Project Development Update
Facilities and Transportation Committee
December 7, 2022
Projects in
Construction
or about to
Start
Construction
1. Annual Street Overlay / Rehab 2019-21, Phase 1
2. Pedestrian Crossings 19-21
3. Secondary Effluent Line Rehabilitation
4. East 14th / Joaquin Ave Traffic Signal Improvements
5. Adaptive Traffic Control System Upgrade – Marina Blvd Annual Street Overlay/Rehabilitation 2019-21, Phase 1
• Scope: reconstruction of 9 street
segments and improvements to 3
additional intersections.
• Engineer Estimate - $6.7 M
– Design – $842,650
– Constr. Contract - $4,891,826
– Contingencies (15%) - $733,774
– Construction Mgt - $202,663
• Start of Construction – Fall 2022
• End Construction – Spring 2023
Pedestrian Crossings 2019-21
• Scope: Pedestrian Crossing
improvements to Williams St/
Joyce St., Anza Way/Monterey
Blvd., Aurora Dr./Walnut Drive
• Start of Construction – Fall 2022
• Improvements include bulbouts
with ADA Standard Ramps, storm
drainage
• Benefits include better visibility
and shorter crossing distances for
pedestrians
SECONDARY EFFLUENT (SE) LINE REPLACEMENT
PROJECT
• Scope: Includes:
1) Installation of CIPP liner in the
existing 36” Secondary Effluent (SE)
pipeline between the SE wet well at the
Secondary Clarifier No. 1 and the
Effluent Pump Station. at the City’s
Water Pollution Control Plant (WPCP).
Construction Contract - $807,055
Constr. Contingencies (15%) - $121,058
Constr. Management - $80,000
• Start of Construction: Summer 2022
• End Construction – December 2022
E14TH ST. (SR 185)/JOAQUIN AVE TRAFFIC
SIGNAL IMPROVEMENTS
• Scope: The work consists of adding a
scramble pedestrian crosswalk, which
includes removal of signal equipment, traffic
signal modifications, ADA curb ramp
installation, drainage improvements, curb &
gutter, sidewalk, new signing, and striping.
• Constr. Contract - $352,296
• Constr. Contingencies - $88,074
• Constr. Management - $35,000
• Start of Construction – January 2023
• End Construction – Summer 2023
Adaptive Traffic Control System
Upgrade – Marina Blvd.
COSL Project No. 2014.0460
• Construction Contract - $380,760
• Constr. Contingencies - $95,190
• Constr. Management - $19,110
Scope:
Upgrade traffic signal equipment and install fiber
network extension to coordinate traffic signals on Marina Boulevard from Merced street east across I-880 to San
Leandro Boulevard.
• Start of Construction – January 2023
• End Construction – April 2023
Projects
Close to
Bidding
1. Annual Street Paving 2021-23 – Curb Ramp Upgrade
2. Washington / Chapman Railroad Crossing Upgrade
3. Annual Sanitary Sewer Point Repair 2021-22
4. Washington Ave Reconstruction
5. Wicks / Manor Signal Improvements
Annual Street Paving 2021-23 –
Curb Ramp Upgrade
Scope:
Upgrade to curb ramps adjacent to the
proposed street work – 88 street segments
scheduled for work
• Status:
• Bid Opened – November 2, 2022
• Council Award – December 19, 2022
• Total Budget - $14.59M
- Curb Ramp Upgrade – $2.07M
- Street Overlay/Rehab - $12.52
Washington/Chapman Railroad
Crossing Upgrade
Scope:
Upgrade to pedestrian crossings across
the railroad tracks.
• Status:
• Bid Opened – October 26, 2022
• Council Award – December 19, 2022
Washington Ave Reconstruction
Scope:
Reconstruction between W. Juana Ave
and Castro Str.
• Status:
• Waiting Authorization from DLAE to advertise
for bids.
• Total Budget - $2,0845,449
• OBAG Grants - $1,0480,000
• Match Funds (Meas. BB) - $542,623
• CDBG Funds - $494,826