Supplemental EIRs to Downtown Strategy 2040 EIR
Project File No. Project Name Type of Env
Document Start Date Approval Date
Review
Time
(months)
Env Review
Hours
SP21-044, HP21-001, ER22-249 19 N. Second St Mixed-Use Project SEIR 11/25/2020 3/28/2023 28 198 H18-038 Almaden Corner Hotel Project SEIR 8/28/2018 1/14/2020 16 132 H19-033 Sobrato Block 8 Office SEIR 7/23/2019 4/13/2021 20 112 H20-038, ER20-243 Bo-Town Mixed-Use Project SEIR 12/2/2020 11/29/2022 23 135 H19-016 CityView Plaza SEIR 4/19/2019 6/16/2020 13 125
H20-037, ER20-272 Energy Hub/Fountain Alley Mixed-Use - Westbank SEIR 12/1/2020 12/13/2022 24 185 H20-004/GP19-008 Woz Way Office Project (KT Urban) SEIR 10/2/2019 6/29/2021 20 235 SP20-021/ER20-127 The Mark (Urban Catalyst) SEIR 6/18/2020 10/14/2021 15 222 SP20-005/ER20-144 Boston Properties - Woz Way SEIR 7/6/2020 9/14/2021 14 389 H19-053/ER20-022 Marriott Townhome Suites West San Carlos SEIR 2/4/2020 8/24/2021 18 163.5 SP21-031/ER21-134/T21-033 The Icon/Echo (Urban Catalyst) SEIR 7/23/2021 11/29/2022 16 547 H21-026/ER21-085 4th Street Pizza (SuZaCo) SEIR 5/28/2021 11/29/2022 18 349 H21-012/ER21-026 Valley Title (Westbank) SEIR 3/16/2021 9/28/2022 18 137 H17-004/ER20-262 439 and 451 S. 4th Street/Metro Station (Caruso) SEIR 1/18/2017 3/12/2024 85 121 SP18-001/T18-001 Garden Gate Tower SEIR 1/9/2018 3/9/2020 26 130 H16-042/HP17-003 Tribute Hotel SEIR 10/18/2016 1/28/2020 39 152.5 Supplemental EIR Summary
Average Review Time (months): 24.6
Average Environmental Review Hours: 208.3
Addendums to DTS 2040 FEIR
Project File No. Project Name Type of Env
Document Start Date Approval Date
Review
Time
(months)
Env Review
Hours
SP21-019, SP21-020, ER21-099 420 S. 2nd St. and S. 3rd. St. Mixed Use Project (NABR) Addendum 6/18/2021 12/14/2022 17 108 H18-045 200 Park Avenue Office Project Addendum 9/27/2018 10/9/2019 12 42 SP21-037,T21-026 255 W. Julian St (Arbor) Addendum 11/16/2020 11/17/2021 12 43 H21-052, ER21-302 250 Stockton Ave Office Project Addendum 12/15/2021 2/22/2023 14 69 H18-037 Adobe North Tower Addendum 8/16/2018 5/29/2019 9 9.5* H20-021 Almaden Blvd Tower Addendum 6/29/2020 12/9/2020 5 95 H20-026 Eterna Tower Mixed-Use Addendum 7/27/2020 8/24/2022 24 118 H21-048, T21-043, ER21-276 Apollo Residential Project Addendum 10/28/2021 11/9/2022 12 87 SP20-020,T19-041 (former H18-025) Carlysle Mixed-Use Project Addendum 6/5/2018 7/8/2020 25 32 GP19-012, CP20-019 Delmas Senior Living Project Addendum 6/25/2020 1/27/2021 7 61 PDC20-020, PT20-036, PD20-011 Dupont/McEvoy Residential Project Addendum 5/11/2021 5/10/2022 11 42 H19-021, ER22-055 4th & St. John Student Housing Addendum 5/13/2019 10/18/2023 53 34 H19-041, HP19-007, T19-035 Fountain Alley Building (FAB) - Urban Catalyst Addendum 9/19/2019 8/12/2020 10 28 H17-059 Hotel Clariana Expansion Addendum 10/25/2017 3/11/2020 28 23 SP20-019/ER20-122 The Madera - now TMBR (Urban Catalyst) Addendum 6/17/2020 3/17/2021 9 36 SP20-039/ER20-126 Camera 12 (Urban Catlyst) Addendum 6/18/2020 12/16/2020 5 29 HA17-059-01 Hotel Clariana Phase II Addendum 8/26/2020 10/5/2022 25 37 SP22-021/SP22-025/ER22-190 Private School in Armory and Moir Buildings (240 N 2nd St and 227 N 1st St) Addendum 6/18/2022 6/28/2023 12 54 H21-027/H21-028/ER21-101/ER21-103 Montgomery Plaza Mixed Use Project Addendum 7/14/2021 12/14/2022 17 45 SP21-045/ER21-312 Terrain (Westbank Project next to Arbor) Addendum 1/6/2022 3/27/2024 26 52 H22-031/ER22-186 Diridon Office Project (Joint Powers Board) Addendum 8/16/2022 12/4/2024 27 63 ER20-011 Lot E Parking Garage Project Addendum 4/19/2019 10/18/2022 41 32 SP20-032 Park Habitat (former Museum Place) Addendum 9/20/2020 11/3/2021 13 30 SPA17-023-01 Star City Co-Living Addendum 12/11/2018 5/29/2019 5 20.5 PP20-001 NSP and Bassett Park Addendum 1/16/2020 12/1/2020 10 37.5 SP19-063/C19--039 Stockton Hotel and Condominium Project Addendum 8/7/2018 3/13/2020 19 43 *Note: Insufficient data.
Addendum Summary
Average Review Times (months): 17.2
Average Environmental Review Hours: 48.9
Attachment A: Downtown Projects Since 2018 Downtown Strategy 2040 EIR Adoption