IN THE CITY COUNCIL OF THE CITY OF SAN LEANDRO
RESOLUTION NO. 2025-XXX
RESOLUTION TO AWARD A $2,250,000 CONSTRUCTION CONTRACT TO ARMER-NORMAN & ASSOCIATES FOR PWSC REPLACE FUEL TANKS, PROJECT NO. 2020.3600; TO AUTHORIZE THE CITY MANAGER TO NEGOTIATE AND APPROVE INDIVIDUAL CHANGE ORDERS UP TO 5% (OR $112,500) OF THE ORIGINAL CONTRACT AMOUNT; TO AUTHORIZE THE CITY MANAGER TO NEGOTIATE AND APPROVE CHANGE ORDERS UP TO A CUMULATIVE VALUE NOT TO EXCEED 15% (OR $337,500) OF THE ORIGINAL CONTRACT AMOUNT; AND TO APPROPRIATE AN ADDITIONAL $1,872,020 TO THE SUBJECT PROJECT
WHEREAS, the City of San Leandro did, on January 23, 2025, publicly open, examine and declare all sealed proposals or bids for doing the work described in the bid documents for the subject project; and
WHEREAS, said proposals were submitted to the Public Works Director who finds that the proposal hereinafter mentioned is the lowest responsive bid by a responsible bidder for doing said work; and
WHEREAS, the subject project is categorically exempt from California Environmental Quality Act; and
WHEREAS, change orders to clarify the work or respond to unusual existing conditions are a normal aspect of public contracting and construction; and WHEREAS, in order to expedite the delivery of public projects on schedule and on budget, provide that subcontractors and workers are paid in a timely fashion, avoid as much as possible costly delay claims, and ensure that the City completes projects and products that are to the City’s highest standards, the City Council finds that providing authorization to negotiate and approve change orders is in the best interest of public health, safety and welfare.

NOW, THEREFORE, the City Council of the City of San Leandro does RESOLVE as follows:

1. That said City Council hereby rejects all said proposals or bids except that herein mentioned; hereby waives any irregularities in the proposal or bid of the lowest responsible bidder; and hereby awards the contract for doing said work to the lowest responsible bidder to wit, Armer-Norman & Associates, in the amount of $2,250,000; and

2. That the City Manager or her designee is authorized to negotiate and approve individual change orders up to a maximum of 5% of the original contract amount, or $112,500 each;

3. That the City Manager or her designee is authorized to negotiate and approve cumulative change orders up to a maximum of 15% of the original contract amount, or $337,500;

4. That $1,872,020 is approved to appropriate for the subject project.

DRAFT
RESOLUTION NO. 2025-XXX 2
BE IT FURTHER RESOLVED that if the above-named contractor is unable to execute the contract, then the City Manager is authorized to award this contract to the next lowest responsible bidder, execute all documents to affect the award, and take all action necessary to recover any bid security from the low bidder necessary to make the City whole in its acceptance of the lowest bid.

Introduced by Councilmember _______ and passed and adopted this 17th day of March 2025, by the following vote:

AYES: ()

NOES: ()

ABSENT: ()