BUILDING
1 Building Permit Fees
A. Filing and Issuance Fee per permit $ 136 $ 212 $ 212 Re-filing Fee upon 2nd resubmittal for plan check on
same project.
per
occurrence
$ 68 $ 212 $ 212
Re-filing Fee for each revision after issued permit
issuance
per
occurrence
NEW $ 319 $ 319
B. Permit Fee [1][2]
Refunds per permit 80% of fees
paid 80% of fees paid
Permit Extension (Requested before permit expires) per permit NEW $ 106 $ 106 Reopen Permit (Requested after permit has expired) per permit NEW $ 637 $ 637 i) New Buildings, Additions, Tenant Improvements,
Residential Remodels, and Combined Mechanical,
Electrical and/or Plumbing Permits, and Deferred
Submittal
$1 - $5,000 per permit $ 209 $ 531 $ 531
$ 5,001 base fee @
$5,001 $ 209 $ 531 $ 531
each additional $1000 or fraction thereof each add'l
$1000 $ 62.75 $ 21.24 $ 21.24
$ 10,001 base fee @
10,001
$ 523 $ 637 $ 637
each additional $1000 or fraction thereof each add'l
$1,000 $ 18.31 $ 14.60 $ 14.60
$ 50,001 base fee @
$50,001 $ 1,255 $ 1,221 $ 1,221
each additional $1000 or fraction thereof each add'l
$1,000 $ 16.73 $ 21.24 $ 21.24
$ 100,001 base fee @
$100,001 $ 2,092 $ 2,283 $ 2,283
each additional $1000 or fraction thereof each add'l
$1,000 $ 13.59 $ 10.75 $ 10.75
$ 500,001 base fee @
$500,001 $ 7,530 $ 6,585 $ 6,585
each additional $1000 or fraction thereof each add'l
$1,000 $ 5.02 $ 2.34 $ 2.34
$ 1,000,001 base fee @
$1,000,001 $ 10,039 $ 7,753 $ 7,753
each additional $1000 or fraction thereof each add'l
$1,000 $ 4.76 $ 1.62 $ 1.62
$ 5,000,001 base fee @
$5,000,001 $ 29,079 $ 14,231 $ 14,231
each additional $1000 or fraction thereof each add'l
$1,000 $ 4.76 $ 5.78 $ 5.78
$ 10,000,001 base fee @
$10,000,001 $ 52,879 $ 43,119 $ 43,119
each additional $1000 or fraction thereof each add'l
$1,000 $ 4.76 $ 1.63 $ 1.63
$ 50,000,001 base fee @
$50,000,001 $ 243,279 $ 108,329 $ 108,329
each additional $1000 or fraction thereof each add'l
$1,000 $ 4.76 $ 2.17 $ 2.17
Fee
No.
Fee Name Fee Unit /
Type Notes Current Fee / Deposit
100% Cost
Recovery
Fee
Rec'd Fee Level /
Deposit
City of San Leandro
Master Fee Schedule
Proposed
Building
1 of 8
BUILDING
Fee
No.
