Contract
Package 2
(CP2)
Specific
Construction
Transportation
Management
Plan (CTMP) For
West Portal Early Works
Revision No. 2
Contract Package 2
(CP2) Specific
Construction
Transportation
Management Plan
(CTMP) for
West Portal Early Works
Revision No.: 04
Issue Date:
05/30/2023
CSS Number:
GR-013126-1.04.E.1
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023 Page ii
DOCUMENT REVISION RECORD
REVISION
NUMBER
PURPOSE DATE
Revision 00 CTMP1 West Portal Early Works (Draft Final) 12-09-2022 Revision 01 CTMP1 West Portal Early Works (Revised Draft Final) 01-16-2023 Revision 02 CTMP1 West Portal Early Works (Final) 04-10-2023 Revision 03 CTMP1 West Portal Early Works (Revised Final) 05-01-2023 Revision 04 CTMP1 West Portal Early Works (Revised Final) 05-30-2023 DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023 Page iii
APPROVALS:
As the KSTJV Design Manager for the BSVII Tunnel and Track Contract, I certify this submittal is in accordance with applicable clauses of the contract.
Eric Halvorson, Design Manager Date
Kiewit/Shea/Traylor Joint Venture
Jon N. Andresen, Jr. Date
KST Civil Design Lead
Jon Marshall Date
KST Engineer of Record
24 DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023 Page iv
TABLE OF CONTENTS
1.0 Introduction ............................................................................................................................ 1
1.1 Project Location ............................................................................................................... 1
1.2 Project Team ................................................................................................................... 1
1.3 BSVII FINAL CTMP ......................................................................................................... 2
2.0 Construction Sequencing and Staging Plan............................................................................ 4
2.1 Construction Sequencing and Staging ............................................................................. 4
2.1.1 Stage 1 Site Grading ............................................................................................... 6
2.1.2 Stage 2 Site Development....................................................................................... 7
2.1.3 Stage 3 Precast Plant and TBM Segment Storage Area.......................................... 7
2.1.4 Stage 4 TBM Shaft and Muck Bin Excavation.......................................................... 7
2.2 Construction Equipment and Material Layout................................................................... 8
2.2.1 Field Offices and Parking ........................................................................................... 8
2.2.2 Interior Concrete Build-out Area ................................................................................. 9
2.2.3 Precast Plant and TBM Segment Storage .................................................................. 9
2.2.4 Grout Plant................................................................................................................. 9
2.2.5 Shaft Support of Excavation (SOE) and Muck Bin .................................................... 10
2.3 Detour Routes and Alternate Routes.............................................................................. 10
2.4 Traffic Control Plans ...................................................................................................... 10
2.5 Haul Routes ................................................................................................................... 10
2.5.1 Holiday Work............................................................................................................ 11
2.5.2 Trucker Management Plan ....................................................................................... 11
2.5.3 Haul Hours ............................................................................................................... 11
2.6 Warning Devices............................................................................................................ 14
2.7 Major Special Events ..................................................................................................... 14
2.8 Inclement Weather......................................................................................................... 14
2.9 Impact on Local Business and Residents....................................................................... 14
2.9.1 Paypal Events Management Plan............................................................................. 14
2.10 Noise and Vibration Abatement...................................................................................... 15
2.11 Concurrent Construction ................................................................................................ 15
2.12 Time of Construction...................................................................................................... 16
2.13 Public Information Requirements ................................................................................... 17
3.0 Traffic Improvements and Operational Analysis.................................................................... 17 DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023 Page v
3.1 INTRODUCTION ........................................................................................................... 17
3.2 Existing Conditions ........................................................................................................ 18
3.3 Background Conditions.................................................................................................. 19
3.4 Project Conditions.......................................................................................................... 20
3.5 Conclusions ................................................................................................................... 25
4.0 Public Operation and Bus Operations................................................................................... 26
4.1 Bus Operations .............................................................................................................. 26
4.2 Rail Transit Operations .................................................................................................. 26
5.0 Maintenance of Property Access .......................................................................................... 28
6.0 School Zone Safety Plan...................................................................................................... 28
7.0 Emergency Access and Response....................................................................................... 30
7.1 Emergency Vehicle Access Plan.................................................................................... 30
7.1.1 Protocol for Unanticipated Changes ......................................................................... 31
7.2 Emergency Vehicle Response Plan ............................................................................... 32
8.0 City Permit Requirements..................................................................................................... 33
9.0 List of Appendices................................................................................................................ 33 TABLES
Table 1 - Summary CTMP Contents 2
Table 2 - Construction Sequencing ...4
Table 3 - Truck Volumes by Month 5
Table 4 - Key Site Facilities and Equipment 8
Table 5 - Concurrent Constructions 15
Table 6 - Proposed Work and Haul Hours ..17
Table 7 - Project Intersections 18
Table 8 - Project Operational Analysis 21
Table 9 - Existing Bus Route .26
Table 10 - KST Emergency Contact 30
Table 11 - 31
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023 Page vi
FIGURES
Figure 1 - Vicinity Map 1
Figure 2 - Haul Routes 13
Figure 3 - Existing Transit Operations 28
Figure 4 Nearby Schools 29
Figure 5 - Emergency Service Area 32
APPENDICES
Appendix A Site Layout, Sequencing and Staging Plan
Appendix B Traffic Control Plans
Appendix C Access to Businesses and Properties
Appendix D Traffic Operation Data and Analysis
Appendix E City Permit Requirements
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023 Page vii
ACRONYMS AND ABBREVIATIONS
ABBREVIATION DEFINITION
BART San Francisco Bay Area Rapid Transit
BMP Best Management Practice
BSV BART Silicon Valley
CP Contract Package
CTMP Construction Transportation Management Plan
CTMP1 Construction Transportation Management Plan for West Portal Early Works EAT External Affairs Team
ESCP Emergency Services Coordination Plan
KST Kiewit/Shea/Traylor
LOS Level of Service
MMRP Mitigation Monitoring and Reporting Program
SEIS / SEIR Supplemental Environmental Impact Statement / Subsequent Environmental Impact Report
SOE Support of Excavation
SWPPP Storm Water Pollution Prevention Plan
TBM Tunnel Boring Machine
TCP Traffic Control Plan
UPRR Union Pacific Railroad
VTA Santa Clara Valley Transportation Authority
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
1.0 INTRODUCTION
Kiewit Shea Traylor Joint Venture (KST) is the design-build contractor for the VTA BART Silicon Valley II Extension Project, Contract Package 2 (BSVII CP2). KST has prepared this CP2 West Portal Early Works specific Construction Transportation Management Plan (CTMP1) for the construction activities described herein.
1.1 PROJECT LOCATION
San
José and Santa Clara. The site is bounded by I-880 to the east, Brokaw Road to the west, Union Pacific Railroad (UPRR) tracks to the south, and Champions Way, Newhall Drive and existing developments to the north.
The site will be utilized as the launch site for the tunnel boring machine (TBM) and staging area during construction. Once construction is complete, the site will be utilized as BART storage and maintenance facility.
Figure 1 - Vicinity Map
1.2 PROJECT TEAM
Owner: Valley Transportation Authority (VTA)
Design-Build Contractor: Kiewit Shea Traylor Joint Venture (KST) Traffic Design Lead: KST and JMA Civil, Inc.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
1.3 BSVII FINAL CTMP
This CTMP1 for CP2 West Portal Early Works is based on the program-wide Draft CTMP for BSVII, dated 9/10/2021, and covers all requirements set in the BSVII Draft CTMP. See Table 1 below for a summary of contents in the BSVII Draft CTMP and corresponding contents in this CTMP1.
This CTMP1 pertains to the Early Works, which consists of establishing construction support facilities and work prior to the launch of the TBM, such as site grading, temporary utility installation, and construction of temporary field office buildings, precast concrete plant and grout plant.
As agreed in prior coordination meetings, KST will handle Early Site Preparation activities outside of CTMP1 due to the low expected construction traffic volumes (less than 50 trucks a day, operating during standard City work hours). These activities include clearing and grubbing, minor demolition, fence installation and portion of lime treatment. KST will closely coordinate all work with the Cities and obtain any necessary permits.
Also agreed in prior coordination meetings, this CTMP1 applies for construction works at West Portal, except for during events at
hauling during PayPal event ingress/egress will be developed in the coming months in coordination with VTA, the Cities of San José and Santa Clara, and PayPal Park.
In addition, subsequent work after the launch of the TBM, such as tunnel boring and hauling of excavated materials (Muck), will be addressed in a subsequent CTMP.
Table 1 - Summary CTMP Contents
No. BSVII Draft CTMP CP2 Early Works Specific CTMP
1 Chapter 2 Construction Sequencing Chapter 2.0 - Construction Sequencing and Staging Plan
2 Section 3.1.1.1 Vehicle, Bicycle and
Pedestrian Traffic
N/A as no impact is anticipated. See Section 2.3
3 Section 3.1.1.2 Allowed Road Closures
and Lane Closure Requirements
N/A as no impact is anticipated. See Section 2.3
4 Section 3.1.1.3 Private Property Access
Requirements
N/A as no impact is anticipated. See Chapter 5.0
- Maintenance of Property Access and Appendix
C - Access to Businesses and Properties
5 Section 3.1.1.4 Detour Routes N/A as no impact is anticipated. See Section 2.3 6 Section 3.1.1.5 Public Transit / Bus
Operations Impacts
N/A as no impact is anticipated. See Chapter 4.0
- Public Operation and Bus Operations
7 Section 3.1.2.1 Construction Staging Section 2.1 - Construction Sequencing and Staging
8 Section 3.1.2.2 Concurrent Construction Section 2.11 - Concurrent Construction 9 Section 3.1.2.3 City Ordinances / Work
Hours
Section 2.12 -
Time of Construction
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
No. BSVII Draft CTMP CP2 Early Works Specific CTMP
10 Section 3.1.2.4 Haul Routes Section 2.5 - Haul Routes 11 Section 3.1.2.5 Emergency Response Chapter 7.0 - Emergency Access and Response 12 Section 3.1.2.6 School Zone Safety Chapter 6.0 - School Zone Safety Plan 13 Section 3.1.2.7 Construction Parking Section 2.1 - Construction Sequencing and Staging
