BID SUMMARY
BID OPENING Kerex Engineering, Inc. Frontline General Engineering S&H Construction, Inc. 4941 Pacheco Blvd. Construction Inc. 5560 Boscell Common DATE: July 31, 2024 Martinez, CA 94553 16440 Ashland Ave. Fremont, CA 94538 TIME: 2:30 p.m. Phone: (925) 387-8913 San Lorenzo, CA 94580 Phone: (510) 579-7382 LOCATION: City Clerk's Office Fax: (925) 387-0853 Phone: (510) 954-0739 Fax: (510) 280-6087 Fax: N/A
ITEM
NO. ITEM UNIT COST ITEM COST UNIT COST UNIT COST UNIT COST

BASE BID
1 CONSTRUCTION SURVEYING PER
SECTION 2-9.2
1 LS $12,000.00 $12,000.00 $5,500.00 $5,500.00 $19,595.08 $19,595.08 $7,500.00 $7,500.00 2 CONCRETE WASHOUT AREA PER
SECTION 7-8.6.2
250 SF $20.00 $5,000.00 $2.00 $500.00 $12.97 $3,242.50 $20.00 $5,000.00 3 INLET PROTECTION PER SECTION
7-8.6.2
1 EA $200.00 $200.00 $1,500.00 $1,500.00 $697.09 $697.09 $2,500.00 $2,500.00 4 STABILIZED CONSTRUCTION
ENTRANCE/EXIT PER SECION 7-

8.6.2 800 SF $10.00 $8,000.00 $4.00 $3,200.00 $12.64 $10,112.00 $15.00 $12,000.00 5 TEMPORARY CONSTRUCTION

FENCE WITH DUST CONTROL
SCREENS PER SECTION 7-8.6.2
670 LF $30.00 $20,100.00 $5.00 $3,350.00 $47.20 $31,624.00 $20.00 $13,400.00 6 FIBER ROLLS PER SECTION 7-8.6.2 600 LF $8.00 $4,800.00 $2.00 $1,200.00 $8.39 $5,034.00 $5.00 $3,000.00 7 EQUIPMENT MOBILIZATION AND

DEMOBILIZATION (NOT TO EXCEED
10% OF TOTAL BID) PER SECTION 9-

3.4 1 LS $25,000.00 $25,000.00 $40,000.00 $40,000.00 $68,939.89 $68,939.89 $30,000.00 $30,000.00 8 REMOVE EXISTING TREES PER
SECTION 300-1
5 EA $650.00 $3,250.00 $2,500.00 $12,500.00 $3,123.70 $15,618.50 $1,000.00 $5,000.00 9 ROUGH GRADING-CUT PER
SECTION 300-2
1 LS $15,000.00 $15,000.00 $25,000.00 $25,000.00 $16,471.03 $16,471.03 $20,000.00 $20,000.00 10 ROUGH GRADING-FILL PER
SECTION 300-4
1 LS $12,000.00 $12,000.00 $25,000.00 $25,000.00 $11,230.06 $11,230.06 $5,000.00 $5,000.00 11 UNIT PAVERS AT LABYRINTH PER
SECTION 302-14
1000 EA $15.00 $15,000.00 $45.00 $45,000.00 $21.89 $21,890.00 $10.00 $10,000.00 Date Approved:6/28/24
Prepared by: N. Castelino

QUANTITY ITEM COST ITEM COST ITEM COST
PROJECT TITLE: Sanctity of Life Memorial at Marina Park PROJECT NO.:

BID NO.:

ENGINEER'S ESTIMATE
2022.034
24-25.001
This document is a summary of bids received for the subject project and are provided only as a convenience. Listing of a particular bid is not a finding that such bid has been found to be responsive or accepted as complete by the City.

An award of contract, if any, is subject to approval of the City Council and/or the City Manager. Contractors should refer to the contract documents for bidding information.

