Text extracted from the city's file for reading and search. Open the original on legistar.granicus.com. That file is the official record.

Potential Microgrids at Critical
Facilities Evaluation Status
Report
February 7, 2022
Transportation & Environment Committee
Item d.2
Walter Lin, Deputy Director, Public Works
What are Microgrids?
• Localized energy grid consisting of distributed energy resources – Solar photovoltaic systems
– Battery energy storage systems
– Backup generators
– Other renewable power generation
• Autonomous switching on and off from utility grid
– Load reduction from grid and provides resiliency from planned or unplanned power outages
What are Microgrids?
Benefits of Microgrids
• Provides power reliability and increased quality
• Can reduce utility power needs for a facility
• Continues power service for essential operations during planned and unplanned utility power outages
Program Background
• Identification of critical City facilities that currently do not have back up power infrastructure
• Planning for resiliency with cleaner technologies
• September 1, 2020: City Council approval of consultant services to assist in microgrid feasibility studies and project identification
Funding and Grant Opportunities
• Public Safety Power Shutdown program funds
• FEMA “Building Resilient Infrastructure and Communities” (BRIC) grant
• Infrastructure funding discussions with the State
• Power Purchase Agreements (PPA)
City of Fremont: Microgrid PPA Program
Site Ranking Criteria
Ranking Criteria and Weighting Scheme
1 Facility Need 35%

1.1Mission Criticality 35%

1.2Community Equity (Based on Median Household Income) 35%

1.3Outage Level 30%
2 Suitability 15%

2.1 Site Resource 25%

2.2Nature of Load 75%
3 Development Capacity 30%

3.1Microgrid Potential (Community or Campus) 15%

3.2 Space for Development 85%
4 Financial Viability 20%

4.1 Size of Load 50%

4.2 Existing Generation 50%
Total 100%
Site Rankings of Critical Sites
New City Development Projects
• Fire Station 37
– Solar photovoltaics and generator
• Fire Training Center and Emergency Operation Center
– Solar photovoltaics and generator
– Future battery energy storage system
• Solar4America Project
– Bloom Energy fuel cell system and generator
Conclusion
• Resource challenges
• Additional assessment work
• Recommendation for projects at Roosevelt
Community Center and Happy Hollow Park and Zoo
Potential Microgrids at Critical
Facilities Evaluation Status
Report
February 7, 2022
Transportation & Environment Committee
Item d.2
Walter Lin, Deputy Director, Public Works

← All documents from this meeting