14 Section 3.1.3 Operational Requirements N/A as no public roadway impact is anticipated.
See Section 2.3 and 2.4
15 Section 3.1.4 Contingency Plan Chapter 7.0 - Emergency Access and Response 16 Section 3.1.5 City of San José General
Requirements
Work Hours See Section 2.12
Haul Routes See Section 2.5
Special Events See Section 2.7
Downtown San José Requirements N/A
Required Permits See Chapter 8.0
17 Section 3.1.6 City of Santa Clara General
Requirements
Work Hours See Section 2.12
Haul Routes See Section 2.5
Special Events See Section 2.7
Required Permits See Chapter 8.0
18 Section 3.2.7 West Tunnel Portal Specific
Requirements
Transit Routes See Chapter 4.0
Haul Routes See Section 2.5
PayPal Park Coordination See Section 2.9;
Private Property Access See Chapter 5.0
19 Appendix A Emergency Services
Coordination Plan
Chapter 7.0 - Emergency Access and Response
20 Appendix B Summary of Access and
Service Needs Memorandum
Appendix C - Access to Businesses and
Properties
21 Appendix C San José Better Bike Plan
2025
N/A as no impact is anticipated. See Section 2.3
22 Appendix D List of Ongoing and Planned
Construction Projects
Section 2.11 - Concurrent Construction
23 Appendix E San José Draft Activity Work
Hours
Section 2.12 -
Time of Construction
24 Appendix F List of Events N/A as no special events are impacted. See Section 2.7
25 Appendix G Downtown Construction
Guidelines
N/A as West Portal is outside of Downtown area
26 Appendix H San José Permit requirements Appendix E City Permit Requirements DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
No. BSVII Draft CTMP CP2 Early Works Specific CTMP
27 Appendix I Santa Clara Draft Activity Work
Hours
Section 2.12 -
Time of Construction
28 Appendix J Santa Clara Permit
Requirements
Appendix E City Permit Requirements
29 Appendix K San José Arena
Transportation & Parking Management Plan
N/A as West Portal is outside of San José Arena
area
30 Appendix L Earthquakes Stadium
Transportation & Parking Management Plan
Section 2.9 - Impact on Local Business
2.0 CONSTRUCTION SEQUENCING AND STAGING
PLAN
This section summarizes construction sequencing and staging, and transportation impacts anticipated during the West Portal early works activities.
2.1 CONSTRUCTION SEQUENCING AND STAGING
The West Portal Early Works consists of establishing the construction yard for West Portal and is planned to begin in summer 2023 and last until winter 2024 to early 2025. Sequencing and staging for the Early Works is summarized below. An overall site layout plan is included in Appendix A.
See Table 2 below for a summary of construction sequencing. As agreed in prior coordination meetings, KST will handle Early Site Preparation activities outside of CTMP1 due to the low expected construction traffic volumes (less than 50 trucks a day, operating during standard City work hours). These activities include clearing and grubbing, minor demolition, fence installation and portion of lime treatment. KST will closely coordinate all work with the Cities and obtain any necessary permits. In addition, work after Stage 4, such as tunnel mining and muck hauling, will be addressed in a subsequent CTMP.
Table 2 - Construction Sequencing
No. Construction Activity Period of Construction
Stage 1 Site Grading Beginning Summer 2023 1for 5 Months Stage 2 Site Development Beginning Summer 2023 1for 9 Months Stage 3 Precast Plant and TBM Segment Storage Area Beginning 2023 1for 13 Months Stage 4 TBM Shaft and Muck Bin Excavation Beginning Fall 2023 for 17 Months Notes:
1. Stage 1-3 to begin immediately after the approval of the CTMP and associated permits.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
Average and peak truck volumes per day for each month of construction are summarized in Table 3 days per month on average. KST will give the City of San Jose ([email protected]) notice two days prior to anticipated peak truck volume days.
Table 3 - Truck Volumes by Month
Date Average Daily Truck Volume
(Trucks/Day)
Peak Truck Volume
(Typical 5 days/month) (Trucks/Day)
Stage 1 Stage 2 Stage 3 Stage 4 Total Stage 1 Stage 2 Stage 3 Stage 4 Total Month 1 73 8 1 0 82 200 20 40 0 260
Month 2 73 8 1 0 82 200 20 40 0 260
Month 3 73 8 37 21 139 200 20 80 40 340
Month 4 73 0 37 21 131 200 0 100 40 340
Month 5 73 2 37 21 133 200 10 90 40 340
Month 6 73 2 37 0 112 200 10 130 0 340
Month 7 0 2 27 0 29 0 50 170 0 220
Month 8 0 2 27 79 108 0 50 170 120 340
Month 9 0 2 27 82 111 0 10 100 230 340
Month 10 0 0 27 113 140 0 0 100 240 340
Month 11 0 0 27 113 140 0 0 100 240 340
Month 12 0 0 27 113 140 0 0 100 240 340
Month 13 0 0 27 113 140 0 0 100 240 340
Month 14 0 0 0 32 32 0 0 0 60 60
Month 15 0 0 0 32 32 0 0 0 65 65
Month 16 0 0 0 32 32 0 0 0 65 65
Month 17 0 0 0 32 32 0 0 0 65 65
Month 18 0 0 0 32 32 0 0 0 65 65
Month 19 0 0 0 32 32 0 0 0 65 65
Notes:
Truck volumes include excavation and off-haul for site grading, imported fill material, deliveries of raw materials such as cement and aggregate, and deliveries of equipment, etc.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
2.1.1 Stage 1 Site Grading
In this stage, KST will establish main site entrance off Newhall Drive, and continue lime treatment and grading, generally from the southeast to the northwest. Key construction activities are summarized below; plans showing the site grading is included in Appendix A.
Relocation of a storm drain inlet, a sanitary sewer manhole and a backflow preventer near Newhall Drive.
Establishment of construction entrances off Newhall Street, Newhall Drive and Brokaw Road.
Approximately 34,000 cubic yards of excavation and off-haul.
Approximately 85,000 cubic yards of imported fill.
Remainder of lime treatment not performed during Early Site Preparation.
Compaction of the subgrade.
Installation of temporary utilities.
The 34,000 cubic yards of off-haul and 85,000 cubic yards of imported fill require approximately 12,000 total truck trips.
Due to the level of site preparation required at the site, KST plans to distribute 75 percent of construction hauling vehicles through the main entrance on Newhall Drive; the rest will enter through the entrance on Brokaw Road. The entrance off Brokaw Road is required to minimize truck queuing at the Newhall Drive entrance. Both the Newhall Drive access and the Brokaw Road access are required access points for construction activities. However, each provides a point of ingress and egress in case one of the entrances is blocked due to unforeseen circumstances.
On Peak days Brokaw handles 85 trucks a day, which is 25 percent of 340 peak day trucks. If unforeseen circumstances do occur on Newhall to render it restricted or unusable, trucks would be queued onsite such that Brokaw would not see more than the typical peak of 85 trucks a day. The distribution between the Newhall Drive and Brokaw Road entrances is estimated based on the site layout and construction activity, but Brokaw will be limited to 85 trucks per day as a peak as a maximum for any stage of Early Works Construction.
Conversely, on peak days Newhall handles 255 trucks a day, which is 75 percent of 340 peak day trucks. If unforeseen circumstances block Brokaw, trucks would be queued or reduced such that Newhall would not see more than the typical peak of 255 trucks per day.
The anticipated maximums for average daily trucks is 73 and for peak daily trucks is 200 for stage
1. The trucking operations will be managed by the KST Truck Boss and as described in section 2.5.2 for all stages.
Construction entrance/exit, vehicle wash out area and other storm water pollution prevention BMPs will be in place. All queuing and stockpile locations will be contained within the construction site; see Appendix A for additional details. Average and peak truck volumes per day for each month of construction are shown in Table 3. The grading activity is estimated to require up to 200 trucks per day during peak days.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
2.1.2 Stage 2 Site Development
In this stage, KST will finish the development of the site, generally from the southeast to the northwest. Key construction activities are summarized below; plans showing the site development is included in Appendix A.
Construction of additional site roads and parking.
Installation of temporary office trailers.
Installation of temporary utilities and connecting to offices.
Approximately 75 percent of construction vehicles will enter through the main entrance on Newhall Drive; the rest will enter though the entrance on Brokaw Road. All queuing and stockpile locations will be contained within the construction site; see Appendix A for additional details. Average and peak truck volumes per day for each month of construction are shown in Table 3 .
The anticipated maximum for average daily trucks is 8 and for the peak daily trucks is 50 for stage
2. 2.1.3 Stage 3 Precast Plant and TBM Segment Storage Area In this stage, KST will construct the precast plant and storage area for the TBM segments. Key construction activities are summarized below; plans showing the construction of precast plant and TBM segment storage area is included in Appendix A.
Surcharging precast plant and TBM segment storage area.
Installation of precast plant utilities.
Construction of plant, gantry crane and storage area foundations and slabs.
Installation of plant building and equipment.
Test production of the precast plant.
Approximately 75 percent of construction vehicles will enter through the main entrance on Newhall Drive; the rest will enter though the entrance on Brokaw Road. All queuing and stockpile locations will be contained within the construction site; see Appendix A for additional details. Average and peak truck volumes per day for each month of construction are shown in Table 3 .
The anticipated maximums for average daily trucks is 37 and for the peak daily trucks is 170 for stage 3.
2.1.4 Stage 4 TBM Shaft and Muck Bin Excavation
In this stage, KST will excavate the tunnel boring machine (TBM) shaft and muck bin and assemble the TBM. Key construction activities are summarized below; plans showing the TBM shaft and muck bin excavation, and TBM assembly are included in Appendix A.
Construction of interior concrete build-out area and grout plant.
Muck bin excavation (soldier piles, excavation and construction of MSE wall and liner).
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
Construction of SOE starter wall.
Construction of Support of Excavation (SOE) slurry walls (confinement walls, TBM shaft walls, and ramp walls).
TBM shaft and ramp excavation (Caterpillar beams and excavation).
Construction of TBM shaft concrete.
Construction of TBM crane pad.
Construction of TBM supporting facilities.
Assemble the TBM.
Approximately 75 percent of construction vehicles will enter through the main entrance on Newhall Drive; the rest will enter though the entrance on Brokaw Road. All queuing and stockpile locations will be contained within the construction site; see Appendix A for additional details. Average and peak truck volumes per day for each month of construction are shown in Table 3. The excavation of the TBM shaft and ramp is estimated to require up to 200 trucks per day during peak days.
The anticipated maximums for average daily trucks is 113 and for the peak daily trucks is 240 for stage 4.
The subsequent tunnel excavation and muck hauling is not part of the Early Works and will be discussed in a separate CTMP
2.2 CONSTRUCTION EQUIPMENT AND MATERIAL LAYOUT
This section summarizes the construction equipment and material layout once the West Portal construction yard has been established. See Table 4 below for a summary of key site facilities and equipment. See Appendix A for site layout plan.
