Facilities and Transportation Committee
I-880 Integrated
Corridor Management
Central Segment
1 Overview
Project
Background
1 2
Project
Location
Funding
Analysis
5 3
Project
Improvements
4 Project
Schedule
2 Project
Milestones
November 13, 2025 FACILITIES AND TRANSPORTATION COMMITTEE 2 What Is
Integrated Corridor Management?
Integrated Corridor Management (ICM) minimizes
impacts of traffic on local streets when incidents
occur on the freeway
November 13, 2025 FACILITIES AND TRANSPORTATION COMMITTEE 3 Intelligent
Transportation
System
Trailblazer Signs
Cameras
Traffic Sensors
Signal
Coordination
ICM uses hardware and
communication
technology to allow
freeways, local streets,
crosswalks, bike lanes
and public transit to
work better together
How Does
ICM Work?
November 13, 2025 FACILITIES AND TRANSPORTATION COMMITTEE 4 Project Background
• North Segment
• Completed 2022
• I-880/980 to Davis Street
• City is partnering with MTC
to deliver Central Segment
• Uses Federal Congestion
Mitigation and Air Quality
Improvement (CMAQ) funds
November 13, 2025 FACILITIES AND TRANSPORTATION COMMITTEE 5 Project
Location
San Leandro Boulevard
• Juana Avenue
• Dolores Avenue
• Williams Street
• Marina Boulevard
• Polar Way
• Washington Avenue
Washington Avenue
• 143rd Avenue
• Floresta Boulevard
• Anza Way
• Springlake Drive
• I-880 Off Ramp
• Beatrice Street
• Fargo Avenue
• Lewelling Boulevard
CALTRANS to maintain the I-880 Off Ramp Signal at Washington Avenue November 13, 2025 FACILITIES AND TRANSPORTATION COMMITTEE 6 Project
Improvements
SynchroGreen
controllers
Traffic signal
controller upgrade
on City’s ATMS
Remote access to
traffic signals
Detection upgrades
Battery back up
systems
Fiber optic
communication
November 13, 2025 FACILITIES AND TRANSPORTATION COMMITTEE 7 Project Milestones
MOU Between
COSL and

CALTRANS
June
2024
100% Design
PS&E completed
by MTC
August
2025
CALTRANS E-76
Authorization
September
2025
Fall
2025
Construction Bid
Advertisement
Winter
2026/27
Project Handoff
From MTC to COSL
November 13, 2025 FACILITIES AND TRANSPORTATION COMMITTEE 8 Project Schedule
Activities Project Schedule
Design and Bid Advertisement January 2026
Contract Award February 2026
Material Procurement
Construction Begins Spring 2026
Construction Complete Winter 2026/2027
November 13, 2025 FACILITIES AND TRANSPORTATION COMMITTEE 9 Funding Analysis
Contract Costs
Construction Contract: $1,120,362
Contract Contingency: $93,838
Alternative Bid Items $283,500
Total Amount Without Bid Alts: $1,214,200
Total Amount With Bid Alts: $1,497,700
Construction Budget
Federal CMAQ Fund - $1,678,000 for Construction
Federal CMAQ Fund - $250,000 for Construction Engineering Total Funds - $1,928,000
November 13, 2025 FACILITIES AND TRANSPORTATION COMMITTEE 10 Questions?
November 13, 2025 FACILITIES AND TRANSPORTATION COMMITTEE 11