Davis Street and Carpentier Street Pedestrian Hybrid Beacon Project, Project No. 2016.0550 Change Order 2 Cost – Labor $ 8,071.68
Equipment $ 4,348.32
Material $27,577.00
Total $39,997.00
Change Order 3 Cost – CMS Boards Rental and Installation $6,981.72 Sewer Lateral Fix at 501 Davis St. $10,697.67
Signage Credit ($ 574.96)
Total $17,104.43