Table 4 - Key Site Facilities and Equipment
No. Site Facility/Equipment Stage of Construction
1 Field Offices and Parking Stage 2 Site Development
2 Interior Concrete Build-out Area Stage 4 TBM Shaft and Muck Bin Excavation
3 Precast Plant and TBM Segment Storage Stage 3 Precast Plant and TBM Segment Storage Area
4 Grout Plant Stage 4 TBM Shaft and Muck Bin
Excavation
5 Shaft Support of Excavation (SOE) and Muck Bin Stage 4 TBM Shaft and Muck Bin Excavation
2.2.1 Field Offices and Parking
Employee parking will be provided at the southeast end of the site with approximately 300 parking stalls. Vehicles will enter and exit through two entrances on Newhall Street.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
Field office trailers will be installed north of the employee parking area. There will be approximately services, including portable water, sanitary sewer, electrical and communications will be provided to the office trailers.
At the peak for Early Works construction, there will be approximately 120 craft employees and approximately 100 staff. Craft workers in the day shift typically arrive at 5:30 6:00 AM and leave from 4:00 to 4:30 PM. Craft workers in the night shift typically arrive from 4:00 to 4:30 PM and leave 4:00 to 4:30 AM. Staff workers typically arrive from 5:00 to 7:30 AM and leave from 3:30 to 6:30 PM.
The Early Works construction activities will require approximately 220 parking stalls, compared to the 300 parking stalls provided. The parking stalls will remain for major construction (such as tunnel mining and muck hauling), when approximately 300 parking stalls will be required. Major construction activities are addressed in a separate CTMP.
2.2.2 Interior Concrete Build-out Area
The interior concrete build-out area is located at the northeast edge of the site, measuring rails. Small mechanical shop, electrical shop, warehouse and drums are also located adjacent to the concrete build-out area.
When materials are received they will be unloaded and stockpiled at the interior concrete build-out area. The site roads are designed so that truck queuing and loading/unloading along the interior concrete build-out area will not impact traffic circulation within the site. No material stockpiling or truck queuing will take place outside the construction yard.
2.2.3 Precast Plant and TBM Segment Storage
The precast plant is located at the northeast edge of the site, north of the interior concrete build-out area. When in full production the precast plant will have a capacity of 10 tunnel liner rings/day. The precast tunnel segments will then be transferred to the TBM segment storage area, located between the interior buildThe TBM segments will be stacked on strip footing and loaded/unloaded by a gantry crane.
All processes relating to the precast plant production will be fully contained within the construction yard.
2.2.4 Grout Plant
The grout plant is located at the southwest edge of the site across the site road from the precast plant. When in full production the grout plant will have a capacity of 50 cubic yards per hour. The grout will be loaded/unloaded at designated areas adjacent to the plant. There are also small storage containers and other equipment in this area.
All processes relating to the grout plant production will be fully contained within the construction yard.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
2.2.5 Shaft Support of Excavation (SOE) and Muck Bin
The TBM Shaft is located at the southwest edge of the site, south of the grout plant and across the site road from the interior build-out area. When in operation excavated material (muck) will be carried out by a conveyor system and stored in the muck bin, located between the shaft and the grout plant. Muck will be loaded to truck around the muck bin perimeter and hauled off site. The muck hauling and other construction activities when the construction yard is in full operation will be covered in a separate CTMP as this CTMP is applicable to the Early Works only.
2.3 DETOUR ROUTES AND ALTERNATE ROUTES
Detour routes and alternate routes are not anticipated for West Portal Early Works at this time as no long-term lane closures are anticipated, since all construction activities, queuing and staging will be within the West Portal site. The traffic operational analysis presented in Section 3.0 shows minimal effects on LOS due to construction traffic at the existing signalized intersections.
All pedestrian, bicycle and vehicular facilities will be maintained throughout the construction; no sidewalk, shoulder or lane closures are currently anticipated.
2.4 TRAFFIC CONTROL PLANS
Long-term traffic control plans are not anticipated for West Portal Early Works at this time as no sidewalk, shoulder or lane closures are currently anticipated. Installation of temporary utilities may require temporary lane closures which lasts a few hours to a couple of days; traffic control plans will be provided accordingly once construction plan for temporary utilities have been established.
2.5 HAUL ROUTES
The Haul routes applicable to West Portal are shown in Figure 2, which were established in the Draft CTMP. Approximately 75% of construction vehicles will enter the site via Newhall Drive; the remainder will enter via Brokaw Road. The entrance off Brokaw Road is required to minimize truck queuing at the Newhall Drive entrance.
Both the Newhall Drive access and the Brokaw Road access provide required points of ingress and egress for the construction traffic. In case one of the entrances is blocked due to unforeseen circumstances the other can act as the sole point of entry to the site. On Peak days Brokaw handles 85 trucks a day, which is 25 percent of 340 peak day trucks.
If unforeseen circumstances occur on Newhall to render it restricted or unusable, trucks would be queued onsite or some hauling might be halted, such that Brokaw would not see more than the typical peak of 85 trucks a day. The distribution between the Newhall Drive and Brokaw Road entrances is estimated based on the site layout and construction activity, but Brokaw will be limited to 85 trucks per day as a peak as a maximum.
Similarly should an unforeseen event render Brokaw unusable, trucks will queue onsite and be directed to Newhall while maintaining the peak truck traffic of 255 trucks (which is 75 percent of 340 peak daily trucks).
of San Jose that details the lines of communication and processes that would be followed in case DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
either the intersection at Brokaw or at Newhall Drive are blocked due to unforeseen circumstances. This plan would be coordinated and developed prior to peak traffic operations.
All trucks will originate or leave from I-880 via Coleman Ave.
KST has conducted Pre Construction Surveys in accordance with the VTA Contract.
The proposed hauling hours are discussed in Section 2.5.3.
Hauling during PayPal ev
2.5.1 Holiday Work
There will be no hauling on major holidays (Day Before Thanksgiving, Thanksgiving Day, Christmas Memorial Day, Independence Day and
Labor Day) as no construction work is anticipated on those days, unless emergency work is required on-site.
2.5.2 Trucker Management Plan
KST will develop and implement a plan to manage the truck drivers using the approved haul routes related to completing the construction of this project. A summary of the plan will include:
Truck Boss to manage trucking activities
Trucker Pre Construction Meetings
Signage at all exits to the site directing the trucks to I-880 Active Management by KST during construction
Trucker Flash Cards to be referred to in cab to reinforce haul routes KST will monitor the truck volumes on days of peak truck traffic, change of construction activities, and major holidays and events to ensure that truck volumes do not exceed the expected volumes.
This will ensure desired split between Newhall Drive and Brokaw Road is achieved. KST control processes to validate truck volumes and provide information that trucks are using the proper entrances will be shared with the City upon request.
2.5.3 Haul Hours
For most of the construction activities the haul hours will match work hours; see Table 6. Typical single-shift construction hauling activity lasts from 6AM to 4PM, for 10 hours, and 6 days a week (Monday to Saturday).
Certain construction activities will be double shift to meet the construction schedule. Among these double shift activities, TBM assembly and starting production of the precast plant only require hauling during the day shift, from 6AM to 4PM. Materials will be double-handled, which require that the materials for the night shift be delivered during the day and stockpiled on-site.
KST expects the TBM Shaft and Ramp Excavation to require hauling during both day and night shifts, from 6AM to 4AM. The Support of Excavation Slurry Walls construction activity will also require hauling during both shifts during times of heightened construction periods.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
The Synchro analysis completed as a part of this CTMP does not indicate an impact to morning AM traffic due to hauling, but KST will work closely with trucking companies to determine if there is a potential to reduce hauling between the 7 AM and 9 AM rush hour traffic period.
Approval of this CTMP by the City of San José and the City of Santa Clara and any revisions thereafter shall also constitute approval of the work and haul hours as presented in Table 6.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
Figure 2 - Haul Routes
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
2.6 WARNING DEVICES
Appendix B for plans. Other warning devices or signs are not anticipated at this time due to no traffic control plans (TCP) being currently identified, as detour routes or alternate routes are not anticipated. When additional TCP and warning devices are identified, they will be provided in Appendix B.
2.7 MAJOR SPECIAL EVENTS
KST has reviewed major special events listed in the Draft CTMP Appendix F and identified no City events (such as marathons) that will be impacted by the West Portal Early Works construction.
KST will continue to coordinate with VTA, City of San José and City of Santa Clara to minimize potential impacts from construction activities.
2.8 INCLEMENT WEATHER
KST will continuously monitor the weather condition and identify potential inclement weather at least one week in advance. KST will identify responses to inclement weather that has the potential to impact construction activities.
A Construction Storm Water Pollution Prevention Plan (SWPPP) is prepared by KST separately from this CTMP, where Best Management Practices (BMPs) will be specified to prevent pollution or erosion due to rain events; it also specifies detailed monitoring requirements and rainfall action plans.
2.9 IMPACT ON LOCAL BUSINESS AND RESIDENTS
KST has reviewed the list of local businesses in the Draft CTMP Appendix B. Impact on local businesses is not anticipated from West Portal Early Works.
A list of local businesses in the vicinity of the West Portal site interviewed by VTA in 2021 is included in Appendix C. KST also included an exhibit showing the driveway locations of nearby properties. No driveways are anticipated to be impacted by West Portal Early Works. KST recognizes that Newhall Drive is the only ingress/egress route for the residential area near the south end of the project site. No impacts to the residents are expected as Newhall Drive and Newhall Street will remain open at all times during construction.
2.9.1 Paypal Events Management Plan
In addition, KST will continuously monitor events at PayPal Park through coordination facilitated by VTA and minimize potential impacts from construction activities. KST will generate a Paypal Events Management Plan to determine trucking activity in relation to events to mitigate, as best as possible, the impacts to both the event and the project.
KST has reviewed the Earthquakes Stadium (now PayPal Park) Transportation and Parking Management Plan and does not anticipate any conflicts between the construction traffic and the plan.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
2.10 NOISE AND VIBRATION ABATEMENT
KST has completed a pre-construction noise assessment to establish ambient noise conditions around the site. A Noise and Vibration Control Plan is currently being prepared, separate from this CTMP, to specify noise reduction and mitigation measures to ensure that surrounding land uses will not be impacted by construction noise. Noise will be monitored in the community during construction continuously to demonstrate compliance with the project noise thresholds.
KST will coordinate with City of San José and City of Santa Clara for nighttime work variances.
Nighttime construction is expected to be within City of San José only and nighttime hauling is expected to be within both cities. See Table 6 for construction activities requiring nighttime work and hauling.
