BID SUMMARY
BID OPENING Basset Engineering D'Arcy & Harty Constructors, Inc. Marinship Development Int.,LLC DATE: Thursday, June 1, 2023 2330 Castro Street 1300 Carroll Avenue 2100 Embarcadero, Suite 205 TIME: 3:00 p.m. San Francisco, CA 94131 San Francisco, CA 94124 Oakland, CA 94606 LOCATION: City Clerk's Office Phone: (415) 930-2385 Phone: (415) 822-5200 Phone: (415) 716-3965 Fax: N/A Fax: (415) 822-0747 Fax: N/A
ITEM
NO. ITEM UNIT COST ITEM COST UNIT COST UNIT COST UNIT COST ITEM COST
BASE BID
1 Mobilization, Staging & Stockpiling per
Sections 7-8.4 & 9-3.4
1 LS $50,000.00 $50,000.00 $136,000.00 $136,000.00 $100,000.00 $100,000.00 $100,000.00 $100,000.00 2 Temporary Traffic Control – Level 1,
per Section 600
44 EA $600.00 $26,400.00 $500.00 $22,000.00 $500.00 $22,000.00 $1,200.00 $52,800.00 3 Temporary Traffic Control – Level 2,
per Section 600
5 EA $800.00 $4,000.00 $600.00 $3,000.00 $1,000.00 $5,000.00 $1,600.00 $8,000.00 4 Temporary Traffic Control – Level 3,
per Section 600
6 EA $1,000.00 $6,000.00 $700.00 $4,200.00 $1,500.00 $9,000.00 $1,700.00 $10,200.00 5 Pipe Cleaning & CCTV Inspection , per
section 500-1.1
27391 LF $3.00 $82,173.00 $15.00 $410,865.00 $7.00 $191,737.00 $18.00 $493,038.00 6 Trench Excavation & Backfill, 0’-5’
Depth, per sections 306-3, 306-5, 306-
6 & 306-12
54 LF $600.00 $32,400.00 $170.00 $9,180.00 $850.00 $45,900.00 $878.00 $47,412.00 7 Trench Excavation & Backfill, 5’-8’
Depth, per sections 306-3, 306-5, 306-
6 & 306-12
340 LF $700.00 $238,000.00 $200.00 $68,000.00 $950.00 $323,000.00 $1,100.00 $374,000.00 8 Trench Excavation & Backfill, 8’-11’
Depth, per sections 306-3, 306-5, 306-
6 & 306-12
22 LF $800.00 $17,600.00 $300.00 $6,600.00 $1,800.00 $39,600.00 $1,170.00 $25,740.00 9 Point Repair, 6-inch Pipeline
Replacement, per section 306-7
294 LF $145.00 $42,630.00 $300.00 $88,200.00 $30.00 $8,820.00 $100.00 $29,400.00 10 Point Repair, 8-inch Pipeline
Replacement, per section 306-7
72 LF $150.00 $10,800.00 $500.00 $36,000.00 $40.00 $2,880.00 $121.00 $8,712.00 11 Point Repair, 10-inch Pipeline
Replacement, per section 306-7
30 LF $160.00 $4,800.00 $700.00 $21,000.00 $100.00 $3,000.00 $127.00 $3,810.00
QUANTITY
This document is a summary of bids received for the subject project and are provided only as a convenience. Listing of a particular bid is not a finding that such bid has been found to be responsive or accepted as complete by the City. An award of contract, if any, is subject to approval of the City Council and/or the City Manager. Contractors should refer to the contract documents for bidding information.
ITEM COST ITEM COST
PROJECT TITLE: Sanitary Sewer Point Repairs 2022 and
PROJECT NO.:
BID NO.:
ENGINEER'S ESTIMATE
2022.0120
22-23.013
Prepared by: Robert Magno
Date Approved: 5/4/2023
Wicks Boulevard Vault Cover Replacement
Sanitary Sewer Point Repairs 2022_Wicks Blvd Vault Cover Replacement.xlsx Page 1 of 3 Printed 6/1/2023 @ 5:46 PM
BID SUMMARY
BID OPENING Basset Engineering D'Arcy & Harty Constructors, Inc. Marinship Development Int.,LLC DATE: Thursday, June 1, 2023 2330 Castro Street 1300 Carroll Avenue 2100 Embarcadero, Suite 205 TIME: 3:00 p.m. San Francisco, CA 94131 San Francisco, CA 94124 Oakland, CA 94606 LOCATION: City Clerk's Office Phone: (415) 930-2385 Phone: (415) 822-5200 Phone: (415) 716-3965 Fax: N/A Fax: (415) 822-0747 Fax: N/A
ITEM
NO. ITEM QUANTITY UNIT COST ITEM COST UNIT COST ITEM COST UNIT COST ITEM COST UNIT COST ITEM COST PROJECT TITLE: Sanitary Sewer Point Repairs 2022 and
PROJECT NO.:
BID NO.:
ENGINEER'S ESTIMATE
2022.0120
22-23.013
Prepared by: Robert Magno
Date Approved: 5/4/2023
Wicks Boulevard Vault Cover Replacement
12 Point Repair, 12-inch Pipeline
Replacement, per section 306-7
18 LF $170.00 $3,060.00 $1,000.00 $18,000.00 $140.00 $2,520.00 $154.00 $2,772.00 13 Reconnect Service Lateral to 6-inch
Main Pipeline, per section 306-7
29 EA $200.00 $5,800.00 $600.00 $17,400.00 $500.00 $14,500.00 $1,500.00 $43,500.00 14 Install New Type A-2 Manhole, 0’-5’
