Project
Overview
• Located along State Route 87 in the
City of San José, Santa Clara
County
• Construction Begins: July 2023
Construction Ends: March 2025
• Total Project Funding:$ 69,630,000
Project Scope
•Replace roadway pavement with
20-year life cycle flexible
pavement structure
•Upgrade 28 curb ramps at six
intersections
•Resurface 2.9 miles of class I
bikeway that runs parallel to the
mainline
•Enhance corridor safety
o Replace median concrete
barrier and guardrails
o Enhanced wet/night
visibility striping
o Upgrade drainage facilities
Full Highway
Closure Details
• Perform significant amount of paving
work using full closures
• Two separate weekends (56-hour
closures)
• Only one direction of SR-87 closed
each weekend
• Closures between I-280 and SR-85
• Northbound SR-87 Closure –
Weekend #1
• 9PM Friday,September 22 to
5AM Monday, September 25
• Southbound SR-87 Closure –
Weekend #2:
• 9PM Friday,October 20 to 5AM
Monday, October 23
Full Highway
Closure -
Project
Benefits
• Improve safety by minimizing worker exposure to traffic: 30+ less shifts • Schedule savings - potentially 3 months
• Reduced amount of overall nighttime lane closures and nighttime work • Improve pavement quality prior to winter 2023
• Overall cost savings to the project
Traffic
Management
Plan
• Regional Changeable
Message Sign (CMS)
Deployment
• Detours
• Emergency Response Access
• Command Center
• Outreach Effort
Northbound SR-87 Closure – PCMS Locations
Detour:
Northbound
SR-87 Closure
• NB SR-87 CLOSED BETWEEN I-
280 AND SR-85
• Use SB SR-85 to NB Bernal
Rd/NB US-101/NB I-280
(Detour A)
• Use NB SR-85/NB SR-17/SB I-
280(Detour B)
Detour:
Southbound
SR-87 Closure
• SB SR-87 CLOSED
BETWEEN I-280 AND
SR-85
• Use SB I-280 to SB US
101/NB SR-85 (Detour
A)
• Use NB I-280 to SR-17
to SB SR-85
Full Highway
Closure
Considerations
• Impact to detour routes (SR-17, I-280,
SR-85, US-101)
• No closures needed on City or County
roads
• Impact to City of San José due to ramp
closures and detour traffic
• SJC Airport, SAP Center, Levi’s Stadium,
Downtown San Jose
• Other weekend closure coordination
around District 4
Outreach
Effort:
• City Council Meetings - Santa Clara
County BOS 8/29, SJ City Council 9/12
• Radio/TV Station News – Week of 9/13
• Paid Media Advertisements – Week of
9/13
• Caltrans Website – Live since July ‘23
• Social Media (Caltrans & Cities) –
Began 8/17
• Press Release/Traffic Advisories –
Began 8/17
• Project Mailers/Flyers – At post office
the Week of 8/27
Outreach
Effort: Project
Website and
Hotline
• For Additional project information:
• Caltrans SR-87 Pave Project Website
• SR87pave.com
• Email Address:[email protected]
• SR 87 Pave Project Hotline Number:
• (510) 286-0319
Thank you • QUESTIONS/COMMENTS