Project Updates
Facilities and Transportation Committee Meeting
July 7, 2023
Community
Workforce
Agreement
• May 2023: Council briefings (2/2/3s) complete
• June – July 2023: Data analysis requested by Mayor,
Councilmembers; in progress
• September 2023: Council review
• October 2023: Consultant RFP & Award
Steven Taylor
Pavilion
Community Outreach Meetings
San Leandro Main Library
300 Estudillo Ave, San Leandro, CA 94577
1. Saturday, July 8, 11:00 am – 1:00 pm, Estudillo Room
2. Tuesday, July 11, 5:30 pm – 7:30 pm, Estudillo Room
3. Wednesday, August 9, 5:30 pm – 7:30 pm, Karp Room
4. Saturday, August 12, 11:00 am – 1:00 pm, Karp Room
Memorial Park
Improvements
Scope: Improvements to an Existing park to an all-abilities park.
Award scheduled for 7/17/2023
Soft costs - $830k
Construction Costs including Contingencies - $4.64M (10% over engineers estimate) Est. Total Project Costs - $5.47M
Total Existing Funds - $5M
Additional Funds to Complete Project - $470,000
MulfordMarina Library
Scope: Replace Library
Revised Design Contract scheduled for 7/17/2023
Design costs increased by 130%
Increased building size
Added solar and other features
Billing rates changed from 2019 to 2024
includes cost of grant application support