Fee Name Fee Unit /
Type Notes Current Fee / Deposit
100% Cost
Recovery
Fee
Rec'd Fee Level /
Deposit
ii) Stand-Alone Plumbing Permit
Up to $2,000 per permit $ 105 $ 425 $ 425
$2,001 - $5,000 per permit $ 209 $ 425 $ 425
$ 5,001 base fee @
5,001
$ 209 $ 956 $ 956
each additional $1000 or fraction thereof each add'l
$1,000 $ 41.83 $ 63.72 $ 63.72
$ 10,001 base fee @
$10,001 $ 418 $ 1,274 $ 1,274
each additional $1000 or fraction thereof each add'l
$1,000 $ 13.94 $ 6.64 $ 6.64
$ 50,001 base fee @
$50,001 $ 976 $ 1,540 $ 1,540
each additional $1000 or fraction thereof each add'l
$1,000 $ 13.94 $ 18.05 $ 18.05
$ 100,001 base fee @
$100,001 $ 1,673 $ 2,443 $ 2,443
each additional $1000 or fraction thereof each add'l
$1,000 $ 13.94 $ 3.05 $ 3.05
$ 500,001 base fee @
$500,001 $ 7,249 $ 3,664 $ 3,664
each additional $1000 or fraction thereof each add'l
$1,000 $ 13.94 $ 7.33 $ 7.33
iii) Stand-Alone Electrical Permit
Up to $2,000 base fee @
$2,000 $ 105 $ 425 $ 425
$2,001 - $5,000 base fee @
$2,001 $ 209 $ 425 $ 425
$ 5,001 base fee @
5,001
$ 209 $ 956 $ 956
each additional $1000 or fraction thereof each add'l
$1,000 $ 41.83 $ 74.34 $ 74.34
$ 10,001 base fee @
$10,001 $ 418 $ 1,328 $ 1,328
each additional $1000 or fraction thereof each add'l
$1,000 $ 13.94 $ 9.29 $ 9.29
$ 50,001 base fee @
$50,001 $ 976 $ 1,699 $ 1,699
each additional $1000 or fraction thereof each add'l
$1,000 $ 13.94 $ 21.24 $ 21.24
$ 100,001 base fee @
$100,001 $ 1,673 $ 2,761 $ 2,761
each additional $1000 or fraction thereof each add'l
$1,000 $ 13.94 $ 3.32 $ 3.32
$ 500,001 base fee @
$500,001 $ 7,249 $ 4,089 $ 4,089
each additional $1000 or fraction thereof each add'l
$1,000 $ 13.94 $ 8.18 $ 8.18
City of San Leandro
Master Fee Schedule
Proposed
Building
2 of 8
BUILDING
Fee
No.
Fee Name Fee Unit /
Type Notes Current Fee / Deposit
100% Cost
Recovery
Fee
Rec'd Fee Level /
Deposit
iv) Stand-Alone Mechanical Permit
$ 2,000 base fee @
$2,000 $ 105 $ 425 $ 425
$ 2,001 base fee @
$2,001 $ 209 $ 425 $ 425
$ 5,001 base fee @
5,001
$ 209 $ 956 $ 956
each additional $1000 or fraction thereof each add'l
$1,000 $ 41.83 $ 74.34 $ 74.34
$ 10,001 base fee @
$10,001 $ 418 $ 1,328 $ 1,328
each additional $1000 or fraction thereof each add'l
$1,000 $ 13.94 $ 6.64 $ 6.64
$ 50,001 base fee @
$50,001 $ 976 $ 1,593 $ 1,593
each additional $1000 or fraction thereof each add'l
$1,000 $ 13.94 $ 23.37 $ 23.37
$ 100,001 base fee @
$100,001 $ 1,673 $ 2,761 $ 2,761
each additional $1000 or fraction thereof each add'l
$1,000 $ 13.94 $ 3.19 $ 3.19
$ 500,001 base fee @
$500,001 $ 7,249 $ 4,036 $ 4,036
each additional $1000 or fraction thereof each add'l
$1,000 $ 13.94 $ 8.07 $ 8.07
v) Residential 1 and 2 Family Re-roof
a) Main dwelling roof per permit $ 292 $ 637 $ 637
b) Detached garages and accessory structures
on same property as main dwelling and done at
the same time as the main dwelling roof.
per permit $ 93 $ 531 $ 319
vi) Inspection of the installation of an earthquake gas shutoff valve per permit $ 35 $ 319 $ 150
vii) Residential Seismic Retrofit projects using "Plan set A" (for one and two family residences) per permit $ 81 $ 743 $ 81 viii) Electric Vehicle Charger at 1 or 2 Family
Residences per permit NEW $ 319 $ 319
ix) Photovoltaic Systems [3]
a) Residential
i) Up to 15kW per permit $ 314 $ 531 $ 450
ii) each additional kW over 15kW per permit $ 16 $ 35 $ 15 b) Commercial
i) Up to 25kW per permit $ 438 $ 956 $ 956
ii) 26kW - 50kW per permit $ 658 $ 956 $ 956
iii) each additional kW (51kW - 250kW) per permit $ 7 $ 19 $ 7 iv) each additional kW over 250kW per permit $ 5 $ 19 $ 5 City of San Leandro
Master Fee Schedule
Proposed
Building
3 of 8
BUILDING
Fee
No.
