 8/5/25 8/5/25
Kick-off Meeting (With City) 8/11/25 8/11/25
Pre-Con 8/19/25 8/19/25
Coordination of Permits 8/6/25 11/6/27
Coordination of City Supplied Materials 9/3/25 9/3/25
Coordinate and Review of Contractors
i
8/6/25 10/9/25
Construction Phase 11/7/25 12/3/26
Observe Delivery of Owner Supplied Materials 11/7/25 11/30/25 Observe Contractor Mobilization/Potholing 11/7/25 11/21/25 Observation of Clarifier Tank 11/14/25 8/17/26
Observation of Filtration Building 11/14/25 12/2/26
Observation of Well 5/16/26 7/28/26
Observation of Yard Piping 7/15/26 10/5/26
Observation of Demo and Installation of 11/14/25 9/25/26 Observation of Hypochlorite System Install 11/21/25 9/16/26 Energize Site (SCE) 11/2/26 12/2/26
Testing and Start-up & Final Demo 12/3/27 1/18/27
Start-up & Test Well, Clarifier Tank, Filtration 12/3/27 1/8/27 Start-up & Test Generator, ATS, MPZ100 1/11/27 1/11/27
Final Demolition (Existing Electrical) 1/11/27 1/18/27
Project Closeout 1/19/27 1/21/27
City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 36
Certification of Proposal
I, Joe Pope, PE, QSD/QSP hereby submit this proposal and, by doing so, agree to furnish services to the City in accordance with the Request for Proposal (RFP), and to be bound by the terms and conditions of the RFP.

Fee Proposal
MNS has prepared a Fee schedule that has been attached according to the requirements of the RFP. Please see the separate file submitted.

City of San Jacinto
Construction Management Services for
Construction of Grand Treatment Plant and Equipping of Grand Well PAGE 37
Appendix A. Staff Resumes
Name Firm Role Page
Joseph Pope, PE, QSD/QSP MNS Principal-in-Charge 38
Patrick Hanify, PE, CCM,

QSD/QSP
MNS QA Oversight and Technical Support 40
Aaron Singer, PE MNS Project Manager 42
Sandra Lee MNS Labor Compliance 44
Estella Wells MNS Labor Compliance 46
Chris Cooper, CPII MNS (Optional) Coating Inspection 48 Donny Spates, CPII MNS (Optional) Coating Inspection 50 Carlos Gaytan, D3 Z&K Construction Observer 52
Ed Nylund, QSP, CWSSWI Z&K Construction Observer 54
Joseph Pope | RESUME PG 1
RESUME
Joseph Pope, PE, QSD/QSP
Principal-in-Charge
Firm
 MNS Engineers, Inc.

Areas of Expertise
 Organizational leadership
 Water/wastewater resources
 Client relations
 Process improvement
 Contract management
 Team building
Years of Experience
 27
Licensing
 Professional Civil Engineer, CA No. 63553
Certifications
 Qualified SWPPP Developer/Practitioner, CA No.63553
 CalOES Safety Assessment Program
 Lean Six Sigma Green Belt Certification
Education
 MS, Civil and Environmental Engineering, University of California, Los Angeles, CA
 BS, Environmental Resources Engineering, Humboldt
State University, CA
Affiliations
 American Public Works Association
 American Water Works Association
 Association of California Water Agencies
 Society of American Military Engineers
Mr. Pope is a collaborative civil engineer with over 27 years of progressive, executive management experience
leading large municipal and federal Public Works
organizations. Joe is a recognized visionary leader in
managing large interdisciplinary engineering, operations, and planning teams in the efficient delivery of sustainable facilities, construction, environmental, water, wastewater, and electrical utilities. He is an exceptional problem
solver with excellent communication skills and an ethical and inspirational leader. His experience includes:

Newell Creek Pipeline Felton/Graham Hill Project,
City of Santa Cruz, CA. Principal Construction Manager.

This $21M project includes installation of approximately 23,400 linear feet of 24-inch ductile iron pipe, a 100-foot crossing over a river, 90-foot trenchless railroad crossing, existing pipeline and facility abandonment, cathodic
protection system, and pavement improvements in
environmentally sensitive habitats and high traffic areas.

Wastewater Program, City of Gonzales, CA. Principal
Project Manager. The City of Gonzales has initiated an
aggressive wastewater program to address compliance
with regulatory requirements. The program undertakes
several components of the wastewater system including
construction of over two miles of 24/27-inch PVC
conveyance piping, a new one MGD industrial
wastewater treatment facility, rehabilitation of the existing municipal wastewater treatment plant, and future
expansion of both treatment plants.

Biosolids and Energy Phase 1 (BESP1), Goleta
Sanitary District, Santa Barbara, CA. Principal
Construction Manager. The Goleta Sanitary District
(GSD) has undertaken the $9.9M BESP1 project, which
includes construction of a new, pre-stressed concrete
digester, installation of a cogeneration system with an integrated digester gas cleaning system, improvements
to the digester heating system, as well as construction of associated demolition, yard piping, and electrical and
instrumentation. The project site is within Coastal
Commission jurisdiction, requiring compliance with a
Coastal Development permit, and is also within the direct vicinity of the Santa Barbara airport, requiring Federal Aviation Administration permitting and coordination. In addition, the WWTP is within a Native American
archeological area of interest, requiring close
coordination with paleontological and archeological
monitors during excavation.

Joseph Pope | RESUME PG 2
RESUME
Somis Ranch Farmworker Housing Project, Somis,
CA. Department Director. Joe led the water and
sanitation team led in the planning, design, permitting, and construction of all potable water infrastructure for new four-lot subdivision farmworker housing community.

Construction included construction of an existing water tower. The 26-acre site included phase 1 construction of 200 individual units and all service connections. Project included installation 8-inch PVC, 10-inch PVC and 3,000 feet of 12-inch PVC water lines within and adjacent to the Caltrans right-of-way. The scope also included new
electrical duct bank, sewer lines and communications
lines and abandonment of existing 4-inch and 8-inch
lines, and construction of a new 300,000-gallon welded
steel, coated water tank.

Well No. 2 Iron and Manganese Facility, County of
Ventura, CA. Department Director. Joe led the water and sanitation team in the planning, permitting, design, and construction of a $3M iron and manganese wellhead
treatment facility for Ventura County Waterworks District No. 19, Somis, CA. The Well No. 2 iron and manganese
removal facilities project included the installation of three horizontal greensand filters, a reclaim tank and chemical treatment facilities.

Ventura County Public Works Agency, CA. Director of
Water and Sanitation. Joe was the Department Director
for 80 employees, overseeing a $90M annual budget and
was responsible for managing water, wastewater,
recycled water, and solid waste services for special
districts and unincorporated areas of Ventura County.

Ventura County Naval Base, Point Mugu, CA. Public
Works Director. Joe served a Navy Base population of
19,000 and led a 300-person Public Works Department
with a $250M annual budget. He was responsible for the
maintenance and operation of 1,600 facilities, civil works, utility infrastructure, roads, services and construction contracting, environmental and code compliance,
facilities, fleet management, and urban planning.

Navy Expeditionary Combat Command Pacific, HI.

Director of Operations – Asia Pacific Region. Joe
collaborated with a diverse team of stakeholders in the annual execution of over $20M in Navy Expeditionary
Operations in support of the Pacific Command Theater
Security Cooperation Program.

NAVFAC Hawaii, Pearl Harbor, HI. Director of Design,
Construction, and Service Contracting. Joe led 150
engineers, architects, contracting officers, and
engineering technicians in the execution of over 370
construction contracts and 96 facilities service contracts worth over $1B. Joe also supported a Joint Base
population of 52,000 personnel.

Naval Mobile Construction Battalion 133, Gulfport,
MS. Executive Officer. Joe was second-in-command of a
600-person Naval Mobile Construction Battalion. He
supervised 70 employees and a $20M budget. Joe
deployed overseas to provide contingency construction,
humanitarian assistance, disaster recovery, and
peacetime construction.

Chief of Naval Operations, Washington, DC. Senior
Strategic Facilities Analyst. Joe served as the Shore
Readiness Planning Programming Budget Execution and
Models/Metrics Analyst, coordinating the programming of the Navy’s $9B annual infrastructure program. He
developed Navy policies to guide future infrastructure
development.

United States Senate, Washington, DC. Legislative
Fellow. Joe served Senator Barbara Mikulski in support
of Defense and Veterans Affairs Policies.

Naval Facilities Engineering Command
Headquarters, Washington, DC. Executive Assistant.

Joe served as the Executive Assistant to the Deputy
Chief of Civil Engineers and provided planning, design, construction and maintenance, acquisition and real
estate services, and environmental and contingency
engineering for the Navy ashore.

Naval Mobile Construction Battalion Forty, Port
Hueneme, CA. Company Commander/Assistant
Operations Officer/Officer-in-Charge. Joe was
responsible for planning projects, training, and
operational reporting requirements for a 600-person
Construction Battalion.

Naval Air Station Sigonella, Sicily, Italy. Public Works Planning and Operations Officer. Joe was responsible for the planning, code compliance, technical plan review,
maintenance, construction, and repair of facilities and operation of utilities while leading 180 employees. He
served a Navy Base population of 7,200 personnel.

Patrick M. Hanify, PE, CCM, QSD/P | RESUME PG 1
RESUME
Patrick M. Hanify, PE, CCM, QSD/QSP
QA Oversight and Technical Support
Firm
 MNS Engineers, Inc.