2.11 CONCURRENT CONSTRUCTION
KST has reviewed the concurrent constructions listed in Draft CTMP Appendix D and identified projects in the vicinity of the West Portal site, and confirmed with the Cities that this is a complete list of concurrent constructions known to date. KST will continue to coordinate with the Cities on any additional future concurrent construction activities.
A list of concurrent constructions is included in Table 5.
Table 5 - Concurrent Constructions
No.
Planned
Construction
Date
Project Location Notes
1 - California High
Speed Rail
Southwest of
Newhall Yard
(Caltrain Tracks)
No impact expected.
Per San José to Merced Final EIR/EIS certified
by the CA High Speed Rail Authority in April
2022, Alternative 4 - Blended at-grade is
selected, which includes no construction near
West Portal.
The San Francisco - Central Valley segment is
expected to be in operation in 2031 Per
Authority's 2022 business plan. No
construction date has been confirmed but it is
likely after West Portal construction activities.
2 - Caltrain
Electrification
Project (CalMod)
Southwest of
Newhall Yard
(Caltrain Tracks)
No impact expected.
The Caltrain Electrification project is expected
to be limited to within the existing Caltrain
corridor.
3 - Diridon Integrated
Station Concept
(DISC) Plan
Diridon Station,
San José
No impact expected.
The DISC is expected to be applicable to
Diridon Station only.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
No.
Planned
Construction
Date
Project Location Notes
4 2027 Airport Connector San José Mineta
International
Airport to Diridon
Station
No impact expected.
5 2023 Aviation Ave
Repaving
Aviation Ave from
Coleman Ave to
North End
The repaving may affect the intersection of
Aviation Ave and Coleman Ave.
6 2023 Martin Ave
Repaving
Martin Ave from
Brokaw Rd to
Reed St
Trucks for the repaving may enter and exit at
the intersection of Coleman Ave and Brokaw
Rd.
7 Under
Construction
Gateway
Crossings
1205 Coleman
Avenue, Santa
Clara
No impact expected.
Bounded by Brokaw Rd, Coleman Ave and
Champions Way.
8 2023 Coleman Highline 1125 Coleman
Avenue, San José
No impact expected.
Bounded by driveway to 1199 Coleman Ave,
Coleman Ave and Aviation Ave.
2.12 TIME OF CONSTRUCTION
KST has reviewed the potential work hours listed in Draft CTMP Appendix E and proposes the following work and haul hours as summarized in Table 6. The approval of this CTMP by the City of San José and the City of Santa Clara shall also serve as approval of the work and haul hours stated within this document or any accepted revision thereafter.
Typically, work that requires concrete pours are double shifted including hauling hours to match so that concrete can be delivered continuously during the pour. Once a concrete pour begins it must continue until the pour is completed and cannot stop midway into the activity.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
Table 6 - Proposed Work and Haul Hours
Early Work Activities Single
Shift
Double
Shift
Work
Hours
Haul
Hours
Stage 1 Site Grading (Beginning Summer 2023, 6 Months)
Site grading X 6AM 6PM 6AM 4PM
Stage 2 Site Development (Beginning Summer 2023, 9 Months) Construction of site roads X 6AM 6PM 6AM 4PM
Installation of site offices X 6AM 6PM 6AM 4PM
Stage 3 Precast Plant and TBM Segment Storage Area (Beginning Summer 2023, 13 Months) Construction of precast plant X 6AM 6PM 6AM 4PM
Stage 4 TBM Shaft and Muck Bin Excavation (Beginning Fall 2023, 17 Months) Muck bin excavation X 6AM 6PM 6AM 4PM
Support of excavation slurry walls X 6AM 4AM 6AM 4AM
TBM shaft and ramp excavation X 6AM 4AM 6AM 4AM
TBM shaft concrete pour X 6AM 4AM 6AM 4AM
TBM supporting facilities X 6AM 6PM 6AM 4PM
TBM assembly X 6AM 4AM 6AM 4PM
Start production of the precast plant X 6AM 11PM 6AM 4PM Construction of interior concrete build-out
area and equipment foundations X 6AM 6PM 6AM 4PM
Construction of grout plant X 6AM 6PM 6AM 4PM
Notes:
1. Construction activities will be 6 days a week.
2.13 PUBLIC INFORMATION REQUIREMENTS
Locations of the signs are presented in Appendix B. Additional Project identification will be provided once requirements are developed by VTA.
3.0 TRAFFIC IMPROVEMENTS AND OPERATIONAL
ANALYSIS
This section summarizes the general construction transportation management requirements for both the Cities of San José and Santa Clara to ensure the traffic generated by construction does not negatively impact the project area corridors and surrounding communities.
3.1 INTRODUCTION
Traffic data and signal timing databases were collected to develop project Synchro models year 2023 existing conditions, year 2023 average truck traffic, year 2023 peak truck traffic, year 2024 DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
background, year 2024 average truck traffic, and year 2024 peak truck traffic. These models were developed using assumptions and information as presented in other sections of this document, as well as information from relevant nearby developments scheduled to implement prior to this project (Gateway Crossings and Coleman Highline).
Measures of effectiveness (MOEs) such as intersection level of service (LOS), intersection delay, intersections and to develop mitigation measures as needed to ensure minimal impact and disruption to the transportation network in the project area. See Table 8 for delay and LOS results; see Appendix D for overall detailed delay, LOS, and queuing results, a queuing analysis related to PayPal Park events, as well as traffic volumes and supporting documentation.Project staff will make periodic observations at the project area intersections, both signalized and unsignalized, to ensure acceptable operations continue.
3.2 EXISTING CONDITIONS
Traffic turning movement counts were field collected Thursday November 3, 2022 for both the AM and PM peak periods, Tuesday March 7, 2023 for the Mid-day peak period, and Saturday March 4, 2023 for the weekend peak period at the intersections listed in Table 7 below. Growth rates were used to adjust the volumes in the models accordingly based on the year collected as discussed under Background Conditions. Additional locations were also collected at the same time to better understand traffic patterns in the project area but were not specifically used in the traffic operations analysis. KST has reviewed the peak hour movements in the field to verify them.
Table 7 - Project Intersections
No. Primary Secondary
A1 Coleman Ave. Brokaw Rd.
A2 Coleman Ave. Champions Way
A3 Coleman Ave. Aviation Ave.
A4 Coleman Ave. Earthquakes Way
A5 Coleman Ave. Newhall Dr.
A6 Coleman Ave. Airport Blvd.
A7 Coleman Ave. I-880 SB Ramp
A8 Coleman Ave. I-880 NB Ramp / McKendrie St.
A9 Coleman Ave. Hedding St.
A10 Brokaw Rd. Costco
Current intersection traffic turning movement counts were compared to pre-COVID historical counts provided by the local agencies. The counts were somewhat comparable, with the exception of the DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
morning peak direction along Coleman Ave. This can be attributable to factors such as an increase in work-from-home and changes in travel patterns. Traffic volumes are not anticipated to return to pre-COVID levels within the timeframe of this Early Works operation.
Current traffic signal timing data was downloaded from the controllers by the Cities of San José and Santa Clara and provided to the KST team. At the intersections listed above, the morning peak is running a 140 second cycle length, and the PM peak is running a 130 second cycle length. The project area intersections run a free operation during the Mid-day peak and on Saturday, except that the intersection of Coleman Ave. & Brokaw Rd. runs a 110 second cycle length during the weekday Mid-day. The project area signalized intersections are running a traffic adaptive system, except at the intersections of Coleman Ave. & Champions Way and Coleman Ave. & Brokaw Rd. (Brokaw Rd. & Costco Driveway will be signalized by others no later than mid-2024, which will also not be an adaptive system), so cycle lengths, offsets, and splits may ultimately vary.
Field intersection and corridor information was gathered through various sources such as online aerials, street views (verified to be recent), and project personnel who frequent the area.
The traffic counts, traffic signal timing information, and field characteristics were used to develop an existing conditions traffic model using the software package Synchro/SimTraffic v11. Models were developed for the AM, Mid-day, PM, and Saturday Mid-day peak periods as determined by the traffic count data. Model outputs for existing conditions were calibrated and validated with field observations. Measures of Effectiveness (MOEs) gathered from the model output include the intersection levels of service (LOS), intersection delay (in seconds), individual approach LOS and delay, and 95th-percentile queue lengths. Results from the existing conditions analysis can be found in Section 3.4 Project Conditions, with supporting documentation in Appendix D.
3.3 BACKGROUND CONDITIONS
Background models were developed for the AM, Mid-day. PM, and Saturday Mid-day peak periods using the existing conditions models as a base, and then inputting a 1.02 or 1.04 growth factor (2% per year growth rate) to develop future year 2024 volumes and operational MOEs. Projected traffic volumes generated by nearby developments (Gateway Crossings and Coleman Highline) have been included in the year 2024 background and project conditions. Various significant mitigation elements associated with these developments have been included in the modeling, such as the widening of Coleman Ave. just south of Brokaw Rd., the widening of Brokaw Rd. west of Coleman Ave., intersection and traffic signal improvements at Coleman Ave. & Brokaw Rd., and a new traffic signal installation at Brokaw Rd. & Costco driveway. See Appendix D for additional information on the traffic generated by these nearby developments that was included in this modeling.
The year 2024 is expected to see the height of the Early Works site work. Signal timing (splits and offsets) was adjusted at the City of San Jose intersections for the year 2024 background and project conditions models to minimize delay and queuing. Signal timing at City of Santa Clara intersections remained relatively unchanged, with only the Brokaw Rd. splits having been adjusted due to the new split phase setup planned as part of the Gateway Crossings development mitigation DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
efforts. The variability in delay and LOS shown in Table 8 is partially due to these signal timing changes, as well as included external project mitigation.
Results from the background conditions analysis can be found in Section 3.4 Project Conditions, with supporting documentation in Appendix D.
3.4 PROJECT CONDITIONS
Project conditions were analyzed using the year 2023 existing and 2024 background models as a base and developing separate year 2023 and 2024 average and peak truck traffic models. Average and Peak project truck volumes as shown in Table 3 (140 trucks and 340 trucks per day, respectively) were distributed through the network (at an hourly scale). Truck volumes were spread uniformly across the hauling hours to determine average and peak truck volumes. These volumes were used to represent a worst-case condition. Brokaw Road was assigned 25% of the truck traffic and Newhall Dr. was assigned 75% of the truck traffic. The 10% non-PayPal 2023 and 2024 Average Trucks operation for the weekend mid-day was also checked. Intersections in between and along the haul route were assigned increases in truck traffic to their respective through and left turn movements. Appendix D contains additional information regarding the truck traffic distribution and assignment.
