Memorial Park
Improvements Update ➢ RRM Design was selected as design consultant for this project.
➢ The State grant deadline was June 30,
2024, which did not allow enough time
to do more public meetings.
➢ Two Budget options were presented
and fully renovated park for $5M
project cost option was selected.
➢ All recommendations from Focus
Group meetings held in July 2019, has
been incorporated into new design.
➢ First All Abilities Park in the City.
1 As discussed with Facilities and
Transportation Committee May, 2022:

Current
Design
Plan
2 Schedule
Contract Award - June 20, 2023.

Design - completed.

Bid Advertisement - April 2023.

Groundbreaking Event - October 2023.

Construction Start - November 2023
Construction Complete - December 2024 (tentatively).

Budget
Note: State Department of Parks and Recreation
extended the Grants Period from June 30, 2024, to
June 30, 2028.

Sanitary Sewer Point Repairs 2022
• Scope:
– Repair sanitary sewer main defects at approximately 100 locations
– Repair or replace approximately 30 manholes
• Project Finances:
– Budget - $1.5 M
– Estimated Construction Cost : $1M
• Status and Schedule:
– 4 bids received for construction on 2/28/2023.
– Bids didn’t comply with local business participation goals – Staff recommends City Council Meeting to reject all bids – April 17, 2023.
– Planned rebid and City Council award – Summer 2023
– Start of Construction - Fall of 2023
Project Manager: Robert Magno, [email protected]