BID SUMMARY

BID OPENING Armer Norman & Associates, Inc.

DATE: January 23, 2025 2600 Williams Street
TIME: 3:00 p.m. San Leandro, CA 94577
LOCATION: City Clerk's Office Phone: (925) 671-9200
Fax: (925) 671-9732
ITEM
NO. ITEM UNIT COST ITEM COST UNIT COST
1 All work shown on plans or
specifications
1 LS $1,383,730.50 $1,383,730.50 $2,100,000.00 $2,100,000.00 2 Sheeting, shoring and bracing 1 LS $182,850.00 $182,850.00 $150,000.00 $150,000.00 TOTAL BASE BID:

REQUIRED DOCUMENTATION:

Agreement to be Bound
SUBCONTRACTORS:

Date: 1/24/2025
Bennett Sanderson, Project Manager
Date:

Austine Osakwe, Senior Engineer
Date Approved: 12/16/24

ITEM COST
$1,566,580.50

ENGINEER'S ESTIMATE
Prepared by: B. Sanderson
Reviewed by:

Reviewed by:
25 % Participation
Jagshaan Trucking, LLC.

Leak Detection Technology
National Construction Rentals
IEC Dervices
Addendum No. 1 - 2 YES
PROJECT TITLE:

PROJECT NO.:

BID NO.:

QUANTITY
PWSC Replace Fuel Tanks
$2,250,000.00
M.A. McClish Excavating, Inc.
2020.3600
23-24.001
YES
YES
N/A
N/A
YES
Bid Bond
San Leandro Local Business
Good Faith Effort
This document is a summary of bids received for the subject project and are provided only as a convenience. Listing of a particular bid is not a finding that such bid has been found to be responsive or accepted as complete by the City. An award of contract, if any, is subject to approval of the City Council and/or the City Manager.

Contractors should refer to the contract documents for bidding information.

PWSC Replace Fuel Tanks Bid Summary Page 1 of 1 Printed 1/28/2025 @ 11:33 AM 1/24/25