Reimbursement Agreement Between City of San Jacinto and Eastern Municipal Water District for Water and Sewer Relocations for San Jacinto Avenue Safety Improvements, CIP 21-005 01375.0006/998637.7
REIMBURSEMENT AGREEMENT
BETWEEN
CITY OF SAN JACINTO, CALIFORNIA
AND
EASTERN MUNICIPAL WATER DISTRICT
FOR
WATER AND SEWER RELOCATIONS FOR SAN JACINTO AVENUE SAFETY IMPROVEMENTS, CIP 21-005
THIS AGREEMENT is made and entered into as of , between the CITY OF SAN JACINTO, California, a municipal corporation, hereinafter referred to as “CITY" and EASTERN MUNICIPAL WATER DISTRICT, a municipal water district organized and operating pursuant to the Municipal Water District Law of 1911 as set forth in the California Water Code, hereinafter referred to as “EMWD.” In consideration of the mutual promises and covenants contained herein, the parties hereto mutually agree as follows:
Section I. Purpose. The purpose of this Agreement is to establish reimbursement to CITY by EMWD for the cost of the construction and relocations of certain water and sewer improvements as shown on the attached plans which are made part of this Agreement as Attachment “A", in conjunction with the improvement of the San Jacinto Avenue Improvement Project, CIP 21-005, hereinafter referred to as “PROJECT". Existing water and sewer improvements owned by EMWD must be relocated as part of the PROJECT. Certain facilities that need to be relocated are situated within the city's right-of-way, while others are located outside of it. Pursuant to this Agreement, EMWD agrees to pay for the relocation of the water facilities that are located in the CITY’s right-ofway and are related to the PROJECT. In addition, the City will relocate other facilities of certain water and sewer improvements as shown on the attached plans which are made part of this Agreement as Attachment “B"; the City agrees to fully pay for the relocation of the water and sewer facilities that are currently located outside City's right- of-way.
Section II. Bid Items. EMWD shall reimburse CITY one hundred percent (100%) of the costs (hereinafter referred to as “REIMBURSEMENTS"), for the construction and relocation of certain water improvements within the PROJECT area as detailed in the tables on the next page and shown on Attachment A. The costs for the REIMBURSEMENT to CITY by EMWD shall include those water items as shown on the attached plans in Attachment “A” and as stated on the Bid Sheet, which are made a part of this Agreement. The estimated costs for the bid items on the Bid Sheet are provided below based on the engineer’s estimate for the PROJECT. EMWD shall reimburse the City using the actual bid prices plus the cost of any EMWD approved change order(s). The City is responsible for the adjustment and relocation of certain EMWD facilities within the PROJECT area as they fall within EMWD’s existing easements. The costs shall include those water and sewer items as shown on the attached plans in Attachment “B” and as stated on the Bid Sheet, which are made a part of this Agreement. The estimated costs for the bid items on the Bid Sheet are provided below based on the engineer’s estimate for the PROJECT.