Areas of Expertise
 Construction management
 Project management
 Inspection
 Resident engineering
 Water and wastewater treatment
 Land development
Years of Experience
 19
Licensing
 Professional Civil Engineer, CA No. 79874
Certifications
 Certified Construction Manager, CA No. 8612
 Qualified SWPPP Practitioner (QSP), CA No. 20942
 Qualified SWPPP Developer (QSD), CA No. C79874
OSHA 30-Hour
Education
 BS, Civil Engineering, Geospatial Option, California State Polytechnic University, Pomona, CA
Affiliation
 American Council of Engineering Companies (ACEC)
Mr. Hanify, with over 19 years of experience in
construction management, project management,
inspection, resident engineering, owners' engineering,
and owner representation, has played a key role in many Southern California public works and infrastructure
projects. Patrick’s expertise spans water and wastewater treatment facilities, large-scale public works, and
complex land development projects. All of Patrick’s
projects are executed with strict adherence to labor
regulations and quality standards. Serving a diverse
client base that includes public and private utilities, joint powers authorities, land developers, municipalities, and state agencies, he excels at managing stakeholder
relationships and navigating regulatory challenges.

Known for delivering projects on time and within budget, Patrick combines proactive problem-solving with a deep
knowledge of local, state, and federal regulations to
provide clients with efficient and effective solutions. His skills in drafting ensure clear communication throughout the life of each project, reducing conflicts while boosting efficiency—making him a trusted partner from start to
finish. His experience includes:

Del Monte Treatment Plant Improvements, Golden
State Water Company (GSWC), Claremont, CA.

Construction Manager. This project improved a treatment plant by installing a booster station, rehabilitating a well, installing an arsenic treatment system, and constructing a steel bolted backwash tank and chemical building with the capacity of 3,200 gallons-per-minute (GPM).

Concrete mortar lined and coated (CML&C) piping and
ductile iron piping were installed. Additionally, the project added a new Southern California Edison service antenna
that was integrated into the existing SCADA system and
modifications to site grading, paving, and drainage were made to plant. This plant contained two welded steel
reservoirs and boosters. These reservoirs and boosters
were demolished upon completion of the new booster
station. Patrick was responsible for leading bi-weekly
project meetings and preparing minutes, handling
submittals and Requests for Information (RFIs),
processing monthly payment recommendations,
reviewing change orders and submitting
recommendations to the GSWC, preparing and
managing project records and close-out documents,
reviewing schedules, and processing job control
documents.

Patrick M. Hanify, PE, CCM, QSD/P | RESUME PG 2
RESUME
Multiple Projects, Golden State Water Company
(GSWC), Southern CA. Construction Manager/Project
Manager. Patrick has served the GSWC as a
Construction Manager and Project Manager for over 17
years. In this role, he assisted and provided oversight on various water infrastructure projects, including reservoirs, pipelines, booster stations, well rehabilitations, and
treatment plant upgrades, from construction to successful completion.

Notable accomplishments under his guidance feature
major reservoir developments, including the Eaton 0.6
MG reservoir; Kiowa Plant with its well, 0.54 MG
reservoir, and booster station; Waalew 0.3 MG reservoir and pipeline installation; Bear Valley’s 0.75 MG welded steel reservoir along with associated pipeline work and grading; Emerald’s 0.50 MG welded steel reservoir; and
the Irwin reservoir featuring a substantial 1.5 MG welded steel tank with pipeline integration.

In addition to new builds, Patrick has managed critical rehabilitation efforts, including Agarita Reservoir
Rehabilitation, Holabird East and West Tank
Rehabilitation, Bear Valley South Tank Rehabilitation,
Wayhill Tank Replacement, and Acorn Tank
Replacement, as well as various design/build capital
improvement pipeline projects across central and
southwest regions.

His expertise extends to water treatment facility
enhancements, such as the Del Monte Water Treatment
Plant Upgrades, involving well rehabilitation, booster
replacement, arsenic treatment systems installation, and chemical injection processes.

Throughout his tenure managing these complex
projects—ranging from new wells like Mountain View
Well No. 5 and Bella Vista New Well to booster station
developments like Bear Valley Phase III—Patrick has
demonstrated strong leadership in coordinating
multidisciplinary teams while ensuring compliance with
safety standards, budget constraints, timelines, and
quality requirements essential for reliable water
infrastructure delivery.

Tapo Canyon Water Treatment Plant, City of Simi
Valley, CA, Assistant Construction Manager/ Field
Engineer/Labor Compliance Official. This $5M project
constructed a 1 million-gallon-per-day (MGD) treatment
plant for the Ventura County Water Works District 8. Key tasks for this project included grading, utility installation, building erection, piping, membrane filters, chlorination equipment, controls, electrical, landscaping and tanks.

Patrick led weekly progress meetings with documented
minutes; oversaw project schedules; managed and
processed Requests for Information (RFIs), submittals,
work change directives, progress payment requests,
change orders, daily construction reports, and digital
photo records; and coordinated with the district. As Labor Compliance Official, Patrick implemented and enforced
the Labor Compliance Program.

Chino Basin Desalter Authority (CDA) Phase 3
Expansion Project, Chino Basin Desalter Authority,
Inland Empire, CA. Assistant Program Manager. This
$151M third phase of the expansion project boosts the
capacity of the CDA’s groundwater desalter facilities to produce more than 35,000 acre-feet of potable water
annually. The project involves building new groundwater wells and laying pipelines, alongside developing a
treatment facility to recover desalter concentrate (i.e., concentrate reduction facility). Additionally, the project features expanding the existing product water pump
station and constructing new product water pump
stations. Patrick was responsible for preparing monthly reports, attending construction progress and biweekly
sponsor group meetings, conducting constructability
reviews, assisting with property acquisition, providing bidding assistance, and assisting with project closeout.

Mojave Water Agency Regional Recharge and
Recovery (R3) Project, Mojave Water Agency, Victor
Valley, CA. Construction Manager. This water supply
project in San Bernardino County recharges the Upper
Mojave River flood plain with up to 40,000 acre-feet of State Water Project water annually. Up to 22 extraction recovery wells, three reservoirs, a pump station capable of handling 25,0000 gallons per minute (GPM), and a
fully integrated conveyance system designed to supply
multiple retail agencies across the High Desert region will be constructed. During the first phase of the project, the scope included building six wells with the capacity to
extract up to 15,000 acre-feet annually. The
infrastructure also featured over 16 miles of pipeline
ranging from 12 to 48-inches in diameter, along with a
welded steel reservoir holding 2.65 million gallons (MG), Additionally, a flow control and recharge facility was
constructed with a capacity of 40,000 GPM and able to
manage pressure drops up to 235 psi. A pump station
was constructed and sized to handle 25,000 GPM and
equipped with pumps to provide 15,000 GPM. Four
turnout flow control facilities were installed to distribute water efficiently among member agencies. Patrick was
responsible for the project’s construction management
and labor compliance.

Aaron Singer, PE | RESUME PG 1
RESUME
Aaron Singer, PE
Resident Engineer/Project Manager
Firm
 MNS Engineers, Inc.

Areas of Expertise
 Construction management
 Civil construction
 Water and wastewater infrastructure
 Project management
Years of Experience
 9
Licensing
 Professional Civil Engineer, CA No. 94535
Certifications
 OSHA 30 Hour Construction Safety and Health Training
Education
 BS, Civil Engineering, California Baptist University, CA Mr. Singer has nine years of construction and
engineering experience. Aaron’s career has been shaped
by mentorship from industry leaders, allowing him to
build a strong track record in construction management, inspection, and constructability reviews. With a diverse background spanning heavy civil construction, precast,
and land development, he excels in design drafting, field supervision, and clear project communication. Recently, Aaron’s focus has been on managing water and
wastewater infrastructure projects, where his skills
continue to drive successful outcomes. His experience
includes:

Del Monte Treatment Plant Improvements, Golden
State Water Company (GSWC), Claremont, CA.

Resident Engineer. This project improved a treatment
plant by installing a booster station, rehabilitating a well, installing an arsenic treatment system, and constructing a steel bolted backwash tank and chemical building with the capacity of 3,200 gallons-per-minute (GPM).

Concrete mortar lined and coated (CML&C) piping and
ductile iron piping were installed. Additionally, the project added a new Southern California Edison service antenna
that was integrated into the existing SCADA system and
modifications to site grading, paving, and drainage were made to plant. Aaron was responsible for assisting with observation of project infrastructure, project
communication and meetings, contract administration
and document control, schedule review, cost control and pay estimate review, submittal and Request for
Information (RFI) review and response, change order
and claim management.

Mountain View Well No. 5, Golden State Water
Company (GSWC), CA. Resident Engineer. This project
constructed an 850 gallons-per-minute well, metering
piping, disinfection building and electrical room, and
onsite retention basin. Key tasks included procuring and installing well motor and appurtenances, structural
framing, site grading, drainage modifications, concrete mortar lining and coating (CML&C) piping, and both
ductile iron pipe (DIP) and C900 piping. Additionally, the project added a new Southern California Edison service, and cellular antenna to communicated with the local
SCADA system. Aaron was responsible for assisting with
observation of project infrastructure, project
communication and meetings, contract administration
and document control, schedule review, cost control and pay estimate review, submittal and Request for
Information (RFI) review and response, change order
and claim management.

Aaron Singer, PE | RESUME PG 2
RESUME
Kiowa Booster Pump Plant Project, Golden State
Water Company (GSWC), Apple Valley, CA. Resident
Engineer / Inspector. This project involved the
construction of a welded steel tank and installation of a booster pump station equipped with a backup generator.

Key components included building a concrete ring wall
foundation, outfitting the tank with necessary
appurtenances, preparing building pads, and providing
chlorination and disinfection. The scope also covered
testing and site cleanup, installation of new yard piping, as well as electrical work for lighting and other site
systems. Site enhancements were made by constructing
an asphalt concrete (AC) access road and concrete
drainage structures to effectively manage stormwater
run-off. Aaron was responsible for assisting with
Inspection of project infrastructure, coordination of
specialty inspection, project communication and
meetings, contract administration and document control, schedule review, cost control and pay estimate review,
submittal and Request for Information (RFI) review and
response, change order and claim management.