Fee Name Fee Unit /
Type Notes Current Fee / Deposit
100% Cost
Recovery
Fee
Rec'd Fee Level /
Deposit
x) Signs [4]
a) 1st New sign attached to building. (Energized
or Not) per permit $ 117 $ 478 $ 478
b) each additional sign thereafter: per permit $ 59 $ 212 $ 212 c) Pylon sign, energized or not, each: (Height -
5'1'' and Taller) per permit $ 248 $ 1,274 $ 1,274
d) Monument sign, energized or not, each (5ft
and Under) per permit $ 185 $ 1,168 $ 1,168
e) Relocation or alteration of any sign
electronically or mechanically, but not including
replacement of tubing, transformers and such
parts subject to failure; or shop inspection by
the local inspection department in lieu of a UL
label (a local electrical inspection department
label of approval shall be required), each
per permit $ 93 $ 850 $ 850
xi) Demolition
a) Commercial/Residential Demolition up to
3,000SF
base fee @
3,000SF
$ 315 $ 850 $ 850
b) Each Additional 10,000SF each add'l
10,000SF
$ 209 $ 637 $ 637
xii) Addressing Fee
a) First 10 Addresses per permit $ 136 $ 319 $ 319
b) Each Additional (Over 10) per permit NEW $ 11 $ 11
City of San Leandro
Master Fee Schedule
Proposed
Building
4 of 8
BUILDING
Fee
No.
Fee Name Fee Unit /
Type Notes Current Fee / Deposit
100% Cost
Recovery
Fee
Rec'd Fee Level /
Deposit
C. Plan Check Fee [5]
80% of building
permit fee
$1 - $5,000 per permit $ 167 $ 212 $ 212
$ 5,001 base fee @
$5,001 $ 167 $ 266 $ 266
each additional $1000 or fraction thereof each add'l
$1000 $ 50.20 $ 10.62 $ 10.62
$ 10,001 base fee @
10,001
$ 418 $ 319 $ 319
each additional $1000 or fraction thereof each add'l
$1,000 $ 14.65 $ 9.29 $ 9.29
$ 50,001 base fee @
$50,001 $ 1,004 $ 690 $ 690
each additional $1000 or fraction thereof each add'l
$1,000 $ 13.38 $ 4.25 $ 4.25
$ 100,001 base fee @
$100,001 $ 1,674 $ 903 $ 903
each additional $1000 or fraction thereof each add'l
$1,000 $ 10.87 $ 1.33 $ 1.33
$ 500,001 base fee @
$500,001 $ 6,024 $ 1,434 $ 1,434
each additional $1000 or fraction thereof each add'l
$1,000 $ 4.02 $ 0.74 $ 0.74
$ 1,000,001 base fee @
$1,000,001 $ 8,031 $ 1,805 $ 1,805
each additional $1000 or fraction thereof each add'l
$1,000 $ 3.81 $ 0.45 $ 0.45
$ 5,000,001 base fee @
$5,000,001 $ 23,263 $ 3,611 $ 3,611
each additional $1000 or fraction thereof each add'l
$1,000 $ 3.81 $ 0.68 $ 0.68
$ 10,000,001 base fee @
$10,000,001 $ 42,303 $ 7,010 $ 7,010
each additional $1000 or fraction thereof each add'l
$1,000 $ 3.81 $ 0.51 $ 0.51
$ 50,000,001 base fee @
$50,000,001 $ 194,623 $ 27,454 $ 27,454
each additional $1000 or fraction thereof each add'l
$1,000 $ 3.81 $ 0.55 $ 0.55
City of San Leandro
Master Fee Schedule
Proposed
Building
5 of 8
BUILDING
Fee
No.