Reimbursement Agreement Between City of San Jacinto and Eastern Municipal Water District for Water and Sewer Relocations for San Jacinto Avenue Safety Improvements, CIP 21-005 01375.0006/998637.7
TOTAL ESTIMATED PROJECT BID ITEMS FROM ATTACHMENT “A”
(EMWD’s RESPONSIBILITY)
No. Item
Estimated
Quantity
Estimated
Unit Cost
Estimated Ext
Amount
Existing water meter to be abandoned 1 EA $5,000.00 $5,000.00 14 Water valve covers to be adjusted to grade
per EMWD standards SB-53, SB-61 & B-668 4 EA $1,500.00 $6,000.00 20 Existing water meter to be relocated behind
sidewalk and adjusted to grade per EMWD
standards 3 EA $5,000.00 $15,000.00
Mobilization, Insurance, and Schedule of Values $5,000.00 Total Estimated EMWD Reimbursements to City: $31,000.00 TOTAL ESTIMATED PROJECT BID ITEMS FROM ATTACHMENT "B"
(CITY'S RESPONSIBILITY)
Estimated
Quantity
Estimated
Unit Cost
Estimated
No. Item Ext Amount
5 Salvage and relocate back flow and cage
per EMWD standards 1 LS $2,000.00 $2,000.00
14 Water valve covers to be adjusted to grade
per EMWD standards SB-53, SB-61 & B668
2 EA $1,500.00 $3,000.00
14 Sewer MH to be adjusted to grade per
EMWD standards SB-53, SB-61 & B-668 2 EA $2,500.00 $5,000.00 20 Existing water meter to be relocated
behind sidewalk and adjusted to grade per
EMWD standards
2 EA $5,000.00 $10,000.00
30 Remove and replace existing 8” sewer
cleanout. Install new composite assembly
cleanout frame and cover with locking
system per specifications and as approved
by EMWD
1 EA $2,500.00 $2,500.00
Subtotal $22,500.00
Mobilization, Insurance and Schedule of
Values $16,000.00
Contingency (10% of Subtotal) $2,250.00
Total City Expenses: $40,750.00
Section III. Construction and Costs.
a. Bidding. Costs for the construction are based upon the construction bids that will be received for the PROJECT for the Bid Items referenced in Section II (“Bid Items”) as shown on the Bid Sheet for the PROJECT. CITY will evaluate and analyze all bids received and select the lowest
Reimbursement Agreement Between City of San Jacinto and Eastern Municipal Water District for Water and Sewer Relocations for San Jacinto Avenue Safety Improvements, CIP 21-005 01375.0006/998637.7
responsible bidder for the PROJECT (hereinafter referred to as “CONTRACTOR”). Per EMWD requirements the CITY agrees that the bid package will require the CONTRACTOR who will perform work on the water items have either an “A" or “C34" Contractor’s License. b. EMWD Right to Perform. To provide EMWD the option to perform the work identified at Section II as work that is EMWD’s responsibility, the CITY’s construction bid package shall identify EMWD’s Bid Items as Additive Bid Items. Upon receipt of the bids and determination of the lowest responsive and responsible bidder for the PROJECT, the CITY shall notify EMWD of its identified portion of the construction costs for the Bid Items. At that time EMWD may elect to construct the Bid Items itself to the same specifications as described in the bid specifications. If EMWD elects to perform the Bid Items, EMWD shall bear all costs associated with that work and the CITY shall not include said Bid Items in the contract with the CONTRACTOR. EMWD shall be given a “construction window" inside the PROJECT traffic control to complete the water relocations and adjustments. Moreover, EMWD shall bear all costs associated with the water relocations and adjustments, included but not limited to, delay to the CITY'S CONTRACTOR or utility coordination efforts needed as a result of having multiple contractors on site. EMWD shall provide written notice to the City Engineer of its determination to perform the Bid Items within fourteen (14) calendar days from the date of receipt of the ClTY’s identification of its lowest responsive and responsible bidder or EMWD waives any right to construct the Bid Items.
c. Payment. EMWD shall maintain a contingency with an amount equal to ten percent (10%) of the total estimated costs of construction or relocation of the water and sewer improvements to account for unforeseen changes to the PROJECT. The CITY shall obtain written approval from EMWD prior to the approval of any change orders associated with the installation of the improvements EMWD is financially responsible for and authorizing the CONTRACTOR to proceed unless failure to act immediately may affect public safety. The cost of any delay in the work due to the delayed action of EMWD in connection with PROJECT construction shall be borne by EMWD. EMWD shall respond to any PROJECT change orders within fourteen (14) calendar days.
CITY shall make payment to CONTRACTOR for all work performed. Actual costs shall be identified and billed to EMWD for payment on the following basis:
The CITY shall invoice EMWD using progress payments or upon completion of the PROJECT, at the discretion of the CITY, for all Bid Items that are the financial responsibility of EMWD. EMWD shall remit payment to the city within thirty (30) days of receipt of the approved invoice.
