City of San Leandro
RMRA Project Fiscal Year 2025
Project Title: RMRA Project Fiscal Year 2025
Project Description: The following streets will receive pavement maintenance as part of the RMRA project for Fiscal Year 2025. The work on the previous RMRA project is complete and will not use funding from Fiscal Year 2025.

The following streets will receive a mill and fill
Location PCI
Pre Proj / Post Proj
Est. Life (years)
Min/Max
Schedule
Start/Complete
Del Valle Cir.

Portola Dr. to end
10 / 100 10 / 20 July 2024 /
July 2024
Del Rio Cir.

Portola To end
10 / 100 10 / 20 July 2024 /
July 2024
Del Campo Cir.

Portola Dr. to end
25 /100 10 / 20 July 2024 /
July 2024
Daniels Dr.

Brookvale Dr. to end
9 / 100 10 / 20 July 2024 /
August 2024
Juneau St.

Barrow St. to Sitka St.
12 / 100 10 / 20 August 2024 /
August 2024
Nome St.

Barrow St. to Williams St.
16 / 100 10 / 20 August 2024 /
August 2024
Barrow St.

Nome St. to Doolittle Dr.
16 / 100 10 / 20 August 2024 /
September 2024
Bradhoff Ave.

Sybil Ave. to Valita Dr.
17 / 100 10 / 20 September 2024/
September 2024
Valita Dr.

Whelan Ave. to Bradhoff Ave.
23 / 100 10 / 20 September 2024 /
September 2024
Thomas Ave.

Barbara Ct. to end
23 / 100 10 / 20 September 2024 /
October 2024
Whelan Ave.

Sybil Ave. to Valita Dr.
17 / 100 10 / 20 October 2024 /
October 2024
Morgan Ave.

Maud Ave to Evergreen Ave.
16 / 100 10 / 20 October 2024 /
October 2024