Sanctity of Life Memorial _Marina Park_ Page 1 of 8 Printed 8/6/2024 @ 11:02 AM

BID SUMMARY
BID OPENING Kerex Engineering, Inc. Frontline General Engineering S&H Construction, Inc. 4941 Pacheco Blvd. Construction Inc. 5560 Boscell Common DATE: July 31, 2024 Martinez, CA 94553 16440 Ashland Ave. Fremont, CA 94538 TIME: 2:30 p.m. Phone: (925) 387-8913 San Lorenzo, CA 94580 Phone: (510) 579-7382 LOCATION: City Clerk's Office Fax: (925) 387-0853 Phone: (510) 954-0739 Fax: (510) 280-6087 Fax: N/A
ITEM
NO. ITEM UNIT COST ITEM COST UNIT COST UNIT COST UNIT COST Date Approved:6/28/24
Prepared by: N. Castelino

QUANTITY ITEM COST ITEM COST ITEM COST
PROJECT TITLE: Sanctity of Life Memorial at Marina Park PROJECT NO.:

BID NO.:

ENGINEER'S ESTIMATE
2022.034
24-25.001
12 MONUMENT SIGN AND PLAQUE
PER SECTION 302-14
1 LS $3,000.00 $3,000.00 $15,000.00 $15,000.00 $11,560.76 $11,560.76 $5,000.00 $5,000.00 13 FRENCH DRAINPIPE (6"

PERFORATED PVC DRAIN PIPE)
PER SECTION 306-7
120 LF $110.00 $13,200.00 $200.00 $24,000.00 $118.19 $14,182.80 $50.00 $6,000.00 14 6" SOLID PVC STORM DRAINPIPE
PER SECTION 306-7
20 LF $100.00 $2,000.00 $500.00 $10,000.00 $146.03 $2,920.60 $100.00 $2,000.00 15 CLEARING AND GRUBBING PER
SECTION 300-1
12575 SF $0.75 $9,431.25 $1.00 $12,575.00 $1.73 $21,754.75 $4.00 $50,300.00 16 GRTED LINE DRAIN PER SECTION
303-1
30 LF $180.00 $5,400.00 $400.00 $12,000.00 $336.91 $10,107.30 $100.00 $3,000.00 17 CONCRETE SEAT WALLS PER
SECTION 303-5
69 LF $300.00 $20,700.00 $400.00 $27,600.00 $482.10 $33,264.90 $500.00 $34,500.00 18 CONCRETE SEAT WALLS (AT ART)
PER SECTION 302-15
20 LF $300.00 $6,000.00 $400.00 $8,000.00 $725.06 $14,501.20 $500.00 $10,000.00 19 CONCRETE WALLS AND FOOTINGS
- MONUMENT SIGN PER SECTION
303-1
1 LS $6,500.00 $6,500.00 $15,000.00 $15,000.00 $2,291.27 $2,291.27 $5,000.00 $5,000.00 20 12" CONCRETE MOW STRIP PER
SECTION 302-15
16 LF $35.00 $560.00 $300.00 $4,800.00 $340.37 $5,445.92 $500.00 $8,000.00 21 CONCRETE PAVING - PEDESTRIAN
PER SECTION 302-15
4010 SF $22.00 $88,220.00 $30.00 $120,300.00 $19.50 $78,195.00 $40.00 $160,400.00 22 CONCRETE PAVING - VEHICULAR
PER SECTION 302-15
500 SF $45.00 $22,500.00 $50.00 $25,000.00 $28.43 $14,215.00 $50.00 $25,000.00 23 PAINTING AT EXISTING STAGE PER
SECTION 310
662 SF $21.50 $14,233.00 $25.00 $16,550.00 $16.74 $11,081.88 $30.00 $19,860.00 24 REMOVAL AND DISPOSAL OF

EXISTING PAVEMENT PER
SECTION 312
500 SF $5.00 $2,500.00 $20.00 $10,000.00 $6.16 $3,080.00 $30.00 $15,000.00 25 REMOVAL AND DISPOSAL OF

