Public Safety Projects
Police Training and Academy - New/Relocated
SCOPING/CEQA/PROPERTY ACQUISITION: Consultant Selection, Programming/Feasibility and Environmental Studies DESIGN: Consultant Selection, Design, Review, Permitting AWARD: Advertise, Bid Opening, Council Award
ESTIMATE: Including refined cost estimates throughout design and final estimates ( 1 = initial estimate, 2 = 50% estimate, 3 = 95% estimate, 4 = final estimate/VE ) BID OPENING: Final project cost will be determined
Notes
- 95% cost estimates are the closest to the final estimate. Staff will perform some value engineering (VE) in between 95% estimate and the final estimate prior to issuing the project for advertisement.
Fire Station No. 36 - New
Police Air Support Unit Hangar - New at Airport
911 Call Center Renovation - Upgraded/New
Fire Station No. 8 - Relocated
Fire Station No. 23 - Relocated
Fire Station No. 32 - New
Feb-23 May-23Mar-23 Apr-23
- The red line denoted within the above schedule is identifying that five of the seven public safety projects will have 95% cost estimates by the end of December 2022.
Public Safety Project Estimates Schedule
Dec-22 Jun-23Aug-22 Sep-22 Oct-22 Nov-22 Jan-23Jul-22
3 2
1 3
3 2
2 3
3 44
4 4
4