Bear Valley Booster Pump Station, Golden State
Water Company (GSWC), CA. Construction Manager.

This project constructed a 2,700 gallons-per-minute
concrete masonry unit (CMU) booster station. Key tasks
included procuring and installing an on-site stand-by
generator, site grading, drainage modifications, concrete mortar lining and coating (CML&C) piping, and ductile
iron pipe (DIP) piping. Additionally, the project added a new Southern California Edison service antenna that was integrated into the existing SCADA system of the active plant. This plant contained two welded steel reservoirs and boosters. These reservoirs and boosters will be
demolished upon completion of the new booster station.

Aaron was responsible for assisting with observation of project infrastructure, coordination of specialty
inspection, project communication and meetings,
contract administration and document control, schedule
review, cost control and pay estimate review, submittal and Request for Information (RFI) review and response,
change order and claim management, constructability,
and pre-construction services.

Mojave Plant Project, Golden State Water Company
(GSWC), Apple Valley, CA. Resident Engineer. This
project involved the construction of a welded steel tank and installation of a booster pump station equipped with a backup generator. Key components included building a
concrete ring wall foundation, outfitting the tank with necessary appurtenances, preparing building pads, and
providing chlorination and disinfection. The scope also covered testing and site cleanup, installation of new yard piping, as well as electrical work for lighting and other site systems. Site enhancements were made by
constructing an asphalt concrete (AC) access road and
concrete drainage structures to effectively manage
stormwater run-off. Aaron was responsible for assisting with observation of project infrastructure, coordination of specialty inspection, project communication and
meetings, contract administration and document control, schedule review, cost control and pay estimate review,
submittal and Request for Information (RFI) review and
response, change order and claim management.

Warren 4R Replacement Well Project, Hillwood
Development and RPU, San Bernardino, CA. Project
Engineer. This project constructed a new well and
abandonment of the existing Warren 4 Well. The new
well has a capacity of 2,800 gallons-per-minute (GPM)
and is approximately 1,000 feet deep. The new well,
along with its pump and related equipment, is housed
inside a prefabricated roll-apart building measuring 13 feet by 13 feet with a height of 10 feet. Aaron was
responsible for assisting with observation of project
infrastructure, coordination of specialty inspection,
project communication and meetings, contract
administration and document control, schedule review,
cost control and pay estimate review, submittal and
Request for Information (RFI) review and response,
change order and claim management, constructability,
and pre-construction services.

Multiple Tank Projects, Golden State Water Company
(GSWC), Southern CA. Construction Manager/Assistant
Construction Manager, Project/Resident Engineer, and
Inspector. Aaron has worked on a variety of Welded
Steel Tank projects with GSWC.
• Eaton 0.6 million gallon (MG) reservoir
• Waalew 0.3 MG Reservoir
• Irwin 1.5 MG Reservoir
• Linda Vista 0.6 MG Reservoir
• Wayhill Replacement Tanks (0.5 MG)
He is responsible for performing the following
construction management tasks: inspection and
observation of project infrastructure, coordination of
specialty inspection, project communication and
meetings, contract administration and document control, schedule review, cost control and pay estimate review,
submittal and Request for Information (RFI) review and
response, change order and claim management,
constructability, and pre-construction services.

Sandra Lee | RESUME PG 1
RESUME
Sandra Lee
Labor Compliance
Firm
 MNS Engineers, Inc.

Areas of Expertise
 Federal and state labor compliance
 Federal and state prevailing wage
 US Department of Housing and Urban Development
(HUD) Section 3 reporting requirements
 Integrated Disbursement and Information System (IDIS) Section 3 compliance and performance reports
 Project labor agreement
 Continuity of work agreement
Years of Experience
 13
Certifications
 US Department of Labor Davis-Bacon Act Prevailing
Wage
 US Department of Housing and Urban Development
Section 3
 US Department of Industrial Relations Prevailing Wage Education
 BA, Contract Compliance, Morgan State University,
Baltimore, MD
Speaking Engagements
 2024 Federal Labor Compliance Training Seminar to the City of Atlanta
Ms. Lee has extensive experience providing quality
project compliance monitoring and reporting services to various public agencies, including cities, counties, and housing authorities. Throughout Sandra's career, she has demonstrated strong communication skills, a strong work ethic, and unwavering trustworthiness. Sandra's
expertise lies in maintaining professional relationships with public agencies that have remained her clients for many years. She understands the importance of effective communication and consistently delivers accurate and
timely reports to ensure compliance with regulatory
requirements. Sandra is knowledgeable in federal
Community Development Block Grant (CDBG), HOME
Investment Partnerships Program (HOME) entitlement,
HOME American Rescue Plan Program (HOME-ARP),
Emergency Services Grant (ESG), Homekey, and
Permanent Local Housing Allocation (PLHA) guidelines
to ensure project and its contractors follow the reporting requirements. Her dedication to excellence is evident in her meticulous approach to monitoring projects and
ensuring all necessary documentation is complete.

Sandra's commitment to professionalism has earned her
a reputation as a reliable partner for public agencies
seeking comprehensive compliance services. With
Sandra's proven track record of success, she continues
to be a trusted resource for public agencies needing
project compliance monitoring and reporting services.

She works closely with public agencies to ensure each
project’s audit is cleared by HUD and Los Angeles
County Development Authority. Her experience includes:

Various Park Improvement, Facility Building
Improvement, and Demolition Projects, City of Long
Beach, CA. Labor Compliance Officer. Sandra served as
the Labor Compliance Officer for various federally, state, and/or locally-funded park improvements, facility building improvements, and demolition projects. Her
responsibilities included preparing contract award notices for the Office of Federal Contract Compliance Programs; monitoring federal and state prevailing wage and
apprenticeship hiring requirements; certifying payroll
records of over 50 contractors; monitoring Section 3 rules and outreach efforts of contractors; monitoring certified payroll reporting and monthly compliance reporting of
contractors using LCP Tracker; maintaining project
compliance files according to the city’s requirements;
preparing compliance requirements presentation and
presenting at pre-bid and pre-construction meetings;
prepared Section 3 Performance Reports, and HUD
Semi-Annual and Annual Reports on behalf of the city;
Sandra Lee | RESUME PG 2
RESUME
preparing project compliance files to be HUD-audit ready; and representing the city during audits.

Various Street Improvement Projects, City of
Hawaiian Gardens, CA. Labor Compliance Officer.

Sandra served as the Labor Compliance Officer for
various federally-funded street improvements projects.

She was responsible for reviewing draft bid specifications to ensure all appliable federal and state labor regulations and labor codes, compliance reporting requirements,
forms, and project goals were provided; guiding the city throughout the project advertisement, bid phase,
contractor selection and award process to ensure project compliance with federal and state regulations; preparing contract award notices to the Office of Federal Contract Compliance Programs; monitoring federal and state
prevailing wage, Section 3 rules, and contractors’
outreach efforts; preparing HUD Semi-Annual and
Annual, and IDIS Section 3 Compliance reports;
preparing for HUD project closeout audits; and
representing the city during audits.

Various Street Rehabilitation Projects, City of
Norwalk, CA. Labor Compliance Officer. Sandra served
as the Labor Compliance Officer for various federally
and/or state-funded street rehabilitation projects. Her responsibilities included reviewing draft bid packages
and specifications to ensure all applicable labor codes and compliance requirements language and forms were
provided; guiding the city to follow the federal and state public works project bid advertisement and bidding
process; preparing contract award notices to the Office of Federal Contract Compliance Programs; monitoring
federal and state prevailing wage, Section 3 rules, and contractors’ outreach efforts; preparing HUD SemiAnnual and Annual, and IDIS Section 3 Compliance reports; and preparing project compliance files to be
HUD-audit ready.

Various Street Improvement Projects, City of Orange,
CA. Labor Compliance Officer. Sandra served as the
Labor Compliance Officer for various federally-funded
street improvements projects. She was responsible for
reviewing draft bid specifications to ensure all appliable federal and state labor regulations and labor codes,
compliance reporting requirements, forms, and project
goals were provided; guiding the city throughout the
project advertisement, bid phase, contractor selection, and award process to ensure project compliance with
federal and state regulations; monitoring federal and
state prevailing wage, Section 3 rules, and contractors’ outreach efforts; preparing HUD Semi-Annual and
Annual, and IDIS Section 3 Compliance reports;
preparing for HUD project closeout audits; and
representing the city during audits.

Various Projects, City of Redondo Beach, CA. Labor
Compliance Officer. Sandra served as the Labor
Compliance Officer for various federally, state, and
locally-funded projects. She was responsible for
monitoring federal and state prevailing wage, Section 3 rules, and outreach; preparing HUD Semi-Annual and
Annual reports; and preparing project compliance files to be HUD-audit ready.

Various Park Improvement and Street Rehabilitation
Projects, City of San Bernardino, CA. Labor
Compliance Officer. Sandra served as the Labor
Compliance Officer for various locally and federallyfunded parks improvements and street rehabilitation projects. Her responsibilities included monitoring over 50 contractors’ certified payroll records, monthly
apprenticeship hiring and certification reports, and Skilled and Trained Workforce Program.

Various Street Rehabilitation and ADA-Compliant
Curb Ramp Projects, City of Torrance, CA. Labor
Compliance Officer. Serving as the Labor Compliance
Officer for various federally-funded street rehabilitation and American with Disabilities Act (ADA) compliant curb ramps projects. Her responsibilities included reviewing draft bid specifications to ensure all appliable federal and state labor regulations and labor codes, compliance
reporting requirements, forms, and project goals were
provided; guiding the city throughout the project
advertisement, bid phase, contractor selection, and
award process to ensure project compliance with federal and state regulations; monitoring federal and state
prevailing wage, Section 3 rules, and contractors’
outreach efforts; preparing HUD Semi-Annual and
Annual, and IDIS Section 3 Compliance reports;
preparing for HUD project closeout audits; and
representing the city during audits.

