Steven Taylor
Sanctity of Life Pavilion
CITY COUNCIL
NOVEMBER 6, 2023
SHEILA MARQUISES, PUBLIC WORKS DIRECTOR
PROJECT LOCATION
2 3
4 5
6 Project
Timeline
March
Council
Presentation
April
Council
Proclamation
Summer
2023
Community
Engagement
September
FTC Meeting
Oct/Nov
Design
Concepts
Nov/Dec
Design
Spring 2024
Construction
April 2024
Groundbreaking
7 Community
Engagement
Opportunities
1. Comment card
2. Survey
3. Voicemail at (510) 519-9215
4. E-mail [email protected]
5. Community Dialogues at the Main Library:
a) Saturday, July 8th, 11 am-1 pm
b) Tuesday, July 11th, 5:30-7:30 pm
c) Wednesday, August 9th, 5:30-7:30 pm
d) Saturday, August 12th, 11 am-1 pm
8 Word Art
9 SEATING for GATHERING
10 LABYRINTH for MEDITATION
11 ART for REFLECTION
12 13
ART
LABYRINTH
SEATING
14 15
16 Art Component
Refer to Arts Culture and Library Commission
a) Solicitation of artist to create new or
b) Selection of existing
Commission to present to 3 options and reccomendation to Council for approval
17 CONSTRUCTION
ESTIMATE
18 Item Amount
Demolition $62,623
Pedestrian path $57,310
Seating $34,500
Labyrinth $15,000
Pavilion Sign $20,000
Landscape and Irrigation $34,030
Project Contingency $55,616
TOTAL $279,329
PROJECT
BUDGET
19 Item Amount
Landscape Architect Design Consultant $168,000
Community Outreach Consultant $50,000
City Staff charges (to date) $30,000
Construction Estimate $280,000
Art Component $95,000
Total Project Cost $623,000
FY 22-23 CIP APPROPRIATION $625,000
Next Steps
1. Council approval of conceptual design
2. Refer art component to the Arts Culture and Library
Commission for artist solicitation and/or selection
20