A queuing analysis was completed for the Coleman Ave. & Newhall Dr. intersection to show what impacts, if any, may happen if truck hauling occurs during a weekday evening (Wednesday) or weekend evening (Saturday) PayPal Park event. T
Synchro software using current intersection geometrics, event signal timing patterns, and typical event volumes as collected by the City of San José. This analysis looked at potential effects to queuing at the intersection, particularly the northbound left and eastbound right turns, during the ingress and egress conditions. Based on the queue analysis, it is concluded that the addition of project trucks does not lead to a significant increase in queuing over normal PayPal Park operations during the weekday or weekend ingress or egress events. The detailed analysis, including assumptions and results, are included in Appendix D.
Traffic volumes due to staff and craft workers arriving and leaving the site are also included in the analysis with the following assumptions:
1. Staff and Craft volumes were added to the four PM Peak Synchro project models (2023 Average and Peak Trucks, 2024 Average and Peak Trucks).
2. The Staff and Craft volumes used were the CTMP1 Early Works 120 Craft and 100 Staff (reduced to 33% or 33 vehicles due to dispersed staff release) for a total of 153 vehicles.
3. Since the PM peak period includes a shift change, the revised models include the Staff and Craft leaving as well as the Craft arriving utilizing Newhall Dr.
4. The volume distribution used was the same as the Coleman Highline development report, with 33% going to the north and 67% going to the south (the same as in Figure D-12 in the CTMP1 Appendix ).
5. The signal timing for the CSC intersections remained unchanged.
6. DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
Table 8 below shows a summary of the year 2023 existing conditions, year 2023 average and peak trucks conditions, year 2024 background conditions, year 2024 average truck traffic conditions, and year 2024 peak truck traffic conditions. Brief discussions for each intersection follow the table, which highlight potential project impacts based on the operational LOS and delay results and possible mitigation measures. Supporting documentation, including results on queuing, can be found in Appendix D.
Table 8 - Project Operational Analysis
Intersection and
Scenario
AM Peak Weekday
Mid-day PM Peak WeekendMid-day
Int.
Delay
(Sec)
HCM
Int.
LOS
Int.
Delay
(Sec)
HCM
Int.
LOS
Int.
Delay
(Sec)
HCM
Int.
LOS
Int.
Delay
(Sec)
HCM
Int.
LOS
A1 Coleman Ave. & Brokaw Rd.1
Existing 2023 26.1 C 60.2 E 116.7 F 39.2 D
Avg Trucks 2023 (10%) - - - - - - 39.5 D
Avg Trucks 2023 (25%) 26.3 C 60.0 E 126.0 F 39.4 D
Peak Trucks 2023 26.5 C 60.3 E 128.1 F 40.3 D
Background 2024 27.3 C 27.5 C 52.8 D 40.7 D
Avg Trucks 2024 (10%) - - - - - - 41.8 D
Avg Trucks 2024 (25%) 25.6 C 27.4 C 56.5 E 42.2 D
Avg Trucks 2024 (Opt.) - - - - 50.8 D - -
Peak Trucks 2024 27.8 C 28.0 C 55.2 E 45.0 D
Peak Trucks 2024
(Opt.) - - - - 55.0 D - -
A2 Coleman Ave. & Champions Way1
Existing 2023 0.7 A - - 0.6 A 3.4 A
Average Trucks 2023 0.7 A - - 0.6 A 3.4 A
Peak Trucks 2023 0.7 A - - 0.6 A 3.4 A
Background 2024 11.2 B - - 8.1 A 2.9 A
Average Trucks 2024 12.9 B - - 8.4 A 2.9 A
Peak Trucks 2024 7.2 A - - 8.4 A 2.9 A
A3 Coleman Ave. & Aviation Ave.
Existing 2023 16.0 B - - 10.6 B 7.1 A
Average Trucks 2023 16.1 B - - 10.4 B 7.2 A
Peak Trucks 2023 16.2 B - - 10.3 B 7.2 A
Background 2024 23.8 C - - 20.6 C 17.1 B
Average Trucks 2024 22.4 C - - 19.2 B 17.1 B
Peak Trucks 2024 15.7 B - - 21.9 C 17.1 B
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
Intersection and
Scenario
AM Peak Weekday
Mid-day PM Peak WeekendMid-day
Int.
Delay
(Sec)
HCM
Int.
LOS
Int.
Delay
(Sec)
HCM
Int.
LOS
Int.
Delay
(Sec)
HCM
Int.
LOS
Int.
Delay
(Sec)
HCM
Int.
LOS
A4 Coleman Ave. & Earthquakes Way
Existing 2023 4.7 A - - 8.4 A 4.2 A
Average Trucks 2023 4.7 A - - 8.3 A 4.3 A
Peak Trucks 2023 4.7 A - - 8.3 A 4.3 A
Background 2024 4.3 A - - 3.7 A 5.3 A
Average Trucks 2024 3.1 A - - 5.0 A 5.3 A
Peak Trucks 2024 4.9 A - - 10.6 B 5.3 A
A5 Coleman Ave. & Newhall Dr.
Existing 2023 15.5 B 26.5 C 19.5 B 28.3 C
Average Trucks 2023 15.8 B 28.0 C 24.3 C 26.0 C
Peak Trucks 2023 16.2 B 27.1 C 29.6 C 25.0 C
Background 2024 13.7 B 22.7 C 17.2 B 21.2 C
Average Trucks 2024 13.0 B 23.6 C 57.5 E 23.0 C
Peak Trucks 2024 16.6 B 23.4 C 80.5 F 22.2 C
A6 Coleman Ave. & Airport Blvd.
Existing 2023 18.3 B - - 14.7 B 8.1 A
Average Trucks 2023 18.2 B - - 15.3 B 8.1 A
Peak Trucks 2023 18.2 B - - 15.4 B 8.1 A
Background 2024 8.0 A - - 7.6 A 8.9 A
Average Trucks 2024 6.4 A - - 7.7 A 9.0 A
Peak Trucks 2024 7.1 A - - 7.6 A 9.0 A
A7 Coleman Ave. & I-880 SB Ramp
Existing 2023 12.2 B - - 19.8 B 8.6 A
Average Trucks 2023 12.5 B - - 27.3 C 9.0 A
Peak Trucks 2023 13.1 B - - 21.8 C 9.6 A
Background 2024 19.9 B - - 11.1 B 16.3 B
Average Trucks 2024 10.7 B - - 11.8 B 17.4 B
Peak Trucks 2024 10.9 B - - 9.7 A 19.2 B
A8 Coleman Ave. & I-880 NB Ramp / McKendrie St.
Existing 2023 25.7 C - - 21.1 C 14.2 B
Average Trucks 2023 26.0 C - - 21.8 C 14.5 B
Peak Trucks 2023 26.5 C - - 22.0 C 15.1 B
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
Intersection and
Scenario
AM Peak Weekday
Mid-day PM Peak WeekendMid-day
Int.
Delay
(Sec)
HCM
Int.
LOS
Int.
Delay
(Sec)
HCM
Int.
LOS
Int.
Delay
(Sec)
HCM
Int.
LOS
Int.
Delay
(Sec)
HCM
Int.
LOS
Background 2024 25.9 C - - 24.8 C 16.3 B
Average Trucks 2024 25.1 C - - 26.0 C 17.2 B
Peak Trucks 2024 26.5 C - - 24.0 C 18.4 B
A9 Coleman Ave. & Hedding St.
Existing 2023 37.0 D - - 28.5 C 22.2 C
Average Trucks 2023 37.0 D - - 29.0 C 22.2 C
Peak Trucks 2023 37.0 D - - 28.4 C 22.2 C
Background 2024 45.2 D - - 44.7 D 23.1 C
Average Trucks 2024 36.6 D - - 45.0 D 23.1 C
Peak Trucks 2024 41.2 D - - 29.0 C 23.1 C
A10 (New) Costco Driveway & Brokaw Rd.1
Existing 2023 (Unsig) 4.6 A 9.7 A 9.8 A 11.1 A
Avg Trucks 2023 (10%) - - - - - - 11.2 A
Avg Trucks 2023 (25%) 4.6 A 9.8 A 9.9 A 11.3 A
Peak Trucks 2023 4.5 A 10.0 A 10.1 A 11.7 A
Background 2024 (Sig) 19.5 B 22.0 C 28.0 C 30.2 C
Avg Trucks 2024 (10%) - - - - - - 30.5 C
Avg Trucks 2024 (25%) 27.8 C 22.1 C 28.7 C 30.9 C
Peak Trucks 2024 21.5 C 22.3 C 28.7 C 32.2 C
Notes:
1. No adaptive system at this intersection.
See Appendix D for detailed delay, LOS, and queuing results, as well as traffic volumes and supporting documentation.
A1 - Brokaw Rd. For both the average and peak truck traffic conditions, the northbound left and eastbound right movements will see increased truck traffic. The project plans to assign 25 percent of the truck traffic to this intersection. The existing LOS varies and is expected to remain or slightly improve to C/D/E once the Gateway Crossings mitigation improvements are implemented by mid-2024.
An operational check was made to see if any short-term year 2023 improvements could help ease congestion at the intersection prior to the Gateway Crossings mitigation. Various elements were adjusted in a representative model to attempt to mitigate intersection delay. The cycle length, timing splits, split phasing, and even restriping eastbound Brokaw Rd. was looked at to see if the delay could be improved. Even with these changes, the LOS and delay was not projected to DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
significantly improve. One other possibility may be for the City of Santa Clara to implement their traffic responsive system at this intersection to further fine-tune the signal timing until the Gateway Crossings developer mitigation is in place. Also, the results shown in the table generally reflect the 25% truck traffic scenario.
A check of the 10% non-PayPal 2023 and 2024 Average Trucks operation for the weekend mid-day shows a slightly better LOS and delay than the 25% condition. The 10% Peak Trucks analysis was similar to the 25% Average Trucks condition.
A2 Champions Way This intersection will only see a slight increase in truck traffic for the north/south movements. The LOS is currently at a level A and is projected to remain at LOS A/B.
A3 Aviation Ave. This intersection will only see a slight increase in truck traffic for the north/south movements. The LOS is currently at a level A/B and is projected to remain at LOS B/C.
A4 Earthquakes Way This intersection will only see a slight increase in truck traffic for the north/south movements. The LOS is currently at a level A and is projected to remain at LOS A/B.
