Project Development Update
Facilities and Transportation Committee
June 7, 2023
Projects in
Construction
or about to
Start
Construction
1. Annual Street Paving 2021-23 – Curb Ramps
2. Annual Street Overlay / Rehab 2019-21, Phase 1
3. East 14th / Joaquin Ave Traffic Signal Improvements
4. Washington Ave Reconstruction
5. Adaptive Traffic Control System Upgrade – Marina Blvd
6. Wicks Blvd and Manor Blvd Traffic Signal Upgrade
7. Washington/Chapman Railroad Crossing Upgrade
Annual Street Paving 2021-23 –
Curb Ramp Upgrade
Scope:
Upgrade to curb ramps adjacent to the
proposed street work – 90 street segments
scheduled for work
• Status:
• Start of Construction – Spring 2023
• Complete Construction – Summer 2023
• Total Budget - $14.59M
- Curb Ramp Upgrade – $2.07M
- Street Overlay/Rehab - $12.52
E14TH ST. (SR 185)/JOAQUIN AVE TRAFFIC
SIGNAL IMPROVEMENTS
• Scope: The work consists of adding a
scramble pedestrian crosswalk, which
includes removal of signal equipment, traffic
signal modifications, ADA curb ramp
installation, drainage improvements, curb &
gutter, sidewalk, new signing, and striping.
• Constr. Contract - $352,296
• Constr. Contingencies - $88,074
• Constr. Management - $35,000
• Start of Construction – January 2023
• End Construction – Summer 2023
Washington Ave Reconstruction
Scope:
Reconstruction between W. Juana Ave
and Castro St.
• Status:
• Start of Construction – June 2023
• Complete Construction – November 2023
• Total Budget - $2,0845,449
• OBAG Grants - $1,0480,000
• Match Funds (Meas. BB) - $542,623
• CDBG Funds - $494,826
Projects
Scheduled
for Award
1. Annual Street Paving 2021-23 – Street Sealing
2. Annual Sanitary Sewer Point Repair 2021-22
3. Memorial Park Improvements
4. Annual Street Sealing 2021-23 – Curb Ramp
Annual Street Paving 2021-23 – Street Sealing
Scope:
Street sealing of 90 street segments Citywide.
• Status:
• Bid Opened – May 18, 2023
• Council Award – June 20, 2023
• Total Budget - $15.12M
- Curb Ramp Upgrade – $2.47M
- Street Sealing - $10.2M
- Street Overlay/Rehab - $2.45M
Sanitary Sewer Point Repairs 2022 and Wicks
Blvd Vault Covers Replacement
Scope:
City sanitary sewer pipeline facilities repair
and two (2) sanitary sewer vault covers
replacement
• Status:
• Bid Opened – June 1, 2023
• Council Award – June 20, 2023
• Estimated Total Project Costs - $1.5M
- Sanitary Sewer Point Repairs – $1.1M
- Wicks Blvd Vault Covers Replacement - $0.4M
Memorial Park Improvements
Scope:
Improvements to an existing park to
an all-abilities park.
• Status:
• Bid Opened – May 24, 2023
• Council Award – July 17, 2023
• Est. Tot. Proj. Costs - $5.31M
- Construction Contract– $4.22M
- Constr. Contingencies - $421,730
- Design, Constr. Mgmt. & Utilities - $670,000
• Funds:
• State Earmark Grant - $2,750,000
• State Per-capita Prop 69 Fund- $232,958
• General Fund - $2,326,078
Annual Street Sealing 2021-23 – Curb Ramp
Scope:
Street sealing of 86 streets City-wide.
• Status:
• Bid Opened – April 19, 2023
• Council Award – June 5, 2023
• Total Budget - $6.72M
- Curb Ramp Contract – $893,400
- Street Sealing - $5.83M