700 LOS ESTEROS ROAD SAN JOSE, CA 95134
SUPPLEMENTAL COUNCIL AGENDA: 4/15/25
FILE: 25-376
ITEM: 6.1

SAN JOSE I SANTA CLARA

WATER POLLUTION CONTROL PLANT
April 10, 2025
The Honorable Mayor and City Council
City of San José
200 East Santa Clara Street
San José, CA 95113
Dear Mayor Mahan and City Council:

TREATMENT PLANT ADVISORY COMMITTEE

At its meeting on 10 April 2025, the Treatment Plant Advisory Committee (TPAC) reviewed this item:

5. A. Report on Bids and Award of Construction Contract for 10186 - Yard Piping Improvements Phase 3 Project at the San Jose-Santa Clara Regional Wastewater Facility
Staff Recommendation:
(a) Accept the report on bids and award of construction contract to the lowest responsive, responsible bidder, Michels Trenchless, Inc., in the amount of $19,490,000, for the 10186 – Yard Piping Improvements Phase 3 Project; and

(b) Approve a 10% construction contingency in the amount of $1,949,000.

Action: On a motion made by Vice Chair Cohen and a second by Committee Member Candelas, TPAC recommended approval of the item:

Ayes – 7 (Candelas, Cohen, Gonzalez, Hardy, Kwok, Montano, Mulcahy) Nays – 1 (Furtado)