Napp Fukuda, Assistant Director, Environmental Services Department Mathew Nguyen, Deputy Director, Public Works Department Digester and Thickener Facilities
Upgrade Project
Fourth Construction Contingency Increase
CITY COUNCIL ITEM 6.1: August 23, 2022
Project Site and Scope
Modifications to existing
digesters
5 6
7 8
New Primary Sludge Screening Building
Polymer Storage & Blending
Odor Control
Modifications to existing
DAFT Tanks
New Elevated Pipe Rack
2 Contract Substantial Completion Achieved in April
3 Summary of Contingency Increases
4 Description Council Date Contingency
Amount Total
Original Contract – Walsh Construction
@107,925,000 May 2016 $13,490,625 $121,415,625
First Contingency Increase
deteriorated pipes, regulatory
requirement, utility conflicts
November 2017 $15,000,000 $136,415,625
Second Contingency Increase
seismic design upgrades, hazardous
material remediation, and other
changes and delay costs
June 2018 $25,000,000 $161,415,625
Third Contingency Increase
additional civil work, changes and re-
sequencing of activities, addressing
digester leakage, and additional costs
and delays associated with the new
COVID-19 mandatory compliance
requirements
April 2021 $14,000,000 $175,415,625
Fourth Contingency Increase
loss of productivity, change in process August 2022 $3,107,049 $178,522,674 Fourth Contingency Increase
-
Loss of Productivity Claim
5 ▪ Walsh Claim
– Loss of Productivity - $5.1M
– Two methods: Ibbs’ Curve and Modified Total Cost
▪ City Review and Analysis
– Led by PMA Consulting in coordination with City staff ▪ Findings
– Large number of changes
– Claim has some merit, supported by various studies &
court cases
– Light on documentation & data to accurately define loss – Valid for only certain set of data and projects
– Claim included loss of productivity due to Covid
6 Fourth Contingency Increase
-
Loss of Productivity Claim
▪ Settlement and Contingency Increase
– Discussed findings with Walsh and negotiated cost
on May 27, 2022
– Loss of Productivity Settlement - $2.55M
– Contingency Increase by $3.1M
» Loss of Productivity – $2.55M
» Changes to Control Systems $0.56K
– Council date: August 23, 2022
7 Fourth Contingency Increase
-
Loss of Productivity Claim
Recommendation
▪ Approve a $3,107,049 increase to the construction
contingency amount of $67,490,625 for a revised total
contingency amount of $70,597,674, increasing the not-to- exceed amount from $175,415,625 to a total revised
contract amount not-to-exceed $178,522,674 for the 7382 – Digester and Thickener Facilities Upgrade Project
▪ Funding in the Project appropriation in 2021-2022 is
sufficient to increase the contingency.
8
Presentation - est. 15 minutes
San Jose City Council
August 23, 2022
- Document
- Presentation - est. 15 minutes