Estella Wells | RESUME PG 1
RESUME
Estella Wells
Labor Compliance
Firm
 MNS Engineers, Inc.

Areas of Expertise
 HOME
 Neighborhood Stabilization Program
 Tax Credit compliance monitoring
 HUD requirements
Years of Experience
 20
Education
 MA, Leadership and Organizational Studies, California Baptist University
 BA, French/English, University of Alabama
Ms. Wells is an exceptional leader with a wealth of
experience in housing and project management spanning
over 20 years. Throughout her career, she has
demonstrated a strong commitment to overseeing
affordable housing units and ensuring their successful
implementation. One of Estella's key strengths lies in her extensive knowledge of various programs related to
housing and economic development. She possesses a
deep understanding of HOME, Neighborhood
Stabilization Program, and Tax Credit compliance
monitoring. Additionally, she is well-versed in the
intricacies of other Federal, State, or local programs that are relevant to the field. With her expertise in these
areas, Estella consistently ensures that all projects under her supervision comply with the necessary regulations
and guidelines. Her meticulous approach to monitoring
affordable housing units guarantees that they meet the
required standards for affordability and accessibility.

Estella's leadership skills combined with her
comprehensive understanding of housing programs
make her an invaluable asset in any housing or project
management endeavor. Her experience includes:

Various Projects. Planner II. Estella facilitated
collaborative community involvement sessions and
stakeholder consultations aligned with HUD
requirements. She managed the annual monitoring of
below-market-rate rental properties across various client portfolios, evaluated applications for Emergency Rental Assistance and Home Repair Programs, and participated
in the development and maintenance of a jurisdiction's
specialized plans, ensuring projects were consistent with applicable regulations and other relevant factors. Estella served as a technical consultant and advisor to
stakeholders, providing guidance on policies, issues,
processes, procedures, and regulations. She designed
and conducted research to collect original data from
reports and surveys, using that data to define issues,
assess trends, and make recommendations.

Various Projects, City of San Bernardino Community
and Economic Development, San Bernardino, CA.

Housing Compliance Specialist. Estella monitored,
inspected, and guaranteed compliance across 34
affordable housing communities, totaling more than 1072 City-funded affordable units. In addition, she enforced division policies and procedures to ensure the prompt
delivery of housing services and associated programs,
adhering to federal, state, and local regulations. She was responsible for conducting onsite inspections of
affordable apartment units in collaboration with City
Estella Wells | RESUME PG 2
RESUME
building inspectors, validating tenant files to ensure
adherence to income and rent eligibility criteria. This included producing comprehensive reports on monitoring
and inspection outcomes, promptly addressing any
identified deficiencies. Estella also led the review and approval process of Affirmative Marketing and Tenant
Services Plans in accordance with HUD regulations,
analyzed property budgets and financial statements,
maintaining a comprehensive database of City-funded
affordable housing projects, inspections, agreements,
loan terms, and monitoring histories.

Various Projects, San Bernardino County Community
Development and Housing, San Bernardino, CA.

Economic Community Development Analyst/Technician.

Estella managed the Emergency Solutions Grant
program by overseeing funding applications, reports, and planning documents. She coordinated subrecipient
activities, conducted client interviews for program
eligibility, and resolved housing-related issues. In
addition, she ensured compliance with regulations
through site inspections and provided information to
various stakeholders. She also organized data, compiled reports, and assisted in financial statement development while maintaining business files and correspondence.

Various Projects, ConAm Property Management, CA.

Compliance Auditor. Estella ensured compliance with
affordable housing regulatory agreements, guidelines,
and management policies for a diverse portfolio of
properties. She collected and analyzed data for over 37 properties comprising more than 3000 units, conducting
performance analysis of rental property housing
programs to align administrative policy with program
regulations and objectives. Estella also reviewed
eligibility determination documentation, obtaining and
disseminating reports to ensure compliance, providing
employee training on compliance topics, and addressing
financial and regulatory matters with company officials.

Various Projects, Riverside County Economic
Development Agency, Riverside, CA. Development
Specialist II (Housing Division). Estella monitored over 90 housing projects funded by various entities to ensure
compliance with regulations. She conducted reviews,
inspections, and workshops for property owners and
management personnel. Estella oversaw Davis Bacon
and prevailing wage projects, reviewed payrolls, and
prepared billing submittals. She assisted in funding
requests for affordable housing development, negotiated contracts, and prepared documents for approval. Estella implemented compliance policies, assessed risks,
conducted internal audits, and kept abreast of industry changes. She developed process guides for staff as
needed.

Chris Cooper, CPII | RESUME PG 1
APPENDIX A. RESUME
Firm
 MNS Engineers, Inc.

Areas of Expertise
 Construction inspection
 Materials testing
 Transportation projects—roadways, interchanges, bridges, highways
 Pavement rehabilitation
Years of Experience
 22
Certifications
 NACE Level 1 Basic Coatings Inspector, No. 115694
 Certified Public Infrastructure Inspector, APWA
 ACI Concrete Field Testing Technician-Grade 1, No.
01057304
 ICC Pre-Stressed Concrete Special Inspector, No.
5312076-92
 ICC Reinforced Concrete Special Inspector, No. 5312076- 49  ICC Soils Special Inspector, No. 5312076-EC
 ICC Spray Applied Fire Proofing Special Inspector, No. 5312076-86
 ICC Structural Masonry Special Inspector, No. 5312076-84  ICC Structural Steel and Bolting, No. 5312076-S1
 Caltrans CTM 105, 125, 125AC, 125AGG, 125PCC, 201,
202, 216, 217, 226, 227, 231, 504, 518, 523, 533, 539, 540, 556, 577
 Radiation Safety Officer, APNGA
 Defensive Driving
 ProCPR Adult CPR/AED and First Aid Certificate, No.
159811010523201
Professional Development
 Temporary Pedestrian Facilities, Caltrans
Mr. Cooper has over 22 years of experience as a
construction inspector and materials technician working on highway/roadway improvements and water resources
and infrastructure projects. Chris’ expertise includes
concrete and hot mix asphalt (HMA) placement
inspection; pre-stressed concrete; masonry, soils and
geotechnical testing; bolting, framing and nailing
inspection; soils and geotechnical testing; coatings
inspection, and electrical inspection. He has provided
field quality control and quality assurance in both
structure and infrastructure projects. He is
knowledgeable with Caltrans methods and procedures.

His experience includes:

Phase 1 Wastewater Treatment Plant Upgrade,
Laguna County Sanitation District, Santa Maria, CA.

Construction Inspector/Materials Technician. This $54M
wastewater treatment plant upgrade project expands the
capacity as well as upgrades the existing plant. The
project includes replacing the existing headworks;
replacing the existing clarifiers and trickling filter with an aeration basin/mixed liquor splitter box; constructing new stormwater capture facilities; repurposing and converting the existing south primary clarifier for the use of a break tank; modifying the existing sludge collection and
digester process; installing UV disinfection; expanding the in-house recycled water system; installing a new 800 kw generator; installing blowers; and constructing a new building to house a new laboratory, blower building,
offices, locker room, programmable logic controls and
motor control center room, control room, and
mechanical/server rooms. Pond A and the basin were
repurposed to accommodate captured stormwater runoff
while Ponds B and C being utilized to receive secondary clarified effluent from the new activated sludge processes prior to screening and membrane ultrafiltration. Chris is providing construction inspection for the structural
concrete facilities and buildings which include structural concrete, bar reinforcement, masonry block, piping,
structural inserts, and anchors. He is also conducting
coatings inspection for exterior and submerged piping.

Additional responsibilities include checking grade, daily reports, and item quantities.

Biosolids and Energy Phase 1 (BESP1), Goleta
Sanitary District, Santa Barbara, CA. Construction
Inspector. The Goleta Sanitary District (GSD) has
undertaken the BESP1 project, which includes
construction of a new, pre-stressed concrete digester,
installation of a cogeneration system with an integrated digester gas cleaning system, improvements to the
Chris Cooper, CPII
Optional Coating Inspection
Chris Cooper, CPII | RESUME PG 2
APPENDIX A. RESUME
digester heating system, as well as construction of
associated demolition, yard piping, and electrical and
instrumentation. The project site is within Coastal
Commission jurisdiction, requiring compliance with a
Coastal Development permit, and is also within the direct vicinity of the Santa Barbara airport, requiring Federal Aviation Administration permitting and coordination. In addition, the wastewater treatment plant (WWTP) is
within a Native American archeological area of interest, requiring close coordination with paleontological and
archeological monitors during excavation. Chris
conducted construction inspection including coatings,
concrete, soils, and electrical on the Digester No. 4
concrete tank and all exterior and submerged piping.

East Cliff Drive Sewer Replacement, County of Santa
Cruz, CA. Construction Inspector. East Cliff Drive Sewer Replacement Project, County of Santa Cruz, CA.

Resident Engineer. The project involved the replacement of deteriorating sanitary sewer infrastructure, including 3,340 feet of 8-inch main pipe and 3,955 feet of larger 18- to 24-inch trunk line pipes. The work included tying new pipes into 42 existing manholes, replacing eight
manholes, rehabilitating seven manholes with polymer
concrete inserts or spray-on liners, and replacing 37
manhole frames and covers. Additionally, the project
completed 91 sewer connections. Construction was
performed using an open cut trench method within
existing paved roads. However, unforeseen poor
subgrade conditions required special excavation and
shoring techniques—such as driven steel plates, soldier piles, and concrete grout injection—to safely complete
approximately 2,000 linear feet of sewer main
replacement at depths exceeding 20 feet. Deep
subgrade stabilization was also achieved through about
825 feet of concrete injection permeation grouting.

