BID SUMMARY
Washington-Chapman Railroad Crossing Improvements
BID OPENING Sposeto Engineering Inc. FBD Vanguard Construction, Inc. Kerex Engineering, Inc.

DATE: October 26, 2022 4558 Contractors Place 550 Greenville Road 4941 Pacheco Boulevard TIME: 3:00 p.m. Livermore, CA 94551 Livermore CA 94550 Martinez, CA 94553LOCATION: City Clerk's Office Phone: (925) 443-4200 Phone: (925) 245-1300 Phone: (925) 387-8913 Fax: (925) 443-6800 Fax: (925) 245-1007 Fax: (925) 387-0853 ITEM
NO. ITEM UNIT COST ITEM COST UNIT COST UNIT COST UNIT COST

BASE BID
1 Mobilization per Section 9-3.4 1 LS $52,000.00 $52,000.00 $28,000.00 $28,000.00 $70,000.00 $70,000.00 $90,000.00 $90,000.002 Work Area Traffic Control per Section 601
1 LS $20,000.00 $20,000.00 $62,000.00 $62,000.00 $109,300.00 $109,300.00 $85,000.00 $85,000.00 3 Remove Vertical Curb per Section 300-
1 89 LF $15.00 $1,335.00 $31.00 $2,759.00 $12.00 $1,068.00 $100.00 $8,900.00 4 Remove Curb & Gutter per Section 300-
1 75 LF $25.00 $1,875.00 $31.00 $2,325.00 $20.00 $1,500.00 $100.00 $7,500.00 5 Remove Concrete Sidewalk per Section
300-1
3,106 SF $10.00 $31,060.00 $6.00 $18,636.00 $12.00 $37,272.00 $8.00 $24,848.00 6 Remove Fence per Section 300-1.1 21 LF $50.00 $1,050.00 $38.00 $798.00 $9.00 $189.00 $250.00 $5,250.007 Roadway Excavation per Section 300-1 (Final Quantity)
137 CY $120.00 $16,440.00 $227.00 $31,099.00 $238.00 $32,606.00 $320.00 $43,840.00 8 Install Decorative Cobblestone per
Section 303-4.3
428 SF $70.00 $29,960.00 $23.00 $9,844.00 $50.00 $21,400.00 $65.00 $27,820.00 9 Imported Borrow Fill per Section 300-

5.3 (Final Quantity)
140 CY $75.00 $10,500.00 $174.00 $24,360.00 ** $314.00 $43,960.00 $250.00 $35,000.00 10 Install Detectable Warning Surface per
Section 303-5.5.3
120 SF $50.00 $6,000.00 $56.00 $6,720.00 $33.00 $3,960.00 $120.00 $14,400.00 11 Install Curb & Gutter per Section 303-

5.5.3 75 LF $110.00 $8,250.00 $112.00 $8,400.00 $120.00 $9,000.00 $200.00 $15,000.00 12 Install 6” Vertical Curb per Section 303-

5.5.3 792 LF $65.00 $51,480.00 $104.00 $82,368.00 $92.00 $72,864.00 $100.00 $79,200.00 13 Install Curb Wall per Section 303-5.5.3 55 LF $150.00 $8,250.00 $190.00 $10,450.00 $217.00 $11,935.00 $200.00 $11,000.0014 Install Sidewalk per Section 303-5.5.3 6,058 SF $35.00 $212,030.00 $20.00 $121,160.00 $19.00 $115,102.00 $18.00 $109,044.00 This document is a summary of bids received for the subject project and are provided only as a convenience. Listing of a particular bid is not a finding that such bid has been found to be responsive or accepted as complete by the City. An award of contract, if any, is subject to approval of the City Council and/or the City Manager. Contractors should refer to the contract documents for bidding information.

PROJECT TITLE:

PROJECT NO.: 2016.0320
BID NO.: 22-23.001

ENGINEER'S ESTIMATE
Date Approved: 9/13/2022Prepared by: J. O'Driscoll

QUANTITY ITEM COST ITEM COST ITEM COST
Bid Summary Washington-Chapman Railroad Crossing Improvements Page 1 of 6 Printed 10/31/2022 @ 5:11 PM

BID SUMMARY
Washington-Chapman Railroad Crossing Improvements
BID OPENING Sposeto Engineering Inc. FBD Vanguard Construction, Inc. Kerex Engineering, Inc.