Fee Name Fee Unit /
Type Notes Current Fee / Deposit
100% Cost
Recovery
Fee
Rec'd Fee Level /
Deposit
ii) For Master Plans (i.e. identical buildings built by the same builder on the same lot or in the same tract and
for which building permits are issued at the same
Master Plan when more than one building will
be built each Full Plan Check Fee Applies
Full Plan Check
Fee Applies
Each production phase building at time of
application each 33% of Plan Check Fee $ 584 $ 584
iii. OTC plan checks for Minor Residential Remodels per permit NEW $ 767 $ 767 iv) Changes, revisions, or additions to plans previously approved and issued
per hour, 1
hour min
[6] $ 209 $ 212 $ 212
v) Additional plan review after the first re-check per hour, 1 hour min
[6] $ 209 $ 212 $ 212
vi) Alternate Methods and Materials
Under $10M in construction valuation per request [6] $ 209 $ 531 $ 531 Over $10M in construction valuation per request [6] $ 209 $ 1,062 $ 1,062 vii) Energy Conservation - for all buildings and projects subject to the California Energy Commission’s
conservation regulations
20% of building
permit fee
$1 - $5,000 per permit $ 42 $ 319 $ 319
$ 5,001 base fee @
$5,001 $ 42 $ 319 $ 319
each additional $1000 or fraction thereof each add'l
$1000 $ 12.55 $ 31.86 $ 31.86
$ 10,001 base fee @
10,001
$ 105 $ 478 $ 478
each additional $1000 or fraction thereof each add'l
$1,000 $ 3.66 $ - $ -
$ 50,001 base fee @
$50,001 $ 251 $ 478 $ 478
each additional $1000 or fraction thereof each add'l
$1,000 $ 3.35 $ 1.06 $ 1.06
$ 100,001 base fee @
$100,001 $ 418 $ 531 $ 531
each additional $1000 or fraction thereof each add'l
$1,000 $ 2.72 $ 0.93 $ 0.93
$ 500,001 base fee @
$500,001 $ 1,506 $ 903 $ 903
each additional $1000 or fraction thereof each add'l
$1,000 $ 1.00 $ 0.32 $ 0.32
$ 1,000,001 base fee @
$1,000,001 $ 2,008 $ 1,062 $ 1,062
each additional $1000 or fraction thereof each add'l
$1,000 $ 0.95 $ 0.13 $ 0.13
$ 5,000,000 base fee @
$5,000,001 $ 5,816 $ 1,593 $ 1,593
each additional $1000 or fraction thereof each add'l
$1,000 $ 0.95 $ 0.13 $ 0.13
$ 10,000,000 base fee @
$10,000,001 $ 10,576 $ 2,230 $ 2,230
each additional $1000 or fraction thereof each add'l
$1,000 $ 0.95 $ 0.10 $ 0.10
$ 50,000,000 base fee @
$50,000,001 $ 48,656 $ 6,266 $ 6,266
each additional $1000 or fraction thereof each add'l
$1,000 $ 0.95 $ 0.13 $ 0.13
vii) Truss Calculation - Deferred Submittal per hour, 1 hour min
[6] NEW $ 212 $ 212
viii) 3rd Party additional plan review fee, after 2nd
review
a) City Processing Fee per review NEW $ 106 $ 106
b) 3rd Party Consultant per review NEW Actual Cost
City of San Leandro
Master Fee Schedule
Proposed
Building
6 of 8
BUILDING
Fee
No.
Fee Name Fee Unit /
Type Notes Current Fee / Deposit
100% Cost
Recovery
Fee
Rec'd Fee Level /
Deposit
D. Miscellaneous Fees
i) Miscellaneous Inspections
a) Fees for Inspection not otherwise set forth
herein
per hour, 1
hour min
[6] $ 209 $ 319 $ 319
b) Fees for inspection conducted outside of
normal business hours - 2 hour minimum
per hour, 2
hour min
[7] $ 315 $ 606 $ 606
ii) Investigation Fees [8]
a) Investigation fee for work commenced
without first obtaining permits as required by
the San Leandro Municipal Code, whether or
not a permit is subsequently issued
See
Administrative
Citations
Schedule
See
Administrative
Citations
Schedule
b) Investigation fee for conditions that are not
in compliance with the San Leandro Zoning
and/or Municipal Codes -
per hour, 1
hour min $ 209 $ 212 $ 212
E. Other Fees and Charges
(i) Technology Fee per permit [11]
6% of permit
fee. Min $7.29
per permit type.
