Pavement Maintenance Status Report
and Funding Strategy Update
John Ristow
Director, DOT
Frank Farshidi
Division Manager, DOT
Anie Yeh
Acting Senior Engineer, DOT
Local Streets
(1552 miles; PCI 63)
“Grading” San Jose Street Conditions
A, B 45%
Good to Excellent
C 27%
At Risk to Fair
D, F 28%
Poor or Failed
“Grades” based on 2021 PCI Ratings
A, B 74%
Good to Excellent
C 20%
At Risk to Fair
D, F 6%
Poor to Failed
Major Streets
(967 miles; PCI 76)
1 Pavement Condition Overview
Street Network Miles 2021 PCI 2022 PCI Total PCI
Change
Major 967 77 76 -1
Local/Neighborhood 1,552 62 63 1
Combined 2,519 67 68 1
2 Local
&
Neighborhood Streets
(0-49 PCI)
(434 Miles, 34 PCI)
Backlog $350.5M
Potholes
& Program
MGMT
Major Streets
(967 Miles, 76 PCI)
Local
&
Neighborhood Streets
(50-100 PCI)
(1,118 Miles, 75 PCI)
Backlog $75.7M
Overall Network
• 2,519 Miles
• PCI 68
• $83.5M Annual Need
• $509.5M Backlog
All Major Streets
• 967 Miles
• Carries Over 85% of Traffic
• PCI 76
• $21.3M Annual Need
• $83.3M Backlog
Local Streets
• 1,552 Miles
• PCI 63
• $55.2M Annual Need
• $426.2M Backlog
Pavement Needs and Funding
3 Pavement Condition Index (PCI) History
PCI
Year
 PCI will continue to increase, potentially reaching 70 in 2023  Likely to begin declining in 2027-28
4 10-Year Funding Status
5 Cost to Recover
Based on Current Funding Level
6 Pavement Production History/Planned
7 2022 Pipeline – 29 Projects!
Major Streets Award Date Project Miles
April 12 Concrete and ADA Ramps
(Sealing & Resurfacing Prep)
April 26 Asphalt Concrete Remove Replace
(Sealing Prep)
May 10 Arterial Resurfacing 27
May 10 Stevens Creek & Winchester Resurfacing 8
May 17 Arterial Sealing 24
Total Major Streets 59
Local Streets Award Date Project Miles
June 23, 2020 2020-2024 LS Multi-year Resurfacing (Option Year 2) 24 February 8 2022-2024 LS Multi-year Resurfacing (Initial Term) 25 March 15 2022 LS Concrete #1
March 29 2022 LS Concrete #2
April 26 2022 LS R&R Project
May 17 2022 LS Resurfacing #1 21
May 24 2022 LS Resurfacing #2 22
June 21 2022 LS Resurfacing #3 19
June 28 2022 LS Resurfacing #4 15
June 28 2022 LS Sealing Project 65
Total Local & Neighborhood Streets 191
Total Combined Major + Local Streets 250
 13 Minor Contracts on Local Streets (6/13 completed or IP)  1 Minor Contract on Major Streets (Start May)
8 135 Pavement Maintenance Zones
 Geographically contiguous
 Efficient planning and
delivery of paving projects
 Maximize work completed in
a neighborhood area
 Provide geographic
spread across the City
 Considers Equity Priority
Community as a tool in
planning phase
Local & Neighborhood Streets
9 Local & Neighborhood Streets
2021 Before and After
19th St
2021 Resurfacing
Minas Dr
2021 Resurfacing
Before
Before After
After
10 Local & Neighborhood Streets
2022 Projects
 13 minor construction projects (prep)
 10 major construction projects (3 prep, 1
sealing, 6 resurfacing)
 Addresses nearly 191 miles
 Total funding: $63 million
 Focused on maintenance zones “poor
and failed” to maximize cost-effective
treatment
 Approximately 458 miles maintained in
2019-2021 (30% of network)
11 Innovation
Reducing Carbon Footprint
• CO2-injected concrete:
 Reduce 5% carbon footprint
 Cost-neutral
 Local material and production
• About 19,000 ADA ramps to be installed in the
next 10 years:
 130,000 tons of concrete, or
 13,000 tons of CO2 emissions
• DOT’s goals:
 Implemented a pilot project in 2021
 Long-term goal: reduce 650 tons of CO2
emissions in the next 10 years
12 Conclusion
 Investments have yielded results
 Major Streets steady at 76 PCI
 PCI on Local Streets has jumped from 60 to
63 since 2018
 Funding has significantly improved
 Sufficient to properly maintain Major Streets
network in “good” condition
 Goal to ensure all Local & Neighborhood
Streets will be maintained by 2028
 PCI projected to increase to 70
 DOT ready to deliver
 303 miles of street pavement projects in 2022
 Building capacity to plan, procure and deliver
in 2022 and beyond
Hostetter Rd, post-resurfacing 2021
Landess Ave, post-resurfacing 2021
13 Pavement Maintenance Status Report
and Funding Strategy Update
John Ristow
Director, DOT
Frank Farshidi
Division Manager, DOT
Anie Yeh
Acting Senior Engineer, DOT
14