DATE: October 26, 2022 4558 Contractors Place 550 Greenville Road 4941 Pacheco Boulevard TIME: 3:00 p.m. Livermore, CA 94551 Livermore CA 94550 Martinez, CA 94553LOCATION: City Clerk's Office Phone: (925) 443-4200 Phone: (925) 245-1300 Phone: (925) 387-8913 Fax: (925) 443-6800 Fax: (925) 245-1007 Fax: (925) 387-0853 ITEM
NO. ITEM UNIT COST ITEM COST UNIT COST UNIT COST UNIT COST PROJECT TITLE:

PROJECT NO.: 2016.0320
BID NO.: 22-23.001

ENGINEER'S ESTIMATE
Date Approved: 9/13/2022Prepared by: J. O'Driscoll

QUANTITY ITEM COST ITEM COST ITEM COST
15 Install Driveway per Section 303-5.5.3 222 SF $50.00 $11,100.00 $23.00 $5,106.00 $22.00 $4,884.00 $30.00 $6,660.0016 Install Curb Ramp per Section 303-

5.5.3 281 SF $50.00 $14,050.00 $34.00 $9,554.00 $35.00 $9,835.00 $75.00 $21,075.00 17 Install Checker Plate Gutter per Section
303-5.5.3
1 EA $1,500.00 $1,500.00 $8,865.00 $8,865.00 $8,500.00 $8,500.00 $18,000.00 $18,000.00 18 Install Reinforced Concrete Gravity
Pipe per Section 306
72 LF $200.00 $14,400.00 $143.00 $10,296.00 $165.00 $11,880.00 $400.00 $28,800.00 19 Install Fence End Post per Section 304-
2 1 LS $1,000.00 $1,000.00 $1,710.00 $1,710.00 $1,500.00 $1,500.00 $7,500.00 $7,500.00 20 Remove Traffic Striping per Section 314-
2 1,242 SF $2.00 $2,484.00 $9.00 $11,178.00 $7.70 $9,563.40 $8.00 $9,936.00 21 Remove pavement Markings per
Section 314-2
148 SF $4.00 $592.00 $9.00 $1,332.00 $7.70 $1,139.60 $8.00 $1,184.00 22 Remove Surface Mounted Delineator
per Section 315-1.2
21 EA $100.00 $2,100.00 $36.00 $756.00 $55.00 $1,155.00 $60.00 $1,260.00 23 Relocate Roadside Sign per Section
315-1.1
2 EA $500.00 $1,000.00 $700.00 $1,400.00 $333.00 $666.00 $750.00 $1,500.00 24 Install Curb Paint per Section 314-4 75 LF $5.00 $375.00 $7.00 $525.00 $5.50 $412.50 $6.00 $450.0025 Install Traffic Striping-Detail 9 per Section 314-4
932 LF $5.00 $4,660.00 $3.00 $2,796.00 $3.00 $2,796.00 $4.00 $3,728.00 26 Install Traffic Striping-Detail 22 per
Section 314-4
45 LF $8.00 $360.00 $14.00 $630.00 $12.00 $540.00 $15.00 $675.00 27 Install Traffic Striping-Detail 25A per
Section 314-4
470 LF $6.00 $2,820.00 $3.00 $1,410.00 $3.00 $1,410.00 $5.00 $2,350.00 28 Install Traffic Striping-Detail 27B per
Section 314-4
565 LF $5.00 $2,825.00 $3.00 $1,695.00 $2.00 $1,130.00 $5.00 $2,825.00 29 Install Traffic Striping-Detail 29 per
Section 314-4
136 LF $8.00 $1,088.00 $27.00 $3,672.00 $23.00 $3,128.00 $30.00 $4,080.00 30 Install Traffic Striping-Detail 38B per
Section 314-4
24 LF $8.00 $192.00 $9.00 $216.00 $8.00 $192.00 $10.00 $240.00 31 Install Object Marker-Type K-1 (CA) per
Section 315-1.-2
5 EA $250.00 $1,250.00 $412.00 $2,060.00 $67.00 $335.00 $500.00 $2,500.00 32 Install Object Marker-Type K-2 (CA) per
Section 315-1.2
3 EA $250.00 $750.00 $412.00 $1,236.00 $67.00 $201.00 $500.00 $1,500.00 Bid Summary Washington-Chapman Railroad Crossing Improvements Page 2 of 6 Printed 10/31/2022 @ 5:11 PM

BID SUMMARY
Washington-Chapman Railroad Crossing Improvements
BID OPENING Sposeto Engineering Inc. FBD Vanguard Construction, Inc. Kerex Engineering, Inc.