6.92% 6.92%
(ii) Community Planning Fee (for commercial,
industrial & residential projects) per permit [9,10]
.3% of total
valuation of
construction
21.68% 10.84%
(iii) Strong Motion Impact Fee: State mandated tax for
the Seismic Safety Commission for seismic monitoring. Set by State Set by State Residential
.00013 per
$1.00 Valuation
or fraction
thereof with a
$0.50
.00013 per $1.00
Valuation or
fraction thereof
with a $0.50
Commericial/Industrial
.00028 per
$1.00 Valuation
or fraction
thereof with a
$0.50
.00028 per $1.00
Valuation or
fraction thereof
with a $0.50
(iv) Building Standards Commission (SB1473) Fee:
State Mandated tax for Green Building Standards
collected for the State by the City.
hourly Set by State Set by State
(v) Exception to Noise Ordinance per permit $ 491 $ 106 $ 106 (vi) Certificate of Occupancy per hour, 1
hour min
[6] $ 209 $ 212 $ 212
(vii) Temporary Certificate of Occupancy per 30 days per hour, 1 hour min
[6] $ 209 $ 212 $ 212
(viii) Certificate of Compliance per hour, 1
hour min
[6] $ 209 $ 212 $ 212
(ix) House Moving permit per hour, 1
hour min
[6] $ 209 $ 212 $ 212
(x) Microfilm Copies per sheet [13] $ 1.20 $ 1.20
- Microfilm Copies that require an affidavit per request NEW $ 425 $ 425 (xi) Photocopies per page [13] $ 0.10 $ 0.10
(xii) Reproduce lost permit (plan sets, supporting
documents and job card) per request NEW $ 531 $ 531
(xiii) Failed C&D Debris per request NEW $ 212 $ 212
(xiv) Appeals each Actual Cost Actual Cost
F. Building Code Violation [12]
First Violation each $ 130 $ 130
Second Violation each $ 700 $ 700
Third Violation each $ 1,300 $ 1,300
Each additional violation of the same ordinance
withing two years of the first violation each $ 2,500 $ 2,500 2 Hourly Services and/or Services not Otherwise Listed per hour $ 209 $ 212 $ 212 City of San Leandro
Master Fee Schedule
Proposed
Building
7 of 8
BUILDING
Fee
No.
Fee Name Fee Unit /
Type Notes Current Fee / Deposit
100% Cost
Recovery
Fee
Rec'd Fee Level /
Deposit
Notes
[1]
[2]
[3]
[4] Sign permit fees are based on all signs being on the same property and on the same permit. [5]
[6] 1 hour minimum.
[7] 2 hour minimum.
[8]
[9]
[10]
[11] Fee charged as a percentage of permit fee.
[12] CA Gov't Code 36900
[13] Set by State
Community Planning Fee will not be charged for the following project types: permits for accessory dwelling units; stand-alone mechanical, plumbing, and electrical permits; minor residential remodels, and; minor tenant improvements.
Determination of Valuation for Fee-Setting Purposes: Valuation shall be based on total value of all construction work, as determined by the Building Official, including all finish work, roofing, electrical, plumbing, heating, air conditioning, elevators, fire-extinguishing systems and any other permanent equipment). For new construction project valuations which the Building Official believes are understated at submittal, valuation may be determined using the most current International Code Council (ICC) valuation table modified to account for a regional construction cost modifier of 16% or the most currently available regional construction cost modifier (i.e. construction value in ICC Table * 1.16). For tenant improvement, residential remodels, or other projects that do not involve new square footage project valuations which the Building Official believes are understated at submittal, valuation may be determined using, up to 50% of, the most current International Code Council (ICC) valuation table modified to account for a regional construction cost modifier of 16% or the most currently available regional construction cost modifier (i.e. up to 50% of construction value in ICC Table * 1.16.) Note: The Building Official may adjust the plan checking/permit fee for an individual project when costs to the City are not congruent with this fee schedule.
Note: For photovoltaic systems, total permit fees, including applicable Permit Issuance and Filing Fees, Automation Fees, Community Planning Fees, and other mandated fees shall not exceed amounts authorized via Government Code Section 66015.
Plan checking fee shall be paid at the time of application for a building permit. The plan checking fee is in addition to the building permit fee.
Note: Payment of any investigation fees does not exempt any person from compliance with all other provisions of applicable codes in the execution of the work nor from any other penalties prescribed by law.
Note: For small tenant improvements to existing buildings and ADUs, the Chief Building Official and/or the Community Development Director may waive the Community Planning Fee at his/her discretion.
City of San Leandro
Master Fee Schedule
Proposed
Building