East Bay Greenway Multimodal Project 1

ALAMEDA COUNTY TRANSPORTATION COMMISSION
East Bay Greenway
Multimodal Project

ALAMEDA COUNTY TRANSPORTATION COMMISSION
San Leandro Facilities and Transportation Committee
Project Update Presentation
February 12, 2026
East Bay Greenway Multimodal Project 2
East Bay Greenway Multimodal (Phase 1)
(EBGWMM)
• Safer pedestrian and bicycle
improvements along Alameda
County high injury network
• Multimodal conneyctivity with
new facilities in Equity Priority
Communities
• 16 miles of regional
trail/complete street facility
• Connects 7 BART stations from
Lake Merritt to South Hayward
North Segment
(Oakland/San Leandro)
County & Hayward Segments
Facilities & Transportation Committee February 12, 2026 East Bay Greenway Multimodal Project 3
East Bay Greenway (Phase 1)- North Segment
Lake Merritt to Bayfair – Construction Packages
E 10th St
E 12th St
Oakland: Lake Merritt to Fruitvale Oakland: Fruitvale to San Leandro San Leandro Caltrans
Facilities & Transportation Committee February 12, 2026 East Bay Greenway Multimodal Project 4
San Leandro Project Limits
E14th Street
San Leandro Blvd
San Leandro / Caltrans Construction Package limits
Facilities & Transportation Committee February 12, 2026 East Bay Greenway Multimodal Project 5
Project Features
Image sources: NACTO, Alta, Google Images, FHWA
Shared use paths
Protected intersections
Protected bike lanes
Pedestrian signals
Flashing beacons
Bus stop improvements Raised medians
Accessible curb ramps
Facilities & Transportation Committee February 12, 2026 East Bay Greenway Multimodal Project 6
Project Features, cont.

Image sources: NACTO, Alta, Google Images, FHWA
Wayfinding signage
New streetlighting
Bioswales
Plaza area
Bike racks
New/replaced trees
Benches
Facilities & Transportation Committee February 12, 2026 East Bay Greenway Multimodal Project 7
Proposed
San Leandro Blvd, north of BART
Existing
Facilities & Transportation Committee February 12, 2026 East Bay Greenway Multimodal Project 8
Proposed
San Leandro Blvd, BART station
Existing
Facilities & Transportation Committee February 12, 2026 East Bay Greenway Multimodal Project 9
Proposed
San Leandro Blvd, south of BART
Existing
Facilities & Transportation Committee February 12, 2026 East Bay Greenway Multimodal Project 10
Proposed
E14th Street (SR 185) Existing
Facilities & Transportation Committee February 12, 2026 East Bay Greenway Multimodal Project 11
Project Features –
Bus loading islands
Facilities & Transportation Committee February 12, 2026 East Bay Greenway Multimodal Project 12
Project Features –
Shared boarding areas
Facilities & Transportation Committee February 12, 2026 East Bay Greenway Multimodal Project 13
Project Features –
Protected Intersections
Facilities & Transportation Committee February 12, 2026 East Bay Greenway Multimodal Project 14
Community Engagement
Final Design
• Focus group with Boys and Girls
Club
• Chamber of Commerce
update presentation
• Pop-ups
• City pilot demonstration along
E 14th at Triangle Plaza
• BPAC presentation
Conceptual Design (2022)
• Mailers
• Pop-ups
• Online survey
• Focus Groups with multimodal
advocates and businesses
• BPAC presentation
• Door-to-door outreach to businesses
Facilities & Transportation Committee February 12, 2026 East Bay Greenway Multimodal Project 15
Project Schedule
Environmental
Clearance Final Design Construction
Summer 2023 –
Fall 2026
Spring 2027 –
Winter 2029
Fall 2022 –
Fall 2025
Design completion –
June 2026
(San Leandro)
Sept 2026 (E 14th)
Construction start –
Spring 2027
(San Leandro)
Winter 2027 (E 14th)
CEQA – Complete
NEPA – Sept 2025
Concept
Design
Spring 2022-
Summer 2023
Local Approvals –
June 2022 (SL),
May 2023 (OAK)
Facilities & Transportation Committee February 12, 2026 East Bay Greenway Multimodal Project 16
Anticipated Construction impacts
• Lane closures, limited to several blocks at a time
➢ One lane per direction
➢ One direction at a time
• Temporary closures of some side streets
• Cyclist detours/diversions
• Pedestrian detours/diversions
• Access to properties and trash service to be maintained throughout • Bus stop changes
Prior to any contractor activity, the City will review/approve Traffic Control Plans.

Alameda CTC will have a public information officer who will work with City staff to communicate and coordinate construction updates.

Facilities & Transportation Committee February 12, 2026 East Bay Greenway Multimodal Project 17
Project costs and funding
Major External Grants Received
• State Active Transportation program -
$19.5 M
• State Solutions for Congested Corridors
Program - $39.375 M
• Federal Reconnecting Communities and
Neighborhoods - $30 M
• Federal One Bay Area Grant - $15.9M
• Regional Measure 3 Safe Routes to
Transit and Bay Trail - $25 M
Phase Total
Costs
Preliminary Engineering/
Environmental Clearance $1,158,000
Final Design $16,164,000
Construction $179,332,000
Total $196,654,000
Facilities & Transportation Committee February 12, 2026 East Bay Greenway Multimodal Project 18 Alameda County Transportation Commission • 1111 Broadway, Suite 800 Oakland, CA 94607 • 510.208.7400
Forging a Path
for the
East Bay Greenway!
Photo TBD
Photo TBD
Photo TBD
For more information, visit
www.AlamedaCTC.org/eastbaygreenway