A5 Newhall Dr. For both the average and peak truck traffic conditions, the northbound through and left and the southbound through and eastbound right movements will see increased truck traffic. The project plans to assign 75 percent of the truck traffic to this intersection. The LOS is currently at a level B/C and is projected to remain at those levels with the exception of the PM peak with LOS B/E/F. This analysis assumed that a pedestrian call would be activated across Coleman Ave. every cycle, but actual operations should be better street splits will be best applied as determined by the adaptive system.
A6 Airport Blvd. This intersection will only see a slight increase in truck traffic for the north/south movements. The LOS is currently at a level A/B and is projected to remain acceptable.
A7 I-880 SB Ramp This intersection will see a slight increase in truck traffic for the southbound through and westbound right movements. The westbound right is projected to see a slight increase in delay and queuing, which should be manageable by either making slight signal timing split adjustments, or by ensuring the traffic adaptive system makes appropriate automatic adjustments.
The City of San José can make signal timing split adjustments upon request. The Gateway Crossings traffic report also recommended striping changes at this intersection, which may further help mitigate the increase in delay and queuing. The LOS is currently at a level A/B/C and is projected to remain at an acceptable LOS A/B.
A8 I-880 NB Ramp / McKendrie St. This intersection will only see a slight increase in truck traffic for the southbound left movement. The LOS is currently at a level B/C and is projected to remain at LOS B/C.
A9 Hedding St. This intersection is outside of the proposed haul route, but was included due to its proximity and the effects that upstream operations may have on this intersection. The intersection LOS currently operates at level C/D and is projected to continue at those levels. The modeled signal timing was slightly adjusted for the 2024 conditions at this and other project intersections, and due to the increase in truck traffic in the southbound direction along Coleman DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
Ave. there was a slight improvement in delay realized due to an increase in provided green time to accommodate the trucks. No impact is expected due to project hauling operations.
A10 Costco & Brokaw This intersection is currently stop controlled and operates at a LOS A. As part of the Gateway Crossings project mitigation, a traffic signal is planned to be installed and activated no later than mid- 2024. This intersection will only see a slight increase in truck traffic for the east and westbound movements. Although the modeling results show a degradation in operations with the traffic signal, future unknown signal timing settings were assumed and could be different resulting in improved operations based on field observations.
The results shown in the table generally reflect the 25% truck traffic scenario. A check of the 10% non-PayPal 2023 and 2024 Average Trucks operation for the weekend mid-day shows a slightly better LOS and delay than the 25% condition. The 10% Peak Trucks was similar to the 25% Average Trucks condition. KST will monitor the intersection due to project truck traffic and will work with the City of Santa Clara to maintain satisfactory operations. One other possibility may be for the City of Santa Clara to implement their traffic responsive system at this intersection to further fine-tune the signal timing.
All of the detailed analysis information can be found in Appendix D Traffic Operation Data and Analysis.
3.5 CONCLUSIONS
Based on traffic operational analysis of the year 2023 and 2024 average and peak Early Works truck traffic, it is projected that there will be minimal intersections. Project signalized and unsignalized intersections may need to be observed on occasion, particularly during peak truck traffic times to ensure the existing signal timing can handle the added truck volume.
The intersections within City of San José should be able to accommodate the added truck volume since an adaptive traffic signal system is in operation. For intersections within City of Santa Clara (Coleman Ave & Brokaw Road and future signalized Brokaw Road & Costco Driveway), no adaptive system is in operation and the signal timing can be adjusted, if needed, to accommodate the truck volumes as demonstrated in this report.
Project staff will make periodic observations at the project area intersections, both signalized and unsignalized, to ensure acceptable operations continue. KST will schedule the observations before construction begins and will continue the observations approximately once every month and/or that the cities can participate in the observation, if desired.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
4.0 PUBLIC OPERATION AND BUS OPERATIONS
The existing transit services are shown in Figure 3.
4.1 BUS OPERATIONS
The existing bus route along the haul route is summarized in Table 9.
Table 9 - Existing Bus Route
Bus Route Route Description Nearest Stop Headway 1
Local Route 60 Milpitas BART to Winchester Station via
SJC Airport
Coleman/Brokaw;
Coleman/Earthquakes;
Coleman/Newhall
10 15 min
Notes:
1. Approximate headways during peak commute hours.
The existing bus operation is provided by VTA. The proposed construction activities are not expected to impact the existing bus operation. No rerouting is anticipated for the operation. No all times. There is no rapid bus service or Transit Signal Priority (TSP) on Coleman Ave. Services on El Camino Real or any other street in vicinity of the site will not be impacted.
4.2 RAIL TRANSIT OPERATIONS
Caltrain, Capitol Corridor and Altamont Corridor Express (ACE) operate rail transit services at existing Santa Clara Station. The existing transit operations will not be impacted by the construction. There is an existing pedestrian underpass connecting Santa Clara Station and Brokaw Road. The underpass and sidewalk will remain open during construction.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
Figure 3 - Existing Transit Operations
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
5.0 MAINTENANCE OF PROPERTY ACCESS
No property access is anticipated to be impacted at this time. There will be no lane closures or driveway closures and no truck queuing or staging outside of the West Portal site that impedes property access. The traffic operational analysis presented in Chapter 3.0 shows minimal impacts to the existing traffic. Special events and routine operations will be coordinated as described in Section 2.7 and 2.9.
Exhibit showing access to adjacent properties and their business hours, access for employees and customers, delivery and city services, and additional information, for those that were interviewed by VTA in 2021, is included in Appendix C. Also included is an exhibit showing driveway locations to all nearby properties; none of which will be impacted by the West Portal construction.
6.0 SCHOOL ZONE SAFETY PLAN
There are no existing school zones near the West Portal site and no impact is anticipated at this time. Adjacent schools include:
Santa Clara University: 0.6 mi
Scott Lane Elementary School: 1.7 mi
Washington Elementary School: 0.9 mi
Wilson High School: 1.5 mi
Herbert Hoover Middle School: 1.3 mi
Hester School: 1.4 mi
Muwekma Ohlone Middle School: 1.6 mi
Banchrodt Elementary School: 1.2 mi
All distances are measured from approximate center of the schools to the approximate center of the West Portal Site, and are straight line distances. None of the schools or school zones are located on the haul routes. See Figure 4 for the location of nearby schools.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
Figure 4 - Nearby Schools
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
7.0 EMERGENCY ACCESS AND RESPONSE
KST will comply with the Emergency Services Coordination Plan (ESCP), included as Appendix A of the Draft CTMP. Based on the ESCP, KST prepared the Emergency Vehicle Access Plan (EVAP) and Emergency Vehicle Response Plan (EVRP).
7.1 EMERGENCY VEHICLE ACCESS PLAN
Emergency vehicle access to all businesses and residences adjacent to the construction site will be maintained. Emergency service vehicles include:
Emergency medical vehicles
Utility maintenance vehicles for emergency purposes
Fire protection vehicles
Police vehicles
Table 10 along with the 24-hour
emergency hotline. The 24-hour hotline will be managed at all times. Once construction begins a safety representative will be on-site during construction hours.
Table 10 - KST Emergency Contact
Name Title Phone No. Email
Dennis Leonard Project Safety Manager (925) 809-4804 [email protected] Staffed 24-hr Emergency Hotline (408) 321-2345
No traffic lane reductions or detours are necessary for West Portal Early Works; if they become necessary, KST will update this plan and submit to VTA for approval at least 30 days prior to the lane reduction or detour.
Once construction begins, weekly updates will be provided to local emergency service providers in writing by Friday noon regarding emergency vehicle access through, around, and into the construction site for the following week; a copy of this weekly written information will also be provided to VTA prior to Friday noon every week. A kick-off meeting will be held with the emergency service providers, KST and VTA, and as necessary, monthly meetings will be held to ensure emergency service providers are made aware of any changes. A list of emergency service providers covering the West Portal site is included in Table 11; KST will request the emergency service providers to verify this information every week in the Friday update to ensure that they are up to date. See Figure 5 for emergency service areas.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
Table 11 - List of Emergency Contacts as of December 2022 No. Department Contact Name Phone Email
1 San José Police Captain
Jaime Jimenez
(408) 472-7747 [email protected]
2 San José Fire Chief
James Dobson
(Main Contact)
(408) 535-7794 [email protected]
3 San José Fire Captain Greg Tuyor (408) 535-7670 [email protected] 4 San José Fire Station 7
(West Portal Coverage)
Station Captain (408) 794-6907 N/A
5 Santa Clara Police Lieutenant
Cuong Phan
(408) 615-4767 [email protected]
6 Santa Clara Fire Fire Marshal
Jake Tomlin
(Main Contact)
(408) 615-4970 [email protected]
7 Santa Clara Fire Deputy Fire Chief
Jeremy Ray
(408) 615-4953 [email protected]
8 Santa Clara
Fire Station 1
(West Portal Coverage)
Fire Chief
Ruben Torres
(408) 615-4900
9 Santa Clara County
Sheriff
Captain David Lera (408) 321-7153 [email protected]
10 Regional Medical Center (408) 259-5000
11 Santa Clara County
Emergency Medical
Services (EMS)
Michael Cabano (408) 316-6682 [email protected] 12 American Medical
Response (AMR)
Mario Vargas (209) 420-4206 [email protected]
13 Royal Ambulance (877) 995-6161
14 O'Connor Hospital (408) 947-2500
7.1.1 Protocol for Unanticipated Changes
During unanticipated changes, such as detours due to emergency utility work, the change shall be emergency providers. If required, flaggers will be positioned at the begin and end points of the detour route to communicate the change to emergency responders.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
Figure 5 - Emergency Service Area
7.2 EMERGENCY VEHICLE RESPONSE PLAN
of contact listed in Table 10 will be available 24 hours a day and responsible for communicating the location and type of incident to emergency responders and the Construction Safety and Security Manager.
Possible incidents include:
Inadvertent traffic stoppages or delays
Traffic accidents
On-site emergencies
Emergencies requiring police or emergency vehicles
For ondepending on the type of incident. Individual KST employee or contractor is allowed to dial 9-1-1 in -1-
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 04 Date: 05/30/2023
al emergency providers and
coordinate with other KST employee or contractor, such as guard posts at gates, to ensure emergency access.
point of contact will coordinate with other KST parties to ensure that emergency access is not impeded during an emergency. Emergency vehicles will have the right-of-way on all site roads during an emergency.
8.0 CITY PERMIT REQUIREMENTS
BSVII Draft CTMP Appendix H and J contains permit requirements for City of San José and City of Santa Clara, respectively. KST has identified permits that pertains to the West Portal Early Works construction, which are highlighted in yellow and included in Appendix E of this CTMP.