Depth, per section 306-7
23 EA $8,000.00 $184,000.00 $11,000.00 $253,000.00 $7,000.00 $161,000.00 $9,000.00 $207,000.00 15 Install New Type A-2 Manhole, 5’-10’
Depth, per section 306-7
10 EA $10,000.00 $100,000.00 $11,400.00 $114,000.00 $12,500.00 $125,000.00 $12,000.00 $120,000.00 16 Repair/Rehabilitate Manhole Bench
and Channel, per section 500-5.2
4 EA $1,000.00 $4,000.00 $6,700.00 $26,800.00 $1,500.00 $6,000.00 $12,000.00 $48,000.00 17 Expose and Raise Manhole Frame &
Cover to Grade, per section 300-1.6
1 EA $2,000.00 $2,000.00 $145.00 $145.00 $2,000.00 $2,000.00 $6,000.00 $6,000.00 18 Sheeting, Shoring & Bracing, per
section 306-4
1 LS $50,000.00 $50,000.00 $20,000.00 $20,000.00 $84,000.00 $84,000.00 $80,000.00 $80,000.00 19 AC Pavement Restoration 6-inch
Depth, per section 302-5
6700 SF $22.00 $147,400.00 $10.00 $67,000.00 $14.00 $93,800.00 $20.00 $134,000.00 TOTAL BASE BID: $1,011,063.00 $1,321,390.00 $1,239,757.00 $1,794,384.00
SUPPLEMENT PROJECT BID
1S. Mobilization & Demobilization per
Section 9-3.4(Not to exceed 10% of
total contract for Wicks Vault Cover
Replacement)
1 LS $10,550.00 $10,550.00 $2,400.00 $2,400.00 $15,000.00 $15,000.00 $25,000.00 $25,000.00 2S. Temporary Traffic Control per Section
600 and 601(Wicks Vault Cover
Replacement)
1 LS $25,000.00 $25,000.00 $2,600.00 $2,600.00 $30,000.00 $30,000.00 $10,000.00 $10,000.00 3S. Concrete Removal per Section 300-
1(Wicks Vault Cover Replacement)
1 LS $5,000.00 $5,000.00 $2,100.00 $2,100.00 $30,000.00 $30,000.00 $12,000.00 $12,000.00 4S. Concrete Slab Top and Collar with
Manhole Access per Section 303 &
Detail 1/5(Wicks Vault Cover
Replacement)
1 LS $44,000.00 $44,000.00 $10,000.00 $10,000.00 $30,000.00 $30,000.00 $50,000.00 $50,000.00 Sanitary Sewer Point Repairs 2022_Wicks Blvd Vault Cover Replacement.xlsx Page 2 of 3 Printed 6/1/2023 @ 5:46 PM
BID SUMMARY
BID OPENING Basset Engineering D'Arcy & Harty Constructors, Inc. Marinship Development Int.,LLC DATE: Thursday, June 1, 2023 2330 Castro Street 1300 Carroll Avenue 2100 Embarcadero, Suite 205 TIME: 3:00 p.m. San Francisco, CA 94131 San Francisco, CA 94124 Oakland, CA 94606 LOCATION: City Clerk's Office Phone: (415) 930-2385 Phone: (415) 822-5200 Phone: (415) 716-3965 Fax: N/A Fax: (415) 822-0747 Fax: N/A
ITEM
NO. ITEM QUANTITY UNIT COST ITEM COST UNIT COST ITEM COST UNIT COST ITEM COST UNIT COST ITEM COST PROJECT TITLE: Sanitary Sewer Point Repairs 2022 and
PROJECT NO.:
BID NO.:
ENGINEER'S ESTIMATE
2022.0120
22-23.013
Prepared by: Robert Magno
Date Approved: 5/4/2023
Wicks Boulevard Vault Cover Replacement
5S. Double Leaf Access Hatch Door per
Section 304-6 & Detail 2/5(Wicks Vault
Cover Replacement)
1 LS $25,000.00 $25,000.00 $40,000.00 $40,000.00 $35,000.00 $35,000.00 $16,000.00 $16,000.00 6S. Access Ladder per Section 304-7 &
Detail 3/5(Wicks Vault Cover
Replacement)
1 EA $2,500.00 $2,500.00 $5,000.00 $5,000.00 $5,000.00 $5,000.00 $6,000.00 $6,000.00 7S. AC Pavement Restoration per Section
302-5(Wicks Vault Cover
Replacement)
184 SF $45.65 $8,400.00 $10.00 $1,840.00 $50.00 $9,200.00 $20.39 $3,751.76 TOTAL SUPPLEMENT PROJECT BID: $120,450.00 $63,940.00 $154,200.00 $122,751.76 TOTAL BASE BID:
TOTAL BASE BID +TOTAL SUPPLEMENT PROJECT BID:
REQUIRED DOCUMENTATION:
Agreement to be Bound
SUBCONTRACTORS:
NOTES:
Reviewed by: Date:
Robert Magno, Project Manager
Reviewed by: Date:
Austine Osakwe, Senior Engineer
Mission City Rebar Inc.
YES YES YES
Addendum #1 YES YES YES
Good Faith Effort N/A YES N/A
25 % Participation YES NO YES
San Leandro Local Business NO NO NO
Bid Bond YES YES YES
$1,321,390.00 $1,239,757.00 $1,794,384.00
$1,917,135.76
$1,011,063.00
$1,131,513.00 $1,385,330.00 $1,393,957.00
Pipe & Plant Solutions Inc. NONE Pipe & Plant Solutions, Inc.
DR Traffic Control, LLC
Sanitary Sewer Point Repairs 2022_Wicks Blvd Vault Cover Replacement.xlsx Page 3 of 3 Printed 6/1/2023 @ 5:46 PM 6/1/23
6/1/2023