Update on Sonic Project in San Leandro
By
Dane Rodgers, Senior Engineer
Engineering Division, PW Dept
June 12 - Facilities & Transportation Committee Meeting 1 City of San Leandro and Sonic Coordination
June 12 - Facilities & Transportation Committee Meeting 2 Pole Evaluation /
Pole Access Temporary Poles Pole Replacement
Aerial and
Underground Permit 10 Gigabits of Speed
20,609 Addresses
Served Future Expansion
Deployment
in City of
San Leandro
June 12 - Facilities & Transportation Committee Meeting 3 June 12 - Facilities & Transportation Committee Meeting 3 # of Addresses:
Butternut A: 10,283
Butternut B: 4,780
Butternut C: 5,546
SONIC PROJECT UPDATES
June 12 - Facilities & Transportation Committee Meeting 4 Evaluated 4,199
existing joint poles
430 temporary poles
needed
Temporary poles
placed near joint poles
for future transfer of
Sonic fiber
442,600 linear feet
of aerial fiber
29,700 linear feet
of underground fiber
January 2025
Sonic completed
underground conduits
and fiber work
SONIC PROJECT UPDATES
(CONTINUED)
Butternut C
By June 2025 – 80 temp
poles removed and areas
restored
Butternut A
June 2025 – Temp
poles being removed
Butternut B
Waiting for PG&E/AT&T
clearance prior to removal
of temporary poles
Butternut B
Sonic removes temp poles
and restore area within 160
days after PG&E/AT&T
replaces old joint poles.
June 12 - Facilities & Transportation Committee Meeting 5 THANK YOU!