Section IV. Plans, Permits and Contacts.
a. Plans and Specifications. EMWD acknowledges that it has reviewed and approved all plans and specifications for the construction and relocation of the water and sewer improvements as shown on the attached plans and the estimated bid amounts are reasonable. b. CEQA. The CITY shall be responsible for obtaining any and all environmental permits and approvals as may be necessary for the PROJECT including, but not limited to, compliance with requirements imposed under the California Environmental Quality Act (“CEQA”) as may be applicable.
c. Agreement Management. Management and administration of the terms expressed herein shall be performed by CITY for the PROJECT. CITY designates Mr. Stuart McKibbin, City Engineer, as the contact for CITY in regard to this Agreement. EMWD designates Mr. Armando Arroyo, Director of Development Services, as the contact for EMWD to facilitate the
Reimbursement Agreement Between City of San Jacinto and Eastern Municipal Water District for Water and Sewer Relocations for San Jacinto Avenue Safety Improvements, CIP 21-005 01375.0006/998637.7
REIMBURSEMENTS identified herein.
Section V. Inspection. EMWD shall provide and pay for inspection of all new and relocated facilities shown on Attachment “A" and described in Section II of this Agreement. The CITY shall be responsible for EMWD’s inspection costs for those Bid Items shown on Attachment “B" as described in Section II of this Agreement. The CITY shall tender an inspection deposit to EMWD equal to 8% of the estimated construction cost for the Bid Items in Attachment “B” prior to holding a pre-construction meeting. EMWD shall reconcile the inspection deposit at the completion of construction.
EMWD shall be responsible to inspect the construction of all facilities which will be owned by EMWD and the performance of the involved work by CITY’s CONTRACTOR for compliance with the approved construction plans and specifications and/or for EMWD’s own work if such work has been undertaken by EMWD pursuant to Section III(b). The City shall pay EMWD for all inspection costs associated with the construction and relocation of the water and sewer improvements within EMWD’s existing easement within the PROJECT area for the water and sewer items shown on the attached plans in Attachment “B". EMWD is responsible for all inspection costs associated with the construction and relocation of the water improvements on San Jacinto Avenue within the PROJECT area. The costs shall include those water items as shown on the attached plans in Attachment “A". EMWD’s inspection personnel shall have the authority to enforce EMWD’s construction plans and specifications for the PROJECT, which authority shall include the authority to require that any and all unacceptable materials, workmanship, and/or installation be replaced, repaired, or corrected by ClTY’s CONTRACTOR without cost to EMWD.
If EMWD undertakes the performance of the PROJECT’s Bid items shown in Section II under Total Estimated Project Bid Items From Attachment A, and if, through the failure of EMWD to provide access and control of the construction site within the time allotted by the Project Specifications, the CITY’s CONTRACTOR sustains loss which could not have been avoided by the judicious handling of forces and/or equipment, EMWD shall be liable for that part of the CITY’s CONTRACTOR's actual loss that was unavoidable in accordance with State of California, Department of Transportation Standard Specifications section 8-1.09, RIGHT-OF-WAY DELAYS.
Section VI. Insurance and Indemnity. For the period during which CITY or its CONTRACTOR(s) controls the job site, CITY will provide, or cause to be provided, for the entire period of construction, a policy of workers’ compensation insurance and comprehensive general liability insurance with coverage broad enough to include the contractual obligation it may have under the construction contract and having a combined single limit of liability in the amount of $2,000,000 per occurrence with a $4,000,000 aggregate covering EMWD’s officers, employees, and agents as additional insureds. Said policy of insurance shall name EMWD as an Endorsed Additional Insured issued by the Insurance Carrier (EMWD does not accept blanket coverage).
Commercial Auto Liability Insurance shall be provided with a combined single limit of liability in the amount of $1,000,000 per occurrence.