SHADE STRUCTURE POSTS PER
SECTION 312
1 LS $1,000.00 $1,000.00 $7,500.00 $7,500.00 $8,602.20 $8,602.20 $5,000.00 $5,000.00 26 REMOVE AND SALVAGE PILASTER
CAPS PER SECTION 312
1 LS $3,000.00 $3,000.00 $1,500.00 $1,500.00 $2,017.80 $2,017.80 $5,000.00 $5,000.00 Sanctity of Life Memorial _Marina Park_ Page 2 of 8 Printed 8/6/2024 @ 11:02 AM

BID SUMMARY
BID OPENING Kerex Engineering, Inc. Frontline General Engineering S&H Construction, Inc. 4941 Pacheco Blvd. Construction Inc. 5560 Boscell Common DATE: July 31, 2024 Martinez, CA 94553 16440 Ashland Ave. Fremont, CA 94538 TIME: 2:30 p.m. Phone: (925) 387-8913 San Lorenzo, CA 94580 Phone: (510) 579-7382 LOCATION: City Clerk's Office Fax: (925) 387-0853 Phone: (510) 954-0739 Fax: (510) 280-6087 Fax: N/A
ITEM
NO. ITEM UNIT COST ITEM COST UNIT COST UNIT COST UNIT COST Date Approved:6/28/24
Prepared by: N. Castelino

QUANTITY ITEM COST ITEM COST ITEM COST
PROJECT TITLE: Sanctity of Life Memorial at Marina Park PROJECT NO.:

BID NO.:

ENGINEER'S ESTIMATE
2022.034
24-25.001
27 REMOVE AND SALVAGE FITNESS
EQUIPMENT PER SECTION 312
1 LS $3,000.00 $3,000.00 $4,500.00 $4,500.00 $6,147.80 $6,147.80 $10,000.00 $10,000.00 28 TRASH AND RECYCLE RECEPTICAL
PER SECTION 313-1.4
1 EA $3,500.00 $3,500.00 $2,500.00 $2,500.00 $2,724.62 $2,724.62 $2,500.00 $2,500.00 29 SKATE DETERRANTS PER
SECTION 313-1.4
3 EA $40.00 $120.00 $500.00 $1,500.00 $516.16 $1,548.48 $500.00 $1,500.00 30 TRENCH GRATE AND FRAME PER
SECTION 313-1.4
1 EA $3,250.00 $3,250.00 $4,500.00 $4,500.00 $12,070.30 $12,070.30 $2,000.00 $2,000.00 31 ORGANIC SOIL AMENDMENTS PER
SECTION 800-1.2.4
7510 SF $0.80 $6,008.00 $1.00 $7,510.00 $2.20 $16,522.00 $5.00 $37,550.00 32 PLANTS PER SECTION 800-1.4 39 EA $46.00 $1,794.00 $450.00 $17,550.00 $421.60 $16,442.40 $200.00 $7,800.00 33 MULCH PER SECTION 800-1.4 68 CY $50.00 $3,400.00 $200.00 $13,600.00 $120.77 $8,212.36 $100.00 $6,800.00 34 SOD AND STOLENS (TURF GRASS)
PER SECTION 800-1.4.5
7510 SF $3.50 $26,285.00 $1.20 $9,012.00 $2.09 $15,695.90 $10.00 $75,100.00 35 IRRIGATION SYSTEM AND
MATERIALS PER SECTION 800-2
1 LS $25,000.00 $25,000.00 $50,000.00 $50,000.00 $65,770.30 $65,770.30 $15,460.00 $15,460.00 36 PLANTING AND SOD AREA
PREPERATION PER SECTION 801
7686 SF $2.10 $16,140.60 $1.00 $7,686.00 $1.49 $11,452.14 $5.00 $38,430.00 37 FINISH GRADING PER SECTION 801-
2 800 SY $0.56 $448.00 $10.00 $8,000.00 $18.30 $14,640.00 $5.00 $4,000.00 TOTAL BASE BID: $407,539.85 $598,933.00 $608,901.83 ** $668,600.00 REQUIRED DOCUMENTATION:

Agreement to be Bound
SUBCONTRACTORS:

All Seasons
NOTES: ** Math Error Corrected and/or
San Leandro Local Business NO NO
Lonestar Landscape Ridgeline Engineering NONE
Bid Bond YES YES YES
NO
25 % Participation NO NO NO
Good Faith Effort YES YES NO

YES YES YES
Addendum #1 YES YES YES
Sanctity of Life Memorial _Marina Park_ Page 3 of 8 Printed 8/6/2024 @ 11:02 AM

BID SUMMARY
BID OPENING Kerex Engineering, Inc. Frontline General Engineering S&H Construction, Inc. 4941 Pacheco Blvd. Construction Inc. 5560 Boscell Common DATE: July 31, 2024 Martinez, CA 94553 16440 Ashland Ave. Fremont, CA 94538 TIME: 2:30 p.m. Phone: (925) 387-8913 San Lorenzo, CA 94580 Phone: (510) 579-7382 LOCATION: City Clerk's Office Fax: (925) 387-0853 Phone: (510) 954-0739 Fax: (510) 280-6087 Fax: N/A
ITEM
NO. ITEM UNIT COST ITEM COST UNIT COST UNIT COST UNIT COST Date Approved:6/28/24
Prepared by: N. Castelino

QUANTITY ITEM COST ITEM COST ITEM COST
PROJECT TITLE: Sanctity of Life Memorial at Marina Park PROJECT NO.:

BID NO.:

ENGINEER'S ESTIMATE
2022.034
24-25.001
Reviewed by: Date:

Nicole Castelino, Project Manager
Reviewed by: Date:

Austine Osakwe, Senior Engineer
Sanctity of Life Memorial _Marina Park_ Page 4 of 8 Printed 8/6/2024 @ 11:02 AM 8/7/2024
8/7/2024

BID SUMMARY

BID OPENING
DATE: July 31, 2024
TIME: 2:30 p.m.

LOCATION: City Clerk's Office
ITEM
NO. ITEM UNIT COST ITEM COST

BASE BID
1 CONSTRUCTION SURVEYING PER
SECTION 2-9.2
1 LS $12,000.00 $12,000.00
2 CONCRETE WASHOUT AREA PER
SECTION 7-8.6.2
250 SF $20.00 $5,000.00
3 INLET PROTECTION PER SECTION
7-8.6.2
1 EA $200.00 $200.00
4 STABILIZED CONSTRUCTION
ENTRANCE/EXIT PER SECION 7-

8.6.2 800 SF $10.00 $8,000.00
5 TEMPORARY CONSTRUCTION

FENCE WITH DUST CONTROL
SCREENS PER SECTION 7-8.6.2
670 LF $30.00 $20,100.00
6 FIBER ROLLS PER SECTION 7-8.6.2 600 LF $8.00 $4,800.00 7 EQUIPMENT MOBILIZATION AND

DEMOBILIZATION (NOT TO EXCEED
10% OF TOTAL BID) PER SECTION 9-

3.4 1 LS $25,000.00 $25,000.00
8 REMOVE EXISTING TREES PER
SECTION 300-1
5 EA $650.00 $3,250.00
9 ROUGH GRADING-CUT PER
SECTION 300-2
1 LS $15,000.00 $15,000.00
10 ROUGH GRADING-FILL PER
SECTION 300-4
1 LS $12,000.00 $12,000.00
11 UNIT PAVERS AT LABYRINTH PER
SECTION 302-14
1000 EA $15.00 $15,000.00
Date Approved:6/28/24
Prepared by: N. Castelino

QUANTITY
PROJECT TITLE: Sanctity of Life Memorial at Marina Park PROJECT NO.:

BID NO.:

ENGINEER'S ESTIMATE
2022.034
24-25.001
Mark Lee and Yong Kay, Inc.