Pavement restoration was a significant component of the project. Improvements included approximately 10,000
square yards of pavement overlay, 30,000 square yards
of slurry seal application, replacement of pavement
disturbed by trenching operations, upgrades to median
islands along East Cliff and Portola Drives within the
project area, installation of Bomacron concrete
crosswalks covering around 200 square yards, and
addition of new green bicycle lanes on these streets.

MNS provided comprehensive construction management
services throughout construction and during project
close-out to ensure quality control and successful
completion. Chris was responsible for as-built drawing
records, traffic control, daily quantities, construction inspection of trench excavation, C900 sewer line
placement, grading, paving, trench backfill, and existing utility tie ins.

Roadway Sealing and Laurel Lane Complete Streets,
City of San Luis Obispo, CA. Construction Inspector.

This $2.3M project consisted of Type II slurry seal and new striping at various locations throughout the City of San Luis Obispo, including a major restriping of Laurel Lane to include new bike lanes. The project also installed new ADA curb ramps and traffic calming speed bumps.

Responsibilities included calibration of placement
equipment, inspection of stripe removal, installation of slurry, inspection of Americans with Disabilities Act
(ADA) ramps, tracking quantities, monitoring traffic
control, and coordinating with the city.

Rancho Monte Allegra Roadway Lots 1-18,
Carpinteria Valley Water District, Carpinteria, CA.

Construction Inspector. This $15M project installed 200 linear feet of 4-inch lateral hydrant lines; 3,000 linear feet of 2-inch and 6-inch service lines; and approximately two miles of 12-inch transmission lines. Additional project elements included offsets of line installations, adequate bedding material, depth and widths of excavations,
testing of compaction efforts utilizing a nuclear gauge, pressure testing of transmission lines after backfill
completion, thrust block placement, hydrant installations, service tie ins, and valve installations. The scope
included roadway grading, building pad grading,
removals, bridge installations, bin wall installations, service installations, concrete roadway placement, slide mitigation involving soil nailing, and tie back wall
systems.

Westlake Reservoir Replacement and Hydrostatic
Test Project, Callegues Water District, CA. Concrete
Technician Field Testing Technician. This $7.3M
removed a reservoir and installed a new underground
concrete reservoir. Additional project features included offset line tie in installations, excavations, bedding
materials and backfill installations, width and depths of excavations, nuclear density gauge testing, and
observation of excavation spoils removals. Chris served as a Concrete Technician Field Testing Technician for
reservoir structure placement.

Water Line Replacement, City of Greenfield, CA.

Construction Inspector. This $230K project involved
offsets of line installation, 6-inch water main replacement with 8-inch mains along four blocks, valve replacements, and alley way improvements.

Donny Spates, CPII | RESUME PG 1
RESUME
Firm
 MNS Engineers, Inc.

Areas of Expertise
 Reinforced concrete and masonry
 Structural steel
 Project management
 Construction inspection
 Waterline and sewer line
 Water/wastewater improvements
Years of Experience
 37
Certifications
 Certified Public Infrastructure Inspector, APWA
 NACE Coating Inspector, Level 1
 ACI Concrete Field Testing Technician, Grade I
 ICC Reinforced Concrete Special Inspector
 10-hour Construction Safety, Cal/OSHA
 Confined Space Awareness
 Defensive Driving
 CPR and First Aid
Education
 AS, Construction Management, San Joaquin Valley
College, CA
Awards
 2016 APWA Project of the Year, Supplemental Water
Project
 2016 National ASCE Project of the Year, Supplemental
Water Project
Mr. Spates has over 37 years of experience in project
supervision and inspection in water and wastewater
facilities, reinforced concrete, structural steel, roadways, and underground piping. Donald is skilled at interpreting plans and specifications to mitigate cost and schedule
risks. He is an excellent project team supervisor and
strives to implement resource-saving solutions. His
experience includes:

Wastewater Reclamation Plant Upgrade, Phase I,
Laguna County Sanitation District, Santa Maria, CA.

Construction Manager/Inspector. This $55M wastewater
treatment plant upgrade project expands the capacity as well as upgrades the existing plant. The project includes replacing the existing headworks; replacing the existing clarifiers and trickling filter with an aeration basin/mixed liquor splitter box; constructing new stormwater capture facilities; repurposing and converting the existing south primary clarifier for the use of a break tank; modified the existing sludge collection and digester process; install UV disinfection; expanded the in-house recycled water
system; installed a new 800 kw generator; and
constructed a new building to house a new laboratory,
offices, locker room, control room, and mechanical/server rooms. Pond A and the basin were repurposed to
accommodate captured stormwater runoff while Ponds B
and C being utilized to receive secondary clarified
effluent from the new activated sludge processes prior to screening and membrane ultrafiltration. Donny was
responsible managing all the field work including
inspection; coordination with plant operations staff,
contractor and designer; submittal and RFI review;
reviewing and negotiating change orders; daily reports; material coordination and verification.
2020 Pipeline Rehabilitation Project, Goleta Sanitary
District, Goleta, CA. Construction Inspector. This $1.5M sewer main rehabilitation project replaced 8-inch vitrified clay pipe (VCP) and rehabilitated over 7,500 feet of
existing 6-inch, 8-inch, and 12-inch pipe through curedin-place pipe (CIPP) liner including rehabilitating 76 laterals using top hat lateral connection sealers. The
project also included rehabilitating 34 manholes using
sprayed polyurethane coating; point repairs; trenching
and shoring; HMA paving; and daily traffic control. The rehabilitation work was performed at various locations
throughout the city requiring close coordination and
communication with residents, businesses, and the
District as well as accommodating the flow of vehicle,
bicycle, and pedestrian traffic. Additionally, a portion of the pipeline required realigning to keep within easement Donny Spates, CPII
Optional Coating Inspection
Donny Spates, CPII | RESUME PG 2
RESUME
boundaries. Donny was the District’s Lead Inspector on
the project responsible for daily inspection, tracking
quantities, coordination, and assisted with submittal and RFI review and recommendations.

Supplemental Water Projects, Nipomo Community
Services District, Nipomo, CA. Construction Inspector.

This $16M supplemental water project involved three
separate construction contracts:
• Horizontal Directional Drilling (HDD) under the Santa Maria River
• Blosser Road waterline and roadway repair
• New pump station construction
A one-mile, 24-inch pipeline extension was constructed
along Blosser Road to the Santa Maria River Levee,
where it was bored and jacked under the levee. The pipe then transitioned to a 30-inch high-density polyethylene (HDPE) pipe, which was installed 100 feet under the
riverbed by horizontal directional drilling (HDD). The new pump station construction included a booster pump
station; electrical system (including portable backup
generator); water chloramination system and
appurtenances; approximately 1,720 linear feet of access road to the pump station site; and 1,750 linear feet of 24- inch ductile iron pipe. The project was constructed within highly sensitive environmental habitat, which required
extensive surveying and coordination with permitting
agencies as well and the surrounding farmland owners.

MNS provided construction management and inspection.

APWA Project of the Year, Winner.

ASCE Project of the Year, Winner.

Joshua Road Pump Station Reservoir, Nipomo
Community Services District, Nipomo, CA.

Construction Inspector. The $3M Joshua Road Pump
Station Reservoir project was phase 2 of the larger
Supplemental Water Project completed in 2016 for the
Nipomo Community Services District (District). Water
purchased by the District from the City of Santa Maria
and imported through the Supplemental Water Project
pipeline allowed the District to reduce pumping from its existing wells. Taking action to slow the depletion of
groundwater to reduce the potential for seawater
intrusion on the Nipomo Mesa was a shared
responsibility of all groundwater users on the basin. By providing an additional source of water other than
groundwater, this project increased the reliability and security of the community’s water supply. This project
constructed a 500,000 gallon, partially-buried concrete reservoir at the Joshua Road Pump Station. Additional
construction elements involved associated piping,
electrical, instrumentation, grading, and landscape
improvements. This project increased delivery capacity to at least 800-acre-feet-per-year and provided operational flexibility. MNS provided construction management
services.

Southland Wastewater Treatment Plant Upgrade,
Nipomo Community Services District, Nipomo, CA.

Construction Inspector. This $11M wastewater treatment
plant upgrade and expansion project included converting the existing aeration basins to the Biolac® Wave
Oxidation System, which was an extended aeration
process; constructing clarifiers; and converting existing ponds to aerated sludge holding lagoons. Additional
project elements involved replacing the existing pump
station, including a new reinforced concrete wet well and installing new screw centrifugal pumps; constructing a
new masonry block electrical building; constructing new headworks, including two parallel shaftless screw
screens and a vortex grit removal system to increase
effluent quality and to reduce maintenance issues; and
associated yard piping. This project required close
coordination with the existing plant staff and operations to avoid any unanticipated disruption to the existing plant operations.

Henry C. Garnett Water Purification Plant Expansion,
Kern County Water Agency, CA. Lead Construction
Inspector. This $70M project expanded the Garnet Water
Purification Plant, a conventional water treatment facility, from a peak capacity of 38 million gallons per day (MGD) to 72 MGD. The contracted annual production increased
from 25,000 to 53,000 acre-feet (af) during a 30-year
ramp-up period. MNS provided project inspection and
administration for this expansion, which included
construction of a new raw water pump station; new
clearwells; new Train B flash mixing structure;
flocculation and sedimentation basins; new filters,
diffusers, and backwash piping and pumping system;
new chemical feed facility; miles of yard piping ranging from 4 inches to 72 inches; massive excavation and
grading; over 30,000 cy of structural concrete; bar
reinforcement; mechanical systems; and instrumentation
and controls. Coordination with the plant staff was critical since daily operation could not be interrupted while
constructing the new facilities and tying into the existing system.