If EMWD undertakes to perform the PROJECT’s Bid Items shown in Section II under Total Estimated Project Bid Items from Attachment “A" pursuant to Section III(b), EMWD, prior to commencement of the work and for the period during which EMWD operates at the job site, will provide, or cause to be provided, for the entire period of construction, a policy of workers’ compensation insurance and comprehensive general liability insurance with coverage broad enough to include the contractual obligation it may have under the construction contract and having a combined single limit of liability in the amount of $1,000,000 per occurrence with a $5,000,000 aggregate covering the CITY’s officials, officers, employees, and agents as additional insureds.
Reimbursement Agreement Between City of San Jacinto and Eastern Municipal Water District for Water and Sewer Relocations for San Jacinto Avenue Safety Improvements, CIP 21-005 01375.0006/998637.7
EMWD and the CITY each hereby agree to indemnify, defend, and hold harmless the other party and their respective directors, officials, officers, employees and agents from and against any claims, actions, damages and liabilities arising out of or in any manner connected with any act or omission of such indemnifying party, performed in connection with such party’s duties and obligations hereunder. This clause shall survive the termination of this agreement.
Section VII. Notices. All notices under this Agreement shall be sent as follows:
EMWD: EASTERN MUNICIPAL WATER DISTRICT
P.O. Box 8300
Perris, CA 92572
Attn: Armando Arroyo, Director of Development Services
CITY: City of San Jacinto
1221 S San Jacinto Ave
San Jacinto, CA 92583
Attn: Stuart McKibbin, City Engineer
Either party may change its address for notices by notifying the other party. All notices given at the most recent address specified shall be deemed to have been properly given.
Section VIII. Amendment. This Agreement may only be amended in writing upon the mutual written consent of both parties.
Section IX. Laws, Venue and Attorney’s Fees. This Agreement shall be interpreted in accordance with the laws of the State of California. If any action is brought to interpret or enforce any term of this Agreement, the action shall be brought in a state of federal court situated in the County of Riverside, State of California. In the event of any such litigation between the Parties, the prevailing Party shall be entitled to recover all reasonable costs incurred, including reasonable attorney’s fees, as determined by the court.
Section X. Interpretation and Headings. This Agreement shall not to be construed against the Party preparing it but shall be construed as if both Parties prepared it. Headings to paragraph/subparagraphs of this Agreement are for convenience purposes only and are not part of this Agreement.
Section XI. Provisions Binding. This Agreement and the Exhibits attached hereto are binding on the heirs, representatives, successors, and assigns of the Parties of this Agreement.
Section XIII. Authority to Sign Agreement. The undersigned individuals hereby warrant and represent that they each have full legal authority to sign this Agreement and bind the
Reimbursement Agreement Between City of San Jacinto and Eastern Municipal Water District for Water and Sewer Relocations for San Jacinto Avenue Safety Improvements, CIP 21-005 01375.0006/998637.7
Parties hereto.
This Agreement is effective as of the date set forth above.
EMWD: EASTERN MUNICIPAL WATER DISTRICT
By: _________________________________
Joe Mouawad, General Manager
By: _________________________________
Sheila Zelaya, Board Secretary
APPROVED AS TO FORM:
Steve O’Neill, General Counsel for EMWD
CITY: CITY OF SAN JACINTO
By: _________________________________
Rob Johnson, City Manager
ATTEST:
Julia Espinoza, City Clerk
APPROVED AS TO FORM:
Craig Hayes, City Attorney
Reimbursement Agreement Between City of San Jacinto and Eastern Municipal Water District for Water and Sewer Relocations for San Jacinto Avenue Safety Improvements, CIP 21-005 01375.0006/998637.7 Attachment “A”
City of San Jacinto Improvement Plans for San Jacinto Avenue Safety Improvements, CIP 21-005
PREPARED BY: CITY OF SAN JACINTO SEAL APPROVED BY: CITY OF SAN JACINTO BENCHMARK SJ-457 Civil Engineering Planning Project Management Internet: WWW.interwestgrp.com Interwest Consulting Group INTERWEST A SAFEbuilt COMPANY BID SET SAN JACINTO AVENUE B CK L NA FESSIOM L NA FESSIO TR DER P S R DER P OE. I V IL I NR FO CALI I V IL I NR FO CALI R TS IS GE E AT R TS IS GE E AT F NO. 44553 OC TE N AU R T R A E IN GNE R A E IN GNE E B C I I 1221 S. San Jacinto Avenue San Jacinto, CA 92583 (951) 654-3592 DIG ALERT 1 TITLE SHEET SAN JACINTO AVENUE SAFETY IMPROVEMENTS (SJ-457)
CITY OF SAN JACINTO, CALIFORNIA
POTTER RD.