9.0 LIST OF APPENDICES
Appendix A Site Layout, Sequencing and Staging Plan
Appendix B Traffic Control Plans
Appendix C Access to Businesses and Properties
Appendix D Traffic Operation Data and Analysis
Appendix E City Permit Requirements
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 02 Date: 04/10/2023
APPENDIX A
SITE LAYOUT, SEQUENCING AND STAGING PLAN
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 02 Date: 04/10/2023
APPENDIX B
TRAFFIC CONTROL PLANS
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 02 Date: 04/10/2023
APPENDIX C
ACCESS TO BUSINESSES AND PROPERTIES
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 02 Date: 04/DD/2023 Page i
1.0 INTRODUCTION....................................................................................................C-1
2.0 GENERAL INFORMATION ....................................................................................C-2
2.1 Hours of Operations...............................................................................................C-2
2.2 Busiest Time of Day...............................................................................................C-2
2.3 Written and Spoken Languages and Accommodations Needed.............................C-2
2.4 Number of Employees and Visitor..........................................................................C-2
2.5 Renovations and Expansions.................................................................................C-3
3.0 ACCESS FOR EMPLOYEES AND CUSTOMERS.................................................C-3
3.1 Access for Employees and Customers...................................................................C-3
3.2 Arrival Times Weekdays .....................................................................................C-3
3.3 Arrival Times Weekends .....................................................................................C-3
4.0 SPECIAL EVENTS AND ROUTINE OPERATION .................................................C-3
5.0 DELIVERY AND CITY SERVICES.........................................................................C-3
5.1 Trash .....................................................................................................................C-3
5.2 Mail........................................................................................................................C-4
5.3 Deliveries...............................................................................................................C-4
5.4 Loading and Unloading ..........................................................................................C-4
6.0 ADDITIONAL INFORMATION PROVIDED ............................................................C-4
7.0 INDIVIDUAL INTERVIEW DOCUMENTATION ......................................................C-4
8.0 SPRINT FACILITY ACCESS..................................................................................C-4 DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 02 Date: 04/DD/2023 Page C-1
1.0 INTRODUCTION
This attachment summarizes local business information and access needs by topic, specifically for the area of West Portal. The information is extracted from the BSVII Draft CTMP Appendix B Summary of Access and Service Needs Memorandum, dated 12/15/2020 and 1/21/2021, with additional verification and supplementation from December 2022.
This attachment only summarizes key businesses and facilities near the West Portal site and is not an exhaustive list. However, KST has reviewed all property access near the site, as presented in the attached Property Access Exhibit, and will ensure that no property access is impacted for the Early Works, even if the property is not included in this appendix. See the table below for a summary of key businesses and facilities included in this appendix.
Table 1 - Key Businesses and Facilities
No. Name Type Impact Business
Hours
Address Contact Phone Email
1 Apple Research and
Development
N 6 am to 6 pm 335 Brokaw
Road, Santa
Clara, CA
95050
John
Rickard III
650-208-4081 [email protected]
2 New Eden
Spa
Salon/Personal
Services
N 10 am to 9 pm 1335 Coleman
Avenue, Santa
Clara, CA
95050
Antion
Zhu
408-320-2878 [email protected]
3 PayPal
Park
Stadium N 8 am to 9 pm 1123 Coleman
Avenue, San
José, CA
95110
Luke De
Vogelaere
408-556-7742
650-804-9031
ldevogelaere
@sjearthquakes.com
4 Santa
Clara
University
School N 6 am to 9 pm
(Weekday)
Residents
remaining on
campus through
the weekend
500 El Camino
Real, Santa
Clara, CA
95053
Chris
Shay
408-551-1606 [email protected]
5 Costco
Wholesale
Retailer N 9 am to 8:30 pm
(Weekday)
9 am to 7 pm
(Weekend)
1601 Coleman
Avenue, Santa
Clara, CA
95050
Javier
Zuniga
408-567-9000
Ext. 1
N/A
6 Coleman
Highline
Office
Development
N 7 am to 6 pm
(Weekday)
Mostly closed on
weekends
West of
Coleman Ave
between
Champions
Way and
Earthquakes
Way
Todd
Trekell
408-200-8904 todd
@hunterproperties.com
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 02 Date: 04/DD/2023 Page C-2
2.0 GENERAL INFORMATION
2.1 HOURS OF OPERATIONS
Below are the hours of operations for local businesses and facilities as of December 2022.
Apple: 6 a.m. to 6 p.m.
New Eden Spa: 10 a.m. to 9 p.m.
Costco Wholesale:
o Weekday: 9 a.m. to 8:30 p.m.
o Weekend: 9 a.m. to 7 p.m.
PayPal Park:
o 8 a.m. to 9 p.m.
o Pre-event setup approximately 8 to 10 hours
o to 5 hours prior to start time
Coleman Highline:
o Weekday: 7 a.m. to 6 p.m. for the majority of the facility Santa Clara University (14,000 students and 2,000 staff/faculty):
o Weekday: 6 a.m. to 9 p.m.
o Residents remaining on campus through the weekend
2.2 BUSIEST TIME OF DAY
Below are the busiest times of day for local businesses and facilities.
Apple: Weekday morning before 12 p.m.
New Eden Spa: Weekday afternoon between 12 p.m. and 5 p.m.
Costco Wholesale: Busy all-day
PayPal Park:
o Weekday: Evening after 5 p.m. kick-off time
o Weekend: Afternoon kick-off at 12 p.m. and evening after 5 p.m.
Coleman Highline: Weekday morning from 9 a.m. to 12 p.m.
2.3 WRITTEN AND SPOKEN LANGUAGES AND ACCOMMODATIONS
NEEDED
Below are written and spoken languages commonly used by t customers besides English, and any special accommodations needed.
New Eden Spa: Mandarin
Costco Wholesale: Spanish
PayPal Park: Spanish
2.4 NUMBER OF EMPLOYEES AND VISITOR
Coleman Highline: At least 2,900 employees when the Verizon construction is completed in December 2021; approximately 100 to 150 daily visitors
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 02 Date: 04/DD/2023 Page C-3
2.5 RENOVATIONS AND EXPANSIONS
Below are businesses that might conduct renovations/expansions in the next 2 to 10 years.
PayPal Park: Plan to conduct major renovation in conjunction with the Coleman Highline construction Coleman Highline: Additional construction of the development through December 2021 (Verizon); Phase 4 (between Verizon and Aviation Ave) 300,000 SF to be completed once a tenant is obtained with estimated construction start of 2023.
3.0 ACCESS FOR EMPLOYEES AND CUSTOMERS
3.1 ACCESS FOR EMPLOYEES AND CUSTOMERS
Businesses near the West Portal area noted that most of their employees and customers will access the properties by driving. The major
including PayPal Park. Downtown locations are more likely to have parking on the street nearby or parking garages.
For schools, there are no schools currently using school buses. At least half of the staff and faculty regularly drive, most parking in on-site school parking lots. Santa Clara University provides residential parking lots and commuter parking garages for staff, faculty and students. Most students live on or near campus and can walk to classes.
3.2 ARRIVAL TIMES WEEKDAYS
At most locations, employees and customers tends to arrive before 12 p.m. on weekdays. See below for additional details.
PayPal Park: 8 to 10 hours in advance of events, as early as 9 a.m.
Coleman Highline: 7 a.m. to 9 a.m.
Santa Clara University:
o Staff/students arrive 7 a.m. to 9 a.m.
o Staff/students leave 3:30 p.m. to 5 p.m.
o Graduate students arrive 4 p.m. to 6 p.m. for night classes
3.3 ARRIVAL TIMES WEEKENDS
At most locations, facilities will be closed on weekends with no arrivals. Notable businesses open on weekends near West Portal include PayPal Park and Costco Wholesale. See below for additional details.
PayPal Park: 8 to 10 hours in advance of events, as early as 9 a.m.
4.0 SPECIAL EVENTS AND ROUTINE OPERATION
PayPal Park will host events throughout the year, which will be considered and coordinated as routine operation.
5.0 DELIVERY AND CITY SERVICES
5.1 TRASH
Costco Wholesale: Everyday between 6 a.m. and 7 a.m.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 02 Date: 04/DD/2023 Page C-4
PayPal Park: Based on events; no regular hours
Coleman Highline: Early mornings; specific days are unknown
5.2 MAIL
Coleman Highline: 8 a.m. to 12 p.m.
5.3 DELIVERIES
Costco Wholesale: 3 to 4 trucks from 3 a.m. to 6 a.m., 2 trucks from 8 a.m. to 10 a.m., and 2 trucks from 4 p.m. to 6 p.m.
5.4 LOADING AND UNLOADING
Apple: Several times a week, a loading dock
New Eden Spa: Not required, FedEx/UPS Deliveries in the parking lot take 1 to 10 minutes each Costco Wholesale: Multiple times a day from 8 a.m. to 12 p.m., has a loading dock, 1 to 10 minutes per delivery
PayPal Park: Has a loading dock behind the stadium and passenger pick up and drop off is currently at the intersection at Coleman with post COVID plans to reevaluate location. No deliveries take place during events but do receive bulk deliveries several times a week and smaller FedEx/UPS deliveries daily from 8 a.m. to 3 p.m.
Coleman Highline: Multiple times a day, typically from 8 a.m. to 12 p.m. with a varied time per delivery. Loading docks are available in Buildings 1, 2 (Brandley), 3, and 4 (Aviation Ave).
Depending on direction of arrival, the delivery vehicles would need to make a left turn into the main campus, but not directly to the loading dock
Santa Clara University: Once a day in the shipping & receiving area loading dock at the dinning hall (opposite side of campus from transit center)
6.0 ADDITIONAL INFORMATION PROVIDED
Apple: Testing lab on site. Apple will internally confirm whether they will be impacted by vibrations due to the tunnel boring machine, but it is unlikely as the West Portal is far from the Apple site.
PayPal Park: Requested that the TPMP be reviewed and continue to coordinate with the Coleman Highline development.
Santa Clara University: Expressed concerns about the main gate at El Camino Real and Palm Drive.
The West Portal Early Works will not affect the main entrance as trucks will not be routed through El Camino Real.
7.0 INDIVIDUAL INTERVIEW DOCUMENTATION
Individual interview documentation and applicable attachments from the BSVII Draft CTMP Appendix B Summary of Access and Service Needs Memorandum, dated 12/15/2020 and 1/21/2021, for businesses and facilities near the West Portal site, are attached to this appendix.