DATE: October 26, 2022 4558 Contractors Place 550 Greenville Road 4941 Pacheco Boulevard TIME: 3:00 p.m. Livermore, CA 94551 Livermore CA 94550 Martinez, CA 94553LOCATION: City Clerk's Office Phone: (925) 443-4200 Phone: (925) 245-1300 Phone: (925) 387-8913 Fax: (925) 443-6800 Fax: (925) 245-1007 Fax: (925) 387-0853 ITEM
NO. ITEM UNIT COST ITEM COST UNIT COST UNIT COST UNIT COST PROJECT TITLE:

PROJECT NO.: 2016.0320
BID NO.: 22-23.001

ENGINEER'S ESTIMATE
Date Approved: 9/13/2022Prepared by: J. O'Driscoll

QUANTITY ITEM COST ITEM COST ITEM COST
33 Install Pavement Markings per Section
314-4
274 SF $6.00 $1,644.00 $15.00 $4,110.00 $13.00 $3,562.00 $15.00 $4,110.00 34 Install Pavement Marker (Type G) per
Section 314-4
28 EA $25.00 $700.00 $32.00 $896.00 $28.00 $784.00 $30.00 $840.00 35 Install Roadsign Sign (R6-2) per
Section 315-1.1
6 EA $500.00 $3,000.00 $600.00 $3,600.00 $500.00 $3,000.00 $550.00 $3,300.00 36 Install Pedestrian Railing per Section
304-2
640 LF $100.00 $64,000.00 $150.00 $96,000.00 $126.00 $80,640.00 $130.00 $83,200.00 37 Install Access Gate per Section 304-6 1 EA $4,000.00 $4,000.00 $13,000.00 $13,000.00 $11,300.00 $11,300.00 $15,000.00 $15,000.0038 Railroad Flagging per Section 7-5 1 LS $80,000.00 $80,000.00 $45,000.00 $45,000.00 $30,000.00 $30,000.00 $100,000.00 $100,000.0039 AC Paving per Section 302-5 82 SF $20.00 $1,640.00 $29.00 $2,378.00 $74.00 $6,068.00 $75.00 $6,150.0040 Survey by the Contractor per Section 2-

9.2.2 1 LS $18,000.00 $18,000.00 $8,300.00 $8,300.00 $8,300.00 $8,300.00 $15,000.00 $15,000.00 TOTAL BID: $685,760.00 $646,640.00 $733,077.50 $898,665.00 REQUIRED DOCUMENTATION:

SUBCONTRACTORS:NOTES:

Reviewed by: Date:

John O'Driscoll, Project Manager
Reviewed by: Date:

Austine Osakwe, Senior Engineer
Bid Bond YES YES YESAddendum 1 & 2 YES YES YES
Golden Bay Fence Plus Ironworks, Inc.

Golden Bay Fence Plus Ironworks, Inc. Delta Survey, Inc.

Benchmark Engineering, Inc. Farwest Safety, Inc. Compass Engineering Contractors, Inc.** Math Error Corrected Compass Engineering Contractors, Inc.

Compass Engineering Contractors, Inc.

Golden Bay Fence Plus Ironworks, Inc.

Bid Summary Washington-Chapman Railroad Crossing Improvements Page 3 of 6 Printed 10/31/2022 @ 5:11 PM 10/31/2022

BID SUMMARY
Washington-Chapman Railroad Crossing Improvem

BID OPENING
DATE: October 26, 2022TIME: 3:00 p.m. LOCATION: City Clerk's Office ITEM
NO. ITEM UNIT COST ITEM COST

BASE BID
1 Mobilization per Section 9-3.4 1 LS $52,000.00 $52,000.002 Work Area Traffic Control per Section 601
1 LS $20,000.00 $20,000.00
3 Remove Vertical Curb per Section 300-
1 89 LF $15.00 $1,335.00
4 Remove Curb & Gutter per Section 300-
1 75 LF $25.00 $1,875.00
5 Remove Concrete Sidewalk per Section
300-1
3,106 SF $10.00 $31,060.00
6 Remove Fence per Section 300-1.1 21 LF $50.00 $1,050.007 Roadway Excavation per Section 300-1 (Final Quantity)
137 CY $120.00 $16,440.00
8 Install Decorative Cobblestone per
Section 303-4.3
428 SF $70.00 $29,960.00
9 Imported Borrow Fill per Section 300-

5.3 (Final Quantity)
140 CY $75.00 $10,500.00
10 Install Detectable Warning Surface per
Section 303-5.5.3
120 SF $50.00 $6,000.00
11 Install Curb & Gutter per Section 303-