SANDERSON AVENUE DE ANZA DR. RAMONA BLVD.
SAN JACINTO AVE. IDYLLWILD DR. COTTONWOOD AVE. ESPLANADE AVE.
PALM AVE.
LYON AVE.
STATE ST.
SANTA FE
KIRBY ST. SEVENTH ST. YOUNG ST.
MISTLETOE AVE. MAIN ST. AVENUE ESPLANADE
ALESSANDRO AVE. RAMONA EXPY. FIRST ST. CHASE ST.
SOBOBA RD.
JORDAN AVE.
CAMINO
LOS BANOS ARTESIAN ST. TIGER LN. TAHQUITZ AVE.
ESTUDILLO AVE.
PICO AVE. 5TH ST. 6TH ST. SEVENTH ST. RAMONAASH ST. MENLO AVE. COMMONWEALTH AVE. EATON AVE. FRUITVALE AVE. OAKLAND AVE. DEVONSHIRE AVE. FLORIDA AVE.
SAN JACINTO AVE.
SANDERSON AVENUE
HEWITT ST. COMMONWEALTH AVE. PARK AVE.
PARK AVE.
COLUMBIA ST. HIGHWAY 74
HIGHWAY 79
LYON AVE.
KIRBY ST.
STATE ST. DEVONSHIRE AVE. MIDWAY ST. OAKWOOD ST.
SANTA FE
EXPY. SHAVER ST. EVANS ST. ACACIA AVE.
GIRARD ST.
YALE ST.
CORNELL ST.
DARTMOUTH ST. CITY OF SAN JACINTO MAIN ST. WATEKA ST. MONTE VISTA PROJECT SITE LOCATION MAP MENLO AVENUE TO 1200' NORTH OF MIDWAY STREET UNDERGROUND STRUCTURES PRIVATE ENGINEERING NOTE: DESCRIPTION SHEET # SHEET INDEX TITLE SHEET 12 4 - 7 INDEX MAP & DETAILS X-SECTIONS 8 - 11 STREET PLAN & PROFILE CMU WALL TYPICAL SECTION & DETAILS 3 BENCHMARK: NOT TO SCALE PROJECT SITE ELSINORE LAKE74 74 60 79 79 79 60 215 215 15 10 15 HEMET MORENO VALLEY RIVERSIDE BEAUMONT 74 PERRIS 74 79 SAN JACINTO NOT TO SCALE VICINITY MAP 9+00 10+00 11+00 12+00 13+00 14+00 15+00 16+00 17+00 18+00 19+00 20+00 21+00 22+00 23+00 24+00 25+00 26+00 27+00 28+00 29+00 29+80.65 30+00 31+00 32+00 33+00 34+00 35+00 36+00 37+00 38+00 39+00 40+00 41+00 42+00 PREPARED BY: CITY OF SAN JACINTO SEAL APPROVED BY: CITY OF SAN JACINTO BENCHMARK SJ-457 Civil Engineering Planning Project Management Internet: WWW.interwestgrp.com Interwest Consulting Group BID SET SAN JACINTO AVENUE B CK L NA FESSIOM L NA FESSIO TR DER P S R DER P OE. I V IL I NR FO CALI I V IL I NR FO CALI R TS IS GE E AT R TS IS GE E AT F NO. 44553 OC TE N AU R T R A E IN GNE R A E IN GNE E B C I DIG ALERT I 2 RETAINING WALL DETAILS SHEET 4 SHEET 5 SHEET 6 SHEET 7 SAN JACINTO AVENUE MENLO AVE. MIDWAY ST. INDEX MAP MIDWAY ST. SAN JACINTO AVENUE SAN JACINTO AVENUE APN 439-170-022 APN 439-140-007 APN 439-130-003 CEMETERY SAN JACINTO VALLEY APN 439-170-014 17+00 18+00 19+00 20+00 21+00 22+00 23+00 24+00 25+00 26+00 SAN JACINTO AVE. RESTAURANT EMILIO'S CEMETERY SAN JACINTO VALLEY VACANT CENTER BUFFALO SHEET 2 SEE DETAIL "E" 439-170-014 439-170-022 439-140-010 