TO: HONORABLE MAYOR

AND CITY COUNCIL
FROM: John Ristow

SUBJECT: List of Pavement
Maintenance Projects
Eligible for Senate Bill 1
Funding
DATE: April 6, 2026

Approved

Date:
4/15/26

COUNCIL DISTRICT: Citywide

RECOMMENDATION

Adopt a resolution approving a list of pavement maintenance projects eligible for San José’s 2026-2027 allocation of the Road Maintenance and Rehabilitation Account funding, which was made available by the approval of Senate Bill 1, otherwise known as the Road Repair and Accountability Act of 2017.

SUMMARY AND OUTCOME

Approval of this list of projects will make an estimated $28,407,911 in Road Maintenance and Rehabilitation Account (RMRA) through the Senate Bill 1 funds available to the City for pavement maintenance in the summer and fall of 2027. The funding will be used to preventively maintain or resurface selected streets throughout the city, improving their condition and extending their useful life before more costly treatments or repairs are necessary.

BACKGROUND

On April 28, 2017, Governor Brown signed Senate Bill 1, which created the RMRA to address deferred maintenance on the state highway and local streets and roads systems. Senate Bill 1 requires the City to meet specific reporting and accountability requirements established by the California Transportation Commission (CTC). To receive the Fiscal Year 2026-2027 RMRA funds, the City must submit a City Council- approved list of projects (streets) to the CTC by July 1, 2026.

COUNCIL AGENDA: 4/28/26
FILE: 26-463
ITEM: 2.12

HONORABLE MAYOR AND CITY COUNCIL
April 6, 2028
Subject: List of Pavement Maintenance Projects Eligible for Senate Bill 1 Funding

Page 2 ends

In October 2025, the Department of Transportation (DOT) released its three-year Pavement Maintenance Plan (2026-2028) to preserve and rehabilitate streets citywide.

DOT coordinated this plan with other City departments, external stakeholders that work on city streets, and City Council offices. The Attachment – List of Projects is largely unchanged with minor edits due to construction conflicts and deferrals. Per the CTC guidelines, the actual projects completed may differ from the original list submitted.

ANALYSIS

The City is projected to receive approximately $28 million in RMRA funds that will serve as one of the several funding sources making up the estimated $89 million of pavement maintenance funding in FY 2026-2027. This total level of funding will allow for maintenance on the Major Street Network in 2027.

DOT utilized information provided by the City’s pavement management system to generate a candidate list of streets for pavement maintenance in 2027 using RMRA funds. The candidate list was then thoroughly analyzed by staff using the following criteria to create the list of recommended streets for submission to the CTC:

• Funding availability and funding use restrictions;
• Streets not affected by current or future street-related projects; • Maintenance history and prescribed treatment schedules; • Streets associated with planned safety, bikeway, or other “complete streets” projects;
• Community and City Council office feedback regarding roadway conditions and priority street segments;
• Relative location of street segments to create multiple continuous segments, consistency within neighborhoods, and project efficiency; and • Multi-year geographic spread across the City and street network.

RMRA funds are being used to support pavement maintenance activities on the Major Street Network. All major streets, including Vision Zero Priority Safety corridors, under the 2027 pavement program will be evaluated for traffic safety improvements. With unsafe speeds continuing to be the leading contributing factor in traffic fatalities and severe injuries, these roadways will be evaluated for quick-build improvements such as narrowed travel lanes, new or enhanced bike lines, and upgraded crosswalks. These improvements are intended to slow vehicular traffic and create a safer, and more comfortable environment for people walking or biking. DOT will be maintaining approximately eight miles in Equity Priority Communities, which is roughly 16% of the 52 miles selected for maintenance on the Major Streets Network in 2027.

HONORABLE MAYOR AND CITY COUNCIL
April 6, 2028
Subject: List of Pavement Maintenance Projects Eligible for Senate Bill 1 Funding

Page 3 ends

EVALUATION AND FOLLOW-UP

As required by the CTC guidelines, DOT will submit the City Council-approved list of projects (streets) identified for RMRA funding to the CTC no later than July 1, 2026.