5.5.3 75 LF $110.00 $8,250.00
12 Install 6” Vertical Curb per Section 303-

5.5.3 792 LF $65.00 $51,480.00
13 Install Curb Wall per Section 303-5.5.3 55 LF $150.00 $8,250.0014 Install Sidewalk per Section 303-5.5.3 6,058 SF $35.00 $212,030.00 PROJECT TITLE:

PROJECT NO.: 2016.0320
BID NO.: 22-23.001

ENGINEER'S ESTIMATE
Date Approved: 9/13/2022Prepared by: J. O'Driscoll

QUANTITY
Mark lee & Yong Kay, Inc. DBA BayCF Contracting, Inc.4026 Martin Luther king Jr. Way 850 South Van Ness Ave., #21Oakland, CA 94609 San Francisco, CA 94110Phone: (510) 658-7225 Phone: (415) 721-7160Fax: (510) 658-4890 Fax: (415) 296-6437

UNIT COST UNIT COST
$40,000.00 $40,000.00 $100,000.00 $100,000.00$80,000.00 $80,000.00 $200,000.00 $200,000.00 $20.00 $1,780.00 $40.00 $3,560.00$50.00 $3,750.00 $60.00 $4,500.00$10.00 $31,060.00 $8.00 $24,848.00 $100.00 $2,100.00 $200.00 $4,200.00$100.00 $13,700.00 $300.00 $41,100.00 $80.00 $34,240.00 $90.00 $38,520.00$80.00 $11,200.00 $250.00 $35,000.00 $100.00 $12,000.00 $75.00 $9,000.00$100.00 $7,500.00 $125.00 $9,375.00$150.00 $118,800.00 $70.00 $55,440.00$300.00 $16,500.00 $150.00 $8,250.00 $20.00 $121,160.00 $16.00 $96,928.00
This document is a summary of bids received for the subject project and are provided only as a convenience. Listing of a particular bid is not a finding that such bid has been found to be responsive or accepted as complete by the City. An award of contract, if any, is subject to approval of the City Council and/or the City Manager. Contractors should refer to the contract documents for bidding information.

ITEM COST ITEM COST
Bid Summary Washington-Chapman Railroad Crossing Improvements Page 4 of 6 Printed 10/31/2022 @ 5:11 PM

BID SUMMARY
Washington-Chapman Railroad Crossing Improvem

BID OPENING
DATE: October 26, 2022TIME: 3:00 p.m. LOCATION: City Clerk's Office ITEM
NO. ITEM UNIT COST ITEM COST
PROJECT TITLE:

PROJECT NO.: 2016.0320
BID NO.: 22-23.001

ENGINEER'S ESTIMATE
Date Approved: 9/13/2022Prepared by: J. O'Driscoll

QUANTITY
15 Install Driveway per Section 303-5.5.3 222 SF $50.00 $11,100.0016 Install Curb Ramp per Section 303-

5.5.3 281 SF $50.00 $14,050.00
17 Install Checker Plate Gutter per Section
303-5.5.3
1 EA $1,500.00 $1,500.00
18 Install Reinforced Concrete Gravity
Pipe per Section 306
72 LF $200.00 $14,400.00
19 Install Fence End Post per Section 304-
2 1 LS $1,000.00 $1,000.00
20 Remove Traffic Striping per Section 314-
2 1,242 SF $2.00 $2,484.00
21 Remove pavement Markings per
Section 314-2
148 SF $4.00 $592.00
22 Remove Surface Mounted Delineator
per Section 315-1.2
21 EA $100.00 $2,100.00
23 Relocate Roadside Sign per Section
315-1.1
2 EA $500.00 $1,000.00
24 Install Curb Paint per Section 314-4 75 LF $5.00 $375.0025 Install Traffic Striping-Detail 9 per Section 314-4
932 LF $5.00 $4,660.00
26 Install Traffic Striping-Detail 22 per
Section 314-4
45 LF $8.00 $360.00
27 Install Traffic Striping-Detail 25A per
Section 314-4
470 LF $6.00 $2,820.00
28 Install Traffic Striping-Detail 27B per
Section 314-4
565 LF $5.00 $2,825.00
29 Install Traffic Striping-Detail 29 per
Section 314-4
136 LF $8.00 $1,088.00
30 Install Traffic Striping-Detail 38B per
Section 314-4
24 LF $8.00 $192.00
31 Install Object Marker-Type K-1 (CA) per
Section 315-1.-2
5 EA $250.00 $1,250.00
32 Install Object Marker-Type K-2 (CA) per
Section 315-1.2
3 EA $250.00 $750.00
Mark lee & Yong Kay, Inc. DBA BayCF Contracting, Inc.4026 Martin Luther king Jr. Way 850 South Van Ness Ave., #21Oakland, CA 94609 San Francisco, CA 94110Phone: (510) 658-7225 Phone: (415) 721-7160Fax: (510) 658-4890 Fax: (415) 296-6437