439-140-009 VACANT 439-140-008 PREPARED BY: CITY OF SAN JACINTO SEAL APPROVED BY: CITY OF SAN JACINTO BENCHMARK SJ-457 Civil Engineering Planning Project Management Internet: WWW.interwestgrp.com Interwest Consulting Group BID SET SAN JACINTO AVENUE B CK L NA FESSIOM L NA FESSIO TR DER P S R DER P OE. I V IL I NR FO CALI I V IL I NR FO CALI R TS IS GE E AT R TS IS GE E AT F NO. 44553 OC TE N AU R T R A E IN GNE R A E IN GNE E B C I DIG ALERT I 5 STREET PLAN AND PROFILE
27+00 28+00 29+00 29+80.65 30+00 31+00 32+00 33+00 34+00 35+00 36+00 SAN JACINTO AVE. HEMACINTO MOBILE PARK VACANT 11+00 439-130-003 439-130-002 VACANT 439-140-008 VACANT 439-140-007 PREPARED BY: CITY OF SAN JACINTO SEAL APPROVED BY: CITY OF SAN JACINTO BENCHMARK SJ-457 Civil Engineering Planning Project Management Internet: WWW.interwestgrp.com Interwest Consulting Group BID SET SAN JACINTO AVENUE B CK L NA FESSIOM L NA FESSIO TR DER P S R DER P OE. I V IL I NR FO CALI I V IL I NR FO CALI R TS IS GE E AT R TS IS GE E AT F NO. 44553 OC TE N AU R T R A E IN GNE R A E IN GNE E B C I DIG ALERT I 6 STREET PLAN AND PROFILE MIDWAY STREET SEE DETAIL "G" ON SHEET 2 37+00 38+00 39+00 40+00 41+00 42+00
BUS STOP SAN JACINTO AVE. VACANT 439-120-049 VACANT 439-120-047 PREPARED BY: CITY OF SAN JACINTO SEAL APPROVED BY: CITY OF SAN JACINTO BENCHMARK SJ-457 Civil Engineering Planning Project Management Internet: WWW.interwestgrp.com Interwest Consulting Group BID SET SAN JACINTO AVENUE B CK L NA FESSIOM L NA FESSIO TR DER P S R DER P OE. I V IL I NR FO CALI I V IL I NR FO CALI R TS IS GE E AT R TS IS GE E AT F NO. 44553 OC TE N AU R T R A E IN GNE R A E IN GNE E B C I DIG ALERT I 7 STREET PLAN AND PROFILE CALTRANS STANDARD PLAN A88A
Reimbursement Agreement Between City of San Jacinto and Eastern Municipal Water District for Water and Sewer Relocations for San Jacinto Avenue Safety Improvements, CIP 21-005 01375.0006/998637.7 Attachment “B”
SJ-457 San Jacinto Ave. Safety Improvements
Probable Cost, CIP 21-005
SJ-457 San Jacinto Ave. Safety Improvements
Probable Cost
10/14/2025