DOT will also submit a “Completed and In-Progress Project Expenditure Report” for FY 2026-2027 to the CTC no later than October 1, 2027. In this report, DOT will describe each project location, funds expended, completion date and estimated useful life among other data points. No City Council action is anticipated for this requirement.

DOT provides an ongoing evaluation of the City’s pavement conditions and provides periodic reports on this topic to the Transportation and Environment Committee and the City Council. DOT will provide the City Council an information memorandum in early 2027 that will include a full list of streets to be maintained in 2027 using all available pavement maintenance funds, along with an updated three-year Pavement Maintenance Plan (2027-2029).

FISCAL IMPACTS

Estimated apportionments from the RMRA, commensurate with the proposed project cost of $28,407,911 including project delivery and contingency, will be included in the 2026-2027 Proposed Traffic Capital Budget, subject to the appropriation of funds.

Future funding is subject to appropriation by the City Council.

BUDGET REFERENCE

Estimated RMRA revenue and the offsetting appropriation for project funding will be included in the 2026-2027 Proposed Traffic Capital Budget. Funding is subject to appropriation by the City Council.

COORDINATION

This memorandum has been coordinated with the City Attorney’s Office, City Manager’s Budget Office, and the Planning, Building, and Code Enforcement Department.

PUBLIC OUTREACH

This memorandum will be posted on the City Council Agenda website for the April 6, 2026 City Council meeting.

HONORABLE MAYOR AND CITY COUNCIL
April 6, 2028
Subject: List of Pavement Maintenance Projects Eligible for Senate Bill 1 Funding

Page 4 ends

BOARD, COMMISSION, COMMITTEE RECOMMENDATION AND INPUT

No board, commission, or committee recommendation or input is associated with this action.

CEQA

Categorically Exempt, File No. ER24-313, CEQA Guidelines Section 15301(c), Existing Facilities.

PUBLIC SUBSIDY REPORTING

This item does not include a public subsidy as defined in section 53083 or 53083.1 of the California Government Code or the City’s Open Government Resolution.

/s/
John Ristow
Director of Transportation

For questions, please contact Jennifer Seguin, Deputy Director, Department of Transportation, at (408) 794-6453.

