SUPPLEMENTAL COUNCIL AGENDA: 4/14/26
FILE: 26-392
ITEM: 2.9
SAN JOSE! SANTA CLARA

WATER POLLUTION CONTROL PLANT
April 9, 2026

TREATMENT PLANT ADVISORYCOMMITTEE
The Honorable Mayor and City Council
City of San José
200 East Santa Clara Street
San José, CA 95113
Dear Mayor Mahan and City Council:

At its meeting on April 9, 2026, the Treatment Plant Advisory Committee (TPAC) reviewed this item:

5.B. Construction Contract Contingency Increase for the 10106 — South Bay Water Recycling Pump Station 5 Bypass Project Rebid
Staff Recommendation:

Approve a $24,200 increase to the construction contingency amount of $18,000 for a revised total contingency amount of $42,200 for the 10106 — South Bay Water Recycling Pump Station 5 Bypass Project Rebid.

Action: On a motion made by Committee Member Michael Mulcahy and a second by Committee Member David Cohen, TPAC recommended approval of item Ayes — 6 (Candelas, Cohen, Gonzales, Pineda, Kwok, Mulcahy) Nays — 1 (Furtado)
Abstain — 0
Absent- 2 (Hardy, Montano)
Sincerely,
Domingo Candelas, Chair

TREATMENT PLANT ADVISORY COMMITTEE