• Centro Callan Development
(196 apartment units including 10 affordable units and retail) 1 Facilities and Transportation Commission
April 5, 2023
Centro Callan
Development
Construction of Upper Levels to start in
April 2023 through September 2023
Cement mixer trucks and concrete pump with
outriggers will be staged on Callan Ave and
Chumalia St.
2 Traffic Impacts:
• Callan Avenue:
• One through lane both directions
will be open
• Partial lane closure on westbound
lane adjacent to curb
• Chumalia Street
• Lane Shift for Eastbound Traffic
• Westbound Traffic Closed