Steven Taylor
Sanctity of Life Project
March 20, 2023
City Council Meeting
City of San Leandro
Engineering Department
Initial
Project Location
2 Sanctity of Life Park
Initial Project
Concepts
3 Initial Project Location
within
Bay Conservation & Development
Commission Jurisdiction (BCDC)
Within 100’ of shoreline band, major permit
requirements: o Public hearing o Application review by: o Commission’s Design Review Board o Engineering Criteria Review Board 4 BCDC Interpretive
Elements and
Public Art
• Complements the bay setting
• Focus on the natural and
historical features of the site
Proposed
Project Location
6 Sanctity of Life Pavilion
Proposed
Location • Existing gathering space • “Blank canvas” • Minimal regulatory requirements depending on design elements
7 8
9 10
• Refresh pavilion
Initial Project Concepts
 Stone column
 Stone sign
• Stone benches
• Decomposed granite trails
• Engraved stone boulders
• Informational kiosk
• Statue
Jerry Garcia Park,
San Francisco
11 • Themed seating levels
Initial Project Concepts
• Stone column
• Stone sign
 Stone benches
 Decomposed granite trails
 Engraved stone boulders
• Informational kiosk
• Statue
12 Initial Project Concepts
• Stone column
• Stone sign
• Stone benches
• Decomposed granite trails
• Engraved stone boulders
 Informational kiosk
 Statue
• Outdoor musical
instruments
• Youth engagement
13 14
Albany Shoreline
Tentative
Timeline
March
1 – FTC
Meeting
20 – Council
Presentation
April
16 – Council
Proclamation
18 – Steven
Taylor Day
May
Community
Outreach
June
Community
Outreach
July
Community
Outreach
August
Community
Outreach
September
6 – FTC
Meeting
18 – Council
Meeting
15 Kearns
and
West
Project
Budget
17 Item Amount
CIP Appropriation FY22-23 $625,000
Landscape Architect - RRM -$168,000
Community Outreach – Kearns and West -$50,000
Staff costs to date -$23,000
Available Funding $384,000
18 Steven Taylor
Sanctity of Life Project
March 20, 2023
City Council
City of San Leandro
Engineering Department