UBJECT: Report on Bids and Award of Contract for the 10091 – Sanitary Sewer Repairs FY 2022-2023 Package VI Project
RE
COMMENDATION
(a
) Report on bids and award of contract for the construction of 10091 – Sanitary Sewer Repairs FY 2022-2023 Package VI Project to the lowest responsive, responsible bidder, Devaney Engineering, Inc., in the amount of $1,375,685; and (b
) Approve a 10% contingency in the amount of $137,568.
S
UMMARY AND OUTCOME
A
ward of the contract to Devaney Engineering, Inc., enables the construction of the 10091 – Sanitary Sewer Repairs FY 2022-2023 Package VI Project (Project), which will provide necessary sewer improvements that will minimize the risk of wastewater leaking out of sanitary sewer pipes and entering adjacent storm sewer pipes as required by the Exfiltration Abatement Program. Approval of a 10% contingency provides funding for any unanticipated work necessary for the proper completion or construction of the Project.
BACKG
ROUND
Th
e City of San José Department of Public Works developed an Exfiltration Abatement Program to minimize the risk of wastewater leaking out of sanitary sewer pipes and entering adjacent storm sewer pipes. The Project is a part of this program and will repair and rehabilitate the most significantly defective sewer mains that are either crossing COUNCIL AGENDA: 6/17/25
FILE: 25-706
ITEM: 2.38
HONORABLE MAYOR AND CITY COUNCIL
May 27, 2025
Subject: Report on Bids and Award of Contract for the 10091 – Sanitary Sewer Repairs FY 2022- 2023 Package VI Project
above or adjacent to (within 10 feet) an existing storm drainpipe. The sanitary sewer segments included as a part of this Project are located throughout City Council District 6 (Attachment A – 10091 – Sanitary Sewer Repairs FY 2022-2023 Package VI Project Location Map).
This Project will video inspect the condition of 32 selected six-inch, eight-inch, and 12- inch diameter vitrified clay and concrete sewer pipe segments, perform necessary point repairs, and install approximately 9,000 linear feet of cured-in-place pipe liner. The Project also includes the construction of a new sanitary sewer manhole, the rehabilitation of existing manholes, and the reconnection of active sanitary sewer service laterals.
Construction is scheduled to begin in September 2025, with substantial completion in February 2026.
ANALYSIS
Bids were opened on April 17, 2025, with the following results:
Contractor
Bid Amount Variance
Amount
Over/(Under)
Percent
C2R Engineering, Inc.
(Los Altos)
(non-responsive)
$1,237,879 ($393,284) (24)
Devaney Engineering, Inc.
(San Francisco) $1,375,685 ($255,478) (16)
Engineer’s Estimate $1,631,163 -- --
SubTerra Construction, Inc.
(San Francisco) $1,870,574 $239,411 15
Procurement Issues
The bid submitted by C2R Engineering, Inc. was deemed non-responsive due to improperly completing the California Air Resources Board compliance form.
HONORABLE MAYOR AND CITY COUNCIL
May 27, 2025
Subject: Report on Bids and Award of Contract for the 10091 – Sanitary Sewer Repairs FY 2022- 2023 Package VI Project
Bid Price Analysis
The low bid submitted by Devaney Engineering, Inc., is 16% below the Engineer’s Estimate. The lower than estimated bid can be attributed to a competitive bidding environment and the contractor’s familiarity with this type of work. Staff considers the low bid to be competitive and acceptable for the work involved.
Contractor Responsibility Analysis
Devaney Engineering, Inc., has successfully completed multiple sanitary sewer projects of similar scope for the City of San José, including 8946 - Sanitary Sewer Repairs FY 2018-2019 Package I accepted in October 2020, and 9014 - Sanitary Sewer Repairs FY 2018-19 Package III accepted in March 2020.
Contingency
San José Municipal Code Section 27.04.050 provides for a standard contingency of 10% on all public works contracts except those involving the renovation of a building or buildings. The standard 10% contingency is appropriate for this Project.