8.0 SPRINT FACILITY ACCESS
There is an existing Sprint fiber optics facility, located at 801 Newhall Drive, as well as an existing fiber optic line at the West Portal site operated by Sprint. The existing fiber optic line is proposed to be relocated, but remaining within the West Portal site. KST has been noted that Sprint has an easement for DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 02 Date: 04/DD/2023 Page C-5
accessing their facilities and fiber optic lines through the VTA-owned West Portal site. KST is in coordination with VTA and Sprint to ensure that their access will not be impacted by the construction activities at West Portal.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document. 1 Date: 11/30/20 @ 15:52pm
Organization: Apple
Type of Organization: Research and Development
Attendees: Rod Diridon, John Rickard III, Monica F., Erica R.
Project Area: Santa Clara
Address: 335 Brokaw Road, Santa Clara, CA 95050
Main Point of Contact
Name: John Rickard III
Phone Number: 650-208-4081
Email Address: [email protected]
------------------------------------------------------------------------------------------------------------------------------ Question Letter
Answer Comments
1. Are you this business or organization’s
owner or manager?
a. Yes
b. No
A
2. Has your business, organization, or
institution made any operational or access
changes due to Santa Clara County Public
Health orders due to COVID-19 (e.g. offer
outdoor seating, outdoor retail or services,
added a virtual storefront, created pick-up
area, increased customer delivery)? If yes,
please describe..
a. Yes [comment box]
b. No
c. Not sure / Prefer not to answer /
Not applicable
C
3. What are your hours of operation?
(i.e. M-F 8 am – 5 pm)
6am to 6 pm
4. Please select your typically busiest times:
a. Weekday Morning (before 12 Noon)
b. Weekday Afternoon (between 12
Noon and 5 p.m.)
c. Weekday Evening (after 5 p.m.)
d. Weekend Morning (before 12
Noon)
e. Weekend Afternoon (between 12
Noon and 5 p.m.)
f. Weekend Evening (after 5 p.m.)
g. Not sure / Prefer not to answer /
Not applicable
Weekday Morning (before 12
Noon)
8:30 am to 10 am
DRAFT--Contact the Office of the City Clerk at (408)
12.15.2020 Access & Service Needs Memo
535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408)
12.15.2020 Access & Service Needs Memo
535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408)
12.15.2020 Access & Service Needs Memo
535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408)
12.15.2020 Access & Service Needs Memo
535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408)
12.15.2020 Access & Service Needs Memo
535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408)
12.15.2020 Access & Service Needs Memo
535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408)
12.15.2020 Access & Service Needs Memo
535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408)
12.15.2020 Access & Service Needs Memo
535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408)
12.15.2020 Access & Service Needs Memo
535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408)
12.15.2020 Access & Service Needs Memo
535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408)
12.15.2020 Access & Service Needs Memo
535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408)
12.15.2020 Access & Service Needs Memo
535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408)
12.15.2020 Access & Service Needs Memo
535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408)
12.15.2020 Access & Service Needs Memo
535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408)
12.15.2020 Access & Service Needs Memo
535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408)
12.15.2020 Access & Service Needs Memo
535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408)
12.15.2020 Access & Service Needs Memo
535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408)
12.15.2020 Access & Service Needs Memo
535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408)
12.15.2020 Access & Service Needs Memo
535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408)
12.15.2020 Access & Service Needs Memo
535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408)
12.15.2020 Access & Service Needs Memo
535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408)
12.15.2020 Access & Service Needs Memo
535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408)
12.15.2020 Access & Service Needs Memo
535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408)
12.15.2020 Access & Service Needs Memo
535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408)
12.15.2020 Access & Service Needs Memo
535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408)
12.15.2020 Access & Service Needs Memo
535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408)
12.15.2020 Access & Service Needs Memo
535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408)
12.15.2020 Access & Service Needs Memo
535-1260 or [email protected] for final document. 408.321.5893
DRAFT--Contact the Office of the City Clerk at (408)
12.15.2020 Access & Service Needs Memo
535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408)
535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 02 Date: 04/10/2023
APPENDIX D
TRAFFIC OPERATION DATA AND ANALYSIS
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
D-1 LOS RESULTS SUMMARY TABLES
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
D-2 FIGURES
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document. 12 (12)
0 (0)
6 (17)
11 (10)
0 (0)
9 (41)
101 (125)
185 (354)
242 (146)
296 (376)
251 (277)
59 (74)
26 (87)
6 (10)
163 (357)
0 (0)
78 (62)
0 (0)
1 (0)
1 (2)
106 (375)
22 (13)
110 (252)
19 (12)
6 (29)
27 (160)
5 (5)
5 (5)
11 (8)
611 (415)
152 (146)
272 (263)
259 (336)
120 (92)
57 (89)
11 (51)
1 (3)
218 (315)
34 (12)
NTS
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document. 000
000
000
000
3460
97 001
292
16 24400
0 00
0000
387
340
16 NTS
00 30
15 54
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document. 201
70 14
81 114
92 175
141
49 3730
94 100
397
13 30004
5 553
104
254
195
82 71
151
468
12 NTS
225
23 21
57 DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document. 14 (34)
[100%]
NTS
4 (9)
[25%]
10 (25)
[75%]
4 (9)
[25%]
4 (9)
[25%]
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document. 12 (12)
0 (0)
6 (17)
11 (10)
0 (0)
9 (41)
101 (125)
185 (354)
242 (148)
296 (380)
251 (277)
59 (74)
26 (87)
6 (10)
173 (471)
0 (0)
78 (114)
0 (0)
1 (0)
1 (2)
110 (379)
22 (13)
110 (252)
19 (12)
6 (29)
27 (160)
5 (5)
5 (5)
11 (8)
611 (443)
152 (146)
287 (297)
259 (336)
120 (98)
57 (89)
15 (55)
1 (3)
218 (315)
38 (16)
NTS
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document. 000
000
000
000
3560
97 001
296
16 24400
0 00
0000
427
340
20 NTS
00 30
15 54
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document. 201
70 14
81 114
92 175
141
49 3830
94 100
401
13 30004
5 553
104
268
195
82 71
191
468
16 NTS
225
23 21
57 DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document. 12 (12)
0 (0)
6 (17)
11 (10)
0 (0)
9 (41)
101 (125)
185 (354)
242 (148)
296 (380)
251 (277)
59 (74)
26 (87)
6 (10)
189 (487)
0 (0)
78 (114)
0 (0)
1 (0)
1 (2)
115 (385)
22 (13)
110 (252)
19 (12)
6 (29)
27 (160)
5 (5)
5 (5)
11 (8)
611 (443)
152 (146)
307 (317)
259 (336)
120 (98)
57 (89)
20 (60)
1 (3)
218 (315)
43 (21)
NTS
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document. 000
000
000
000
3710
97 001
301
16 24400
0 00
0000
477
340
25 NTS
00 30
15 54
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document. 201
70 14
81 114
92 175
141
49 3980
94 100
406
13 30004
5 553
104
288
195
82 71
241
468
21 NTS
225
23 21
57 DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document. -1 (12)
-3 (12)
42 (-18)
173 (18)
-28 (91)
-9 (94)
5 (3)
75 (39)
1 (3)
18 (73)
43 (170)
NTS
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
NTS
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document. 8 (1)
12 (2)
89 (17)
62 (212)
19 (4)
NTS
36 (236)
17 (116)
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document. 103 (128)
188 (361)
254 (161)
311 (397)
256 (283)
60 (76)
6 (10)
150 (364)
23 (14)
285 (275)
20 (12)
6 (29)
27 (163)
5 (5)
106 (83)
11 (8)
684 (531)
155 (149)
NTS
49 (248)
0 (0)
23 (133)
11 (10)
0 (0)
9 (42)
26 (88)
166 (364)
0 (0)
79 (63)
0 (0)
1 (0)
1 (2)
147 (110)
58 (90)
331 (374)
264 (342)
0 (0)
86 (90)
1 (3)
223 (321)
52 (85)
43 (170)
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document. 000
000
000
000
3530
99 001
340
16 42200
0 00
0000
NTS
00 31
15 55
0 1148
347
35 43
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document. 2380
117
70 14
83 116
107
193
144
50 3800
96 100
387
13 324
5 672
106
565
199
91 72
NTS
225
23 21
58 0
544
477
86 171
04 DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document. 103 (128)
188 (361)
254 (163)
311 (401)
256 (283)
60 (76)
6 (10)
154 (368)
23 (14)
285 (275)
20 (12)
6 (29)
27 (163)
5 (5)
106 (83)
11 (8)
684 (560)
155 (149)
NTS
49 (248)
0 (0)
23 (133)
11 (10)
0 (0)
9 (42)
26 (88)
177 (480)
0 (0)
79 (116)
0 (0)
1 (0)
1 (2)
147 (116)
58 (90)
345 (409)
264 (342)
0 (0)
90 (95)
1 (3)
223 (321)
56 (89)
43 (170)
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document. 000
000
000
000
3630
99 001
344
16 42200
0 00
0000
NTS
00 31
15 55
0 1188
347
39 43
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document. 2380
117
70 14
83 116
107
193
144
50 3910
96 100
391
13 324
5 672
106
579
199
91 72
NTS
225
23 21
58 0
584
477
90 171
04 DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document. 103 (128)
188 (361)
254 (163)
311 (401)
256 (283)
60 (76)
6 (10)
159 (373)
23 (14)
285 (275)
20 (12)
6 (29)
27 (163)
11 (8)
684 (560)
155 (149)
NTS
49 (248)
0 (0)
23 (133)
11 (10)
0 (0)
9 (42)
26 (88)
192 (496)
0 (0)
79 (116)
0 (0)
1 (0)
1 (2)
147 (116)
58 (90)
366 (430)
264 (342)
0 (0)
96 (100)
1 (3)
223 (321)
61 (95)
43 (170)
5 (5)
106 (83)
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document. 000
000
000
000
3680
99 001
349
16 42200
0 00
0000
NTS
00 31
15 55
0 1238
347
44 43
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document. 2380
117
70 14
83 116
107
193
144
50 4060
96 100
396
13 324
5 672
106
600
199
91 72
NTS
225
23 21
58 0
634
477
95 171
04 DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
D-3 QUEUING ANALYSIS
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
D-4 SYNCHRO MODEL RESULTS
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
D-5 TRAFFIC COUNT DATA
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
CTMP for West Portal Early Works Revision Number: 02 Date: 04/10/2023
APPENDIX E
CITY PERMIT REQUIREMENTS
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.
DRAFT--Contact the Office of the City Clerk at (408) 535-1260 or [email protected] for final document.