PROJECT
UPDATES
by District
FACILITIES AND TRANSPORTATION COMMITTEE
DECEMBER 6, 2023
1 District 5
2 Council District 5 Projects
3 Name Location/Limits Status Total Project
Cost (est.)
Completion
Date (est.)
Annual Street Overlay/Rehab. 19-21
Phase 1 and 2 Citywide Complete (Ph. 1)Design (Ph. 2) $13.5M Fall 2024 Annual Street Paving 21-23 Citywide Construction $20.3M Fall 2024 Annual Street Sealing 24 Maintenance Area 1 Construction $2M Fall 2024 E.14th Pedestrian Lighting E14th St. - Durant to
Dutton Design $850,000 Fall 2024
Memorial Park Callan @ Bancroft Construction $5.5M Summer 2025
MacArthur Roundabout Superior @ MacArthur Design $3M Spring 2025 Centro Callan Development E14th St and Callan Construction N/A Dec 2024 Caltrans Paving/Concrete Project E14th Street (SR 185)
Davis Street (SR114) Construction N/A June 2024
Pavement Maintenance
4 District 6
5 Council District 6 Projects
6 Name Location/Limits Status Total Project
Cost (est.)
Completion
Date (est.)
Annual Street Overlay/Rehab. 19-21 Phase 1
and 2 Citywide Complete (Ph. 1)
Design (Ph. 2) $13.5M Fall 2024
Fairway Drive Class IV Protected Bike Lanes Fairway Drive Preliminary Engineering $65k Summer 2025
Annual Street Paving 21-23 Citywide Construction $20.3M Fall 2024 Annual Street Sealing 21-23 Maintenance Areas 3 & 4 Construction $6.7M Fall 2024 Shoreline Fiber Optics Marina-Monarch BayFarrallon-Wicks Design $700,000 Fall 2024 Steven Taylor Sanctity of Life Pavilion Marina Park Design $625,000 Spring 2024 Shoreline Park Marina Design ~ $3-4M TBD
Shoreline Development (SFR Element) Monarch Drive Design N/A TBD San Leandro Davis St – Tenant Improv. 2002 Davis St Construction N/A TBD Caltrans Paving/Concrete Project Davis Street Paving (SR 112, Caltrans) Construction N/A June 2024
Pavement Maintenance
7