E. 14th Street/Mission Boulevard & East Bay Greenway Near Term Phase 1 3: E 14th St from San Leandro Blvd to Plaza Dr
existing section, looking north
City of San Leandro, in Caltrans ROW
1 1A
2 3A
3 4A
4 5 6 7 8
9 9A 7A 10
11 11A
80’
100’
Existing Cross Section
Attachment A
E. 14th Street/Mission Boulevard & East Bay Greenway Near Term Phase 2 3: E 14th St from San Leandro Blvd to Plaza Dr
one-way protected bikeway
with parking, looking north
City of San Leandro, in Caltrans ROW
1 1A
2 3A
3 4A
4 5 6 7 8
9 9A 7A 10
11 11A
80’
100’
*Note: parking could be placed on east side instead of west. Draft for illustrative purposes Not for Construction
Concept
E. 14th Street/Mission Boulevard & East Bay Greenway Near Term Phase 3 General notes:
*While not all lane lines are shown, they are striped between driving and biking lanes per standard unless otherwise noted. *Placement of street trees and vegetation is conceptual and will be finalized during concept design.
*Depiction of features in sidewalk and outside of the public right of way is intended to provide context only and may not
accurately reflect real world placement or type of buildings or vegetation.
3A: San Leandro Blvd from Davis St to Williams St
existing section, looking north
City of San Leandro
1 1A
2 3A
3 4A
4 5 6 7 8
9 9A 7A 10
11 11A
88’
112’
37’ 14’ 37’
Existing Cross Section
E. 14th Street/Mission Boulevard & East Bay Greenway Near Term Phase 4 General notes:
*While not all lane lines are shown, they are striped between driving and biking lanes per standard unless otherwise noted. *Placement of street trees and vegetation is conceptual and will be finalized during concept design.
*Depiction of features in sidewalk and outside of the public right of way is intended to provide context only and may not
accurately reflect real world placement or type of buildings or vegetation.
3A: San Leandro Blvd from Davis St to Williams St
one-way protected bikeway, looking north
City of San Leandro
1 1A
2 3A
3 4A
4 5 6 7 8
9 9A 7A 10
11 11A
88’
112’
37’ 14’ 37’
Draft for illustrative purposes
Not for Construction
Concept
E. 14th Street/Mission Boulevard & East Bay Greenway Near Term Phase 5 General notes:
*While not all lane lines are shown, they are striped between driving and biking lanes per standard unless otherwise noted. *Placement of street trees and vegetation is conceptual and will be finalized during concept design.
*Depiction of features in sidewalk and outside of the public right of way is intended to provide context only and may not
accurately reflect real world placement or type of buildings or vegetation.
3A: San Leandro Blvd from Williams St to Hudson Ln
existing section, looking north
City of San Leandro
1 1A
2 3A
3 4A
4 5 6 7 8
9 9A 7A 10
11 11A
80’
95’
33’ 14’ 33’
Existing Cross Section
E. 14th Street/Mission Boulevard & East Bay Greenway Near Term Phase 6 General notes:
*While not all lane lines are shown, they are striped between driving and biking lanes per standard unless otherwise noted. *Placement of street trees and vegetation is conceptual and will be finalized during concept design.
*Depiction of features in sidewalk and outside of the public right of way is intended to provide context only and may not
accurately reflect real world placement or type of buildings or vegetation.
3A: San Leandro Blvd from Williams St to Hudson Ln
one-way protected bikeway, looking north
City of San Leandro
1 1A
2 3A
3 4A
4 5 6 7 8
9 9A 7A 10
11 11A
80’
95’
33’ 14’ 33’
Draft for illustrative purposes
Not for Construction
Concept
E. 14th Street/Mission Boulevard & East Bay Greenway Near Term Phase 7 General notes:
*While not all lane lines are shown, they are striped between driving and biking lanes per standard unless otherwise noted. *Placement of street trees and vegetation is conceptual and will be finalized during concept design.
*Depiction of features in sidewalk and outside of the public right of way is intended to provide context only and may not
accurately reflect real world placement or type of buildings or vegetation.
3A: San Leandro Blvd from Hudson Ln to Coburn Ct
existing section, looking north
City of San Leandro
1 1A
2 3A
3 4A
4 5 6 7 8
9 9A 7A 10
11 11A
80’
95’
33’ 14’ 33’
Existing Cross Section
E. 14th Street/Mission Boulevard & East Bay Greenway Near Term Phase 8 General notes:
*While not all lane lines are shown, they are striped between driving and biking lanes per standard unless otherwise noted. *Placement of street trees and vegetation is conceptual and will be finalized during concept design.
*Depiction of features in sidewalk and outside of the public right of way is intended to provide context only and may not
accurately reflect real world placement or type of buildings or vegetation.
3A: San Leandro Blvd from Hudson Ln to Coburn Ct
one-way protected bikeway, looking north
City of San Leandro
1 1A
2 3A
3 4A
4 5 6 7 8
9 9A 7A 10
11 11A
80’
95’
33’ 14’ 33’
Draft for illustrative purposes
Not for Construction
Concept
E. 14th Street/Mission Boulevard & East Bay Greenway Near Term Phase 9 General notes:
*While not all lane lines are shown, they are striped between driving and biking lanes per standard unless otherwise noted. *Placement of street trees and vegetation is conceptual and will be finalized during concept design.
*Depiction of features in sidewalk and outside of the public right of way is intended to provide context only and may not
accurately reflect real world placement or type of buildings or vegetation.
3A: San Leandro Blvd from Coburn Ct to E 14th St
existing section, looking north
City of San Leandro
1 1A
2 3A
3 4A
4 5 6 7 8
9 9A 7A 10
11 11A
92’
110’
36’ 20’ 36’
Existing Cross Section
E. 14th Street/Mission Boulevard & East Bay Greenway Near Term Phase 10 General notes:
*While not all lane lines are shown, they are striped between driving and biking lanes per standard unless otherwise noted. *Placement of street trees and vegetation is conceptual and will be finalized during concept design.
*Depiction of features in sidewalk and outside of the public right of way is intended to provide context only and may not
accurately reflect real world placement or type of buildings or vegetation.
3A: San Leandro Blvd from Williams St to E 14th St
one-way protected bikeway, looking north
City of San Leandro
1 1A
2 3A
3 4A
4 5 6 7 8
9 9A 7A 10
11 11A
92’
110’
36’ 20’ 36’
Draft for illustrative purposes
Not for Construction
Concept
Attachment A - Project Cross Sections.pdf
Facilities & Transportation Committee
May 4, 2022
- Document
- Attachment A - Project Cross Sections.pdf
- Meeting
- May 4, 2022
- Body
- Facilities & Transportation Committee
- Original file
- 4.4 MB
Text extracted from the city's file for reading and search. Open the original on legistar1.granicus.com. That file is the official record.