Wage Theft Prevention Policy Check
The Office of Equality Assurance reviewed bidders for compliance with the City’s Wage Theft Prevention Policy on April 17, 2025, and again on April 29, 2025. No wage theft issues were identified.
Project Labor Agreement Applicability
The City’s Project Labor Agreement is applicable to this Project because the Engineer’s Estimate is over $1.21 million.
Local and Small Business Analysis
The recommended contractor is not a local or a small business enterprise. No local and/or small business enterprise were listed as subcontractors.
EVALUATION AND FOLLOW-UP
No additional follow-up action with the City Council is expected at this time.
HONORABLE MAYOR AND CITY COUNCIL
May 27, 2025
Subject: Report on Bids and Award of Contract for the 10091 – Sanitary Sewer Repairs FY 2022- 2023 Package VI Project
COST SUMMARY/IMPLICATIONS
The source of funding for the Project is through the 545 Sewer Service & Use Charge Capital Improvement Fund. The proposed operating and maintenance costs of this Project have been reviewed, and it has been determined that the Project will have no significant adverse impact on the Sewer Service and Use Charge Fund or General Fund operating budgets. This Project is consistent with the City Council-approved Budget Strategy Economic Recovery section in that it will spur construction spending in our local economy.
1. TOTAL COST OF PROJECT:
Project Delivery* $ 459,777
Construction (See Cost Breakdown Below) 1,375,685
Contingency 137,568
TOTAL PROJECT COSTS $1,973,030
Prior Years’ Expenditures 119,200
TOTAL REMAINING PROJECT COSTS $1,853,830
*Project delivery includes $181,667 for design services and $278,110 for construction management and inspection services.
2. COST ELEMENTS OF CONTRACT AS RECOMMENDED AS PART OF THE MEMORANDUM:
Mobilization and Traffic Control $ 175,000
Point Repairs 120,000
Cured-in-Place-Pipe Liner Installation 775,195
Manhole Rehabilitation 71,500
Other Construction Costs 233,990
TOTAL CONTRACT AMOUNT $1,375,685
BUDGET REFERENCE
Project costs and associated expenses are expected to be incurred within the 2025- 2026 fiscal year. All funding is subject to the appropriation of funding by City Council.
HONORABLE MAYOR AND CITY COUNCIL
May 27, 2025
Subject: Report on Bids and Award of Contract for the 10091 – Sanitary Sewer Repairs FY 2022- 2023 Package VI Project
COORDINATION
This memorandum has been coordinated with the City Attorney’s Office, the City Manager’s Budget Office, and the Planning, Building and Code Enforcement Department.
PUBLIC OUTREACH
This memorandum will be posted on the City’s Council Agenda website for the June 17, 2025 City Council meeting.
COMMISSION RECOMMENDATION AND INPUT
No commission recommendation or input is associated with this action.
CEQA
Exempt, File No. ER23-189. CEQA Guidelines Sections 15301(b) Existing Facilities, and 15302(c) Replacement or Reconstruction. (Attachment B – Statement of Exemption, ER23-189.)
PUBLIC SUBSIDY REPORTING
This item does not include a public subsidy as defined in section 53083 or 53083.1 of the California Government Code or the City’s Open Government Resolution.
/s/
Matt Loesch
Director of Public Works
For questions, please contact Mathew Nguyen, Public Works Deputy Director, at [email protected] or (408) 535-8300.
ATTACHMENTS
A – 10091 – Sanitary Sewer Repairs FY 2022-2023 Package VI Overview Map B – Statement of Exemption ER23-189
ER22-048 Page 2 of 3
which might fall within Class 1. The key consideration if whether the project involves negligible or no expansion of an existing use. Examples include but are not limited to:
(b) Existing facilities of both investor and publicly owned utilities used to provide electric power, natural gas, sewerage, or other public utility services
15302. REPLACEMENT OR RECONSTRUCTION
Class 2 consists of replacement or reconstruction of existing structures and facilities where the new structure will be located on the same site as the structure replaced and will have substantially the same purpose and capacity as the structure replaced, including but not limited to:
(c) Replacement or reconstruction of existing utility systems and/or facilities involving negligible or no expansion of capacity.