DBA Bay Construction Co.
4026 Martin Luther King Jr. Way
Oakland, CA 94609
Phone: (510) 658-7225
Fax: (510) 658-4890

UNIT COST
$27,500.00 $27,500.00
$50.00 $12,500.00
$375.00 $375.00
$3.75 $3,000.00
$6.25 $4,187.50
$3.75 $2,250.00
$25,000.00 $25,000.00
$2,500.00 $12,500.00
$100,000.00 $100,000.00
$50,000.00 $50,000.00
$75.00 $75,000.00

ITEM COST
Sanctity of Life Memorial _Marina Park_ Page 5 of 8 Printed 8/6/2024 @ 11:02 AM

BID SUMMARY

BID OPENING
DATE: July 31, 2024
TIME: 2:30 p.m.

LOCATION: City Clerk's Office
ITEM
NO. ITEM UNIT COST ITEM COST
Date Approved:6/28/24
Prepared by: N. Castelino

QUANTITY
PROJECT TITLE: Sanctity of Life Memorial at Marina Park PROJECT NO.:

BID NO.:

ENGINEER'S ESTIMATE
2022.034
24-25.001
12 MONUMENT SIGN AND PLAQUE
PER SECTION 302-14
1 LS $3,000.00 $3,000.00
13 FRENCH DRAINPIPE (6"

PERFORATED PVC DRAIN PIPE)
PER SECTION 306-7
120 LF $110.00 $13,200.00
14 6" SOLID PVC STORM DRAINPIPE
PER SECTION 306-7
20 LF $100.00 $2,000.00
15 CLEARING AND GRUBBING PER
SECTION 300-1
12575 SF $0.75 $9,431.25
16 GRTED LINE DRAIN PER SECTION
303-1
30 LF $180.00 $5,400.00
17 CONCRETE SEAT WALLS PER
SECTION 303-5
69 LF $300.00 $20,700.00
18 CONCRETE SEAT WALLS (AT ART)
PER SECTION 302-15
20 LF $300.00 $6,000.00
19 CONCRETE WALLS AND FOOTINGS
- MONUMENT SIGN PER SECTION
303-1
1 LS $6,500.00 $6,500.00
20 12" CONCRETE MOW STRIP PER
SECTION 302-15
16 LF $35.00 $560.00
21 CONCRETE PAVING - PEDESTRIAN
PER SECTION 302-15
4010 SF $22.00 $88,220.00
22 CONCRETE PAVING - VEHICULAR
PER SECTION 302-15
500 SF $45.00 $22,500.00
23 PAINTING AT EXISTING STAGE PER
SECTION 310
662 SF $21.50 $14,233.00
24 REMOVAL AND DISPOSAL OF

EXISTING PAVEMENT PER
SECTION 312
500 SF $5.00 $2,500.00
25 REMOVAL AND DISPOSAL OF

SHADE STRUCTURE POSTS PER
SECTION 312
1 LS $1,000.00 $1,000.00
26 REMOVE AND SALVAGE PILASTER
CAPS PER SECTION 312
1 LS $3,000.00 $3,000.00
Mark Lee and Yong Kay, Inc.

DBA Bay Construction Co.
4026 Martin Luther King Jr. Way
Oakland, CA 94609
Phone: (510) 658-7225
Fax: (510) 658-4890

UNIT COST ITEM COST
$3,750.00 $3,750.00
$150.00 $18,000.00
$75.00 $1,500.00
$6.25 $78,593.75
$250.00 $7,500.00
$250.00 $17,250.00
$375.00 $7,500.00
$5,000.00 $5,000.00
$87.50 $1,400.00
$37.50 $150,375.00
$37.50 $18,750.00
$8.75 $5,792.50
$16.25 $8,125.00
$500.00 $500.00
$625.00 $625.00
Sanctity of Life Memorial _Marina Park_ Page 6 of 8 Printed 8/6/2024 @ 11:02 AM

BID SUMMARY

BID OPENING
DATE: July 31, 2024
TIME: 2:30 p.m.

