1. 2.

3. 4.

5. 6.

7. 8.

9. Item # Unit Price Quantity Unit Extended Price
Date Submitted: 09/19/2022
Proposal #: 25-CA-220850
Power wash entire roof system with simplegreen/tsp and water solution.

Inspect roof system and clear any debris. Any voids, lap failures, or leak concerns shall be prepped and reinforced with Uni-Bond and Liquitec.

MICPA # PW1925
CALIFORNIA General Contractor License #: 949380
Scope of Work: Base Bid
Remove any loose walkpads or walkpads that have voids and have allowed water under.

Repair any damaged membrane or loose membrane with new weather cured single ply membrane. Where membrane sags at base flashings contractor to pull tight, install term bar, and new skirt flashing.

Purchase orders to be made out to: Garland/DBS, Inc.

Please Note: The following budget/estimate is being provided according to the pricing established under the Master Intergovernmental Cooperative Purchasing Agreement (MICPA) with Racine County, WI and OMNIA Partners, Public Sector (U.S. Communities). The line item pricing breakdown from Attachment C: Bid Form should be viewed as the maximum price an agency will be charged under the agreement. Garland/DBS, Inc. administered an informal competitive process for obtaining quotes for the project with the hopes of providing a lower market-adjusted price whenever possible.

Garland/DBS, Inc.
3800 East 91st Street
Cleveland, OH 44105
Phone: (800) 762-8225
Fax: (216) 883-2055

ROOFING MATERIAL AND SERVICES PROPOSAL
City of San Leandro
Marina Community Center
15301 Wicks Blvd
San Leandro, California 94579
Apply Liquitec to all seams, details, and repaired areas at 2 gallons per square. Apply 8” wide over seams. Allow to cure.

Apply a base coat of Liquitec at 1.5 gallons per square across entire roof section.

Attachment C: Bid Form - Line Item Pricing Breakdown
Item Description
Apply a base coat of Liquitec at 1 gallon per square across entire roof section.

Caulk and seal all details and transition areas with Tuff-Stuff MS.

Install new skirt flashing to parapet copings using 22 ga. Flat stock.

Page 1 of 4 ends

23.01 $ 0.77 16,000 SF $ 12,328

15.15 $ 6.55 16,000 SF $ 104,832

15.31 $ 10.98 2,250 LF $ 24,705
$ 141,865

22.03 25 $ 141,865 % $ 35,466

22.08 25 $ 141,865 % $ 35,466

22.06 35 $ 141,865 % $ 49,653

RESTORATIONS - RECOATING OF EXISTING ROOF
SYSTEMS : RESTORATION OF A SINGLE-PLY WITH

TWO-COMPONENT, LOW-ODER URETHANE &

STRIPPED SEAMS
Prepare Roof Surface by Cleaning with TSP or Simple
Green, Use Portable Blowers to Clear the Roof Surface
of Moisture; Strip in Seams by Applying a TwoComponent, Low-Oder Urethane 2 Gallons per Square USE SEPARATE LINE ITEM, Wait 24-48 Hours, Apply
Two-Component, Low-Oder Urethane as a Base Coat
at a Rate of 1.5 Gallons per Square and a Top Coat at
a Rate of 1.0 Gallon per Square Over the Entire Roof
According to Manufacturer's Specifications.

RESTORATIONS - RECOATING OF EXISTING ROOF
SYSTEMS : REINFORCING SEAMS WITH TWOCOMPONENT, LOW-ODER URETHANE Reinforce Seams by Applying a Two-Component, LowOder Urethane 2 Gallons per Square / Reinforcement / 1 Gallons per Square (3 Gallons per Square on Seams)

MULTIPLIER - ROOF OR WALLS HAVE LARGE

AMOUNT OF PENETRATIONS / ROOF TOP

OBSTRUCTIONS
Multiplier is applied when labor production is effected a large number of roof penetrations, a limited amount of
open roof areas or low overhead clearance requiring
more hand work. Situations include, but are not limited to rooftop penetrations like: soil stacks, sky lights, roof drains, exhaust vents, HVAC equipment, etc. or rooftop
obstructions such as: pipes, duct work, electrical wires, hoses or raised equipment, etc.

Cleaning & Caulking: Pressure Wash to Clean
Horizontal Surfaces
Sub Total Prior to Multipliers
MULTIPLIER - ROOF HEIGHT IS GREATER THAN 20
FT, BUT LESS THAN OR EQUAL TO 50 FT STORIES
Multiplier is applied when labor production is effected by the roof height. This multiplier applies to roof heights that exceed an estimated 2 stories, but are less than or equal to an estimated 5 stories. Additional roof height can require increased safety requirements, larger lift
equipment, tie-offs, etc.

MULTIPLIER - MULTIPLE MATERIAL STAGINGS
Multiplier is applied when labor production is effected by the time it takes to stage a roof multiple times.

Situations include, but are not limited to staging
materials to perform work on multiple roof levels,
planned shutdowns and restarts, portion of the job is
over sensitive work areas requiring staging from more
than one point, etc.

Page 2 of 4 ends

22.01 30 141,865$ % $ 42,560
$ 305,010
$ 305,010
Proposal Price Based Upon Market Experience: $ 294,334
Garland/DBS Price Based Upon Local Market Competition:

San Francisco Roofing
Western Roofing Service
Waterproofing Associates

1. Garland/DBS Price Based Upon Local Market Competition:

San Francisco Roofing
Western Roofing Service
Waterproofing Associates

1. Garland/DBS Price Based Upon Local Market Competition:

San Francisco Roofing
Clarifications/Exclusions:

1. 2.

3. $ 80,316
Scope of Work: Add Alt 2
Coat all duct seams by applying 4” Unibond and 2 gallons of Liquitect in 6” wide application. $ 330,649
$ 350,125
$ 438,398
Base Bid Total Maximum Price of Line Items under the MICPA:

MULTIPLIER - DIFFICULT ROOF OR BUILDING
ACCESS
Multiplier is applied when labor production is effected by roof or building access. Situations that can cause roof access to be more difficult include, but are not limited to: no access for lifts or cranes, access is dependent
upon road closure, access point requires the closure of a building entrance, roof level is not accessible from the ground, roof area is interior to adjacent roofs or roof materials and materials and equipment must be loaded
to one roof area and carried to another roof area, roof materials and equipment must be carried to the roof
through an interior building access point, no or limited staging areas on the ground, etc.
$ 375,727
Sales and use taxes are included.

Please Note – The construction industry is experiencing unprecedented global pricing and availability pressures for many key building components. Specifically, the roofing industry is currently experiencing long lead times and significant price increases with roofing insulation and roofing fasteners. Therefore, this proposal can only be held for 30 days. DBS greatly values your business, and we are working diligently with our long-term suppliers to minimize price increases and project delays which could effect your project. Thank you for your understanding and cooperation.

Scope of Work: Add Alt 1
Match above scope but install 4” uni-bond to all seams before applying seam coating.

Total After Multipliers
$ 294,334
$ 299,217
Permits are excluded.

Bonds are included.

Page 3 of 4 ends

4. 5.

6. 7.

Respectfully Submitted,
Evan Clark
Garland/DBS, Inc.
(216) 430-3690
Plumbing, Mechanical, Electrical work is excluded.

Masonry work is excluded.

Interior Temporary protection is excluded.

If you have any questions regarding this proposal, please do not hesitate to call me at my number listed below.

Evan Clark
Any work not exclusively described in the above proposal scope of work is excluded.

Page 4 of 4 ends