Principal
Hydrogeologist
Senior
Hydrogeologist
Project
Hydrogeologis
Staff
Hydrogeologist GSI Technician Project Coordinator
Item Description Labor Direct Costs Total Labor Direct Costs Total Labor Direct Costs Total 1 Project Management and Progress Meetings 2 4 $ 1,190 $ 1,190 $ 1,482 $ 30 $ 1,512 $ 1,620 $ 1,620 2 Provide Construction Management and Support, including Pre-Construction Meeting, Submittal Review, Response to RFIs, COR Review, Schedule Review, Progress Payment Review, and Construction Updates
2 8 4 $ 2,590 $ 129 $ 2,719 $ 3,326 $ 357 $ 3,683 $ 3,540 $ 3,540 3 Field Observation during Mechanical Brushing 1 3 6 $ 1,530 $ 129 $ 1,659 $ 1,927 $ 357 $ 2,284 $ 2,240 $ 161 $ 2,401 4 Field Observation during Pre-Repair Video Survey 1 3 6 $ 1,530 $ 129 $ 1,659 $ 1,927 $ 357 $ 2,284 $ 2,240 $ 161 $ 2,401 5 Field Observation During Installation of Casing Patches 1 1 6 16 $ 3,650 $ 257 $ 3,907 $ 4,546 $ 357 $ 4,903 $ 5,415 $ 483 $ 5,898 6 Field Observation during Post-Repair Video Survey 1 3 6 $ 1,530 $ 129 $ 1,659 $ 1,927 $ 357 $ 2,284 $ 2,240 $ 161 $ 2,401 7 Field Observation during Dynamic Video Survey 2 4 8 $ 2,430 $ 129 $ 2,559 $ 3,194 $ 357 $ 3,551 $ 3,500 $ 161 $ 3,661 8 Field Observation during Well Disinfection 1 3 8 $ 1,820 $ 129 $ 1,949 $ 2,273 $ 357 $ 2,630 $ 2,670 $ 161 $ 2,831 9 Prepare Summary TM with Recommendations for Next Steps 2 4 8 12 4 $ 4,650 $ 4,650 $ 5,750 $ 130 $ 5,880 $ 6,820 $ 6,820 9 25 38 54 4 0 $ 20,920 $ 1,031 $ 21,951 $ 26,352 $ 2,659 $ 29,011 $ 30,285 $ 1,288 $ 31,573 IMPORTANT: This notice is an award of bid only. No work is to be started on-site until the City issues a formal Notice to Proceed. Any work performed prior to that date is done at the Contractor's own risk and expense.
Dudek
Cost Proposal for Professional Hydrogeological Services City Of San Jacinto
Kyle Groundwater Kleinfelder
Total Hours and Cost: