1 Agenda Item 3.5
March 3, 2026
Matt Loesch – Director, Public Works Department
Nicholas Cochran – Chair, Community Oversight Committee Carolyn Bauer – Vice Chair, Community Oversight Committee The Measure T COC’s annual report dated January 15, 2026 covering the most recent fiscal year ended June 30, 2025. The following is a summary of the report.

COC Findings and Conclusions FY 2024-2025
The bond issuance and related expenditures have been reviewed by the COC to ensure that the proceeds have been:
• Used within the spending categories defined and authorized by Measure T
• Expended on a timely basis to ensure that the municipal bonds issued retain their tax-exempt status.

Measure T COC Report to the City Council
March 3, 2026
2 3
Measure T COC Report to the City Council
March 3, 2026

4 Measure T COC Report to the City Council
March 3, 2026

General Observations and Comments

1. Original projections were to repave 420 miles of city streets utilizing 49% of Measure T funds
• 516 miles have actually been repaved
• An additional 163 miles are slated to be repaved before Measure T funds are exhausted in 2027 • This outperformance has been achieved through operational efficiencies and leveraging other funding sources
5 Measure T COC Report to the City Council
February 24, 2026

2. Ten public safety construction projects were originally scoped with an allocation of 33% of Measure T funds
• Three projects have been completed
o Fire Station 20
o Fire Station 37
o Emergency Operations Ctr
• Four projects are under construction and are expected to be completed utilizing currently allocated Measure T funds o Fire Station 8
o Fire Station 32
o Police Dept. Training Ctr
o Police Dept. Hangar
• The remaining public safety construction projects are in the design phase with a total of $14.5 million in unallocated reserves available to cover any and all future shortfalls o 911 Call Center Upgrades (awarded in December 2025)
o Fire Station 36
o Police Admin Bldg. Upgrades
• Fire Station 23 - land only; acquisition pending
• DPW indicated that project(s) will not proceed if insufficient funds are available to fully fund the project (seeking alternative funding)
6 Measure T COC Report to the City Council
March 3, 2026
Specific Recommendations
• City Council should consider establishing rank-ordered priorities for the three public safety construction projects still in the design phase
• Four COC seats are currently unfilled as of the date of this presentation: D10, Citywide Public Safety, Citywide Environmental Issues and Citywide Finance and Accounting; filling these remaining seats lowers the risk of not being able to achieve a required quorum to conduct COC meetings and, more importantly, ensures representation on the COC by all city stakeholders
7 Measure T COC Report to the City Council
March 3, 2026
8 Thank You
Agenda Item 3.5
March 3, 2026
Matt Loesch – Director, Public Works Department
Nicholas Cochran – Chair, Community Oversight Committee Carolyn Bauer – Vice Chair, Community Oversight Committee