UNIT COST UNIT COST ITEM COST ITEM COST
$30.00 $6,660.00 $30.00 $6,660.00$30.00 $8,430.00 $80.00 $22,480.00 $10,000.00 $10,000.00 $15,000.00 $15,000.00
$400.00 $28,800.00 $2,000.00 $144,000.00
$1,000.00 $1,000.00 $1,930.00 $1,930.00
$10.00 $12,420.00 $10.00 $12,420.00$10.00 $1,480.00 $10.00 $1,480.00$60.00 $1,260.00 $71.00 $1,491.00 $700.00 $1,400.00 $786.00 $1,572.00
$6.00 $450.00 $7.00 $525.00$3.00 $2,796.00 $4.00 $3,728.00 $13.00 $585.00 $15.00 $675.00
$3.00 $1,410.00 $4.00 $1,880.00$3.00 $1,695.00 $3.00 $1,695.00 $30.00 $4,080.00 $30.00 $4,080.00$10.00 $240.00 $10.00 $240.00 $400.00 $2,000.00 $464.00 $2,320.00$400.00 $1,200.00 $464.00 $1,392.00 Bid Summary Washington-Chapman Railroad Crossing Improvements Page 5 of 6 Printed 10/31/2022 @ 5:11 PM

BID SUMMARY
Washington-Chapman Railroad Crossing Improvem

BID OPENING
DATE: October 26, 2022TIME: 3:00 p.m. LOCATION: City Clerk's Office ITEM
NO. ITEM UNIT COST ITEM COST
PROJECT TITLE:

PROJECT NO.: 2016.0320
BID NO.: 22-23.001

ENGINEER'S ESTIMATE
Date Approved: 9/13/2022Prepared by: J. O'Driscoll

QUANTITY
33 Install Pavement Markings per Section
314-4
274 SF $6.00 $1,644.00
34 Install Pavement Marker (Type G) per
Section 314-4
28 EA $25.00 $700.00
35 Install Roadsign Sign (R6-2) per
Section 315-1.1
6 EA $500.00 $3,000.00
36 Install Pedestrian Railing per Section
304-2
640 LF $100.00 $64,000.00
37 Install Access Gate per Section 304-6 1 EA $4,000.00 $4,000.0038 Railroad Flagging per Section 7-5 1 LS $80,000.00 $80,000.0039 AC Paving per Section 302-5 82 SF $20.00 $1,640.0040 Survey by the Contractor per Section 2-

9.2.2 1 LS $18,000.00 $18,000.00
TOTAL BID: $685,760.00
REQUIRED DOCUMENTATION:

SUBCONTRACTORS:NOTES:

Reviewed by: Date:

John O'Driscoll, Project Manager
Reviewed by: Date:

Austine Osakwe, Senior Engineer
Bid BondAddendum 1 & 2
Mark lee & Yong Kay, Inc. DBA BayCF Contracting, Inc.4026 Martin Luther king Jr. Way 850 South Van Ness Ave., #21Oakland, CA 94609 San Francisco, CA 94110Phone: (510) 658-7225 Phone: (415) 721-7160Fax: (510) 658-4890 Fax: (415) 296-6437

UNIT COST UNIT COST ITEM COST ITEM COST
$15.00 $4,110.00 $17.00 $4,658.00$30.00 $840.00 $36.00 $1,008.00 $600.00 $3,600.00 $679.00 $4,074.00$300.00 $192,000.00 $163.00 $104,320.00 $14,000.00 $14,000.00 $14,524.00 $14,524.00
$100,000.00 $100,000.00 $150,000.00 $150,000.00
$100.00 $8,200.00 $300.00 $24,600.00
$20,000.00 $20,000.00 $0.00 **
$922,446.00 $1,157,473.00
YESYES Acknowledged
YES
Golden Bay Fence Plus Ironworks, Inc.

Golden Bay Fence Plus Ironworks, Inc.

Ridgeline Engineering Compass Engineering Contractors, Inc. ** Math Error Corrected
Striping Graphics
Bid Summary Washington-Chapman Railroad Crossing Improvements Page 6 of 6 Printed 10/31/2022 @ 5:11 PM 10/31/2022