ATTACHMENT: List of Projects

ATTACHMENT
Subject: List of Projects

Page 1 of 2 ends

LIST OF PROJECTS

CD STREET NAME BEGIN LOCATION END LOCATION SCHEDULE DESCRIPTION OF

PROJECT

PREDICTED

USEFUL LIFE
1 MILLER AV BOLLINGER RD RAINBOW DR SUMMER/FALL 2027 STREET RESURFACING 20 YEARS 1 PROSPECT RD WB LAWRENCE EXPY CITY LIMIT SUMMER/FALL 2027 STREET RESURFACING 20 YEARS 1 PROSPECT RD WB DE ANZA BL S BLANEY AV SUMMER/FALL 2027 STREET RESURFACING 20 YEARS 1 WILLIAMS RD SARATOGA AV WINCHESTER BL SUMMER/FALL 2027 STREET SEALING 7 YEARS 2, 9,
10 HILLSDALE AV FOXWORTHY AV COMMUNICATIONS HILL SUMMER/FALL 2027 STREET RESURFACING 20 YEARS 2 MCKEAN RD N CITY LIMIT BAILEY AV SUMMER/FALL 2027 STREET RESURFACING 20 YEARS 2 NARVAEZ AV FAYE PARK DR BRANHAM LN SUMMER/FALL 2027 STREET RESURFACING 20 YEARS 2 SILICON VALLEY BL HWY 101 BASKING RIDGE AV SUMMER/FALL 2027 STREET SEALING 7 YEARS 2 SILVER CREEK
VALLEY RD HWY 101 SILVER CREEK VALLEY
PL SUMMER/FALL 2027 STREET SEALING 7 YEARS
3 GRAHAM AV GOODYEAR ST WILLOW ST SUMMER/FALL 2027 STREET RESURFACING 20 YEARS 3 GOODYEAR ST 1ST ST S GRAHAM AV SUMMER/FALL 2027 STREET RESURFACING 20 YEARS 3 HEDDING ST E HWY 101 N 13TH ST SUMMER/FALL 2027 STREET RESURFACING 20 YEARS 3, 5 KING RD N MCKEE RD STORY RD SUMMER/FALL 2027 STREET SEALING 7 YEARS 3 ST. JAMES ST E MARKET ST 19TH ST SUMMER/FALL 2027 STREET RESURFACING 20 YEARS 3, 6 WILLOW ST LELONG ST 1ST ST SUMMER/FALL 2027 STREET RESURFACING 20 YEARS 4 CHARCOT AV ZANKER RD ORCHARD PKWY SUMMER/FALL 2027 STREET RESURFACING 20 YEARS 4 TASMAN DR E 680’ E/O CISCO WY 583’ W/O RENAISSANCE
DR SUMMER/FALL 2027 STREET SEALING 7 YEARS
6 JULIAN ST W N MONTGOMERY ST THE ALAMEDA SUMMER/FALL 2027 STREET SEALING 7 YEARS 6, 9 LEIGH AV CAMDEN AV MCBAIN AV SUMMER/FALL 2027 STREET SEALING 7 YEARS 6, 9 LINCOLN AV CURTNER AV DELYNN WY SUMMER/FALL 2027 STREET RESURFACING 20 YEARS 7 STORY RD SENTER RD MCLAUGHLIN AV SUMMER/FALL 2027 STREET RESURFACING 20 YEARS 7 UMBARGER RD MONTEREY RD CRAMER CIR SUMMER/FALL 2027 STREET RESURFACING 20 YEARS

ATTACHMENT
Subject: List of Projects

Page 2 of 2 ends

CD STREET NAME BEGIN LOCATION END LOCATION SCHEDULE DESCRIPTION OF

PROJECT

PREDICTED

USEFUL LIFE
6 TAYLOR ST STOCKTON AV SAN PEDRO ST SUMMER/FALL 2027 STREET RESURFACING 20 YEARS 8 SAN FELIPE RD

YERBA BUENA RD THE VILLAGES PKWY SUMMER/FALL 2027 STREET SEALING 7 YEARS 8 YERBA BUENA RD VILLA VISTA RD ALTIA AV SUMMER/FALL 2027 STREET SEALING 7 YEARS 9 BLOSSOM HILL RD 100’ E/O
MEADOWBROOK DR CAMDEN AV SUMMER/FALL 2027 STREET SEALING 7 YEARS 9 CAMDEN AV 250’ S/O DEL PASO AV COLEMAN RD SUMMER/FALL 2027 STREET SEALING 7 YEARS 9, 10 WINFIELD BL BLOSSOM HILL RD THORNWOOD DR SUMMER/FALL 2027 STREET RESURFACING 20 YEARS 10 BERNAL RD SANTA TERESA BL SAN IGNACIO BL SUMMER/FALL 2027 STREET SEALING 7 YEARS 10 CAHALAN AV BLOSSOM HILL RD COLLEEN DR SUMMER/FALL 2027 STREET RESURFACING 20 YEARS 10 CALERO AV BLOSSOM AV CAHALAN AV SUMMER/FALL 2027 STREET RESURFACING 20 YEARS 10 CURIE DR SNELL AV KORHUMMEL WY SUMMER/FALL 2027 STREET RESURFACING 20 YEARS

Description of Project:

Street Resurfacing: Projects that may consist of removal of failed top layer of asphalt, cold-in place recycling, overlay with hot-mix asphalt or rubberized hot-mix asphalt, striping and bike lane enhancements, and Americans with Disabilities Act (ADA) curb ramp upgrades
Street Sealing: Projects that may consist of removal of failed areas of asphalt, application of a thin layer of emulsified asphalt mixture to protect streets from water penetration and provide a new wearing surface, striping and bike lane enhancements, and ADA curb ramp upgrades.