Compensation for the work identified in Exhibit A of Amendment #5 shall not exceed $397,859 as outlined below:
Design Fees – BKF Engineers
Cost per original contract and
Amendment #1
Amendment
#2 Cost
Amendment
#4 Cost
Amendment #5
Cost
Task Total
Task 1 – Project Management
and Coordination
$6,211.00 $824.00 $2,008 $18,130 $27,173
Task 2 – Preliminary Studies,
Investigations, and Design
$19,376.00 $2,985.00 $0.00 $35,972 $58,333
Task 3 – Geometric Approval
Drawing
$3,023.00 $0.00 $0.00 $3,023
Task 3A – Intersection Design
Alternatives
$11,154.00 $0.00 $0.00 $11,154
Task 4 – 70% PS&E $22,776.00 $6,690.00 $0.00 $29,466
Task 5 – 100% PS&E $11,243.00 $1,869.00 $0.00 $48,042 $61,154 Task 6 – Final PS&E $8,641.00 $1,057.00 $0.00 $9,906 $19,604 Task 7 – Right-of-way
Surveying and Mapping
$0.00 $22,101.00 $14,958 $37,059
Task 8 – Final Ready to List /
PEER PS&E Package
$0.00 $0.00 $0.00 $17,239 $17,239
Subtotal (BKF Engineers): $82,424.00 $35,526.00 $16,966 $129,289 $264,205 Design Fees – Harris Design
Cost per original contract and
Amendment #1
Amendment
#2 Cost
Amendment
#4 Cost
Amendment #5
Cost
Task Total
Task 1 – Project Management
and Coordination
$2,250.00 $0.00 $0.00 $0.00 $2,250
Task 2 – Preliminary Studies,
Investigations, and Design
$1,190.00 $0.00 $0.00 $0.00 $1,190
Task 3 – Geometric Approval
Drawing
$4,900.00 $0.00 $0.00 $0.00 $4,900
Task 4 – 70% PS&E $10,085.00 $0.00 $0.00 $0.00 $10,085
Task 4A – Design of Additional
Streetscape, Landscape, and
Irrigation Improvements in
Opportunity Areas**
$0.00 $3,000.00 $0.00 $5,000 $8,000
Task 5 – 100% PS&E $4,555.00 $0.00 $0.00 $0.00 $4,555
Task 6 – Final PS&E $2,240.00 $0.00 $0.00 $0.00 $2,240
Subtotal (Harris Design): $25,220.00 $3,000.00 $0.00 $5,000 $33,220 Design Fees – Biggs Cardosa Associates
Tasks 1-4 – Structural
Engineering and Wall Type
Selection
$0.00 $0.00 $0.00 $45,500 $45,500
Design Fees – Parikh Consultants
Tasks 1-4 – Structural
Engineering and Wall Type
Selection
$0.00 $0.00 $0.00 $53,770 $53,770
Total Design Fees $107,644.00 $38,526.00 $0.00 $233,559 $396,695 Reimbursable Expenses
(printing, delivery, computer,
plotter, mileage, parking, tolls)
$1,000.00 $164.00 $0.00 $0.00 $1,164
Total Contract Amount $108,644.00 $38,690.00 $16,966 $233,559 $397,859.00