ANALYSIS
Public Project Exemption for the inspection, removal and replacement, and rehabilitation of existing sewer segments ranging from approximately 4- to 44-inch diameter in size. This project will evaluate the current condition of each segment of sewer main to determine the appropriate repair method and deploy appropriate point repairs, Cured-In-Place-Pipe (CIPP) liners, or removal and replacement of entire segments to eliminate exfiltration. The purpose of this work is to upgrade and ensure efficiency and safety of the existing utility service system. If replacements are needed, the replacement will not increase the size of the sewer mains and will not result in expansion of capacity. Associated equipment, such as manholes, may need replacement as well.
All of the sewer main segments are located within the City boundary. Most are located within the right-of- way and/or a PUE. There are a few segments of sewer mains that are not within the public-right-of way and/or a PUE, within 100 feet of a water way, or within the wildlife survey areas or other fee zones as defined by the Santa Clara Valley Habitat Conversation Plan. Even so, the type of work proposed would qualify for a Habitat Conservation Plan exemption from all conditions as the proposed work is considered as, “Routine infrastructure maintenance by public agencies within the planning limit of urban growth that do not affect stream, riparian, serpentine, ponds, or wetland land cover types” (Habitat Conservation Plan, Chapter
6.2). In addition, the work taking place would be within existing disturbed areas and the project would not expand the capacity or length of the sewer main segments. Therefore, the project will not result in substantial adverse impact to sensitive biological resources and will not adversely affect creeks or riparian corridor areas.
In addition, as mentioned above, any tree that is not a Heritage tree that must be removed as a result of the project shall be removed and replaced in accordance with the Department of Transportation regulations. This exemption is only valid for projects that are within the scope of work described. This exemption will not be valid for any segments that have significant impacts to scenic highways, historical resources, or in areas that are included on any list compiled pursuant of Section 65962.5 of the Government Code.
As the project consists of inspection, removal and replacement, and repair of existing utilities facilities or structures, the project, will not involve expansion of the existing infrastructure. Therefore, the project is exempt to CEQA Guideline Section 15301(b) and 15302(c). Projects that are not within the scope of work will require separate environmental review and determination. This exemption is valid until August 21, 2028.
Exceptions:
CEQA Guidelines Section 15300.2 provides exceptions to the use of a Categorical Exemptions where the use of a Categorical Exemption is prohibited under certain circumstances. The City evaluated the proposed project’s applicability to all of the exceptions under Section 15300.2. An analysis of each of these exceptions in reference to this proposed project is provided below.
ER22-048 Page 3 of 3
(a) Location. Class 3, 4, 5, 6, and 11 are qualified by consideration of where the project is to be located.
Section 15300.2(a) started that a project that is ordinarily insignificant in its impact on the environment may in a particularly sensitive environment be significant. Section 15300.2(a) does not apply to the Class Category 1 and 2 of exemptions as the project will not occur in a sensitive area. (b) Cum
ulative Impact. Based on the above analysis, there is no evidence of a potential significant cumulative impact on the environment from the proposed project. The project proposes review and rehabilitation of existing sewer mains throughout the city. It has been determined that the project will not cumulatively impact traffic, noise, air quality, or water quality. (c) S ignificant Effect. The proposed project site does not have any unusual circumstances that would negatively impact the environment, thus, the project would not result in any significant environmental effects.
(d) S cenic Highways. It is not anticipated that the specific project sites will results in damage to any scenic resources. If one does, it is subject to 15300.2(d) and may not utilize this categorical exemption.
(e) H azardous Waste Sites. It is not anticipated that the specific project sites will be implemented in area that is included on any list compiled pursuant to Section 65962.5 of the Government Code. If one does, it is subject to 15300.2(e) and may not utilize this categorical exemption. (f) H istorical Resources. It is not anticipated that the specific project sites will results in damage to any historic resources. If one does, it is subject to 15300.2(f) and may not utilize this categorical exemption.
Christopher Burton, Director
Planning, Building and Code Enforcement
Date: August 23, 2023
Deputy
Environmental Project Manager:
Tina Garg