Bid Item # Bid Item Description Construction Note Est. Qty Units Unit Cost Total 1 Mobilization 0 1 LS $ 16,000.00 $ 16,000.002 Traffic Control 0 1 LS $ 15,000.00 $ 15,000.003 Water Pollution Control 0 1 LS $ 5,000.00 $ 5,000.004 Weed Removal 0 1 LS $ 10,000.00 $ 10,000.005 Protect in place 1 1 LS $ 5,000.00 $ 5,000.006 Sawcut 2 3,770 LF $ 3.00 $ 11,310.007 Demolition 3, 4, 32 368 CY $ 80.00 $ 29,440.008 Salvage and relocate backflow & cage 5 1 LS $ 2,000.00 $ 2,000.009 Relocate sign and replace wooden pole with steel 6 6 EA $ 350.00 $ 2,100.00 10 Existing signs to be removed and salvaged 7 3 EA $ 200.00 $ 600.0011 Reset existing brass benchmark 8 1 EA $ 2,000.00 $ 2,000.0012 Construct 6" AC 9 300 TONS $ 125.00 $ 37,500.0013 Construct base 9, 24 700 TONS $ 70.00 $ 49,000.0014 Construct sidewalk 10 9,784 SF $ 10.00 $ 97,840.0015 Construct mod. A-8 curb & gutter 11 921 LF $ 35.00 $ 32,235.0016 Construct residential driveway 12 5 EA $ 4,000.00 $ 20,000.0017 Construct commercial driveway 13 2 EA $ 13,000.00 $ 26,000.0018 Adjust sewer MH to grade 14 2 EA $ 2,500.00 $ 5,000.0019 Adjust water valve to grade 14 6 EA $ 1,500.00 $ 9,000.0020 Construct 3' chain link fence 15 82 LF $ 24.00 $ 1,968.0021 Construct access ramp per ADA & RCTD Std 403, Case A 16 4 EA $ 8,000.00 $ 32,000.0022 Construct access ramp per ADA & RCTD Std 403, Case B 25 1 EA $ 8,000.00 $ 8,000.0023 Construct A-8 curb & gutter 17 1,143 LF $ 25.00 $ 28,575.0024 Construct SD manhole 18 1 EA $ 4,000.00 $ 4,000.0025 Extend access ramp 19 1 EA $ 3,700.00 $ 3,700.0026 Relocate existing water meter 20 5 EA $ 5,000.00 $ 25,000.0027 Adjust traffic signal box to grade 22 2 EA $ 1,500.00 $ 3,000.0028 Construct CMU wall 26 93 LF $ 750.00 $ 69,750.0029 Grind 0.15' cold mill 27 860 SF $ 3.00 $ 2,580.0030 Construct 0.15' overlay 27 43 TONS $ 125.00 $ 5,375.0031 Relocate existing traffic signal pole 28 1 LS $ 10,000.00 $ 10,000.0032 Construct 6" HMA dike 29 52 LF $ 18.00 $ 936.00 SJ-457 San Jacinto Ave. Safety Improvements
Probable Cost
10/14/2025
Bid Item # Bid Item Description Construction Note Est. Qty Units Unit Cost Total 33 Remove and replace 8" sewer cleanout 30 1 EA $ 2,500.00 $ 2,500.0034 Construct catch basin 31 1 EA $ 4,000.00 $ 4,000.0035 Remove or relocate irrigation 33 1 LS $ 1,000.00 $ 1,000.0036 Install 12" stop line 34 113 LF $ 4.00 $ 452.0037 Install pavement markings 35 85 SF $ 4.00 $ 340.0038 Install 6" lane line 36 243 LF $ 2.00 $ 486.0039 Sandblast striping 37 1 LS $ 1,000.00 $ 1,000.0040 Remove existing fence, post, conduits, etc. 38 1 LS $ 2,000.00 $ 2,000.00 $ 581,687.00$ 58,168.70$ 58,168.70
TOTAL $ 698,024.40
Contingency(10%)
Administrative/Inspection(10%)
SUBTOTAL