2 Background
The San José and Santa Clara City Councils adopted the Plant Master Plan (PMP) in November 2013 and December 2013, respectively.
The PMP identified more than 100 capital improvement projects totaling over $2.1 billion to be implemented at the RWF over the next 30 years.
A validation process was completed in early 2014 to update and prioritize the recommended PMP projects and additional gap projects into 33 projects to be initiated over 10 years.
Beginning in fiscal year 2014-2015, the validation process was used to inform the five-year CIP and ten-year funding strategy, which are approved by the San José City Council.
Biosolids Disposition Procurement Strategy
RFP for transportation and beneficial use services advertised Nov. 2021 Proposals due in February 2022
Disposition agreement awards anticipated in coming months Services to begin in FY 2024-25
Testing, Startup and Commissioning (TSC)
Two full-time consultant TSC experts brought on early 2021 for support Testing of new equipment and systems ramped up in summer 2021 Four concurrent projects in the nitrification area were in TSC Critical TSC support will be needed this summer in key process areas 3 Significant Program Activities
Program Snapshot: All Projects
4 Seven Projects in Feasibility/Development
Scoping
Final Effluent Pump Station and Stormwater Channel Improvements Plantwide Security Systems Upgrade
Severely corroded steel reinforcing bars at pipe crown
Conceptual Design
Flood Protection
CCTV station of inspection crawler for condition assessment of 96” pipe for Yard Piping Improvements – Phase 2 5 Project Alternatives
Aeration Basin Modifications – Phase 1
Main Guard Shack Replacement
New Headworks Access Road
Yard Piping Improvements – Phase 2
Six Projects in Design and Bid/Award
6 Detailed Design
Facility Wide Water Systems Improvement
Fire Life Safety Upgrades
HVAC Improvements
Bid & Award
Outfall Channel and Instrumentation Improvements
Storm Drain System Improvements
Preliminary Services
Digested Sludge Dewatering Facility
Site Preparation work for the Digested Sludge Dewatering Facility project
Nine Projects in Construction
7 Advanced Facility Control and Meter Replacement – Phase 1 ($5.8m) Advanced Facility Control and Meter Replacement – Phase 2 ($7.0m) Blower Improvements ($29.5m)
Digester and Thickener Facilities Upgrade ($107.9m)
Filter Rehabilitation ($33.3m)
Headworks ($126.9m)
Nitrification Clarifiers Rehabilitation – Phase 1 ($26.2m) Switchgear M4 Replacement and G3 & G3A Removal ($5.5m)
Yard Piping Improvements – Phase 1 ($3.1m)
Nine Projects In Construction
Total Base Construction Value: $345M
Yard Piping Improvements Phase 1
Advanced Facility Phase 1
Blower Improvements
Digesters
Nitrification Phase 1
Headworks
Switchgear
Advanced Facility Phase 1
Blower Improvements
Advanced
Facility -
Phase 2
Advanced Facility – Phase 2
Filter Rehab
Yard Piping Improvements Phase 1
Yard Piping Improvements Phase 1
Headworks Project
Construction Value: $126.8M | Estimated Beneficial Use: Summer 2023
Headworks
Progress on construction of New Headworks facilities including grit removal, pump station, influent screenings removal, electrical building, emergency overflow basin, and odor control system as of November 2021. 10 Headworks
11 Installation of a new bar screen
Construction work in the emergency overflow basin
Headworks
Installation of 96” pipe
12 Realignment of existing Santa Clara pipeline
Installation of 96” pipe over Santa Clara pipeline
Switchgear M4 Replacement and G3 & G4 Removal
Construction Value: $5.5M | Estimated Beneficial Use: Winter 2022
Switchgear M4 Replacement and G3 & G4 Removal
14 Delivery and installation of outdoor M4 switchgear enclosure
Switchgear M4 Replacement and G3 & G4 Removal
15 Duct installation and supports
Interior of Switchgear enclosure
Expected Activities through June 2022
16 Reach Substantial Completion on three projects
Obtain Council approval to execute the Definitive Contract Amendment for Digested Sludge Dewatering Facility project Obtain Council approval to award the construction contract for Storm Drain System Improvements project Advertise construction contracts for Fire Life Safety Upgrades and HVAC Improvement projects Obtain Council approval of a fourth contingency increase for settlement of inefficiency claims for the Digester and Thickener Facilities Upgrade project Advertise request for prequalification for Facility Wide Water Systems Improvement