LOCATION: City Clerk's Office
ITEM
NO. ITEM UNIT COST ITEM COST
Date Approved:6/28/24
Prepared by: N. Castelino

QUANTITY
PROJECT TITLE: Sanctity of Life Memorial at Marina Park PROJECT NO.:

BID NO.:

ENGINEER'S ESTIMATE
2022.034
24-25.001
27 REMOVE AND SALVAGE FITNESS
EQUIPMENT PER SECTION 312
1 LS $3,000.00 $3,000.00
28 TRASH AND RECYCLE RECEPTICAL
PER SECTION 313-1.4
1 EA $3,500.00 $3,500.00
29 SKATE DETERRANTS PER
SECTION 313-1.4
3 EA $40.00 $120.00
30 TRENCH GRATE AND FRAME PER
SECTION 313-1.4
1 EA $3,250.00 $3,250.00
31 ORGANIC SOIL AMENDMENTS PER
SECTION 800-1.2.4
7510 SF $0.80 $6,008.00
32 PLANTS PER SECTION 800-1.4 39 EA $46.00 $1,794.00
33 MULCH PER SECTION 800-1.4 68 CY $50.00 $3,400.00
34 SOD AND STOLENS (TURF GRASS)
PER SECTION 800-1.4.5
7510 SF $3.50 $26,285.00
35 IRRIGATION SYSTEM AND
MATERIALS PER SECTION 800-2
1 LS $25,000.00 $25,000.00
36 PLANTING AND SOD AREA
PREPERATION PER SECTION 801
7686 SF $2.10 $16,140.60
37 FINISH GRADING PER SECTION 801-
2 800 SY $0.56 $448.00
TOTAL BASE BID: $407,539.85
REQUIRED DOCUMENTATION:

Agreement to be Bound
SUBCONTRACTORS:

NOTES:

San Leandro Local Business
Bid Bond
25 % Participation
Good Faith Effort
Addendum #1
Mark Lee and Yong Kay, Inc.

DBA Bay Construction Co.
4026 Martin Luther King Jr. Way
Oakland, CA 94609
Phone: (510) 658-7225
Fax: (510) 658-4890

UNIT COST ITEM COST
$1,250.00 $1,250.00
$6,250.00 $6,250.00
$187.50 $562.50
$2,500.00 $2,500.00
$1.88 $14,118.80
$500.00 $19,500.00
$275.00 $18,700.00
$3.75 $28,162.50
$62,500.00 $62,500.00
$2.50 $19,215.00
$25.00 $20,000.00
$829,732.55
Land Clearing
Sandis Construction Survey
NO
All Seasons Tree Service and
YES
NO
YES
YES
YES
Sanctity of Life Memorial _Marina Park_ Page 7 of 8 Printed 8/6/2024 @ 11:02 AM

BID SUMMARY

BID OPENING
DATE: July 31, 2024
TIME: 2:30 p.m.

LOCATION: City Clerk's Office
ITEM
NO. ITEM UNIT COST ITEM COST

ENGINEER'S ESTIMATE
Date Approved:6/28/24
Prepared by: N. Castelino

QUANTITY
PROJECT TITLE: Sanctity of Life Memorial at Marina Park PROJECT NO.: 2022.034
BID NO.: 24-25.001
Reviewed by: Date:

Nicole Castelino, Project Manager
Reviewed by: Date:

Austine Osakwe, Senior Engineer
Mark Lee and Yong Kay, Inc.

DBA Bay Construction Co.
4026 Martin Luther King Jr. Way
Oakland, CA 94609
Phone: (510) 658-7225
Fax: (510) 658-4890

UNIT COST ITEM COST
Sanctity of Life Memorial _Marina Park_ Page 8 of 8 Printed 8/6/2024 @ 11:02 AM Aug 6, 2024