Carlos Gaytan, D3 Certified, will serve as the Senior Construction Observer for the City of San Jacinto Grand Well Site project. With more than 30 years of experience in public works construction, underground utilities, and water infrastructure, Carlos brings extensive field knowledge and a disciplined approach to observing and documenting all aspects of construction activities for potable water systems. Carlos has supported a wide variety of water and sewer infrastructure projects, including well equipping, manhole rehabilitation, confined space operations, bypass pumping coordination, and trench restoration. He has observed and documented work related to excavation, backfill, pipe installation, structural concrete, treatment system components, coatings, pressure testing, traffic control, and ADA-compliant surface restoration. He is well-versed in monitoring contractor performance for compliance with plans, specifications, CEQA mitigation measures, and SWPPP best practices.

As a certified Water Distribution Operator (D3), Carlos offers technical expertise in pipeline construction, potable water system installation, and inspection of structural and mechanical components. He is proficient in maintaining detailed daily field reports, capturing photographic documentation, and facilitating coordination between the contractor, engineers, utility companies, and City personnel. Carlos’s bilingual communication skills (English and Spanish) help ensure clear and prompt issue resolution in the field. Carlos’s dedication to quality, safety, and schedule adherence—combined with his familiarity with public agency standards and regulatory compliance—makes him a trusted observer for complex water infrastructure projects.

He has served as Senior Construction Observer on the following representative projects:

ELSINORE VALLEY MUNICIPAL WATER DISTRICT, HIGHWAY 74
WATERLINE RELOCATION (DAY WORK) | This project was implemented to accommodate roadway widening improvements by Caltrans along State Route 74 in the City of Lake Elsinore. The scope involved the relocation and installation of approximately 2,400 linear feet of new 12-inch C900 PVC water main along the north side of Highway 74, spanning from Meadow Ridge Drive to Ardenwood Drive. Work included the installation of new mains, gate valves, fittings, fire hydrants, and appurtenances, as well as multiple service and system connections to the existing active potable water distribution network. Construction activities required extensive trench excavation, pipe bedding and backfill, hot tap installations, and execution of pressure testing and disinfection protocols in compliance with AWWA standards. The project also involved the removal and abandonment of segments of the existing waterline infrastructure, requiring close coordination to sequence shutdowns and minimize service disruptions. Given the project’s location within an active Caltrans corridor, strict adherence to traffic control requirements and construction phasing was necessary to maintain public safety and minimize impacts to the traveling public. Additional responsibilities included utility coordination, trench restoration, and ensuring compliance with local, state, and agency-specific construction and safety standards. This project exemplifies the challenges and complexity of performing utility relocation within constrained transportation corridors while maintaining continuous water service to surrounding communities.

CITY OF CHINO, PUBLIC WORKS INSPECTOR | As a Public Works Inspector for the City of Chino, Carlos Gaytan provides comprehensive inspection services for public infrastructure projects, including domestic water wells, water distribution systems, storm drains, roadways, and erosion control measures. His role includes reviewing construction drawings, permits, and site plans to ensure compliance with local, state, and federal regulations. Carlos facilitates preconstruction meetings with developers, contractors, and engineers to clarify technical requirements and confirm that all permits and approvals are secured prior to mobilization. In the field, he performs regular and milestone inspections of well equipping, pump installations, vault construction, electrical and SCADA infrastructure, and waterline tie-ins—verifying compliance with design specifications, safety protocols, and agency standards. He monitors the installation and maintenance of erosion control and stormwater BMPs to ensure environmental compliance and CEQA consistency. Carlos documents construction progress through detailed daily reports, capturing field changes, deficiencies, and corrective measures. He oversees final walkthroughs and project closeouts, verifying all infrastructure components—including wells and appurtenances—are fully functional and compliant prior to final acceptance. He also conducts post-construction warranty inspections to identify and resolve latent issues. Carlos’s attention to detail, strong documentation practices, and deep field knowledge support successful delivery of complex water infrastructure improvements, making him an ideal fit for the Grand Well Site project.

Carlos Gaytan, D3
Senior Construction Observer

LICENSES & REGISTRATION
» SWRCB Water Distribution
Operator D3, Operator #14889
» Bilingual in English and Spanish
» 30 Cal/OSHA
» Confined Space Training
» Fall Protection
» Traffic Control Safety

EDUCATION
»Chaffey College | 1982–1984
Automotive Technology
» Mt. San Antonio College | 2000–
2003, Intro to Water Systems, T1-T2
Treatment Operations and Water
Distribution, Cross-Connection &
Backflow Prevention
City of Chino Projects Include:

CITY OF CHINO, WELLS 4 & 6 WATER TREATMENT FACILITY | This project involved the design and construction of a centralized groundwater treatment facility to bring inactive Wells 4 and 6 back into service in response to updated drinking water regulations issued by the SWRCB. The goal was to reduce the City’s dependence on imported water by increasing utilization of local groundwater resources. The new facility was designed to treat up to 1,700 gallons per minute (GPM), providing approximately 34% of the average daily demand within the pressure zone that serves over half the City’s service area. The project scope included the construction of a 2.0 million gallon per day (MGD) treatment plant and interconnection of the two wells.

CITY OF CHINO, WELL 11 RAW WATER TRANSMISSION MAIN PROJECT | This project involved the installation of approximately 1.5 miles of new 16-inch raw water transmission main using both PVC and cement mortar–lined and coated (CML&C) steel pipe. The scope included associated valves, fittings, blow-off assemblies, and combination air valves, with construction taking place within existing city streets. The project also included electrical and instrumentation upgrades, such as modifications to the existing control panel, integration with the SCADA host system, and installation of a new humanmachine interface (HMI) with associated programming.

CITY OF CHINO, WELL 17 EQUIPPING PROJECT | This project involved the equipping and activation of existing Well 17 to support the City of Chino’s potable water supply system. Improvements included installation of mechanical, electrical, and structural components to fully integrate the well with the Eastside Water Treatment Facility (EWTF). The scope of work consisted of trenching across the EWTF site for installation of new piping and electrical conduit, site grading and compaction, and construction of a masonry block well building with shear walls and a continuous footing foundation. The well building was designed to house the wellhead pump, discharge piping, electrical panels, and operational controls. Additional improvements included construction of a pump-to-waste swale and access infrastructure.

CITY OF CHINO, CENTRAL AVENUE AND DUPONT AVENUE WATERLINE REPLACEMENT PROJECT | This project consisted of two major waterline replacement efforts within the City of Chino. On Central Avenue, a 16-inch steel water main was replaced with an 18-inch PVC pipeline extending from Chino Avenue to C Street. The project also included replacement of an 8-inch steel line on D Street, from Central Avenue to the alley west of 6th Street, and tie-ins at multiple intersections and alleys. Line stops were required due to limited existing valving. The Dupont Avenue portion of the project involved replacing an existing 8-inch ductile iron pipe (DIP) waterline with a new 12-inch C900 PVC main from Alton Street to Gates Street. Scope included installation of new domestic water service connections, fire service laterals, and system tie-ins.

CITY OF CHINO, RUSSELL AVENUE WATER LINE REPLACEMENT PROJECT | This project involved the removal and replacement of an existing water main along Russell Avenue, from Walnut Avenue to Terry Avenue. The work included installation of approximately 700 linear feet of new 8-inch PVC C900 DR-14 water main, trench backfill, and roadway surface restoration. Key components included new fire hydrant assemblies, gate valves, tees with thrust blocks, and 1-inch domestic water service laterals connected to existing meters. The project also required lateral connections within 3 feet of the water main centerline, saw cutting and replacement of cross gutters, and abandonment of the existing water main and associated fire hydrants.

CITY OF CHINO, YORBA AVENUE AND EUCALYPTUS AVENUE SEWER MAIN REPLACEMENT PROJECT | This project involved the replacement of existing 10-inch and 15-inch vitrified clay pipe (VCP) sewer mains with upsized VCP or high-density polyethylene (HDPE) pipe using both trenchless and open-cut construction methods. The scope included steel casing installation across railroad property, temporary bypass pumping systems, and the replacement or rehabilitation of multiple sewer manholes. Additional work consisted of reconnecting existing sewer laterals, removing outdated manholes, and completing trench backfill and pipe bedding. Surface restoration included full-depth asphalt concrete pavement repairs, slurry sealing, crack sealing, and striping. The project also involved adjusting utility lines, restoring traffic detector loops, weed abatement, and implementing traffic control measures, including night work. Post-construction closed-circuit television (CCTV) inspections were required to verify alignment and system integrity.

CITY OF CHINO, WATER MAIN REPLACEMENT PROJECT, WASHINGTON AVE, LINCOLN AVE, MONTE VISTA AVE, & TELEPHONE AVE | This multi-location infrastructure improvement project involved the replacement of existing 8-inch waterlines along Washington Avenue, Lincoln Avenue, Monte Vista Avenue, and Telephone Avenue within the City of Chino.

The work included trench excavation, removal of outdated piping, and installation of new 8-inch PVC C900 water mains, gate valves, and appurtenances. Additional scope included pressure testing, chlorination, bacteriological testing, and system tie-ins to ensure safety and compliance with public health standards. Construction activities also required traffic control implementation, surface restoration, and coordination with residents and businesses to minimize service disruptions.

Carlos Gaytan’s deep understanding of water infrastructure construction, combined with his decades of hands-on field experience and D3 Water Distribution certification, makes him a trusted and capable Senior Construction Observer. His proven ability to support well equipping, treatment facility construction, pipeline installation, and regulatory compliance ensures that projects are delivered with precision, safety, and accountability. With a proactive communication style and meticulous documentation practices, Carlos brings exceptional value to complex utility and public works projects and is well-prepared to support the successful delivery of the Grand Well Site improvements for the City of San Jacinto.

