Wednesday, December 4, 2024
Facilities and Transportation
Committee
MacArthur/Superior
Roundabout Project Update
1 Overview
▪ Background /History
▪ Current Status
▪ Outstanding Issues
▪ Funding
▪ Project Schedule
December 4, 2024 FACILITIES AND TRANSPORTATION COMMITTEE 2 Existing Condition
3 December 4, 2024 FACILITIES AND TRANSPORTATION COMMITTEE 3 Project Milestones
Feasibility
Study
2006
Preliminary
design
completed
Project on
hold due to
funding
2008
Project
funded
Traffic study
initiated
2014
Project
Concept A
presented
Protected
bike lanes
added
2016
Project
Concept B
presented
and
accepted
2019
Council
approved
Acquisition/
Maintenance
Agreement
with Oakland
2022
Staff directed
to abandon
right-of-way
acquisition
2023
Caltrans
issues R/W
decertification
Caltrans
review ongoing
2024
December 4, 2024 FACILITIES AND TRANSPORTATION COMMITTEE 4 Interim Safety Measures
Tuff Curb & delineators were
installed along MacArthur
Blvd to prevent left turns
from Foothill Blvd.
5 December 4, 2024 FACILITIES AND TRANSPORTATION COMMITTEE Speed Reader & Ped. Xing
Speed Bumps on Lewis Ave
5 Project Status
• Letter received from City of Oakland to support the project and to agree to accept the right-of-way to be decertified from Caltrans. • Design for relocation of utility poles completed by PG&E • Right-of-way decertification by Caltrans approved on November 16, 2023
• City has requested concurrent review of Caltrans submittals 6 December 4, 2024 FACILITIES AND TRANSPORTATION COMMITTEE Outstanding Issues
• Caltrans Structures Review approval for retaining wall • Temporary Construction Easement (TCE)/Right of Entry from the Liquor Store property
• PG&E Undergrounding of Overhead Lines
• Caltrans Maintenance agreement
• Caltrans encroachment permit approval
December 4, 2024 FACILITIES AND TRANSPORTATION COMMITTEE 7 Funding
• Estimated Total Project Costs: $4.9M
• Estimated Construction Costs: $3.9M
• Current Budget: $1.6M
• FY26 Allocation: $1.3M
• Additional Funding Needed: $2M
December 4, 2024 FACILITIES AND TRANSPORTATION COMMITTEE 8 Project Schedule
December 4, 2024 FACILITIES AND TRANSPORTATION COMMITTEE 9 Activities Current Schedule Projected Schedule
CALTRANS Structural Review
Approval November 2024 January 2025
PG&E Construction Spring 2023 Summer 2025
PS&E Approval May 2025 August 2025
Bid and Award June 2025 Fall 2025
Start of Construction July 2025 Spring 2026