Lewelling Boulevard
Class IV Bikeways
Information Only
Facilities & Transportation Committee, April 9, 2026 1
Sara Dowling
Civil Engineer
Introductions
Thomas Kabandama
Civil Engineer
Rob Rees
Traffic Engineer
Facilities & Transportation Committee, April 9, 2026 2
Iman M. Fawzy
Assistant Engineer
Project
Location
1 AGENDA
Guiding
Policies
2 Project & Design
Features
3 Traffic Study
4 5
Schedule &
Next Steps
6 Costs &
Funding
Facilities & Transportation Committee, April 9, 2026 3
Project Location
Bus stops
Legend
Facilities & Transportation Committee, April 9, 2026 4
Guiding Policies
Vision Zero Policy (2022):
• Eliminate fatalities and serious injuries by making travel safer for all modes of transportation and people of all ages and abilities.

Local Road Safety Plan (LRSP, 2022)
• Outlines goals and policies and identifies 7 priority corridors for safety improvements.

Bicycle and Pedestrian Master Plan (BPMP, 2024)
• Expands on LRSP
• Guide infrastructure projects and programs to support bicycling and walking as safe, enjoyable, and practical transportation options.

Facilities & Transportation Committee, April 9, 2026 5
• Protect EB & WB LT movements
• LPI for all approaches
• Adjust all-red intervals to be
consistent; adjust yellow
• Increase min. green for bike xing
• Optimize cycle lengths and splits
• No RT on red all approaches
Farnsworth St
• LPI for all approaches
• Increase min. green for bike xing
• Optimize cycle lengths and splits
• No RT on red all approaches
• Protect RT w/ overlap for SB RT
Planned Bicycle
Network
Facilities & Transportation Committee, April 9, 2026
6 PROJECT

LOCATION
Collision Summary
Facilities & Transportation Committee, April 9, 2026 7
KSI: Killed or Seriously Injured
Street From To
Lewelling Boulevard Washington Avenue Wicks Boulevard
From To
Period 9/1/2020 8/31/2025
Total Collisions 66
Total Injury 34
Total KSI 3
Total Pedestrian Collisions 4
Pedestrian KSI 2 (Serious Injuries)
Total Bicycle Collisions 4
Bicycle KSI 1 (fatality)
Goals & Project Features
Protected Left Turn
Movements
Facilities & Transportation Committee, April 9, 2026 8
High Visibility
Crosswalks
Protected Bike Lanes
Accessible Curb Ramps No Right Turn on Red Tighten Turn Radii at Corners
Pavement Surface Seal
Recommended goals:

1. Enhance bicycle safety

2. Enhance pedestrian safety

3. Improve safety at
intersections
Lewelling Blvd (Sedgeman to Washington) Cross Section
Existing
Proposed
Facilities & Transportation Committee, April 9, 2026 9
Concept: Eastbound at Sedgeman St
Facilities & Transportation Committee, April 9, 2026 10 Lewelling Blvd (Wicks to Sedgeman) Cross Section
Existing
Proposed
Facilities & Transportation Committee, April 9, 2026 11 Concept: Eastbound at Calgary St
Facilities & Transportation Committee, April 9, 2026 12 Level of Service
Facilities & Transportation Committee, April 9, 2026 13 Delay
(sec/veh)
LOSDelay
(sec/veh)
LOS
Standard
> 35-55 secD≤10 secA
> 55-80 secE> 10-20 secB
≥ 80 secF> 20-35 secC
Acceptable limit
Level of Service (LOS)
• Measures the delay of vehicles through
the intersection
• Represented by a grading system with
A meaning little or no delay and going to
F meaning stop and go traffic
• General Plan Policy acceptable LOS is D
Traffic Study Results
Findings and Recommendations
• Level of Service (LOS) at
intersections stays within
acceptable range
• Update signal timing to
separate phases for drivers
and pedestrians/bicyclists
Facilities & Transportation Committee, April 9, 2026 14 Budget
Analysis
Project Cost
• Design Cost: $675,000
• Construction Cost: $5,825,100
Total Project Costs: $6,500,100
Available Funding
• Local Funds: $1,194,000
• Capital Reserve/Grant Funds*: $1,239,957
• ACTC Grant: $2,207,000
• HIP Grant (Construction only): $1,859,000
Total Funding: $6,500,100
*While capital reserves have been designated to fund the project, staff continues to actively seek grant funding opportunities and perform value engineering to offset the use of capital reserves.

Facilities & Transportation Committee, April 9, 2026 15 Bike Way Separators Considered
Fairmont Dr.

Grand Ave.

Facilities & Transportation Committee, April 9, 2026 16 Planted and Stamped
Concrete Medians
$3,400,000
Flexible Posts with
Armadillos
$140,000
Concrete Bumpers
with K-71 Bollards
$210,000
Tack-On Curb with
Flexible Posts
$890,000
Project Schedule and Next Steps
Facilities &
Transportation
Committee meeting
April 9, 2026
Bicycle & Pedestrian
Advisory Commission
Meeting
April 21, 2026
Value Engineering &
Design
Development
March – October
2026
Final Design
End of 2026
Bid & AwardDesign
Fall 2025- Dec 2026
Pre-Design Start Construction
Early 2027 Spring 2027 Complete
Facilities & Transportation Committee, April 9, 2026 17 Dec 2027
Q&A
Facilities & Transportation Committee, April 9, 2026 18