Ed Nylund is a highly experienced Senior Construction Observer with over 34 years of hands-on expertise in public works inspection, utility construction, and field supervision throughout Southern California. Ed’s background spans a wide array of water and wastewater infrastructure, including potable and recycled water pipelines, sewer and storm drain systems, pump stations, reservoirs, and major utility coordination.

For more than 20 years, Ed served as the Lead Public Inspector for the City of Chino, where he oversaw daily inspection operations for capital improvement projects involving waterline and sewer main replacements, grading, encroachment permits, fiber optics, traffic signal systems, and ADA-compliant improvements. He regularly collaborated with City engineers and contractors to ensure construction met all applicable codes, safety regulations, and specifications.

Ed brings additional value through his leadership in inspector training. He served as the lead instructor for the Maintenance Superintendents Association’s (MSA) 12- week online Public Works Inspector Training Program in 2024, developed a 16-week Traffic Signal Inspection Training Program for the City of Chino in 2019, and delivered a tailored best practices session for the City of San Bernardino in 2025.

With certifications in Water Treatment (Grade 2), Water Distribution (Grade 3), Traffic Signal Inspection, and Field Supervision, Ed brings unmatched technical depth and communication skills to his observer role.

As Alternate Senior Construction Observer, Ed is prepared to step in seamlessly to maintain project continuity, review inspection documentation, coordinate field activity, and uphold the highest standards of quality and compliance on the Grand Well Site project.

He has served as Senior Construction Observer on the following representative projects:

ELSINORE VALLEY MUNICIPAL WATER DISTRICT, HIGHWAY 74 WATERLINE RELOCATION (NIGHT WORK) | This project was implemented to accommodate roadway widening improvements by Caltrans along State Route 74 in the City of Lake Elsinore. The scope involved the relocation and installation of approximately 2,400 linear feet of new 12-inch C900 PVC water main along the north side of Highway 74, spanning from Meadow Ridge Drive to Ardenwood Drive. Work included the installation of new mains, gate valves, fittings, fire hydrants, and appurtenances, as well as multiple service and system connections to the existing active potable water distribution network. Construction activities required extensive trench excavation, pipe bedding and backfill, hot tap installations, and execution of pressure testing and disinfection protocols in compliance with AWWA standards.

The project also involved the removal and abandonment of segments of the existing waterline infrastructure, requiring close coordination to sequence shutdowns and minimize service disruptions. Given the project’s location within an active Caltrans corridor, strict adherence to traffic control requirements and construction phasing was necessary to maintain public safety and minimize impacts to the traveling public. Additional responsibilities included utility coordination, trench restoration, and ensuring compliance with local, state, and agency-specific construction and safety standards.

CITY OF ENCINITAS, AIR VALVE AND BLOW OFF REPLACEMENT PROJECT, PHASE 1 | This citywide infrastructure upgrade project involved the removal and replacement of multiple aging air release (AR), air/vacuum (AV), and blow-off valve assemblies across various water system locations. The scope included installation of new 4-inch and 6-inch AV/AR and blow-off assemblies, along with related gate valves, fittings, couplings, thrust blocks, and associated appurtenances.

Each installation site was unique and required tailored construction approaches to meet existing site conditions and system configurations. The project also included the construction of new concrete and masonry retaining walls at several locations to provide structural support, site containment, and accessibility for the upgraded assemblies. Work required precise shutdown coordination, pressure zone isolation, utility locating, trench excavation and backfill, and restoration of impacted surfaces. The improvements enhanced the operational reliability of the City’s potable water distribution system by replacing aging infrastructure with modern, maintainable components, improving system resiliency, and ensuring compliance with updated standards for air release and drainage. All work was performed in active rights-of-way and required careful traffic control and coordination with City staff and residents.

Ed Nylund, QSP, CWSSWI
Senior Construction Observer (Alternate)

EDUCATION
» California State University,
Sacramento - Industrial Waste
Pretreatment Facility Inspection
» Chaffey Community College -
Business Management
» Maintenance Superintendents
Association -
Basic Supervision in PW
» University of Southern
California - Backflow Assembly
Testing
» San Bernardino Valley
College - Water Supply
Engineering

LICENSES & REGISTRATION
» Water Treatment Operator –
Grade 2 | Certificate No. 17150
» Water Distribution Operator –
Grade 3 | Certificate No. 4903
» QSP Certificate No. 26356
» Traffic Signal Senior Field
Technician III Certificate No.
97687
» Traffic Signal Inspector
Certificate No. SI97687
CITY OF CORONA, LESTER POST DISINFECTION STATION PROJECT | This project involves critical upgrades to the City of Corona’s Lester Water Treatment Plant to enhance operational flexibility and treatment efficiency. The work relocates the chlorine and ammonia injection point onto the 30-inch filter effluent line between Filters 5 and 6, allowing them to operate independently. Improvements include a new open-top cast-in-place concrete vault housing a magnetic flow meter, inline static mixer, and chemical injection points. The project also installs new steel piping, isolation valves, SCADA connections, and associated site restoration. Designed to be completed during the plant’s winter shutdown, the project supports improved disinfection control and long-term system performance.

CITY OF CORONA, DESALTER SURGE ANTICIPATOR IMPROVEMENT PROJECT | The City of Corona’s Desalter Surge Anticipator Improvement Project was designed to enhance the operational safety and efficiency of the city's potable water system by upgrading its surge management infrastructure. The project scope includes structural concrete demolition and repair, pavement restoration, and installation of new mechanical and electrical components to improve surge control at the desalter facility. Key mechanical improvements include the installation of stainless-steel piping systems, rupture disc assemblies for pressure management, and upgraded butterfly valve and actuator assemblies for both the surge relief discharge and permeate dump valve systems. Electrical work involves installation of new NEMA-rated electrical control panels and junction boxes to support real-time monitoring and system automation. All work is to be performed within a 180- calendar-day schedule, with construction activities occurring in a critical operational facility. The upgrades will significantly improve the facility’s ability to manage hydraulic transients, reduce equipment stress, and enhance the overall reliability of water delivery to the community.

CITY OF CORONA, WATER RECLAMATION FACILITY 1 CHEMICAL INJECTION FLASH MIXER AND STATIC MIXER INSTALLATION PROJECT | The City of Corona’s Water Reclamation Facility 1 (WRF1) Chemical Injection Flash Mixer and Static Mixer Installation Project is a key infrastructure upgrade aimed at enhancing the City’s water treatment capabilities and operational efficiency. The project includes the demolition and reconstruction of the existing Flash Mixer used for chemical injection and the installation of a new Static Mixer for influent flow to the Chlorine Contact Basin. The scope encompasses mechanical, structural, electrical, civil site, utility, and process work, including modifications to support chemical dosing, mixing, and flow control. Major improvements involve replacing aging mixer components, integrating new process piping and equipment, constructing reinforced structural elements, and implementing upgraded electrical panels and control systems for automation and monitoring. Inspections are required on an as-needed basis to ensure strict compliance with project plans, technical specifications, and regulatory requirements. This includes oversight of critical items such as subgrade preparation, formwork, mechanical assembly, electrical integration, pressure testing, and verification of process flow functionality.

CITY OF RIVERSIDE, 36” BUTTERFLY VALVE REPLACEMENT | This critical water infrastructure project involved the de-energizing and dewatering of an existing 54-inch domestic water transmission main to facilitate the removal and replacement of key valve components. The scope of work included demolition and removal of a 20-foot section of existing cement mortar–lined and coated (CMLC) steel water main and its corresponding valve assembly.

New construction involved installation of a 20-foot segment of 54-inch CMLC water main, including a new 36-inch butterfly valve assembly, 8-inch bypass line with valve, cathodic protection systems, and a new testing station. Final activities included pipeline and appurtenance pressure testing, chlorination, and disinfection in accordance with applicable AWWA standards. The work was conducted within an active urban corridor and required careful planning to minimize service disruption and maintain system integrity throughout the shutdown and commissioning process.

CITY OF RIVERSIDE, LINCOLN AVENUE TECHITE PIPE REPLACEMENTPROJECT, PHASE I | The project involved constructing approximately 3,400 linear feet of 54-inch cement mortar-lined steel pipe and related appurtenances along Lincoln Avenue in the City of Riverside. This included trenching in the public right-of-way, welding steel pipe, and installing various infrastructure elements. The excavation varied from 4 to 18 feet deep and affected local residential and arterial streets. The scope covered traffic control, including signalized intersections and striping, as well as asphalt paving and concrete work. Daily construction reports were produced using the City’s construction management software.

CITY OF CHINO | LEAD PUBLIC INSPECTOR | As Lead Public Inspector for the City of Chino, Ed Nylund directed the daily activities of the Public Works Inspection team for more than two decades, serving as the primary authority for field oversight, coordination, and technical mentorship. Ed supervised multiple inspectors across a wide range of capital improvement projects and ensured compliance with municipal codes, construction standards, and regulatory requirements.

His leadership responsibilities included assigning daily inspection tasks, providing hands-on training and technical guidance, and reviewing inspection documentation for accuracy and completeness. Ed coordinated inspections for projects involving roadway reconstruction and widening, domestic and recycled waterline installation, sewer and storm drain improvements, traffic signal and fiber optic systems, grading, utility relocations, and park and civic facility upgrades. He acted as the main liaison between contractors, field staff, and City engineers—facilitating clear communication, resolving field issues in real time, and maintaining project momentum. Ed also reviewed shop drawings and submittals, conducted bi-weekly progress meetings, and ensured inspectors upheld rigorous standards of safety, documentation, and compliance. Throughout the project lifecycle, Ed managed final inspections, punch list verification, ADA accessibility reviews, and closeout procedures to guarantee alignment with agency specifications and regulatory expectations. His leadership and technical oversight were instrumental in delivering high-quality, on-time public infrastructure improvements across the City.

