COMMUNITY

WORKFORCE

AGREEMENT
UPDATE
Facilities & Transportation
Committee
May 3, 2023
Kurry Foley
Senior Management Analyst
CWA Administrator

PRESENTATION

OVERVIEW
Timeline
Definition & Benefits
Evaluation Data
Updates to Agreement
CWA Consultant Selection

Page 2 ends

S
TEP01
STEP02
STEP03
STEP04
Negotiations
Aug. 2022-Feb. 2023
UpdatetoCM
April2023
CouncilReview
June2023
UpdatetoFTC
May2023Pa
ge
3 STEP05
ConsultantRFP&Award
July-September2023
2015 City Council approved
2016 Implementation
Social impact outcome - investing public funds
in employment opportunities
Guarantee no strikes, work stoppages for City
infrastructure projects
Local Hire Goal – pathway to union careers
What is the Community Workforce Agreement?

Page 4 ends

$1M Project
Threshold Apprentice 10%
Journeypeople
20%
Local Hire Goals
City, Trades &
Industry reps
Monitors CWA
projects progress
Joint Administrative
Committee

Page 5 ends

CWA EVALUATION DATA
28 projects since 2016
Approximately 60% streets projects
Trades used - operator/engineers,
laborers, cement masons &
electricians
Need more robust data
management, will seek consultant

Page 6 ends

LOCAL HIRE GOALS

Page 7 ends

4.8% OF 20% GOAL

SAN LEANDRO

JOURNEYPEOPLE

SAN LEANDRO APPRENTICES

1.26% OF 10% GOAL
UPDATE
CITY & TRADES:

ANNUAL GOAL: 20

SL RESIDENT

PRE-APPRENTICESHIP

PROGRAM GRADUATES
01

Page 8 ends

UPDATE
02 CITY & TRADES:

Standardized dispatch
request form

Page 9 ends

UPDATE
CITY:

IMPLEMENTATION OF WORKFORCE

DEVELOPMENT TRUST
03

Page 10 ends

WORKFORCE DEVELOPMENT
TRUST

Page 11 ends

construction careers programming
apprenticeship-related learning programs
apprenticeship costs
$.30/project hour for all CWA projects
Ex: Farrelly Pool project: 29,160 hrs would yield
$8,748
Dedicated revenue source for construction training
for SL residents
90% funds for

CWA CONSULTANT
CSA award to
Council; value not
to exceed current
$140k
appropriation
Evaluate
consultants:
workforce
development,
data management
Release RFP

Page 12 ends

JULY 2023 AUGUST 2023 SEPTEMBER 2023
QUESTIONS?

Page 13 ends