MNS MNS MNS MNS MNS MNS Z&K (Sub)
Joe Pope Patrick
Hanify Aaron Singer Sandra Lee Estella
Wells
Chris
Cooper
Carlos
Gaytan
Geotech.

Inspector
Concrete /
Specialty
Project Fee - T&M Not -to-Exceed $336.00 $277.00 $220.00 $158.00 $152.00 $200.00 $193.20 $163.30 $174.80 Scope of Services
Task 1 - Project Coordination 4 22 120 $ 33,838.00
Task 2 - Document Control 44 260 $ 69,388.00
Task 3 - Materials Testing (Geotechnical & Concrete) 160 80 $ 40,112.00 $ 22,265.00 Task 4 - Meetings 20 235 $ 57,240.00 $ 1,500.00
Task 5 - Schedule Reviews 38 $ 8,360.00
Task 6 - Construction Observation 1200 $ 231,840.00 $ 15,000.00 Task 7 - Site Maintenance & Best Management Practices 8 $ 1,760.00 Task 8 - Reports 77 $ 16,940.00
Task 9 - Project Cost Control & Cert.Payroll (Labor Compliance) 36 205 48 $ 47,606.00 $ 1,500.00 Task 10 - Change Order and Claims Review 32 $ 7,040.00
Task 11 - Start-up Coordination, Observation, and System Doc. 4 60 $ 14,308.00 $ 1,500.00 Task 12 - Notice of Completion 1 3 $ 937.00
Task 13 - Project Close-out 2 20 70 $ 21,612.00
TOTAL ESTIMATED HOURS 6 111 939 205 48 0 1200 160 80
BUDGET $ 2,016.00 $ 30,747.00 $ 206,580.00 $ 32,390.00 $ 7,296.00 $ 0.00 $ 231,840.00 $ 26,128.00 $ 13,984.00 $ 279,029.00 $ 271,952.00 $ 19,500.00 $ 22,265.00 Key Notes (Refer to Proposal Scope for additional Assumptions not referenced here):
$ 1,760.00
$ 49,106.00
$ 7,040.00
$ 15,808.00
$ 937.00
$ 21,612.00

9. Submittals: MNS assumes review of up to seventy-one (71) total submittals, including resubmittals, based on the contractor’s schedule. Our review will be limited to contract conformance only. We assume all technical reviews will be performed by the City or Engineer of Record and are therefore not included in our fee. A 10-working-day turnaround is assumed, excluding City or EOR review time if required.

8. Allocation of Funding: MNS understands that the entire contract is a not-to-exceed agreement. We acknowledge that the project may conclude before the full budget is utilized; however, no work will continue once the authorized funding is fully expended. Additionally, we understand that funds may be reallocated between tasks, including subconsultant budgets and direct costs, at MNS’s discretion to best support the successful delivery of the project.

10.RFIs: We assume no more than twenty (20) total RFIs shall be submitted by the contractor. MNS assumes no technical review to be necessary and that review will be solely in conformance with the contract requirements or EOR/City issued changes - thus no deviations, substitutions, or ”or-equals” will be reviewed. Time for review is assumed to be five (5) workings days and does not include City or EOR review time should it be necessary $ 592,746.00
$ 246,840.00
2749

1. General Durations and Start: Total Duration based on a 18 month (August 2025, to January 2027) construction period from CM Consultant notice-to-proceed - Anticipated to be provided on August 5th, 2025. Labor Compliance will require efforts within February 2027 for close out.

2. Overtime and Night work: Cost estimate assumes no overtime (OT) or night work. Any OT would be x1.5 or that required by governing laws, and such OT will be at the availability of the staff requested. Requests for night work will be subject to the availability of personnel, will require no less than (5) Working day Notice, and will be charged at premium time of no less than 1.5x the standard rate and that required by law. Some efforts may require the assessment of a rate of 2x the standard rate as required by Law.

5. Procore: Procore Licensing cost detailed within the optional services, includes training that the City is welcome to join virtually. It is understood that the Contractor also possesses a License that could be shared to the City and CM Consultant.

18. Preconstruction Meeting: MNS Assumes (1) such 1-hr Virtual Recorded Meeting attended by the Construction Manager, Technical Support, Labor Compliance Officer. $ 16,940.00

17. Internal Kick-off Meeting: MNS Assumes (1) such 1-hr Virtual Recorded Meeting attended by the Construction Manager and Technical Support

7. Construction Observation: MNS will provide half-time observation (up to 4 hours per day, portal-to-portal) from Pacific Hydrotechs Mobilization (November 7, 2025) through Project Closeout (January 21, 2027), covering 300 working days. Site visits canceled with less than one working day's notice or concluded without inspection will be billed at a 4-hour minimum. Repeated cancellations or extended periods of inactivity may result in staff reallocation.

SubConst.

Field/ODCs
(Includes 15%
O&P)
SubConst.

Labor
Extension
(Includes
15% O&P) TOTAL COST
MNS
Field/ODCs
Construction Management Services
Construction of Grand Treatment Plant and Equipping of the Grand Well
City of San Jacinto
Project Team & Rate
MNS
Labor
Estimated Hours Extension
Landmark (Sub)
$ 33,838.00
$ 69,388.00
$ 62,377.00
$ 58,740.00
$ 8,360.00

4. Overhead and Profit: Sub-consultant, ODC, and Software services (I.E. Procore) mark-up is 15%.

3. DIR Prevailing Wage Rate: Construction Observer/Geotechnical/ Specialty Inspector's rate is subject to adjustment if DIR Prevailing Wage rates are updated.

6. Landmark Geotechnical and Specialty Inspection: Specialty inspections beyond Geotechnical Observation and Testing, and Concrete/Rebar Observation, Collection, and Testing are not included per the clarifications detailed within the RFP. However, Landmark is fully fit to provide such specialty inspections as desired by the City. Scope included within our scope and fee include: (1) Rough grading observation and testing, (2) Compaction testing of trenches, C&G, subgrade and basegrade, driveway approaches and sidewalk, (3) Concrete inspection, including onsite inspection of the reinforcement, and collection and testing of concrete cylinders, (4) Three Maximum Density/Optimum Moisture tests will be performed, (5) twenty-five concrete cylinders are assumed to be collected and tested. Price reflects 20 Half-time, and 10 Full-time Site visits by a Soil Technician, and 10 Full-time ICC Concrete Inspections. Visits to site are subject to a 2hr surcharge for the respective staff assigned. 2hr minimum will be charged for all field work and thereafter in 4hrs increments. No night work is assumed. Requests for night work will be subject to the availability of personnel, require no less than (5) Working day Notice, and will be charged at premium time of no less than 1.5x the standard rate and that required by law.

11. Progress Payments: We assume no more than (18) Complete Progress Payment Packages (Progress Payment Estimate, All Unconditional and conditional Waivers) submissions and subsequent reviews with no resubmissions from the contractor.

12. Contractor Verficiation: It is assumed that the City has conducted and filed the Contractor Verifications at the time of project award (pre-construction phase). If the City wishes for MNS to conduct and file the Contractor Verification files, MNS can perform this service for additional fee.

13. Public Request: If the City receives a Request for Public Information, it is assumed that the City will prepare the response. If the City wishes for MNS to prepare the response, MNS can perform this service for additional fee.

14. Change Orders: MNS assumes coordination and review of up to four (4) contractor-provided potential change orders, and issuance of up to two (2) contract change orders upon City authorization, with no requested revisions.

15. Close Out Report: One Project Close-out report will be provided to the city in electronic format via Procore.

16. Weekly Progress Meetings: MNS assumes up to 75 one-hour virtual progress meetings. These meetings will be recorded and attended by the Construction Manager. Technical support staff is assumed to participate in no more than 16 of these meetings. Additionally, MNS assumes up to 4 one-hour onsite meetings, to be held during the Observer’s scheduled half-time shift. The Observer will attend meetings the first week of Mobilization.

MNS MNS MNS MNS MNS MNS Z&K (Sub)*
Joe Pope Patrick
Hanify Aaron Singer Sandra Lee Estrella Wells
Chris
Cooper
Carlos
Gaytan
Geotech.

Inspector
Concrete /
Specialty
Project Optional Fee - T&M Not -to-Exceed $336.00 $277.00 $220.00 $158.00 $152.00 $200.00 $193.20 $163.30 $174.80 Scope of Services
Task 2 - Document Control - Procore Licensing $ 34,120.50 Task 6 - Construction Observation - Tank Coating (Shop) 48 $ 9,600.00 Task 6 - Construction Observation - Tank Coating (Field) 248 $ 49,600.00 $ 15,000.00 Task 6 - Construction Observation - Fulltime Observation (Add'l Hrs) 904 $ 174,652.80 $ 26,197.92 TOTAL ESTIMATED HOURS 0 0 0 0 0 296 904 0 0
OPTIONAL BUDGET (Does not include Scope Fee) $ 0.00 $ 0.00 $ 0.00 $ 0.00 $ 0.00 $ 59,200.00 $ 174,652.80 $ 0.00 $ 0.00 $ 233,852.80 $ 26,197.92 $ 15,000.00 $ 34,120.50 $ 200,850.72
SubConst.

Labor
Extension
(Includes
15% O&P)
MNS
Field/ODCs
$ 64,600.00
$ 9,600.00
SubConst.

Field/ODCs
(Includes 15%

O&P) TOTAL COST
Project Team & Rate
MNS
Labor
Extension
1200
$ 309,171.22
Optional Value Added Services (NOT INCLUDED WITHIN FEE TOTAL ) Construction Management Services
Construction of Grand Treatment Plant
and Equipping of the Grand Well
City of San Jacinto
Landmark (Sub)*
Estimated Hours
$ 34,120.50